FC 1 300 09n
FC 1 300 09n
1 May 2014
Change 2, 21 Aug 2015
FC 1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FACILITIES CRITERIA (FC)
NAVY AND MARINE CORPS
DESIGN PROCEDURES
Any copyrighted material included in this FC is identified at its point of use.
Use of the copyrighted material apart from this FC must have the permission of the copyright
holder.
U.S. ARMY CORPS OF ENGINEERS
NAVAL FACILITIES ENGINEERING COMMAND (Preparing Activity)
AIR FORCE CIVIL ENGINEER CENTER
Date
1 Apr 2015
1 Sep 2015
Location
Added Building Information Management/Modeling
(BIM) Requirements to Chapter 12
Updated Drawing Requirements for Chapter 12
Updated Special Inspection Requirements
Added eOMSI Facility Data Workbook to Design Phase
Chapters
Revised Posting of Controlled, Unclassified Information
in Chapter 2, clarified signature requirements in Chapter
12, and updated BIM submittal requirements.
This FC supersedes UFC 1-300-09N, dated 25 May 2005, with Changes 1-9.
FC 1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FOREWORD
Facilities Criteria (FC) provide functional requirements (i.e., defined by users and operational
needs of a particular facility type) for specific DoD Component(s), and are intended for use with
unified technical requirements published in DoD Unified Facilities Criteria (UFC). FC are
applicable only to the DoD Component(s) indicated in the title, and do not represent unified DoD
requirements. Differences in functional requirements between DoD Components may exist due
to differences in policies and operational needs.
All construction outside of the United States is also governed by Status of Forces Agreements
(SOFA), Host Nation Funded Construction Agreements (HNFA), and in some instances,
Bilateral Infrastructure Agreements (BIA.) Therefore, the acquisition team must ensure
compliance with the most stringent of the UFC (replace w/ FC), the SOFA, the HNFA, and the
BIA, as applicable.
Because FC are coordinated with unified DoD technical requirements, they form an element of
the DoD UFC system applicable to specific facility types. The UFC system is prescribed by
MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and
modernization criteria, and applicable to the Military Departments, Defense Agencies, and the
DoD Field Activities. The UFC System also includes technical requirements and functional
requirements for specific facility types, both published as UFC documents and FC documents.
FC are living documents and will be periodically reviewed, updated, and made available to
users as part of the Services responsibility for providing criteria for military construction.
Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities Engineering
Command (NAVFAC), and the Air Force Civil Engineer Center (AFCEC) are responsible for
administration of the UFC system. Defense agencies should contact the preparing service for
document interpretation and improvements. Technical content is the responsibility of the
cognizant DoD working group. Recommended changes with supporting rationale should be
sent to the respective service proponent office by the following electronic form: Criteria Change
Request. The form is also accessible from the Internet site listed below.
FC are effective upon issuance and are distributed only in electronic media from the following
source:
Whole Building Design Guide web site http://dod.wbdg.org/.
Refer to UFC 1-200-01, General Building Requirements, for implementation of new issuances
on projects.
AUTHORIZED BY:
FC 1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FACILITIES CRITERIA (FC)
REVISION SUMMARY SHEET
Document:
Superseding:
Description: This FC provides specific guidance on how and when to provide a project
design deliverable for NAVFAC. This document is organized into design deliverables
and design phases. Requirements for design deliverables, beyond or in more detail of
what is already required by a Core UFC, are provided for NAVFAC-only. The
requirements for when or to what extent these deliverables are provided are in the
Phase chapters.
Reasons for Document:
Impact:
Unification Issues
Design and Submittal procedures contained herein are pertinent to standards, software,
and templates used, required, and unified within NAVFAC, and centered around the
NAVFAC organization and operation. Procedures for NAVFAC may not work for
USACE and Air Force operations due to organizational and operational differences.
Similar uniform standardization and procedures are not available from the other
Services.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION ....................................................................................... 1
1-1
1-1.1
1-2
APPLICABILITY. ....................................................................................... 1
1-3
1-4
EXCEPTIONS. ........................................................................................... 1
1-5
REFERENCES. ......................................................................................... 2
1-6
GLOSSARY. .............................................................................................. 2
CHAPTER 2 POLICY...................................................................................................... 3
2-1
CRITERIA. ................................................................................................. 3
2-2
2-2.1
SI Definitions.......................................................................................... 3
2-2.2
2-3
2-4
REGISTRATION. ....................................................................................... 4
2-4.1
Certification. ........................................................................................... 4
2-5
2-6
DESIGN DELIVERABLES FOR NAVAL CONSTRUCTION FORCES MARINE LOGISTICS GROUPS AND NAVY CONSTRUCTION
BATTALIONS (SEABEES). .................................................................... 4
2-7
3-1.1
3-1.2
3-1.3
3-1.4
3-1.5
3-2
3-2.1
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
3-2.2
3-2.3
3-2.4
3-2.5
3-2.6
3-2.7
3-2.8
3-3
4-2
RESPONSIBILITIES................................................................................ 11
4-3
COORDINATION. .................................................................................... 11
4-4
4-5
4-5.1
4-5.2
4-5.3
4-5.4
Boring Logs.......................................................................................... 16
4-5.5
4-5.6
4-6
4-6.1
4-6.2
4-7
4-8
5-2
FORMAT. ................................................................................................ 19
5-3
SUSTAINABILITY. .................................................................................. 19
5-3.1
5-3.2
5-3.3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
5-4
5-5
GEOTECHNICAL. ................................................................................... 20
5-6
CIVIL........................................................................................................ 21
5-6.1
5-6.2
Demolition. ........................................................................................... 21
5-6.3
5-6.4
5-6.5
5-6.6
5-6.7
5-6.8
Stormwater Management..................................................................... 23
5-6.9
5-6.10
Permits................................................................................................. 23
5-7
STRUCTURAL. ....................................................................................... 23
5-8
6-2
6-3
FORMAT. ................................................................................................ 25
6-4
6-5
6-6
CIVIL........................................................................................................ 25
6-6.1
6-7
6-7.1
6-7.2
6-7.3
6-8
7-2
PRESENTATION. .................................................................................... 29
7-3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
7-4
7-5
7-5.1
7-5.2
Demolition Plan.................................................................................... 31
7-5.3
7-5.4
7-5.5
7-5.6
7-5.7
7-6
7-7
7-8
8-2
8-2.1
8-2.2
8-2.3
8-2.4
8-2.5
8-3
8-3.1
8-3.2
8-3.3
8-3.4
8-3.5
8-4
8-4.1
8-4.2
8-4.3
Coordination. ....................................................................................... 40
8-5
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
8-6
8-6.1
Coversheet. ......................................................................................... 40
8-6.2
8-6.3
Format. ................................................................................................ 41
8-6.4
8-6.5
8-6.6
8-6.7
9-2
9-2.1
9-2.2
10-2
10-3
SELECTION OF CLINS........................................................................... 51
10-4
10-5
10-6
10-7
10-8
10-9
SYNOPSIS. ............................................................................................. 53
11-2
11-3
11-3.1
11-3.2
11-4
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
11-4.1
11-4.2
11-4.3
11-5
11-6
11-7
11-7.1
11-7.2
SUMMARY. ............................................................................................. 63
12-2
12-3
12-3.1
Specifications....................................................................................... 64
12-3.2
12-3.3
Drawings. ............................................................................................. 64
12-3.4
12-3.5
12-3.6
12-3.7
12-4
12-4.1
12-4.2
12-4.3
12-5
12-5.1
BIM Definitions..................................................................................... 78
12-5.2
12-5.3
12-5.4
12-5.5
12-5.6
12-6
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-6.1
General. ............................................................................................... 82
12-6.2
12-6.3
13-2
13-3
13-4
13-5
13-5.1
13-5.2
13-6
DD 1391................................................................................................... 86
13-7
13-8
13-9
14-2
14-3
14-3.1
Geotechnical. ....................................................................................... 89
14-3.2
Sustainability........................................................................................ 89
14-4
DRAWINGS. ............................................................................................ 89
14-4.1
Architectural. ........................................................................................ 89
14-4.2
Civil. ..................................................................................................... 90
14-4.3
14-4.4
Electrical. ............................................................................................. 90
14-4.5
14-4.6
Geotechnical. ....................................................................................... 90
14-5
14-6
CALCULATIONS. ................................................................................... 90
14-7
14-7.1
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
14-7.2
14-7.3
14-8
14-8.1
15-2
15-2.1
15-3
15-3.1
Architectural. ........................................................................................ 93
15-3.2
15-3.3
15-3.4
Geotechnical. ....................................................................................... 94
15-3.5
Civil. ..................................................................................................... 94
15-3.6
Structural. ............................................................................................ 95
15-3.7
Mechanical........................................................................................... 95
15-3.8
Electrical. ............................................................................................. 95
15-3.9
15-4
15-5
15-5.1
15-6
15-6.1
15-6.2
Civil. ..................................................................................................... 97
15-6.3
Architectural. ........................................................................................ 97
15-6.4
Mechanical........................................................................................... 97
15-6.5
Electrical. ............................................................................................. 98
15-6.6
15-6.7
GENERAL. .............................................................................................. 99
16-2
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
16-2.1
Geotechnical. ....................................................................................... 99
16-2.2
Sustainability........................................................................................ 99
16-3
DRAWINGS. ............................................................................................ 99
16-3.1
Civil. ..................................................................................................... 99
16-3.2
Electrical. ............................................................................................. 99
16-3.3
16-4
16-5
16-5.1
Sustainability...................................................................................... 101
16-5.2
16-5.3
16-6
16-7
16-7.1
16-7.2
FF&E.................................................................................................. 102
16-8
16-8.1
Mechanical......................................................................................... 102
16-8.2
16-9
16-10
16-11
16-12
16-13
17-2
17-2.1
Sustainability...................................................................................... 105
17-2.2
17-2.3
17-3
17-3.1
17-3.2
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
17-4
17-5
17-5.1
17-6
17-7
17-7.1
17-7.2
Sustainability...................................................................................... 107
17-7.3
17-7.4
17-7.5
17-8
17-9
17-9.1
17-9.2
FF&E.................................................................................................. 108
17-10
17-11
17-12
17-13
RFP........................................................................................................ 108
17-13.1
17-14
17-14.1
18-2
18-3
18-4
18-5
18-5.1
18-5.2
18-5.3
18-5.4
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 19 PHASE: POST-CONSTRUCTION DOCUMENTS ............................... 119
19-1
19-1.1
19-1.2
19-1.3
19-1.4
Sustainability...................................................................................... 119
C-2
TABLE 8-1 COMMONLY USED DBB UFGS DIVISION 00 AND 01 SECTIONS ........ 42
TABLE 8-2 COMMONLY USED DB RFP PART TWO UFGS DIVISION 01 SECTIONS
...................................................................................................................................... 43
TABLE 11-1 DESIGN AND CONSTRUCTION SUBMITTAL SUMMARY .................... 60
TABLE 18-1 SPECIFICATION OR RFP CHANGES FORMAT .................................. 113
TABLE 18-2 DRAWING CHANGES FORMAT .......................................................... 114
FIGURES
FIGURE 8-1 SAMPLE TABLE OF CONTENTS FOR COMBINED DBB PROJECTS . 46
FIGURE 8-2 SAMPLE COMBINED DB AND DBB PROJECT .................................... 48
FIGURE 12-1 DRAWING PROGRESSION CHART DBB ............................................ 66
FIGURE 12-2 DRAWING PROGRESSION CHART DB ............................................... 66
FIGURE 12-3/1/ NAVFAC SIGNATURES .................................................................... 77
FIGURE 12-4 DRAWING AND MODEL PROGRESSION DB ...................................... 81
FIGURE 17-1 QUALITY REVIEW BLOCK. ................................................................ 106
FIGURE 18-1 SAMPLE AMENDMENT ...................................................................... 115
FIGURE 18-2 SAMPLE CONTRACT MODIFICATION .............................................. 117
xi
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
xii
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 1 INTRODUCTION
1-1
This FC provides policy and standards for the design, development, and revision of
project documents, including drawings, specifications, and Requests for Proposal, for
facilities under the cognizance of NAVFAC. This FC has been developed to ensure
consistency and clarity of project documents that form the basis of contracts for the
design and construction of facilities.
1-1.1
Organization of Document.
This document is organized into design policy, roles and responsibilities, design
deliverables, and design phases. The design deliverables chapters contain general
requirements that apply throughout the design process. For the disciplines, additional
information is provided only if it is not already in another UFC; thus a discipline
paragraph may not be provided if the Core UFC already provides the requirements for
that deliverable, or the level of completion of that deliverable. Core UFCs are defined
and listed in UFC 1-200-01.
Detailed level of completion for each type of submittal, and for each discipline, only
beyond what is specified in other UFCs, are included in each design phase.
1-2
APPLICABILITY.
Comply with UFC 1-200-01 and UFC 1-200-02. UFC 1-200-02 must be used in
conjunction with UFC 1-200-01 and the UFCs and government criteria referenced
therein. UFC 1-200-01 provides applicability of model building codes and governmentunique criteria for typical design disciplines and building systems, as well as for
accessibility, antiterrorism, security, sustainability, and safety. UFC 1-200-02 provides
minimum unified requirements and coordinating guidance for planning, designing,
constructing, renovating, and maintaining high performance and sustainable facilities
that will enhance DOD mission capability by reducing total ownership costs. Use this
FC in addition to UFC 1-200-01, UFC 1-200-02, and the UFCs and government criteria
referenced therein.
1-4
EXCEPTIONS.
Austere Requirements may be invoked on a per-project basis, and only by formal letter
from Commander, Naval Installations Command (CNIC). Austere requirement options
are included in UFC 4-610-01 FC 4-721-10N, FC 4-722-01N, and FC 4-740-02N.
1
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
1-5
REFERENCES.
Appendix A contains a list of references used in this document. The publication date of
the code or standard is not included in this document. In general, the latest available
issuance of the reference is used.
1-6
GLOSSARY.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 2 POLICY
2-1
CRITERIA.
Design Naval shore facilities in accordance with all Navy and Department of Defense
(DoD) Criteria. DoD Design Criteria are available from the Whole Building Design
Guide web site (http://dod.wbdg.org/) and from the Construction Criteria Base (CCB)
web site (http://www.wbdg.org/ccb.) Design criteria include general criteria, as well as
specific criteria on particular elements of the work (e.g., Geotechnical Engineering) and
facility types (e.g., Bachelor Quarters). Design requirements are typically in the form of
Unified Facilities Criteria (UFC). The contract will reference the specific requirements
applicable to a particular project. Deviations from criteria must be approved by the
NAVFAC Chief Engineer and in accordance with MIL-STD-3007.
