1-Initial set-up
Setup default options:
File --> Option --> their you can change the defaults
Display
Schedule
Setup project start date
project--> project information --> You can assign start date for the project
Setup working times
project--> change working time --> You can change the calendar
Setup time scale
Double click on time scale it will give you a window
Setup layout
Format-> Format --> layout, gridlines and text style
1-Input project activities into Gantt Sheet
Activity Ids, descriptions and durations
Adding relationship for Schedule
Double click on an activity
Schedule data
After inputting the activities and durations specify the start date and the
relation between them, then click on Task --> Tasks --> auto schedule
Modifying the bar chart