TQ No: MSET/M2-256/V35253/TQ-02
TECHNICAL QUERY
(for clarification/deviation/waiver)
DATE:
CONTRACT / PO/WO NO
CONTRACTOR
DISCIPLINE; P/M/C/S/E/I
29/07/2015
4120104272
MSET ENGINEERING CORPORATION SDN BHD
M
DESCRIBE ALL CLARIFICATION, USE ONE SUBJECT and ONE DISCIPLINE PER QUERY,
ORIGINAL SCOPE
POST FORMING HEAT TREATMENT (NORMALIZING) FOR PRESSURE VESSEL
TOP HEAD AS PER PTS 12.20.01
REVISED SCOPE / NEW SCOPE
PROPOSE TO CHANGE THE METHOD OF POST FORMING HEAT TREATMENT
OF TOP HEAD FROM NORMALIZING TO STRESS RELIEF.
JUSTIFICATION / PURPOSE
BASED ASME SECTION VIII, DIV 1 2013 ED, CLAUSE UCS-79, HEAT
TREATMENT SHALL BE PERFORMED TO ALL PARTS THAT HAVE BEEN COLD
FORMED WITH FIBER ELONGATION GREATER THEN 5% FOR CARBON STEEL
MATERIAL. POST FORMING HEAT TREATMENT (STRESS RELIEF) SHALL BE
PERFORMED AT TEMPERATURE 610C - 625C FOR 2 HOURS HOLDING TIME
(MINIMUM).
(include deviation/waiver)
WHILE IN PTS 12.20.01 CLAUSE 5.2.4.i MENTION THAT HEAT TREATMENT
(NORMLIZING) SHALL BE PERFORMED TO ALL PARTS THAT HAVE BEEN
COLD FORMED WITH FIBER ELONGATION GREATER THEN 5% FOR CARBON
STEEL [Link] SHALL BE PERFORMED AT TEMPERATURE
OF 910C WITH 10 MINUTES HOLDING TIME.
SINCE THE MATERIAL OF TOP HEAD IS CARBON STEEL CLADDING (SA 516
GR 60N +3.5MM SS316L), WITH EXPOSING TO TEMPERATURE ABOVE 425 C 870 C FOR SUFFICIENT TIME WILL LEADS TO FORMATION OF CHROMIUM
CARBIDE AT AUSTENITE GRAIN BOUNDRIES WHICH CALLS SENSITIZATION
EFFECT. INTER-GRANULAR CORROSION WILL OCCURS WHEN A SENSITIZED
MATERIAL IS EXPOSED TO SUFFICIENTLY STRONG CORROSIVE MEDIUM
FOR A LONG ENOUGH TIME.
INORDER TO MINIMIZE THE EFFECT OF SENSITIZATION, MSET PROPOSE TO
MAKE A DEVIATION ON THE REQUIREMENT OF POST FORMING HEAT
TREATMENT FROM NORMALIZING TO STRESS RELIEF.
ATTACHMENT
NOT APPLICABLE
REFERENCE
MSET/M2-256/V-35253/01 (GENERAL ARRANGEMENT DWG FOR SUPHUR COALESCER (V-35253))
MSET/M2-256/V-35253/DC/REV D (DEISGN CALCULATION)
Issued By:
THIS PROPOSAL IS REQUIRED IN ORDER MINIMIZE THE EFFECT OF
SENSITIZATION.
Contractor project Manager /Authorize
representative
PP(M)SB/MRC Respond (reject/revise/resubmit etc.):
NOTE:
Upon receive the respond of the clarification/queries as above, if Contractor/Vendor/Consultant consider this is an additional
work to the contract with schedule or cost impact, Contractor/Vendor/Consultant shall formalize the Change impact and/or schedule
through the Variation Order Procedure prior proceeding with the stated work. Failure to formalize it in accordance to procedure may
void of Contractor/Vendor right.
Prepared By:
Name:
Position:
Date:
NURU HIDAYAH
MOHAMAD RAWI
DESIGN
ENGINEER
29/07/15
Reviewed By:
Name:
Position
Date:
MOHAMAD AZAHAR
BIN AHMAD
ENGINEERING
MANAGER
29/07/15
* refer to whoever applicable, PTS deviation shall seek BTA/TP signature..
Reviewed By:
Approved By:
Name:
Position
Name:
Position :
Date:
Date:
*TP/SME
*Manager/TP/Above
Template; May 2015