2-2
METRIC POLICY.
Comply with MIL-STD-3007 for the use of SI in projects and criteria documents.
NAVFAC policy is to use the metric system of measurement (International System of
Units, SI) in planning and design criteria, Unified Facilities Guide Specifications (UFGS),
and construction contract documents for all MCON/MILCON, BRACON, and family
housing, regardless of acquisition method. See exception under the paragraph in this
chapter entitled, General Policy.
2-2.1
SI Definitions.
General Policy.
In accordance with Public Law 94-168, design and construction of new or renovated
facilities must use the metric system of measurement, unless its use is impractical or is
likely to cause significant inefficiencies or loss of markets to United States firms.
Specify hard metric products unless such products are unavailable or uneconomical.
Do not use dual units on drawings on any type of project. The design agent project
manager is responsible for making the determination on whether or not to use the
metric system of measurement on a project-by-project basis. Decisions to not use the
metric system must be justifiable and documented in permanent project files. Comply
with Facilities Engineering Command (FEC) process for determination of exception for
the metric system.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
2-3
The clauses set forth in DFAR 252.227-7023, Drawings and Other Data to Become
Property of Government, DFAR 227.71, Rights in Technical Data, and DFAR 227.72
Rights in Computer Software and Computer Software Documentation, apply to all
project documents and data.
2-4
REGISTRATION.
Certification.
Where special certifications are required for the design, certify in accordance with the
contract and local requirements.
2-5
PROHIBITION OF POSTING CONTROLLED UNCLASSIFIED
INFORMATION DESIGN DELIVERABLES ON UNSECURED SERVERS.
\1\Design deliverables may contain Controlled Unclassified Information (CUI) such as
For Official Use Only (FOUO) or Department of Defense Unclassified Controlled
Nuclear Information (DoD UCNI). The release of this type of information into the public
domain may compromise an installation or facilitys Anti-Terrorism Force Protection
(ATFP) or physical security protective measures. Examples include the explosive
weights contained in UFC 4-010-02 and the location of a Sensitive Compartmented
Information Facility (SCIF) or Special Access Program Facility (SAPF). \2\Protect
deliverables, such as drawings, specifications, calculations, cost estimates, and other
design related information, that contain CUI, in accordance with DODM 5200.01 Volume
4. /2//1/
2-6
DESIGN DELIVERABLES FOR NAVAL CONSTRUCTION FORCES MARINE LOGISTICS GROUPS AND NAVY CONSTRUCTION BATTALIONS
(SEABEES).
Due to the nature of the work performed by the Marine Logistics Groups and the
Seabees, the design deliverables for their use must be tailored for expedient
construction. Deployed battalions may be in remote locations under austere conditions.
4
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Researching materials and transmitting submittals can be difficult, if not impossible. All
materials and performance requirements should be specified on the drawings to the
most practical extent. Specify materials available on the Federal schedule supply lists,
the battalions supply schedules, or by product name. Avoid referencing codes or
standards where possible, as reference materials may be difficult for the Battalion to
obtain in the field.
2-7
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 3 ROLES AND RESPONSIBILITIES
3-1
3-1.1
Engage in and provide liaison with the Activity, and appropriate Activity personnel, as
required by the contract, and during early design-development or RFP development.
The \1\ /1/DOR is responsible for architectural and engineering aspects of the project to
ensure reasonable facility cost appropriate for the functions to be performed through
design and RFP development.
3-1.2
Coordinate design input and reviews with other Government organizations described in
this chapter in paragraph Other Government Organizations and as required by the
contract.
3-1.3
The Document Review and Checking System (DrChecks) facilitates the formal review of
complex project documents. DrChecks automatically tracks, collates, and measures
technical discussions. Project documents can be uploaded into the project folders for
download and review. Provide design reviews in DrChecks as required by the Contract.
Contact the Government Project Manager to obtain registration information. DrChecks
can be accessed at https://www.projnet.org.
3-1.4
Final Approval.
The \1\/1/DOR reviews and gives final approval for contract project documents prepared
under their direction. The \1\/1/DOR must be registered in the discipline for the
documents they approve as described in Chapter 2 in paragraph Registration.
7
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
3-2
3-2.1
For facilities projects that require industrial hygiene technical assistance and that
involve potential health hazards such as toxic materials, non-ionizing radiation, noise, or
other health hazards, consult the appropriate Naval Environmental Health Center
(NEHC) for the activity. The NEHC activity is required to participate in design and RFP
development reviews and reviews of plans, specifications, or RFP for these projects.
The NEHC activity will ensure that engineering designs properly consider and provide
for adequate environmental controls for the elimination of health hazards. Also use this
review process for medical facility designs in excess of $1 million.
3-2.3
SPAWAR provides reviews and design input for projects where SPAWAR is providing
and installing equipment as identified in the 1391. The drawings of cable and
equipment layout are often provided by SPAWAR to the \1\/1/DOR, for incorporation
into the design. Coordinate closely with Project Manager and their SPAWAR
representative to receive timely input and to reduce impact to design and construction
schedules and project costs.
Projects, even if prepared by SPAWAR, must bear the standard NAVFAC title blocks
and drawing numbers. On drawings that require SPAWAR approval, SPAWAR
signature can be applied in the NAVFAC Signature Block in the supplemental location
and the SPAWAR drawing cross reference number can be provided on the border
sheet. SPAWAR may also need to review where project impacts an adjacent facility,
such as electro-magnetic radiation from police stations or hospitals affecting antennae,
transmitters, and receivers.
3-2.4
Civil Works.
NAVFAC approves drawings and specifications prepared for civil works subcontracts.
Assign NAVFAC drawing numbers to civil works contract drawings, and approve and
sign the drawings as "Satisfactory to" the prime contractor of the particular Navy
industrial plant for whose use the facility is provided.
3-2.5
Section 106 of the National Historic Preservation Act requires Federal agencies to take
into account the effects of their undertakings on historic properties that are eligible for
listing in the National Register of Historic Places (NRHP). Historic properties may
8
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
include archaeological sites, individual buildings, historic districts, landscapes,
structures, objects, and traditional cultural properties. In accordance with established
procedures at each installation, an action proponent files a National Environmental
Policy Act (NEPA) Compliance Checklist plus a copy of the Work Request or Project
Description with the Installation Cultural Resource Manager (CRM). The CRM then
reviews the Project Description and determines whether the project has the potential to
affect historic properties or whether it is exempt from Section 106 compliance. The
CRM will then either record that the undertaking is exempt, or engage in consultation for
Section 106 Compliance as required by 36 CFR 800.
3-2.6
At Installations outside of the United States, coordinate with the applicable host nation
regarding possible adverse effects to cultural resources. \1\/1/
3-2.7
COMMANDER, NAVFAC.
Authority and responsibility for formal approval of drawings and specifications and RFPs
by, or for, the Commander, NAVFAC, is vested in the Facility Engineering Command,
Chief Engineer and their delegated signatory representative(s).
The level of approval and responsibility for Design-Build drawings and documents,
submitted by the Contractor and signed by the Government, are defined in the RFP
contract.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
10
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 4 DELIVERABLE: FIELD INVESTIGATION
4-1
The site approval process includes field investigation and verification. This early effort
provides more defined project scope and cost, and can rule out a site. Many of the
functions identified under this heading are also essential during the DD1391 validation
process to assure the project has the appropriate funding based on the scope of work.
This section is not applicable for post-award design services of design-build contracts
unless specifically addressed in the RFP.
4-2
RESPONSIBILITIES.
The Government installation planners are responsible for obtaining information required
for project site approval prior to design. The \1\ /1/DOR must obtain all site and building
data and investigate existing site conditions, utilities, and facilities as necessary to
properly integrate the design of the project with existing conditions. Except as
otherwise contracted, field investigations must include complete and accurate site
investigation, topographic/hydrographic survey, and verification of location and
availability of utility and drainage systems. When available, research existing \1\/1/
record drawings for information. Field verify \1\record drawings/1/ \1\/1/ information and
other site features that may influence project design.
In a Design-Build contract, the \1\/1/DOR is responsible to verify all site information
\1\furnished in/1/ the Government issued RFP. In addition, the DOR must provide
additional field investigations and verification of existing site conditions as may be
required to support the development of the design and construction of the project.
4-3
COORDINATION.
Coordinate all site work, including topographic/hydrographic and soil surveys, with
representatives of the Public Works, Utilities and Energy team, and other NAVFAC
design personnel. During execution of field investigation work, the \1\/1/DOR is
responsible for obtaining necessary permits, and complying with applicable laws, codes,
and regulations, including OSHA regulations. The exact location of the geotechnical
excavation, whether by drilling or digging, must be approved by the appropriate
authorities, be it the local utility service or by a company hired by the geotechnical
engineering firm to scope utilities. The DOR is responsible for all damages to persons
and property that occur as a result of their fault or negligence. The DOR must take
proper safety precautions to protect the public, the property of the public and the
Government from physical hazards and unsafe conditions. Upon completion of field
investigation, return the property to its original condition except as released in writing by
the client activity.
11
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
4-4
TOPOGRAPHIC SURVEY.
Provide a topographic survey of the project site in accordance with the National Society
of Professional Surveyors (NSPS) Model Standards for Topographic Surveys with the
following modifications:
Ensure that adequate adjacent areas are included within the survey limits
to clearly indicate and accommodate standoffs required by antiterrorism
criteria, offsite drainage and offsite utility connections impacting the
project.
Show horizontal control used during field survey. Indicate the reference
coordinate plane and provide two permanent control points for reference.
Include description of points (i.e. PK nail in cap). Provide a minimum of
three reference distances to existing permanent structures (reference
points) so that control can be re-established.
If match lines are used involving more than three sheets, provide a key
map with current sheet highlighted. Remove any extraneous lines and
text from key map.
North must be oriented toward the top (or left edge) of the plotted sheet.
Coordinate north direction with other disciplines so that all plans are
oriented the same.
Accurately locate (by means of structures visible from the surface and
through research of Activity utility maps, \1\record/1/ drawings, data from
local utility companies) the following list of utilities (both above and below
ground), structures and features. Provide notes indicating the sources
and any limitations or assumptions of the data and that the Contractor
must field verify the location of all utilities prior to construction. The survey
must include the following specific items and their related appurtenant
above-ground features, but is not limited to:
o Buildings: Describe building material and number of stories.
o Pavements: Include type of material. In areas where pavement
demolition is to occur, note all pavement thicknesses, including layer
thicknesses and joint patterns for replacement. Pavement layer
12
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
thicknesses may be obtained by reviewing \1\record drawing/1/
information, digging at the edge of the pavement, core drilling, and
consulting with Activity personnel. Where proposed pavements are
expected to abut existing pavements, provide pavement markings, joint
pattern and indicate joint types of the existing pavements.
o Surface Drainage Features: Indicate normal water level for permanent
standing water.
o Utilities: Include rim elevations for utility structures; location and
identification of lines as underground or aboveground; pipe sizes and
materials. Identify water system as potable, nonpotable, high pressure
or saltwater as applicable.
o Fences: Note height, type of fabric, barbed wire, direction of outrigger,
top or bottom rails, tension wires, gate locations and types.
o Foundations: Indicate visible foundations of demolished buildings.
o Fuel Pipes and Storage Tanks: Include information such as fill ports,
vent lines, and tank drains.
o Pump Stations: Include invert of influent pipe and elevation of force
main. Locate all aboveground elements including controls.
o Railroads and Crane Rails: Include turnouts, rail sizes, compromise
joint locations, and curve information, such as P.C., P.T., and P.I. as
they may be applicable to the design requirements of the proposed
project.
o Tidal Shoreline: Note water elevation, time of day, date, and tidal
condition at time of survey. Indicate normal high/low water elevations
referenced to the datum used.
o Trees/Woods: In wooded areas, locate outside drip line of wooded
area, include general density and type of trees. Where selective
clearing will be accomplished, locate individual trees and tree size over
a 6-inch (152.4 mm) diameter.
o Wetland Areas: Wetland and marsh areas must be flagged and
numbered by the Government prior to the survey. Locate flags and
label in the same manner as marked in the field. If unanticipated
wetlands are found during the survey, advise the Governments Civil
Reviewer to establish any additional survey requirements.
4-5
4-5.1
Existing Information.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
firms preparing, planning or designing documents are encouraged to use this resource
to research existing conditions or past design approaches for facilities, structures, or
pavements. Viewing or discussion of the files contents is possible by contacting the
Government. For Design-Build contracts, any relevant geotechnical or pavement
information that is available will be furnished in the Design-Build RFP.
4-5.2
Perform foundation and soils investigations, including sampling, testing, and evaluation,
with requirements and guidance set forth in the IBC, UFC 3-250-01FA, UFC 3-260-02,
and UFC 3-220-01. In using the IBC, the terms owner, applicant, and building
official are synonymous with the Government. In addition, the following requirements
apply:
4-5.2.1
General.
Investigations and evaluations (including soil borings, test pits, ground penetrating radar
surveys, seismic refraction surveys, and electrical resistivity testing, laboratory testing)
must be in accordance with ASTM standards to the fullest practical extent. The
classification and investigation of the soil must be supervised by a registered
professional engineer. Where ASTM methods are not applicable, procedures and
apparatus used must be in accordance with generally accepted engineering practice.
4-5.2.2
The qualifications of the geotechnical testing laboratory and personnel must meet
ASTM D3740.
4-5.2.3
Field Testing.
Field testing for geotechnical investigation typically consists of soil borings and standard
penetration tests (SPT) or cone penetration tests (CPT). Conduct and provide the soil
borings, SPT, and CPT in accordance with ASTM D1452, ASTM D1586, and ASTM
D5778, respectively. For standard penetration testing, modify the ASTM D1586
procedure to make continuous standard penetration and sampling tests for the initial 13
feet (4 meters) of the boring. If the proposed facility will have a basement level, the
ASTM D1586 procedure must be modified to make continuous standard penetration
and sampling tests for the initial 13 feet (4 meters) of the boring below the proposed
basement floor elevation. During drilling, visually classify all soils in accordance with
ASTM D2488. If evidence is discovered indicating soil or groundwater contamination,
report it immediately to the Government. If soft cohesive materials are discovered
14
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
within 20 feet (6 meters) below the ground surface, take undisturbed samples for
laboratory testing. Undisturbed sampling and testing must be performed at the
discretion of the Geotechnical Engineer responsible for performing the investigation.
Perform other testing, such as percolation testing, seismic refraction surveys, and soil
resistivity testing, as required by the contract, or by the Contractors Geotechnical
Engineer or DOR in a Design-Build contract.
4-5.2.5
Use of Piezometers.
