100% found this document useful (1 vote)
4K views1 page

Labour Schedule for Construction Work

The document provides a list of 13 items for construction work including materials and labor requirements. For each item, it specifies the item description, unit of quantity, required labor types and their quantities on the basis of 8 hours of work per day. The labor types include masons, mazdoors, carpenters, fitters and painters. The item quantities range from 2 square meters to 100 cubic meters. The number of laborers required for each item ranges from 1 to 27.

Uploaded by

Manas
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
4K views1 page

Labour Schedule for Construction Work

The document provides a list of 13 items for construction work including materials and labor requirements. For each item, it specifies the item description, unit of quantity, required labor types and their quantities on the basis of 8 hours of work per day. The labor types include masons, mazdoors, carpenters, fitters and painters. The item quantities range from 2 square meters to 100 cubic meters. The number of laborers required for each item ranges from 1 to 27.

Uploaded by

Manas
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
  • Construction Material List

[Link].

Item Description Unit of Labour(on the basis Quantity


Qty of 8 hours working (Nos.)
per day)
1 Cement concrete in 10 m3 Head mason 1/4
foundation Mason 2
Mazdoors 20
2 R.C.C. ([Link]) 10 m3 Head Mason(Mate) 1/2
Mason 3
Mazdoor(ins. 23
Bhisti)
3 Supplying, fitting, 7 m2 Carpenter 1
fixing and removing Mazdoor 2
shuttering and staging
4 Reinforcement for 100 kg Bar binder 1
R.C.C. work including Mazdoor 1
cutting, bending and
placing in position
5 Damp proof course 100 m2 Head Mason 1/2
Mason 5
Mazdoor 6
3
6 First class brickwork in 10 m Head Mason 1/2
1: 6 in superstructure Mason 9
Mazdoor (2 nos as
Bhisti) 20
2
7 Brick on edge flooring 100 m Head Mason 1/2
with cement mortar 1:3 Mason 10
Mazdoor (1 no as
Bhisti) 15
2
8 Ironite flooring (40mm 100 m Head Mason 1
thick) Mason 24
Mazdoor 27
Mazdoor for 3
rubbing
2
9 C.G.I. sheet on roof 10 m Carpenter 1
Fitter (Blacksmith) 1/2
Mazdoor 2
10 H.C.I. rain water pipe 9 m (1.8m Mason 1/2
fixing length 5no Mazdoor 21/2

11 12mm thk. cement 100 m2 Head Mason 1


plaster on brickwork in Mason 10
1:6 or any proportion Mazdoor (incl. 1 no.
Bhisti) 15
2
12 Ruled Pointing (1:3) 100 m Head Mason 1/2
Mason 10
Mazdoor (incl. 1 no.
Bhisti) 10
2
13 White washing primer 100 m Painter 1/2