I.
WORK PROGRESS STATUS
A. TILING WORKS @ LANAI
1.0 Accomplishments 95%
2.0 Target Completion Date May 24, 2014
3.0 Cost to Complete ( LABOR Only) PHP 820.00
B. PAINTING WORKS
1.0 WALLS
1.1 Accomplishments 30%
1.2 Target Completion Date May 27, 2014
1.3 Cost to Complete ( LABOR Only) PHP 1,500
2.0 CEILING
1.1 Accomplishments 0%
1.2 Target Completion Date May 28, 2014
1.3 Cost to Complete ( LABOR Only) PHP 2,000
3.0 WINDOWS
1.1 Accomplishments 10%
1.2 Target Completion Date May 29, 2014
1.3 Cost to Complete ( LABOR Only) PHP 2,000
`