If drilling techniques are used that prevent the measurement of the water table levels,
provide at least two piezometers per drilling site to more accurately measure the depth
to the water table. Piezometers are required for storm water pond investigations.
Piezometers are not required if the ground water levels can be accurately measured
during drilling operations or there is good evidence that the water table is not within the
depth of the borings or zone of influence for the foundation or structure.
4-5.2.6
Seismic site class must be based on field testing for all projects.
For Design-Build projects, state in the RFP the seismic site class to be used for design.
This can be determined by the cognizant NAVFAC Geotechnical engineer. NAVFAC is
the ultimate authority on site class determination for design.
4-5.2.7
Laboratory.
The minimum laboratory testing must include grouping like samples, conducting a sieve
analysis and Atterberg Limits tests, and performing natural moisture content
determinations to effectively depict in-situ conditions. The field logs must be updated in
accordance with ASTM D2487. Other testing, such as California Bearing Ratio,
unconfined compressive strength, consolidation testing, triaxial testing, and potential
volume change in suspected expansive clay areas, must be performed as required by
the contract, or by the Contractors Geotechnical Engineer or DOR in a Design-Build
contract.
4-5.3
Geotechnical Report.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
compact disc (CD) or Digital Video Disc (DVD) in \1\a DWG/1/ compatible format
\1\/1/conforming to Chapter 12 in paragraph Drawings. Provide a CD or DVD with a
\1\/1/ PDF copy of geotechnical report and two (2) print copies of the report. The PDF
copy of the report must be produced directly from the reports authoring software. All
Geotechnical Reports must be signed by a registered Professional Engineer. For
archiving purposes, directly mail a PDF copy of the geotechnical report on CD or DVD
to one of the respective Echelon III command below for projects residing in their area of
responsibility.
NAVFAC Atlantic
Capital Improvements
Civil/Geotechnical Section
6506 Hampton Blvd.
Norfolk, VA 23508-1278
4-5.4
NAVFAC Pacific
Capital Improvements
Civil/Geotechnical Section
258 Makalapa Dr.
Pearl Harbor, HI 96860
Boring Logs.
Provide a scaled location plan, boring logs, ground water observations, laboratory data,
and boring log description notes on NAVFAC \1\drawings/1/ as indicated in Chapter 12.
Summarize the laboratory data in tables. No scanned boring logs will be accepted.
4-5.5
Discuss the facility under design and make recommendations for the foundation type.
Describe and specify the improvements that are required for shallow foundations, such
as compaction, removal and replacement, surcharging, and wick drains. Describe the
soil bearing capacity, anticipated settlements, seismic aspects, pile capacity, pile length,
pile type and special instructions such as jetting, pre-drilling and testing required.
Discuss earthwork associated with foundation design and construction or site
improvements, including settlement, liquefiable soils, expansive soils, slope instabilities
or near surface groundwater. The discussion must address existing conditions, studies,
or analysis performed, and recommendations for mitigation of the effects of these
conditions. Address dewatering, and sheeting/shoring considerations, in design and
construction, as applicable. If required by the \1\DOR/1/, state the pavement design
parameters and the pavement design. If the pavement design is to be completed by
others, provide design parameters determined from the subsurface investigation. If
multiple structures are being designed, address structures on an individual basis.
Discuss the site preparation and susceptibility to rain and construction equipment.
Discuss any soil conditions relating to potential concrete or piping corrosion and
recommendations to mitigate effects thereof.
4-5.6
16
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
4-6.1
Water flow testing of the existing water supply system(s) is required to determine the
capability of the available water supply to support the expected demands. Perform
testing in accordance with FM Global Property Loss Prevention Data Sheet 3-0.
Provide a fire protection water flow test report in the Basis of Design. Comply with UFC
3-600-10N (DRAFT).
4-6.2
Obtain information regarding the exterior fire alarm reporting system and the base mass
notification systems.
4-7
Provide Building Code and Life Safety Code Surveys in accordance with UFC 3-60010N (DRAFT).
4-8
ENVIRONMENTAL REQUIREMENTS.
Conduct surveys, information gathering and analytical testing required by the contract.
Provide in accordance with UFC 3-800-10N (DRAFT), which is a requirement, as
invoked by this FC.
17
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
18
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 5 DELIVERABLE: BASIS OF DESIGN
5-1
GENERAL REQUIREMENTS.
FORMAT.
Format the Basis of Design as an 8 x 11 inch (216 x 279 mm) document, organized
by Discipline. Provide a cover sheet identifying the document as the Basis of Design,
and include the submittal stage, the project title, the location, the A-E Contract or
Construction Contract number (Post-Award DB Contracts only); the eProjects Work
Order Number\1\/1/; the Firms name, the Command, or the Contractor name; and the
date. \1\Only use the Maximo number, in lieu of the eProjects Work Order Number, if
eProjects is not required for the project./1/
5-3
SUSTAINABILITY.
Provide a Sustainability section in the Basis of Design that summarizes how the design
will achieve the requirements for Guiding Principles, and Third Party Certification (TPC)
(where applicable) in accordance with UFC 1-200-02. The summary must state the
level of Guiding Principle compliance, and elaborate on the various requirements from
UFC 1-200-02. Provide narrative, the NAVFAC Sustainable Energy Data Record
Card/High Performance Sustainable Building (NSERDC/HPSB) Checklist, Third Party
Commissioning (TPC) Checklist (where applicable), and justification (where applicable).
\1\/1/The HPSB Checklist is the NAVFAC Sustainable Data Record Card (NSERDC).
Update at each phase of design. No variations or substitutions to the Checklist are
allowed without Government approval.
5-3.1
Provide for all projects in accordance with UFC 1-200-02. It is the responsibility of the
DOR to verify Guiding Principles Validation requirements, by including design
requirements in the contract documents and verifying construction submittals when
required by the contract. For each of the Guiding Principles Requirements that is not
attempted or achieved, provide narrative explaining how effects on the project for each
19
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Guiding Principle precludes achieving specific sustainability requirement or goal.
Provide analysis of particular requirement and level to which project is able to comply.
5-3.2
For projects requiring TPC Certification, project must also achieve all Guiding Principles
Validation (GPV) in accordance with UFC 1-200-02.
5-4
ANTITERRORISM (AT).
Provide an Antiterrorism (AT) section in the Basis of Design that summarizes how the
design complies with the DoD minimum AT standards in UFC 4-010-01 and the
applicable Geographic Combatant Commanders AT Construction Standards. As a
minimum, include the following in the summary:
Level of Protection
Note Identify explosive weights as explosive weight I, II, or III as described in UFC 4010-01, to avoid disclosure of FOUO information.
5-5
GEOTECHNICAL.
The Basis of Design (BOD) must include a paragraph briefly describing the geotechnical
investigation program, the recommendations for the site preparation, and the
recommendations for the building foundation and pavement design.
It is preferred that the geotechnical report be included in the BOD as an appendix.
However, the schedule may preclude the completion of the field investigation prior to
the submittal of the BOD. If this is the case, describe the assumed basis of design for
the foundations and pavement, and submit the geotechnical report as soon as possible,
and as acceptable to the Government.
20
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
5-6
CIVIL.
Identify the governing codes and criteria including federal and military handbooks being
used for the design. References may be noted in the related sections listed below.
Include reference titles and date of publications. Provide BOD with adequate narrative
to describe design logic and assumptions. Show adherence to scope of work.
5-6.1
Existing Conditions.
Demolition.
Discuss demolition relating to Civil issues only, typically 5 feet (1.5 m) outside of
building line. Identify all buildings slated to be demolished by building number.
Generally describe structure types (i.e. 1-story frame, 2-story block); include building
specifics under the Architectural BOD. Describe pavement to be demolished, including
existing pavement section. Describe underground and overhead utility demolition,
relocation, and abandonment. Describe other features to be removed (i.e. play
equipment or fencing).
21
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
5-6.3
Describe new building and its function with respect to civil issues, such as vehicle
ingress/egress and pedestrian movement. Address internal functions under
Architectural BOD. Describe pedestrian access. Identify number of parking spaces;
include stall and aisle widths. Describe handicap access in and around site, number
and size of handicap parking spaces. Identify physical security requirements, such as
intrusion detection provisions, fencing type and height, and lighting requirements. Also
identify antiterrorism standoff distance requirements for the specific site conditions.
Identify vehicle type expected on project site; note non-standard vehicle sizes and
weights. Identify design wheel loading. Define projected traffic volume. Define new
pavement types and sections. For airfield pavement, discuss design parameters,
including pavement use, loadings, design life adopted in design, design methodology to
be used, and availability of materials anticipated for construction, and possible impacts
construction may have on airfield operations, such as haul routes and closures. For
railroads and crane rail, state type of service for which rail track will be provided;
anticipated volume and type of traffic; the ruling grade and the maximum curvature.
Describe proposed type, source and thickness of ballast, weight of rail and source,
treatment and dimensions of ties. For small arms ranges, list expected weapons and
ammunition including the most powerful weapons/ammunition combination that the
design is based on. Discuss critical features such as impact berms (including height
and slope), side berms, firing lines, firing directions, target locations, bravo flag poles,
road gates, fencing, access roads, supporting facilities, and any other prominent
feature. Do not include the SDZ since this has nothing to do with the construction
project.
5-6.4
Water Supply.
State design parameters; include domestic and fire flow, residual pressure, and recent
flow test data. State anticipated demand. Fire flow requirements must be established
by the \1\DORs/1/ fire protection engineer. Describe water main and supply line sizes
and capacities. Identify connection points. Identify connection methods. Identify
whether existing infrastructure has capacity to support project. Identify requirements for
backflow protection and freeze protection. Identify needs for metering. Identify need for
booster pumps or pressure reducing valves. State number of new fire hydrants.
Coordinate with the \1\DORs/1/ fire protection engineer. Provide number of wells and
proposed pump rates.
5-6.5
Sanitary Sewer.
Describe waste stream and whether it is from domestic or industrial source. Include
sources of any hazardous substances. Identify design population, peak and average
flows. State whether sewer will be gravity or force main. Identify pre-treatment
requirements and solutions. State minimum pipe slopes and velocities. Identify special
installation requirements. State new pipe sizes and capacities. Identify pump station
type, wet/dry well, types of pumps, pump capacity and total dynamic head, horsepower,
telemetry requirements and compatibility with existing on-base systems, backup power
22
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
requirements, and assumed response time by Activity personnel. Consult Activity as to
whether existing system is operating at or near capacity. Discuss adequacy of existing
system to handle current and future flows.
Wastewater Treatment.
5-6.6
5-6.7
Identify factors such as receiving waters, classification (if applicable), storm frequency,
and C factors. Discuss adequacy of existing storm system and its effects on
downstream facilities and systems. Discuss whether existing system will require
upgrades. Identify use of collection system versus sheet flow. Describe materials and
pipe sizes. Describe how upstream flows that impact site will be handled.
Stormwater Management.
5-6.8
5-6.9
Identify total disturbed area acreage. Discuss erodibility of soil, devices or methods to
be used to control erosion and sediment losses, and protection devices at outfalls.
Discuss compliance with Activity, State, and local requirements.
5-6.10
Permits.
Identify the permits necessary for both construction and operation of facilities. Identify
fees associated with each permit. Submit PROD form with BOD.
5-7
STRUCTURAL.
Provide a narrative report on how the design concept satisfies the customers
requirements, meets criteria and is cost effective. Include statements on the following:
List a summary of the criteria upon which the structural design is based.
Including a statement of all loads: dead, live, wind, snow, earthquake and
any other significant load.
List all assumptions required for the structural design where the design
criteria is undefined, unclear, conflicting or unknown. State the basis of
the assumption made.
23
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
5-8
Provide fire protection design in accordance with the contract and UFC 3-600-10N
(DRAFT).
24
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 6 DELIVERABLE: CALCULATIONS
6-1
GENERAL REQUIREMENTS.
Submit design calculations required at each design stage in accordance with the
contract, the Core UFCs, and the additional Discipline requirements listed herein. If
another UFC adequately describes the requirement for a Disciplines deliverable, a
paragraph for that Discipline is not provided below.
Prepare calculations in metric units when metric design is required. Provide reference to
the source (Navy and non-Navy criteria used) to produce the calculations.
6-2
Provide the software program name, version and source used to produce each
computer output or report.
6-3
FORMAT.
Provide calculations in accordance with UFC 1-200-02 for life cycle cost analysis \1\/1/.
6-5
GEOTECHNICAL REQUIREMENTS.
The geotechnical calculations normally appear in the geotechnical report; however, they
may be in a separate package if another consultant other than the geotechnical
consultant prepares the calculations for foundations or pavement. The calculations
must indicate the loadings, capacities, the safety factors, and the text from which the
calculations were based for the foundation and pavements. Graphs and formulae must
be clearly indicated along with the derivation of curve slopes and data derived from the
laboratory testing.
6-6
CIVIL.
Provide design calculations for erosion and sediment control, stormwater drainage
system, stormwater management, pavement and utility systems. Calculations must be
25
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
legible, orderly and easily understood and checked by a registered practicing civil
engineer.
6-6.1
Comply with UFC 3-210-10. If the project footprint exceeds 5000 SF (464.5 SM) the
project must be documented on the \1\NAVFAC Low Impact Development (LID) Data
Card (NLIDDC)/1/, approved by the Governments civil reviewer who will document on
the eProjects LID tab. In-house design projects must be reviewed and approved by
either the civil engineers supervisor or the Civil Technical Discipline Coordinator (TDC).
The \1\NLIDDC is located/1/ at: \1\
http://www.wbdg.org/pdfs/NAVFAC_LID_Data_Card_v2.0.pdf/1/
For Navy and Marine Corps projects, comply with Navy LID Policy (commonly referred
to as the Penn Memo). The Navy LID policy sets a goal of no net increase in
stormwater and sediment or nutrient loading from major renovation projects and
construction projects. Major renovation projects are defined as having a storm water
component and exceeding $5 million and major construction projects are defined as
exceeding $750,000. If LID is not implemented to the METF as defined in UFC 3-21010, a waiver must be obtained from the Regional Engineer. Projects exceeding the
dollar values above must be documented on the \1\NLIDDC/1/ and approved by the
Governments civil reviewer, who will then document in the eProjects LID tab. In-house
design projects must be reviewed and approved by either the civil engineering
supervisor or the Civil Technical Discipline Coordinator (TDC). \1\NAVFAC Low Impact
Development (LID) Waiver Form is located at:
http://www.wbdg.org/docs/NAVFAC_LID_Waiver_Form_v3.doc
Coordinate waiver review and approval with Civil Technical Discipline Coordinator
(TDC).
6-7
STRUCTURAL REQUIREMENTS.
Provide calculations to support all items and details outlined on the drawings and
specifications. Include calculations for the main framing systems and all beams,
columns, walls, foundations, bracing, diaphragms, equipment supports, and component
inter-connections to provide a safe, stable efficient and cost-effective structural system,
considering all design loads and criteria. They must be legible, orderly and easily
understood and checked by a registered practicing structural engineer.
Also include the following:
Table of contents.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Materials: Include all materials used and their allowable stress limits, yield
strengths, type, grade, class or other applicable material properties.
6-7.1
Provide Calculations or test reports for the following systems demonstrating compliance
with applicable Antiterrorism (AT) requirements:
Note Identify explosive weights as explosive weight I, II, or III as described in UFC 4010-01, to avoid disclosure of sensitive information.
6-7.2
Design for lateral forces must include design calculations for wind, seismic, and other
potential loadings. The construction drawings must depict the governing design
elements base on both seismic and wind design requirements.
6-7.3
Provide input data, including loads, loading diagrams, node diagrams, and adequate
documentation to illustrate the design. The schematic models used for input must
show, as a minimum, nodes/joints, elements/members, materials/properties, and all
loadings, induced settlements/deflections, and a list of load combinations. Results must
27
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
include an output listing for maximum/minimum stresses/forces and deflections for each
element, and the restrictions for each loading case and combination. If required, submit
narratives. In addition, provide the following:
Submit graphical plots of structural models which must include, but not be
limited to, main structural elements, boundary conditions, loading
diagrams, and deflected shapes. Submit graphical plots with each
deliverable at each submittal stage. Provide in both native, editable format
and in PDF.
Provide calculations at the earliest possible stage in design, but no later than the Design
Development Submittal and as further required by Chapter 15 of this FC. Comply with
UFC 3-600-10N (DRAFT).
28
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 7 DELIVERABLE: DRAWINGS
7-1
GENERAL REQUIREMENTS.
Provide drawings in accordance with the Core UFCs, the contract, Chapter 12,
Electronic Design Deliverable (EDD) Format, and the additional Discipline requirements
herein, for every stage of design. If another UFC adequately describes the requirement
for a Disciplines deliverable, a paragraph for that Discipline is not provided below.
7-2
PRESENTATION.
DRAWING NUMBERS.
Request NAVFAC drawing numbers from the Governments Project Manager or the
Design Manager. Provide them with the following information:
1) The amount of numbers required;
2) The eProjects\1\/1/ Work Order Number, and
3) The project title. Request enough numbers (usually 10% more) that
additional sheets can be added if necessary.
/1/Only use the Maximo number, in lieu of eProjects Work Order Number, if eProjects is
not required for the project.\1\
7-4
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Do not use new for work in the contract. All work shown on the drawings
is considered new, unless indicated otherwise. Inconsistent use of new
throughout the drawings could mean that only some of the work is
required.
Do not use terms that are not biddable by the Contractor nor enforceable
by the Government, such as recondition, as directed, equal to, as
required, similar to, as necessary, as close as possible, repair,
match existing, or refurbish.
Some terms are only enforceable if quantities are shown on the drawings
or included in the specifications, such as as indicated, as shown,
specified herein, and as noted.
30
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
7-5
CIVIL DRAWINGS.
7-5.1
Cover Sheet, Drawing Index, Vicinity Map, Location Plan,
Abbreviations, Legend, and Notes, or First Civil Sheet.
If project is not a Civil Engineering lead, assure that the following items are coordinated
with the lead discipline responsible for creating cover sheet:
a) If General Development Maps (GDM) are used for the Vicinity and
Location Maps, edit for the specific project being designed. Ensure
street names, main gates, and the Public Works office of the base are
identified. Ensure that text is legible at the plotted scale and remove
extraneous lines.
b) The Vicinity Map must identify the Activity and have enough main
highway names and street names to allow an out-of-town contractor to
locate the work.
c) The Location Plan must allow the contractor to find the project on the
base. This is generally a good place to show laydown areas, haul
routes, any construction traffic routing restrictions, and off-site
benchmark locations. Provide an adequate amount of street names to
allow coordination between the Vicinity Map and the construction
plans.
d) In general, it is desirable to show the Vicinity Map and the location
Plan on the Cover Sheet along with the project title.
e) Coordinate with FEAD or ROICC, and Activity for laydown area.
f) Edit standard details, abbreviations, legends, and general notes for the
specific project being designed.
g) Provide a single Civil legend on one sheet (preferably sheet C-001).
h) Datum must be securely tied between project datum and local datum.
For projects near tidal waters, show datum sketch indicating project vertical datum and
relationship to range of tide and other important datum.
7-5.2
Demolition Plan.
31
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
b) Indicate the beginning and ending points of utility removals and
methods of plugging pipes (e.g. cap, brick & mortar). Show locations of
valves to be used for isolating work.
c) Show limit of pavement removal and pavement thickness.
d) Describe the existing items in detail with supplemental descriptions if
necessary. Indicate depth of pavements/bases to allow uniform
contractor bids.
e) Provide a sequence of demolition if necessary. Include any known
requirement for continuous operation and limited shutdown
requirements. These must be identified in the special scheduling
paragraphs of the specification.
f) Do not show any items that are being demolished with the current
project on subsequent Civil plan sheets.
g) Show locations of all erosion and sediment (E&S) control items and
add E&S notes. Show erosion control details on drawings or refer to
applicable details in the State Erosion and Sediment Control Handbook
or manual. Verify that the erosion control legend is edited, clear and
coordinated with the drawings.
h) Provide a Tree Protection Detail for existing trees, which are to be
preserved during construction. All trees are not amenable to the same
barrier fence application. Consult a Registered Landscape Architect or
State Certified Arborist. As a minimum, show a 4 foot (1.2 m)- high
safety-orange, plastic barrier fence with metal or 4 x 4 inch (101 x 101
mm) wood stakes at 8 foot (2.5 m) on center spacing, continuously
located around the trees drip-line, unless otherwise directed by a
certified arborist. If trees are in a group or cluster, use only one fence
to surround the entire cluster.
7-5.3
Site Plan.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
horizontal control point locations and descriptions. Use of coordinates
for layout purposes is discouraged, however their use may be
considered on a case-by-case basis. Contact Governments Civil
Reviewer for approval of coordinate layout prior to project submittal.
d) Show areas requiring pavement patching, repairs and new pavement.
Provide pavement jointing plans for rigid pavements. Include separate
pavement marking plans for airfield projects.
e) Eliminate extraneous items that may congest the drawing (e.g.
contours, elevations) and detract from the layout information.
f) Show locations of any additional E&S control items not already
included on the Demolition Plan. Coordinate with E&S notes, details,
and legend.
g) Indicate all trees and plant material to remain.
h) Provide statement concerning location of soil borings and soil
information.
7-5.4
7-5.5
33
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
a) Show profiles where needed for clarity and to avoid potential conflicts.
Discuss profile requirements with Governments Civil Reviewer.
b) Indicate structure tops, pipe invert elevations, slopes, lengths, and
diameters of all new gravity lines.
c) Coordinate structure numbers with plan sheets.
d) Reference the plan sheets where pipes/structures are shown.
e) Show and label existing and new surface materials, such as concrete
pads, curbs, and roads, traversed by the new lines. Accurately show
depth of existing pavements.
f) Show and label all crossing utility lines, both existing and new.
g) If depths of existing utilities are unknown, indicate the horizontal
location of the utility and indicate the vertical location with a line
representing the anticipated range of elevations where the utility will be
found in the field. Indicate the method of new utility installation routing
above or below conflicts, (i.e. concrete encasement or pressure pipe).
7-5.6
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
concrete pavements. Consider if these slopes are maintainable for the
service life of the facility.
g) Coordinate with the Landscaping Plans (L sheets) to prevent new
plantings from blocking site drainage.
h) Provide numbers (or letters) for each drainage structure so that plans
and profiles are easily coordinated.
i) Provide erosion and sediment control details.
7-5.7
GEOTECHNICAL DRAWINGS.
Provide structural drawings that sufficiently detail all structural work. The drawings must
contain a set of Structural Notes in accordance with UFC 1-200-01, and which provide
critical reference information for future building modifications or evaluations. As a
minimum, note Design Criteria, Design Standard References, General Construction
requirements, and the following:
Loads: Provide loading information and identify source for all listed loads.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
rest design pressures, the coefficient of friction and the sub-grade
modulus. Indicate if a site specific design spectrum is to be used in the
design and give the site class in accordance with the seismic design
criteria used.
Materials: Clearly define the types, grades and properties of materials for
each structural element and system.
Marine Structures: List mooring berthing and deck loads for marine
structures, including ship classes (e.g. DDG 51, CG 47, CVN) with
associated displacements.
7-8
DRAWINGS PREPARED FOR OTHER GOVERNMENT
ORGANIZATIONS.
Approval of drawings for projects of other Government organizations or approval of
modifications or revisions of drawings prepared by such organizations is required as
follows:
When NAVFAC drawings are prepared for construction projects for other
Government departments or agencies, submit fully developed concept
designs to the appropriate departments or agencies for formal approval.
36
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 8 DELIVERABLE: SPECIFICATIONS
8-1
GENERAL REQUIREMENTS.
Provide specifications in accordance with UFC 1-200-01, the Core UFCs, UFC 1-30002, and Chapter 12. Provide specifications that are as brief as possible, definitive, and
free of ambiguities and omissions that may result in controversy and contractor claims
for additional compensation.
8-2
GUIDE SPECIFICATIONS.
Specifications offer criteria for materials, equipment, and test methods. Guide
specifications are documents that describe products and materials and the work
necessary to incorporate them into a construction project. A guide specification
facilitates the preparation of project specifications by standardizing products and
processes, and their order of presentation. DoD uses the Unified Facilities Guide
Specifications (UFGS) database, provided on the Whole Building Design Guide website
(http://www.wbdg.org), which is updated quarterly. Edit guide specifications to specific
project requirements for incorporation into the contract documents. Guide specification
and project specification sections describe the following in detail:
Quality of that product or system and methods used to ensure the quality,
including on-site and off-site testing,
Use Unified Facilities Guide Specifications (UFGS) for all projects, including DesignBuild. UFGS are available at the Whole Building Design Guide website at
http://dod.wbdg.org/. Tailor and modify the UFGS as necessary to suit the work
required by the specific project, including editing for metric or inch-pound. In addition,
modify and edit to reflect the latest proven technology, materials, and methods, for the
project.
37
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
There is only one current version of a guide specification at any time. The guide
specification with the latest revision date and change number automatically cancels
specifications of the same number with a previous date and change number.
8-2.2
Some Supported Commands have modified some of the UFGS for their region; these
are referred to as Regional Guide Specifications. Use Regional Guide Specifications
when sections are available by the Region and Activity for the project location, and as
required by the contract. Regional specifications are located on the Whole Building
Design Guide website at http://www.wbdg.org/ccb/browse_cat.php?o=3&c=43 and
where indicated in the contract.
Regional specifications are limited in number and scope to selected subjects particular
to a location and contain a majority of local requirements. Regional specifications are
used in the same way as the UFGS except that they are used only in the area of the
specific facility engineering command jurisdiction. Regional specifications are
numbered the same as the UFGS that has been used as a basis for the regional
specification, with the exception of a regional designation at the fifth level for
specifications in CSI MasterFormat 12; for example, in UFGS Section number, 01 13
30.00 22, 22 indicates the region. Assigned regional designations can be found with
the Regional specifications at http://www.wbdg.org/ccb/browse_cat.php?o=3&c=43.
8-2.3
Other guide specifications are only allowed as a basis for information when not
available in the UFGS. These developed specifications must be provided in UFGS
format and modified to meet requirements of UFC 1-300-02. Do not use NASA UFGS
specification sections (ends with 40 at the fifth level).
8-2.4
Unless specified otherwise in the contract, the order of precedence for selecting which
UFGS to start from, for CONUS jobs that require the use of the UFGS, is as follows:
1) Regional Guide Specifications (for the project location and where
sections are available).
2) UFGS, Navy only (UFGS with a 20 at the fifth level in CSI
MasterFormat 12).
3) UFGS (unified, no designator at the fifth level).
4) Other DoD UFGS (Army UFGS with .00 10 designation and modified
for Navy job)
5) Other Guide Specifications.
38
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
8-2.5
Download, use, and edit the most current UFGS database available from the Whole
Building Design Guide website, http://dod.wbdg.org/. Unless otherwise specified by the
contract, the version that is current at the official start of the Pre-Final design phase
must be used, and continue to be used, through Final design. Coordinate the version of
the UFGS database used with the Governments project manager, and report this date
to them.
8-3.2
\1\Modify and edit the guide specification to fit the project and to meet UFC
requirements. Follow the Notes to the Designer to make selections in the UFGS. Use
language and format in accordance with UFC 1-300-02. Delete portions of the guide
specification not included in the project design and scope./1/
Use guide specifications only as source documents, and do not reference them in
project specifications. Do not combine work covered by various UFGSs into one
section unless the project is small and work is of a minor nature, and the Government
Project Manager concurs.
8-3.2.1
Do not edit outside of the guide specifications bracketed selections for Geotechnical
and Civil UFGS sections in Division 32, without prior approval of the Government
project manager./1/
8-3.3
Provide plates, sketches, boring logs, and details on the drawings, and not in the
specifications.
8-3.4
Unrestricted Bidding.
Provide only the actual minimum needs of the Government in the specifications, and
describe the salient characteristics of materials and installation so as to encourage
maximum competition in bidding. Eliminate, insofar as possible, any restrictive features
that might limit acceptable offers to one supplier's product, or to the products of a
relatively few suppliers, and as required further by UFC 1-300-02. Do not list
39
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
manufacturers unless Contracting Officer approval is received in accordance with NFAS
6.304. Master UFGSs that list manufacturers must have a class justification on file.
8-3.5
Contract Parties.
FAR 52-236-21, Specifications and Drawings for Construction states: "Where 'as
shown, 'as indicated, 'as detailed, or words of similar import are used, the reference is
made to the drawings accompanying this contract unless stated otherwise."
8-4.1
For Design-Bid-Build contracts, the Contract Order of Precedence is defined in FAR 52236-21. In general, treat anything mentioned in the specifications but not shown on the
drawings or shown on the drawings but not included in the specifications, as if shown or
mentioned in both. In the case of discrepancies between the drawings and
specifications, the specifications take precedence.
8-4.2
For Design-Build, the Order of Precedence for RFP contracts is described in NFAS
Clause 5252.236-9312.
8-4.3
Coordination.
Coordinate the drawings and the specifications to ensure that all items depicted in the
drawings are covered by an appropriate specification section and that all specification
sections relate to items in the drawings.
8-5
Edit and provide UFGS sections in accordance with UFC 1-300-02, using SpecsIntact
software and UFGS format. SpecsIntact is the word processing software used to edit
the UFGS database. SpecsIntact software is available for download, free of charge, at
the SpecsIntact web site (http://specsintact.ksc.nasa.gov/).
8-6
8-6.1
Coversheet.
Include an overall cover sheet, for signature, with project specification package. Type in
the name and title of the principle DOR, who must sign in the Submitted By location.
40
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
The coversheet for electronic signature is available on the Whole Building Design Guide
at http://www.wbdg.org/ccb/browse_cat.php?c=226.
\1\Use the eProjects Work Order Number; only use the Maximo number on coversheet
and other project documents if eProjects is not required for the project./1/
8-6.2
Contract Documents.
The DOR prepares and provides the following documents to the Governments Project
Manager for the Contract Specialist. The Contract Specialist consolidates bidding and
contract requirements, along with the drawings and specifications, into a single
solicitation package.
8-6.2.1
Project Synopsis.
The scope in the project synopsis is taken from the Description of Work located in
UFGS Section 01 11 00. This description of work must be concise, and summarize the
location, facilities, and type of work involved. A sample synopsis is provided in
Appendix C. Provide the scope of work for the Synopsis at Pre-Final and Final in
accordance with contract requirements.
8-6.3
Format.
Provide specifications in UFGS format in accordance with UFC 1-300-02. Print job
headers with the job title, exactly as it appears on the drawings, justified to the left, and
with the eProjects Work Order Number \1\/1/ justified to the right. For Prefinal
submittals, follow the job title with (Prefinal).
8-6.4
Edit the UFGS Division 00 and 01, General Requirements Divisions to describe the
general project requirements of the project. Provide any additional requirements, of a
general nature, rather than of a technical nature, in General Requirements.
The UFGS sections in Table 8-1 are typically used in a Design-Bid-Build project Use
other Division One sections as required, depending on the scope of the project, or as
41
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
required by the Contract. Omit UFGS Document 00 22 13.00 20 from the Table of
Contents, and provide separately in the submittal package with the PIF. Provide UFGS
Document 00 01 15 as part of the specifications package, or separately, in accordance
with Contract requirements.
Table 8-1 Commonly Used DBB UFGS Division 00 and 01 Sections
UFGS Number
TITLE
00 01 15
01 11 00
01 14 00
01 20 00.00 20
01 30 00
01 32 17.00 20
01 33 00
01 33 29
01 35 26
\1\01 42 00
01 45 00.00 20
01 50 00
01 57 19.00 20
01 57 19.01 20
01 58 00
\1\/1/
01 78 00
01 78 23
01 78 24.00 20
8-6.5
CLOSEOUT SUBMITTALS
OPERATION AND MAINTENANCE DATA
FACILITY ELECTRONIC OPERATION MAINTENANCE AND
SUPPORT INFORMATION (eOMSI) (attach Facility Data Workbook)
Design-Build RFP.
For Part 2, General Requirements, of the six part Design-Build RFP, use the UFGS
sections provided in Part Two of the Whole Building Design Guide, NAVFAC DesignBuild master, as appropriate, available at the following location:
http://www.wbdg.org/ndbm. Table 8-2 shows commonly used Design-Build RFP Part
Two UFGS section.
42
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Table 8-2 Commonly Used DB RFP PART Two UFGS Division 01 Sections
UFGS Number
TITLE
01 14 00.05 20
WORK RESTRICTIONS FOR DESIGN-BUILD
01 20 00.05 20
PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01 30 00.05 20
ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD
01 31 19.05 20
POST AWARD MEETINGS
\1\/1/01 32 17.05 20 \1\COST-LOADED \1\NETWORK ANALYSIS SCHEDULES (NAS)
FOR DESIGN-BUILD
01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES
01 33 29.05 20
\1\SUSTAINABILTY REPORTING/1/ FOR DESIGN-BUILD
01 35 13.05 20
SPECIAL PROJECT PROCEDURES FOR DESIGN-BUILD
01 35 26.05 20
GOVERNMENTAL SAFETY REQUIREMENTS FOR DESIGNBUILD
01 45 00.05 20
DESIGN AND CONSTRUCTION QUALITY CONTROL
01 50 00.05 20
TEMPORARY FACILITIES AND CONTROLS FOR DESIGNBUILD
01 57 19.00 20
TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
\1\01 74 19.05 20
CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
FOR DESIGN-BUILD/1/
01 78 23
OPERATION AND MAINTENANCE DATA
01 78 24.00 20
FACILITY ELECTRONIC OPERATION MAINTENANCE AND
SUPPORT INFORMATION (eOMSI)
Include within Division 01, a section instructing the project team and stakeholders to use
an integrated design process throughout the planning, design and delivery stages. The
MOU Technical Guidance for the integrated design process is available from the WBDG
web site (http://www.wbdg.org/references/mou.php). Include applicable references to
the MOU Technical Guidance throughout project documentation.
8-6.6
Project Reports.
Design-Bid-Build.
43
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Provide and attach reports to the end of the appropriate UFGS specification section; i.e.
provide the asbestos report at the end of UFGS 02 82 16.00 20, Engineering Control of
Asbestos Containing Materials.
8-6.6.2
Design-Build.
Design-Bid-Build Parts.
In Part A, provide one General Requirements (Division 01) specification for the entire
package. This Division 01 must be edited and accurate for all of the combined projects.
The header in Part A must list the titles of each project, justified to the left, and the
corresponding eProjects Work Order Number \1\/1/ number, for each project, justified to
the right. Example is provided in Figure 8-1.
Part B consists of the technical specifications (Divisions 02-49) for the first project, and
Part C consists of the technical specifications for the second project. Add additional
parts depending on the number of projects being combined. Provide a Divider, a Table
of Contents, and the technical specification sections. The header in each part must
contain only the title of that Project, and the corresponding eProjects Work Order
Number, for that project. An example is provided in Figure 8-1.
8-6.7.2
Design-Build Parts.
Part A consists of the General Requirements Division (Division 01), Part B consists of
the RFP (Parts 3-6) for the first project, and Part C consists of the RFP for the second
project. Add additional parts depending on the number of projects being combined.
Provide a Divider, a Table of Contents, and the RFP sections (Parts 3-6). The header
in each part must contain only the title of that Project, and the corresponding eProjects
Work Order Number, for that project.
For RFPs in which Parts are shared, such as Part 2, Part 4, and Part 5, projects may
be combined by simply using a Part 3 for each project, distinguished by the cover page
and title, and inserted in Part 3; and a Part 6 for each project, distinguished by the title,
and inserted in Part 6. In this case, parts A, B, and C dividers may not be required.
Reflect the layout in the overall Table of Contents.
8-6.7.3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
not combine the General Requirements (Division 01) of these two different types of
projects. An example is provided in Figure 8-2.
8-6.7.4
Coversheet.
Provide one overall coversheet for signature. The coversheet must contain all of the
eProjects Work Order Numbers. Contact the Government for which Work Order
Number to use first as the primary. Also include all project titles, and if different
Designers of Record prepared the RFP or specification, the information of each DOR
firm or agency. Be careful not to change the location of the electronic signature portlets
when adding information to the coversheet.
8-6.7.5
List of Drawings.
Provide UFGS 00 01 15, List of Drawings, listing all of the drawings in the entire
package. Group drawing lists by Project.
8-6.7.6
Table of Contents.
Provide a single, overall Table of Contents, listing each Part and the sections or
documents in each Part. Note that SpecsIntact uses Courier New (10 pt) as the default
font. Use this font to generate the Table of Contents and any other documents in Word.
A sample Table of Contents is provided in Figure 8-1 and Figure 8-2.
8-6.7.7
Submittal Registers.
Provide submittal registers for each Part at the end of UFGS 01 33 00, Submittal
Procedures (for DBB) or UFGS 01 33 00.05 20, Construction Submittal Procedures (for
DB). Separate the submittal register for each part with a Divider; for example,
bookmark Part A: Submittal Register (for Division 01 only), Part B: Submittal
Register, and Part C Submittal Register, within the PDF package.
45
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Figure 8-1 Sample Table of Contents for Combined DBB Projects
GATE 5 SECURITY IMPROVEMENTS, NSA NORFOLK
SECURITY IMPROVEMENTS, GATE 10, NAS OCEANA
222088
235341
LIST OF DRAWINGS
11
14
20
30
32
33
00
00
00.00 20
00
17.00 20
00
01
01
01
01
01
01
01
01
01
01
01
33
35
45
50
57
57
57
58
78
78
78
29
26
00.00
00
19.00
19.01
19.02
00
00
23
24.00
20
20
20
20
20
SUMMARY OF WORK
WORK RESTRICTIONS
PRICE AND PAYMENT PROCEDURES
ADMINISTRATIVE REQUIREMENTS
COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
SUBMITTAL PROCEDURES
SUBMITTAL REGISTER PART A
SUBMITTAL REGISTER PART B
SUBMITTAL REGISTER PART C
SUSTAINABILITY REPORTING
GOVERNMENTAL SAFETY REQUIREMENTS
QUALITY CONTROL
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
TEMPORARY ENVIRONMENTAL CONTROLS
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS FOR GATE 5
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS FOR GATE 10
PROJECT IDENTIFICATION
CLOSEOUT SUBMITTALS
OPERATION AND MAINTENANCE DATA
FACILITY ELECTRONIC OPERATION MAINTANANCE AND SUPPORT
OPERATION INFORMATION (eOMSI)
DEMOLITION
DIVISION 26 ELECTRICAL
26 08 00
26 32 13.00 20
DIVISION 31 EARTHWORK
31 00 00
EARTHWORK
46
222088)
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
DIVISION 34 TRANSPORTATION
34 71 13.19
-- End of Part B --
PART C: SECURITY IMPROVEMENTS GATE 10, NAS OCEANA, VIRGINIA BEACH, VA (WON
235341)
DIVISION 02 - SITE WORK
02 41 00
DEMOLITION
DIVISION 31 EARTHWORK
31 23 00.00 20
DIVISION 08 - OPENINGS
08 11 13
08 71 00
-- End of Part C --
47
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Figure 8-2 Sample Combined DB and DBB Project
PART A:
11
14
20
30
32
33
33
35
45
50
57
57
57
58
78
78
00
00
00.00
00
17.00
00
29.05
26
00.00
00
19.00
19.01
19.02
00
00
23
20
20
20
20
20
20
20
SUMMARY OF WORK
WORK RESTRICTIONS
PRICE AND PAYMENT PROCEDURES
ADMINISTRATIVE REQUIREMENTS
NETWORK ANALYSIS SCHEDULES (NAS)
SUBMITTAL PROCEDURES
SUSTAINABILITY REPORTING FOR DESIGN-BUILD
GOVERNMENTAL SAFETY REQUIREMENTS
QUALITY CONTROL
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
TEMPORARY ENVIRONMENTAL CONTROLS
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS FOR GATE 5
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS FOR GATE 10
PROJECT IDENTIFICATION
CLOSEOUT SUBMITTALS
OPERATION AND MAINTENANCE DATA
48
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 9 DELIVERABLE: COST ESTIMATES
9-1
GENERAL REQUIREMENTS.
Provide cost estimates at each submittal stage as required \1\by and in accordance with
the NAVFAC Cost Engineering Policy and Procedures unless specifically indicated
otherwise in the contract documents/1/. NAVFAC standard Cost Engineering practices
are as defined by UFC 3-701-01, UFC 3-730-01, and UFC 3-740-05, as modified by the
requirements of NAVFAC Cost Engineering Policy and Procedures. In cases of conflict
between any of these documents, the NAVFAC Cost Engineering Policy and
Procedures guidance governs.
9-2
9-2.1
Detailed cost estimates, when required by contract for projects over $500,000, must be
prepared using SUCCESS Estimator (SUCCESS). The acceptable SUCCESS
software version must be compatible with that in use by NAVFAC. While standard
NAVFAC SUCCESS Templates \1\and reports/1/ are available free of charge at
http://www.uscost.net/CostEngineering/index.htm, the AE is responsible for purchase of
the software and databases. Comply with the NAVFAC Cost Engineering Policy and
Procedures for detailed cost estimate requirements for NAVFAC.
9-2.2
Prepare Parametric cost estimates as required by the contract using NAVFAC approved
software. PACES (PArametric Cost Estimating System) is an application utilized by
NAVFAC that was developed specifically for developing DOD and commercial
parametric estimates. \1\/1/Comply with the NAVFAC Cost Engineering Policy and
Procedures for Parametric cost estimate requirements for NAVFAC.
49
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
50
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 10 DELIVERABLE: CONTRACTING REQUIREMENTS
10-1
GENERAL REQUIREMENTS.
The Contract Specialist incorporates Contract Line Items (CLINs) from the information
provided in the Project Information Form (PIF) and Document 00 22 13.00 20,
Supplementary Instructions to Offerors. Provide and submit the PIF and UFGS
Document 00 22 13.00 20 in Microsoft Word or Adobe PDF format, to the Government
Project Manager who will provide it to the Contracting Specialist.
10-2
Prepare and provide a Project Information Form (PIF); attach the completed UFGS
Document 00 22 13.00 20 to it. The PIF communicates to the Contract Specialist which
contract clauses to include in the solicitation. The Government representative forwards
the PIF to the Contracting Specialist to prepare the contract clauses for the solicitation.
A downloadable version of the PIF is available at
http://www.wbdg.org/ccb/browse_cat.php?c=44.
10-3
SELECTION OF CLINS.
The Base Contract Line Item must provide a complete and usable facility (primary
facility, supporting facilities, and design in accordance with previous paragraph). Option
items and additive items must be able to be logically separated from the project without
rendering the facility unusable. Intention is for the Base CLIN, together with all the
contract line items, to provide the maximum, usable facility within the funds available.
Do not use Additive and Option items in the same contract; use one or the other.
Additive items are only allowed for sealed bids; do not use unless allowed by
Contracting Officer.
Use multiple SUB-CLINs for cost breakdown of facilities and site, and unit prices. Use
multiple CLINS for multiple funding sources (such as when combining one or more
projects into one contract package), and option or additive line items. Provide separate
SUB-CLINs for 1) Each facility (as indicated by the Category Code), 2) The total project
supporting facility (utility) cost (outside the five foot (1.5 m) line, and 3) Design Fee (if a
Design-Build project). The number of items and the estimated cost per item depends
upon the nature of the project. Provide no more than four contract line items (base
item, plus three), unless specifically approved by the Contracting Officer. Each
estimated option or additive item should tend to approximate 2% to 10% of the
estimated base item.
10-4
Options and Additives can change up to award of the contract. Do not indicate Contract
Line Items on the drawings, or reference anywhere in the specifications, unless
approved by the Government, who may allow only if a description of the line item in
schedule does not adequately describe the work. Samples of Document 00 22 13.00
20 are provided in Appendix C.
51
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Do not use the term alternate to represent line items. Do not use terms, such as base
item to indicate items in the primary contract line item.
10-5
OPTION ITEMS.
When different funding sources are used, or when funding is not available to cover
certain portions of the work at the time of proposal opening, but there exists a high
probability of attaining the funding in the near future, option items provide a means to
separate the funding sources, or to obtain and hold competitive prices for future award
of items of work. Typically, the price for the option item(s) is added to the base item
price to determine the low offer. Options need not be listed in a particular order. They
are executed individually at the Governments discretion. A time limit is given in the
contract documents for the Governments right to execute each option. Use of options
in construction contracts must be approved by the Contracting Officer prior to
advertisement.
10-6
ADDITIVE ITEMS.
Since additive line items are only allowed in sealed bid, do not use these unless allowed
by the Contracting Officer. If used, arrange additive items such that the most essential
portion of the work is added first. Arrange succeeding items in decreasing importance.
During evaluation of the offers, additive items are added to the base item in the order
listed. As each additive item is added, a new bid price is computed and compared to
the available funds. As additive items are determined to be within the funds available
they are added to the Offerors bid price. If they are not within the funds available, they
are skipped. Each additive item must be independent of the others.
10-7
DEDUCTIVE ITEMS.
Do not use deductive items. The base contract line item must contain the minimum
requirements of the contract. Using deductive items implies that the project is designed
above those minimum requirements. Use Options instead.
10-8
Planned Modifications are changes to the contract that the Government can only award
after the initial award of the contract, due to the nature of the work. Award time of a
planned modification is measured from construction completion date (usually 6 months
prior to completion), rather than award date. This differentiates them from Option Items.
Planned funding for Furniture, Fixtures & Equipment (FF&E) is from a different source
than the Base Contract Line Item. Therefore, provide a separate CLIN for the purchase
and installation coordination of all FF&E; designate it as a Planned Modification. The
Offeror must propose a Handling and Administration (HAR) not to exceed 5% within this
CLIN which will be applied to the final FF&E package amount at modification award.
HAR is limited to 5% for NAVFAC in accordance with NAVFAC Furniture, Fixtures &
Equipment (FF&E) Contracting Guide for Design-Build Construction Projects, which is
also valid for Design-Bid-Build Projects by Amendment, and available for download by
52
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
NAVFAC employees at
\1\https://hub.navfac.navy.mil:443/webcenter/content/conn/WebCenterSpacesucm/path/Enterprise%20Libraries/aq/Legacy%20%28Will%20Be%20Deleted%29/Files/
AQ_HI/9---9648628bc9974c17910abfe04400144f414f26?lve/1/.
10-9
SYNOPSIS.
Provide a brief scope for the project synopsis, which is used in solicitation of bids by the
Government. Describe facility in terms of square footage (or square meters), height
(e.g. 2-story). A sample of scope and Synopsis is provided in Appendix C.
53
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
54
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 11 DELIVERABLE: DESIGN-BUILD REQUEST FOR PROPOSAL (RFP)
11-1
GENERAL REQUIREMENTS.
Requirements for preparation of RFP are also provided in Chapter 12, Electronic Design
Deliverables (EDD) Format.
11-2
1391 Documentation
Funding Documents
User Requirements
55
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
11-3
DESIGN-BUILD REQUEST FOR PROPOSAL WEBSITE, FORMAT,
AND DOCUMENTS.
Guidance on preparing the RFP for Design-Build projects and Design-Build Template
documents are available on the NAVFAC Design-Build Master web site
(http://www.wbdg.org/ndbm). This site is intended to (1) familiarize those new to the
NAVFAC Design-Build process with the RFP format and typical RFP specification
sections and (2) allow those preparing a Design-Build RFP to download the current and
archived electronic documents. The Design-Build RFP web site is organized using links
to major components of the Design-Build RFP, including:
Design Guidance.
Model RFP Templates - The Model RFP Templates use the Standard
Template as its foundation. Each Model Template modifies the Standard
Template to suit a particular building type. These Models are an
advanced starting point toward creating an RFP, however they do require
coordination with User and facility requirements to properly define the final
RFP. The building type templates in the Design-Build Master Website are:
o Armory
o Child Development Centers
o Dining Facility
o Entry Control Facility
o Fire Station
o Fitness Center
o Hangar
o Magazine
o Marine Corp BEQ
o Market Style BEQ
Small Project Template (SPT): The SPT is a scaled down version of the
Standard Template to be used on projects of low-complexity and a limited
56
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
number of construction trades. SPT projects utilize routine designs with
limited plans & specifications and fit within monetary thresholds.
o A tool located with the SPT at web link: \1\
http://www.wbdg.org/ndbm/pdfs/decision_guidance_navfac_spdb.pdf
/1/ includes a table Decision Guidance for Use of Small Project
Design-Build Process to provide guidance in the application of the
SPT.
11-3.1
RFP Format.
The RFP must include all six RFP Parts indicated below unless they are not applicable
to the project. The typical facility project will have information in every RFP Part, with
the possible exception of RFP Part Five, Prescriptive Specifications. Typically, Part
One is not prepared by the RFP developer, but is provided by the NAVFAC Acquisition
office after RFP Parts Two through Six have been completed by the RFP developer.
The RFP developer is required to provide certain information such as the Project
Information Form (PIF) for the NAVFAC Acquisition office to properly prepare the RFP
Part One. Verify with the NAVFAC Facility Engineering Command, what provisions are
necessary to allow for the RFP Part One to be integrated into the RFP.
The DB Templates utilize different types of information in different Parts of the RFP.
Therefore, there are different information structures employed to organize the
information in the different RFP Parts. The following list indicates the type of
information and information structures are used in the RFP Parts:
Part One includes the Proposal Form and Documents and specifies the
contractual requirements.
o This Part uses the Standard Procurement System documents that are
organized using the CSI Masterformat.
Part Five contains any Prescriptive Specifications required for the DesignBuild RFP.
o This Part uses CSI Masterformat.
57
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
11-3.2
Refer to Chapter 8 for guidance, when multiple RFPs are combined into one solicitation
package.
11-4.2
Provide and complete the PIF for Prefinal and Final submittals. Refer to Chapter 8 for
further PIF requirements.
11-4.3
11-4.3.1
Usually, all Guiding Principles are required in the RFP. Occasionally, the RFP Preparer
may have enough information at the RFP stage to determine some Guiding Principles
are unobtainable. For each of the Guiding Principles Requirements that is not attempted
or achieved, provide narrative explaining how effects on the project for each Guiding
Principle precludes achieving specific sustainability requirement or goal. Provide
analysis of particular requirement and level to which project is able to comply in
accordance with Chapter 5.
11-4.3.2
When the project requires design commissioning services, incorporate Owner Project
Requirements (OPR), and any other documentation related to commissioning effort into
RFP.
58
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
11-5
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
a) RFP Part 6 Table of Contents
(1) Attachments (bookmark first page of each attachment)
11-6
DB DESIGN SUBMITTALS.
Because the DB projects require design and construction submittals, the submittals are
more complex than Design-Bid-Build. The DB process utilizes the RFP and the UFCs
to define design submittals and the RFP and the UFGS to define construction
submittals.
11-7.1
Because the DB submittals are spread into different documents, the preparers of DB
submittals are required to refer to multiple locations to obtain the complete submittal
requirement. The design and construction requirements are found in the six major
locations designated in the following table:
Table 11-1 Design and Construction Submittal Summary
NO
1
B. UFGS 01 33 00.05 20
Construction Submittal
Procedures
C. UFGS 01 33 10.05 20
Design Submittal Procedures
Engineering System
Requirements (ESR)
Performance Technical
Specification (PTS)
4.
5.
2.
3.
60
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
6.
Procedures
Discipline Specific UFCs
(Arch, Struct, Civil, Geotech,
Mech, Elect, Fire Protection,
Force Protection AntiTerrorism)
11-7.2
The RFP DB submittals are organized to allow the RFP editor the flexibility to evaluate
the project needs, determine the availability of Government resources to review
submittals, and modify the submittal approval requirements to suite the project. The
following Government approvals are built into the RFP Part Two DB Templates but may
need input from the RFP editor to tailor the submittal to the project;
a) RFP Part Two, UFGS 01 33 00.05 20, Submittals Reserved for
Government Approval - all RFP Part Two UFGS section submittals
denoted with a G submittal action code.
b) RFP Part Two, UFGS 01 33 10.05 20, Government Approving
Authority Government approves all design submittals.
c) RFP Part Two, UFGS 01 33 10.05 20, Exception to Contractor
Construction Actions Identifies certain Government design
submittals approvals that have to be accomplished before construction
related to that design submittal can begin.
d) RFP Part Two, UFGS 01 33 10.05 20, Design Documents, and UFGS
01 33 00.05 20, Contractor Reviewing, Certifying, Approving Authority Government identified construction submittals required to be
incorporated in the design submittals. DOR approval of identified
construction submittals precedes Government approval of associated
design submittals.
e) RFP Part Two, UFGS 01 33 00.05 20, Submittals Reserved for
Government Approval - Construction submittals reserved for
Government approval. The approval of these identified construction
submittals prevents the contractor from beginning construction on that
portion of the work until Government approval is obtained.
11-7.2.1
Surveillance Submittals.
The Government requires the contractors DOR to approve most of the construction
submittals; however, the RFP identifies certain construction submittals for Government
surveillance. Government surveillance does not prevent the contractor from proceeding
with construction but allows the Government a chance to confirm the submittal
approvals of the DOR. Surveillance of construction submittals are built into the DB
Template at the following location:
61
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
RFP Part Two, UFGS 01 33 00.05 20, Submittals Reserved for Government
Surveillance - Construction Submittals Reserved for Government surveillance.
11-7.2.2
62
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 12 ELECTRONIC DESIGN DELIVERABLES (EDD) FORMAT
12-1
SUMMARY.
This Chapter sets the policy for NAVFAC compliance with DoD and Navy policy for
paperless acquisition systems. The DoD requires implementation of electronic bid
solicitation at all NAVFAC components for all construction projects. These Electronic
Design Deliverables (EDD) requirements provide NAVFAC specific format guidance.
Regardless of acquisition method, all projects must follow these EDD requirements. DB
RFP submittals follow the requirements for the phase of design in the following
paragraphs.
12-2
\1\Contract Drawing
source/1/ files
\1\Record Drawings/1/
\1\Contract Drawings/1/
Shop Drawings/transmittals
\1\/1/Specifications or RFP
Submittal Register
Calculations
Cost Estimate
Basis of Design
\1\Design Model*/1/
\1\Record Model*/1/
63
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3
12-3.1
Specifications.
From the SpecsIntact Job File, provide the following source files:
Submittal Register. Printdata does not have to be provided.
12-3.1.2
Pulldata and
Develop RFP and Part 2 specifications in accordance with Chapter 11 of this FC.
If a program other than SpecsIntact is allowed to be used, all original source data must
be provided as follows:
12-3.2
\1\\2\Electronic Operation and Maintenance Support Information
(eOMSI)/2/ Facility Data Workbook (FDW).
\2\Provide the /2/Excel workbook, which contains the Model & Facility Data Matrix tab
(used to \2\select/2/ Mastersystems, Systems and Subsystems included in the design).
Use the original eOMSI FDW source file\2\, as referenced in Appendix A, for each
project./2/
Complete the eOMSI FDW in accordance with the Instructions tab of the eOMSI
FDW./1/
12-3.3
Drawings.
12-3.3.1
\1\Drawing Definitions.
12-3.3.2
Produce all source drawings using vector based Computer Aided Design (CAD)
software. Provide all source drawing files in native DWG format meeting the following
requirements.
12-3.3.2.1
64
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
The native DWG CAD files (i.e. plans, elevations, sections, details) created by the DOR
for the project. The Contract Drawing Source Files are not the legal record of the
project Design.
12-3.3.2.2
Contract Drawings.
The PDF files created from the Contract Drawing Source Files that represent the scope
of the projects. The Contract Drawings are the legal record of project Design which are
awarded to the construction contractor (KTR).
12-3.3.2.3
As-Built Drawings.
The hard copy prints of the Contract Drawings marked up by the KTR (as required by
the project specifications) to represent approved changes to the Contract Drawings.
12-3.3.2.4
The Contract Drawing Source Files edited by the KTR or DOR (depending on contract
requirements) to reflect the changes shown on the approved As-Built Drawings.
Prepare Record Drawing Source Files as described in this Chapter, Record Drawing
Preparation. Record Drawing Source Files are not a legal record of the Project.
12-3.3.2.5
Record Drawings.
The PDF files created from the Record Drawing Source Files that represent the final
installed condition of the project. Prepare the project Record Drawings as described in
this Chapter, Record Drawing Preparation. The Record Drawings are the legal record
of the completed project.
12-3.3.3
Drawing Progression
65
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Contract
Drawing
Source Files
(DWG)
CONSTRUCTION
POST CONSTRUCTION
Contract Drawings
(PDF)
PRINT
To
PDF
MARKUP
Contract
Drawings
KTR
DOR
DESIGN
As-Built
Drawings
(Hardcopy)
UPDATE
Contract
Drawing
Source Files
Record
Drawing
Source Files
(DWG)
PRINT
To
PDF
Record Drawings
(PDF)
KTR
DESIGN
PRINT
To
PDF
MARKUP
Contract
Drawings
UPDATE
Contract
Drawing
Source Files
Contract
Drawing
Source Files
(DWG)
CONSTRUCTION
PRINT
To
PDF
Contract Drawings
(PDF)
MARKUP
Contract
Drawings
As-Built
Drawings
(Hardcopy)
POST CONSTRUCTION
UPDATE
Contract
Drawing
Source Files
Record
Drawing
Source Files
(DWG)
PRINT
To
PDF
Record Drawings
(PDF)
/1/
12-3.3.4
CAD Standards.
Comply with the DoD A/E/C CAD Standard latest version except as noted below. The
A/E/C CAD standard is available at https://cadbim.usace.army.mil/CAD or
66
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
http://www.wbdg.org/ccb/browse_org.php?o=65 . In cases where the DoD A/E/C CAD
Standard version changes after a project has commenced, the project PM must be
consulted prior to adoption and integration of the newer standard into the drawing
\1\source/1/ files.
In cases where the DoD A/E/C CAD Standard does not provide guidance for (or
reference to) a specific CAD Standard element, refer to the referenced National CAD
Standards (NCS) document identified in the DoD A/E/C CAD Standard for guidance. In
all cases, the project PM must be consulted.
12-3.3.4.1
All sheet drawings must use the NAVFAC standard title block (border sheet). Provide all
sheet drawings in ANSI D (22 x 34 inches) size format for projects using imperial units.
Provide all sheet drawings in ISO A1 (594 x 841 mm) for projects using metric units
(ANSI D is assumed in other parts of this FC, but modify and scale as appropriate if ISO
A1 is used). See this chapters paragraph NAVFAC Supported EDD Standard
Components.
All \1\source/1/ drawings must contain only (1) one plotted sheet. \1\Drawing source/1/
files which contain more than one sheet will be rejected with the following exceptions:
Civil Sheet Files which the entirety of the project site cannot be legibly
shown on a single sheet.
Plan Sheet Files which the entirety of the project plan cannot be legibly
shown on a single sheet at 1/8 = 1 0 (1 = 100) scale.
In both cases consult with the project PM prior to developing sheet files to ensure
concurrence.
12-3.3.4.2
Plotting Guidelines.
Pen weights and colors must be in accordance with the NAVFAC pen table. NAVFAC
has developed a comprehensive pen table that utilizes the NCS 255-pen table as a
basis, but has added thinner lines and grayscale pens.
The NAVFAC pen tables are provided on the Whole Building Design Guide (WBDG)
(See the paragraph in this Chapter entitled, NAVFAC Supported EDD Standard
Components).
This pen table and corresponding line weights were established to be legible when
printed at half-size (11 x 17 inches (279 x 431 mm)), when the displayed text height is
1/16 inch (1.5 mm). All plotted files (hardcopy or PDF) must be monochrome, unless
color plots are specifically requested. Use color numbers assigned to black or
halftone only.
12-3.3.4.3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Use standard text heights for a plotted full-size drawing of 1/8 inch (3 mm) for typical
text, 1/4 inch (6 mm) for titles, and 1 inch (25mm) maximum for project titles on cover
sheets. For existing features on plotted full-size civil drawings, a minimum text height of
0.1 inch (2.5 mm) and an oblique angle of 12 degrees are allowed. Use a width factor
of 0.8 for all fonts that are not a part of the border sheet.
Use the ROMANS.SHX font file for all 1/8 inch (3 mm) or smaller text.
Use SWISS.TTF (Swis721 BT) font file for all 1/4 inch (6 mm) or larger
text.
In cases where a CAD program (see the paragraph in this chapter entitled, CAD
Standards) does not support the specified font styles/format, the use of alternate font
styles which match the specified fonts styles (both in the printed PDF and DWG files), is
permitted. In this case, it is required that the original source CAD files be provided in
addition to the DWG files. Notify the project PM prior to commencement of drawing
development with the following information:
Name, Version, File format and Vendor of CAD application being used
Translations.
Use File Naming Convention for all CAD Files as specified in the DoD AEC CAD
Standard except as noted below:
68
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
\1\Model Files
Facility Type Designator
Facility I.D. Designator (four characters*)
Job Number (eProjects Work Order No.)
Discipline Designator w/ Optional Level 2 Designator
Model File Type
User Definable (Optional**)
69
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3.3.4.6
=
=
=
=
=
=
=
=
=
=
=
=
=
=
AIRFIELD
BUILDING
DREDGE
DRYDOCK
BERTH
PIER
WET SLIP
PARKING LOT
ROAD
RAIL
FENCE
GATE
UTILITY
CRANE
SWTR
FWTR
PWTR
NGAS
STEM
SSWR
STRM
CAIR
POWR
COMM
CATV
SALT WATER
FRESH WATER
POTABLE WATER
NATURAL GAS
STEAM
SANITARY SEWER
STORM DRAIN
COMPRESSED AIR
POWER
COMMUNICATIONS
CABLE TV
12-3.3.5
=
=
=
=
=
=
=
=
=
=
=
CRAN
TRAK
=
=
Support files necessary for initializing, editing and plotting drawing files must be a
standard DWG or Microsoft Windows component (or they must be an integral and
standard component within the drawing file that require no third party custom utility or
program to use). Support files include, but are not limited to, line types, hatch patterns,
font styles, layer filters, display configurations and object styles. DWG files containing
objects, styles, or definitions that require any external files (e.g. SHX, LIN or LAY) to
initialize, operate and display properly will be rejected.
12-3.3.6
Cost Estimates.
Submit the contract cost estimate electronically in PDF and SUCCESS Estimator native
format (or as otherwise required by contract) with each submittal. Do not submit the
cost estimate on the project CD/DVD when provided. Make all cost estimating
submissions in accordance with the NAVFAC Cost Engineering Policy and Procedures
manual.
70
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3.4
Preliminary design includes all phases of Design except for the Final Design phase./1/
All source drawings and their associated PDFs must maintain a PRELIMINARY Not
For Construction stamp across the signature areas of the title block, until the actual
final design submittal. The NAVFAC D-size borders have this block on the default title
block displayed on layer G-ANNO-TTLB-PRLM. That layer must be frozen at the time
of creating the final deliverables. Except for the final submittal, indicate the submittal
phase designation, such as Prefinal, after the project title in the header and on the
coversheet of the specifications or the RFP.
12-3.5
12-3.5.1
Convert \1\source drawings/1/ to PDF format directly from their authoring software. Any
drawing (DWG) files larger than 17Mb must be broken into smaller files. Drawing PDF
file sizes must be a maximum of 17Mb with digital signatures. There is no limit on file
size for specifications or RFPs.
12-3.5.2
Combine all drawings into a single PDF file to facilitate ease of use unless file size
requires a multi-file submission. Do not combine multiple PDFs into a PDF package
prior to submission.
Bookmark PDF files and create visual thumbnails. Create a bookmark for the
beginning of each drawing discipline. Create a sub-bookmark for individual drawing
sheets. Bookmark wording must be as descriptive as practical (i.e., S-101 Foundation
Plan). When complete, the files must open to the bookmarks view as the default view
with the drawing sheets visible in fit to page magnification. Before submission to
NAVFAC, the professional must electronically sign and seal all sheets and appropriate
locations on the NAVFAC Title Block(s) (See paragraph NAVFAC Electronic Signature
Requirements.)
12-3.5.2.1
Multi-File Drawings.
If the PDF drawing set must be broken into several PDF sets due to the file size
restrictions given in the paragraph in this chapter entitled, Record Drawing
Preparation, every attempt should be made to package complete discipline sets (i.e.,
do not break-up discipline specific sheets).
12-3.5.3
Convert all specifications to PDF format directly from their authoring software. Combine
specification sections into a single PDF file to facilitate ease of use. Insert PDF of
attachments, such as Submittal Register and Environmental Forms, following the
respective UFGS section and Bookmark.
71
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3.5.3.1
12-3.5.4
Provide PDF of RFP following the requirements for Specifications in the paragraph in
this chapter entitled, Record Drawing File Naming, except add a bookmark for each
Part. Insert attachments following the same convention.
If the RFP contains drawings, provide a separate PDF for the RFP and the drawings.
Typically, reference drawings are provided in Part 6. This should be a separate file
because of the sheet size (11 x 17 inches (279 mm x 432 mm) or 22 x 34 inches (558.6
mm x 863.6 mm)), and will facilitate printing of this file separately by the Contractor.
72
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3.5.5
File naming convention for the final design drawings and specifications is:
Job Number (eProjects Work Order No.)
Document Type (dwg or spc)
Suffix to indicate multi-file solicitations
####### type xofx.pdf
12-3.5.6
73
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-3.6
Record Documents
12-3.6.1
Prepare Record Drawings in accordance with the drawing format guidelines of this
Chapter and the following additional requirements. Make all drawing changes in native
Drawing (*.DWG) format incorporating modifications and as-built conditions. Use the
CAD standards used for the \1\Contract Drawings Source Files/1/ for as-built
modifications and the following guidelines:
Make revisions on the original layer of the object being changed. Draw a
cloud around the changed portion and place it on layer Z-ANNO-REVC.
Place revision symbols and notes, including those placed in each
drawings revision block, on the Z-ANNO-REVS layer.
RECORD DRAWING
LETTER DATED
dd/mm/yy
Type in the signatures, initials, dates and SAT-TO information, in the title
block area on the contract drawings, as text on the record drawings. The
record drawings are not signed again by the DOR. The record drawings
do not have to be sealed, and the seal from the DOR is not transferred.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Produce a PDF file of each individual record drawing using a PDF page
size that corresponds to the original document sheet size. Provide a PDF
print resolution that results in clear detail of all drawing features.
Electronic signatures are not required.
12-3.6.2
/1/Source Documents.
In addition to the drawings, provide the specifications, cost estimate, design analysis,
reports, surveys, calculations, and any other contract documents utilized in creating the
design package (drawings, specifications, and cost estimate) on the CD or DVD disk(s)
as specified in this chapter, in paragraph, \1\Minimum Record Drawing Submittal
Requirements/1/.
12-3.6.3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-4
Federal legislation has established the legality and acceptability of electronic signatures
(\2\in accordance with /2/Public Law 106-229, Electronic Signatures in Global and
National Commerce Act). NAVFAC requires the use of electronic signatures for the
certification of all drawings and specifications. The following sections outline the
requirements for electronic signatures on NAVFAC deliverables.
12-4.1
General Requirements.
Electronically sign the PDF of the specification coversheet (RFP coversheet for DB
\2\RFP Preparer/2/) and seal and sign each drawing PDF sheet, using Sign-it. If the
professional is required to submit wet-signed documents to be in compliance with their
state regulations, then a separate wet-signed drawing and specification set may be
submitted, meeting the requirements of paragraph Wet-Signed Documents. A fully
electronic solicitation, including electronic signatures is still required.
At a minimum, NAVFAC will sign the For Commander NAVFAC\2\ in the title block on
\2\each Drawing and on the coversheet of the Specifications/2/. This is required on final
designs including designs prepared under Design-Build contracts. Once the
Government Project Manager receives SATISFACTORY TO (SAT-TO) from the Client,
type Approved By [Name of Client Representative] via [media (such as email or fax)]
in the ACTIVITY field, and the date the SAT TO was received, in the DATE field. In
exception, if project requires Client signature for this field, the Client must sign the
package using Sign-It./2/ Type in the initials of the DES, DRW, and REV areas on
the border to indicate the individual(s) who designed, drafted, and checked the sheet,
respectively. These areas must display the responsible individuals initials in CAD text.
The REV initials CANNOT be the same as the DES and DRW initials. The
\2\PM/DM,/2/ BRANCH MANAGER, CHIEF ENG/ARCH, and FIRE PROTECTION
fields are for use by NAVFAC only and may be either signed with Sign-it or initialed
with CAD text. If signed, the individual signing is a supervisor or has delegated
signature authority under NAVFACINST 5216.1L. \1\\2\Individual NAVFAC activities
may assign the use of the CHIEF ENG/ARCH field (such as to the Integrated Product
Team Lead);/2/ clear the CAD text if not used. A signature block is shown in Figure 123./1/
76
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
\1\Figure 12-3/1/ NAVFAC Signatures
\2\CI4, CI BLTL, PMEB or
Design Director/2/
SignIT Signature and Date
Client/Customer\2\
Typed Approved by [Clients
name] via [media], and date
SAT-TO received/2/
DES DRW REV
Typed Initials
PM/DM
\1\Typed Initials/1/
BRANCH MANAGER
\2\Typed Initials or /2/SignIT
Signature
CHIEF ENG/ARCH
\2\Typed Initials (if
designated by NAVFAC
Activity), or clear CAD text/2/
FIRE PROTECTION
\2\Typed Initials or /2/SignIT
Signature
12-4.2
\1\Sign design documents/1/ using the Sign-it software. Current version information,
points of contact, and order forms for Sign-it are located on the WBDG
(http://www.wbdg.org/ccb/browse_org.php?o=78).
12-4.3
Wet-Signed Documents.
If required, produce any wet-signed documents from the final electronic PDF documents
(prior to electronic signature application) submitted to NAVFAC.\2\/2/
77
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-5
\1\BUILDING INFORMATION MANAGEMENT/MODELING (BIM)
REQUIREMENTS.
For BIM projects, comply with requirements for Drawings and as follows.
12-5.1
12-5.1.1
BIM Definitions.
BIM Project Execution Plan (PxP).
The DOR is responsible for the PxP, which is a mandatory document that identifies \2\in
detail: key contacts, quality control, software used, model organization, and project
deliverables when designing with a BIM application/2/.
Download the PxP file found on the NAVFAC BIM Page of the Whole Building Design
Guide website (http://www.wbdg.org/bim/navfac_bim.php).
12-5.1.2
A software application which uses select criteria, parameters and variables to determine
the characteristics (e.g. length, width, height) of a Model Element and defines
relationships between other model elements.
12-5.1.3
Model.
Model Element.
A self-contained object within a Model with a unique identification, whose behavior and
properties are defined by data fields (Element Data). Model Elements can represent a
physical entity, such as a pump or a concrete wall, and range from the simple (e.g. a
standalone pump) to the complex (e.g. a multi-component wall system).
12-5.1.5
Element Data.
Design Model.
The Model created and delivered by the DOR which is developed to a specific Level of
Detail (LOD) as defined in the Model & Facility Data Matrix tab of the \2\eOMSI FDW/2/.
78
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-5.1.7
Record Model.
The Design Model modified by the KTR which incorporates the real world conditions of
the facility as constructed.
12-5.2
12-5.2.1
DOR completes the Model & Facility Data Matrix tab of the \2\eOMSI/2/ FDW (XLS)
utilizing the Instructions tab found in \2\the eOMS/2/ FDW. Download the \2\eOMSI/2/
FDW from the NAVFAC BIM Page of the Whole Building Design Guide.\2\/2/
12-5.2.3
Model Files.
Produce an independent Design Model for each discipline that can be linked to each
other. Document the Model names and Model links in the PxP.
12-5.2.4
Element Data.
Use the Required Facility Asset Fields (Element Data) specified in the Model & Facility
Data Matrix tab of the \2\eOMSI/2/ FDW for all modeled elements.
12-5.2.5
Include room space data defining net square footage and net volume to develop the
room finish schedule including room names and numbers.
12-5.2.6
Schedules.
Design Model.
DOR develops the Design Model using a 3D Parametric Modeling Application \2\/2/to
produce a complete set of \2\Contract Drawings/2/. All submittals must be compatible
and editable using their native software as defined in the PxP.
79
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-5.3.1
Refer to Table 12-1 for the Facility Type and Facility I.D. Designators.
Use the following naming convention for all BIM Design Models files:
Facility Type Designator
Facility I.D. Designator (four characters)
Job Number (eProjects Work Order No.)
Discipline Designator
File Extension (defined in \2\eOMSI FDW
Instructions Tab/2/)
XXXX XXXX-#######-A.xxx
12-5.4
Record Model.
KTR develops the Record Model by modifying the DORs Design Model as the facility is
being constructed. Utilize the Record Model Grade specified in the Model & Facility
Data Matrix tab in the\2\ eOMSI/2/ FDW.
12-5.4.1
XX XXXX TXXX-A-RM.xxx
80
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
12-5.5
Model and Drawing naming conventions and procedures are indicated in Figure 12-4.
Figure 12-4 Drawing and Model Progression DB\2\/2/
Drawing and Model Progression through Design and Construction DB (BIM Projects)
Design
Model
PRINT
To
PDF
PRINT
To
PDF
POST
CONSTRUCTION
CONSTRUCTION
Contract Drawings
(PDF)
MARKUP
Contract
Drawings
KTR
DOR
DESIGN
As-Built Drawings
(Hardcopy)
UPDATE
Design Model
Record
Model
PRINT
To
PDF
Record Drawings
(PDF)
MARKUP
Contract
Drawings
UPDATE
Design
Model
12-5.6
12-5.6.1
The DOR must produce a report (PDF) which compares the Mastersystems, Systems
and Subsystems list in the Design Model with the Mastersystems, Systems and
Subsystems list identified in the Model & Facility Data Matrix tab in the \2\eOMSI FDW
at each Design Phase/2/. Identify discrepancies (omitted and unintended Model
Elements) between the two lists, including an explanation for each. Address omitted
and unintended Mastersystems, Systems and Subsystems in the Design Model by Final
Design. Provide a written explanation for omitted and unintended Model Elements that
remain in the Design Model.
12-5.6.2
The DOR must conduct a clash detection of the Design Model at each design phase.
\2\Provide a report (PDF) at each phase showing existing clashes in the Model. The
final Clash Detection report must reflect zero clashes./2/
12-5.6.3
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Provide the final Design Model in native format and exported CAD files in DWG format.
12-5.6.5
Provide the final Record Model in native format and exported CAD files in DWG
format./1/
12-6
12-6.1
General.
Provide Official submittals on CD or DVD Discs or as directed. Submit all CAD files in
native Drawing (*.DWG) format in the NAVFAC supported version. Drawing files must
be uncompressed and unzipped. Purge files of all unused items (e.g. blocks, layers,
line types, and nested items). Do not submit single drawing files with multiple layouts
except as described in the paragraph in this chapter entitled, NAVFAC Standard
Drawing Format. Do not bind cross referenced parent and child drawings. If the
submitted native DWG files are not the native file format for the authoring software,
provide all native design data in the original authored format in addition to the native
DWG compliant format.
12-6.2
82
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
/RFP folder - All source files of RFP package, further divided by subfolders into
Parts, except for specification section files or CAD files.
/Calculations folder (pdf and input/source files)
/Support folder
/Reports-Surveys- Studies folder
/Basis of Design folder
/Architectural Color Boards folder (photos)
/Other folder (i.e. Photos, Project background/support files)
CD/DVD#3 - Cost Data (-.pwz file) (1 copy)
12-6.3
Submit Four CD/DVDs. Each must have the following folders and content.
/Record Drawings/
/CAD - All record CAD files and X-refs for all disciplines must be stored in the
same folder (directory).
/PDF
/Specs
/Calcs
/Cost
/Basis of Design
/Other
83
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
84
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 13 PHASE: PREDESIGN SUBMITTALS
13-1
GENERAL REQUIREMENTS.
SITE CONSTRAINTS.
ENVIRONMENTAL DOCUMENTATION.
Time required for the completion of environmental documentation varies and may be
developed in parallel to the design effort, but must be completed prior to award of
construction contract.
13-4
ADDITIONAL DATA.
Include other data in the project documentation such as site drawings and sketches, site
location, map of existing supporting facilities and site utilities, location of identified
constraints, diagrams and sketches that suggest the relationships among project
Functional Space Areas, adjacent or related projects, and existing facilities.
85
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
13-5
COST REQUIREMENTS.
Develop budgetary cost estimates following the guidance of UFC 3-730-01, UFC 3-70101, and NAVFAC Cost Engineering Policy and Procedures. In cases of conflict
between these documents, NAVFAC Cost Engineering Policy and Procedures governs.
13-5.1
Include a Life Cycle Cost Analysis justifying the project as programmed by the activity.
Guidance for developing a Life Cycle Cost Analysis is provided in Economic Analysis
Handbook NAVFAC P-Pub 442.
13-5.2
DD 1391.
Typically, provide Special Projects and most MILCON projects on Form DD 1391.
Identify Special Projects and MILCONs by the project number and make available for
review. Attach the necessary documentation to the projects, including a DD 1354,
NSERDC/HPSB Checklist, and \1\Third Party/1/ Checklist where applicable. For more
information about special project authorization, see OPNAVINST 11010.20G.
13-7
Identify FF&E cost on Form DD 1391, Block 12b, Equipment from Other Appropriations
(EFOA). Identify FF&E separately from other EFOA (i.e. Audio/Visual, PSE, and CI4).
Identify the \1\funding source and/1/ funding year for FF&E. FF&E cost can be
generated using estimating guides provided by NAVFAC Interior Designers.
\1\/1/
13-8
ENVIRONMENTAL REQUIREMENTS.
Conduct all required surveys, information gathering, and analytical testing required by
the contract and in accordance with UFC 3-800-10N (DRAFT). Review Installation
Focus Plans (IFPs) and GEO Readiness Database for identified site and development
constraints that may include site contamination, hazardous waste (lead paint, PCBs,
asbestos) abatement issues, cultural and natural resources (such as historic structures,
endangered species, wetlands), and Clean Water Act. Some projects may require
NEPA documentation prior to construction authorization.
86
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
13-9
For Air Force projects only, the RAMP provides project planning information such as
base architectural guidelines; base standards and regulations for fire protection, safety,
security, communications, systems operability, and maintainability, energy conservation,
and other base or site specific requirements, such as a Base Long Range Plan. The
RAMP is prepared at the project base or major command level, and will be provided to
the DOR by the Governments PM.
87
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
88
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 14 PHASE: CONCEPT DESIGN SUBMITTALS (10-15%)
14-1
GENERAL REQUIREMENTS.
The Concept Design Submittal is intended to convey the extent of the work in a
preliminary conceptual manner. Deliverables are approximately 10% to 15% complete
at this stage. In addition to the requirements of the Core UFCs and the contract, include
the deliverables described herein, as a minimum.
14-2
For Design-Build, if defined by the RFP, the concept design may be the Contractor's
technical response to the RFP, including layout, functional drawings, and design. When
this is used, any exceptions to the UFC requirements must be outlined in the RFP
solicitation.
14-3
BASIS OF DESIGN.
Submit a preliminary version of the Basis of Design addressing items defined in the
contract, the Core UFCs, Chapter 5, and as follows.
14-3.1
Geotechnical.
Sustainability.
DRAWINGS.
Provide drawings required by the contract, the Core UFCs, and herein as applicable to
the project:
14-4.1
Architectural.
Floor Plans Provide all floor plans, new and demolition, indicating room
names and basic dimensions.
89
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
14-4.2
Civil.
Conceptual Site Plan - Indicate above and below grade utility lines,
vehicular and pedestrian circulation paths, buildings, parking, paved
areas, and existing site features to remain.
14-4.3
Landscape Architecture.
14-4.4
Provide the following in accordance with UFC 3-501-01. The drawings need not provide
extensive details but must be complete enough to thoroughly express the Designers
intentions:
Site Plan.
Preliminary floor plans with dedicated space clearly identified for electrical
and telecommunications rooms.
14-4.5
14-4.6
Fire Protection.
\1\BIM PXP.
Provide a completed PxP within thirty (30) days after the Charrette, Facility Analysis
Concept Design (FACD) or Design Kick-Off Meeting for government review and
approval. Format in accordance with Chapter 12./1/
14-6
CALCULATIONS.
Provide calculations complete and in sufficient detail to support the items outlined in the
preliminary Basis of Design, as indicated on the drawings, in accordance with the Core
UFCs and herein.
14-7
SUSTAINABILITY NOTEBOOK.
90
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Maintain an up-to-date Sustainability Notebook that contains the electronic files of the
deliverables required for the project. The amount of information in the Sustainability
Notebook is based on the level of Guiding Principle compliance tracking required, and
may also be used in the Basis of Design. The Sustainability Notebook contains the
following components:
14-7.1
Provide the Sustainability Action Plan with each submittal. The amount of planning and
documentation in the Sustainability Action Plan is based on the level of Guiding
Principle compliance tracking required for the project. Provide, as a minimum, a
description of how DOR intends to achieve each GP requirement and other
sustainability goals for the project.
14-7.2
HPSB/NSEDRC Checklist.
14-7.3
\1\TPC is required for new construction and major renovations that are equal to or
greater than 50% plant replacement value. Register project with TPC organization
within 30 days of the Charette, FACD, or design kickoff meetings./1/
14-7.3.1
Format.
Project Title First Line: U.S. Navy or U.S. Marine Corps, Building Name (if
applicable)
14-7.3.2
Provide TPC management and documentation all online (or offline, with secure
facilities) throughout the design of the project. Maintain TPC Checklist and obtain TPC
Design Review. Include up-to-date copy in Notebook.
14-8
CHARETTES AND FUNCTIONAL ANALYSIS CONCEPT
DEVELOPMENT (FACD) STUDIES.
91
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Charettes and FACDs may be used in DBB to develop the design of the project or in DB
to develop the Project Program in the RFP. Both use value-engineering techniques to
develop concept designs. \1\The formal Value Engineering process is required for all
DBB MCON projects over $30 Million and is suggested for all other high value
multidisciplinary DBB projects./1/ Provide charette or FACD when required by the
contract.
14-8.1
Description.
FACD studies and design charettes are cooperative efforts by the design team, user
and client representatives, installation planning staff, 1391 project team members, other
appropriate Regional staff, facility engineering command personnel, and other
interested parties. A charette may last one to three days, while a FACD may last one to
two weeks. They include on-site development of a conceptual design in response to
functional, aesthetic, environmental, base planning, site, budgetary, and other
requirements. Submittals include meeting minutes, conceptual design, and
documentation of the decision and information that led up to that decision, including a
partnering agreement signed by all the principle participants.
92
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 15 PHASE: DESIGN DEVELOPMENT SUBMITTALS (35% - 50%)
15-1
GENERAL REQUIREMENTS.
The Design Development Submittal is intended to convey the complete extent of the
work in a preliminary manner. The deliverables are typically about 35% to 50%
complete at this stage. Update and include submittals from the previous submittal
stage, and provide additional detail to bring them to the required completion percentage.
In addition to the requirements of the Core UFCs and the contract, include the following
as a minimum:
15-2
BASIS OF DESIGN.
Update and submit a complete Basis of Design addressing items defined in this
document and the Core UFCs.
15-2.1
\1\Update to Sustainability
DRAWINGS.
Provide updated drawings from the previous submittal and additional drawings required
by the contract, the Core UFCs, and herein as applicable to the project.
15-3.1
Architectural.
Floor Plans Provide all floor plans, new and demolition, indicating room
names and dimensions.
Roof Plan Provide a plan of all roof areas, indicating direction of slope
and method of drainage.
15-3.2
Interior Design.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FF&E Summary List corresponding to the FF&E Plan with estimated item
costs
15-3.3
Landscape Architecture.
Miscellaneous Plans and Details. Provide plan drawings and details for
specialized construction including such items as plazas, courtyards, child
play equipment, monuments, memorials, site furniture, fences, walls, and
signage.
Irrigation Plan. Show all water lines, sprinkler heads, valves, backflow
preventers, water source connections, wells, automatic controllers,
schedules, and similar items when a site irrigation system is required.
15-3.4
Geotechnical.
15-3.5
Site Plan.
Drawings indicated above can be combined. Contact Governments Civil Reviewer for
approval of combined drawings prior to project submittal. For example, on small
projects a Site and Water and Sewer Plan can show the Site Plan, and Water and
94
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Sanitary Sewer Plan all on the same sheet or the Site and Grading and Drainage Plan
can show the Site Plan and Grading and Drainage Plan all on the same sheet.
15-3.6
Structural.
Framing Plans. Include a framing plan for each structural level of the
facility, showing dimensions, elevations, and column locations and
numbering referenced to a column line grid system, and overall sizes of
major members and components. Show the layout of system, including,
but not limited to, beams, joists, and stringers.
15-3.7
Mechanical.
Plumbing Floor Plan. Show plumbing fixtures, floor drains and equipment
locations.
HVAC Floor Plan. Show equipment locations, one or two-line duct layout
and preliminary piping runs.
15-3.8
Electrical.
Site Plan.
Preliminary floor plans with dedicated space clearly identified for electrical
and telecommunications rooms.
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Lighting Plan(s).
Power Plan(s).
Communications Plans.
Additional Plans/Risers.
15-3.9
15-4
Fire Protection.
Detail Sheets.
\2\BIM DESIGN MODEL.
OUTLINE SPECIFICATIONS.
Provide outline specifications, in the form of a list of specification sections the DOR
intends to use in the job.
Use Unified Facilities Guide Specifications, as required in Chapter 8. Provide a listing
of the UFGS used in the job by Section Number, Title, and Section Date. Follow the
Order of Precedence for choosing UFGS master guide specifications in Chapter 8,
unless required otherwise by the contract.
15-5.1
Provide Model & Facility Data Matrix tab of the Facility Data Workbook, in sufficient
detail to document the level of design completed in this phase. The FDW is an
attachment to UFGS 01 78 24.00 20 in subsequent phases. The Facility Data
Workbook is available for download at http://www.wbdg.org/bim/navfac_bim.php./1/
15-6
CALCULATIONS.
Provide calculations complete, and in sufficient detail to substantiate the design level in
this concept Basis of Design, as indicated on the drawings, in accordance with the Core
UFCs and herein, and any updated from the previous design phase.
96
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
15-6.1
Provide Structural and Geotechnical calculations in sufficient detail to support the items
outlined in the Basis of Design and indicated on the drawings.
15-6.2
Civil.
Provide calculations in sufficient detail to indicate compliance with LID criteria, Navy LID
Policy, and state or local stormwater regulations. Provide calculations for utility systems
and pavements in sufficient detail to support items outlined in the Basis of Design and
indicated in the drawings and specifications.
15-6.3
Architectural.
Mechanical.
Provide a bookmarked Adobe PDF, on CD-R or DVD-R media, of all input and output
data, and summary sheets for Energy Analysis, Life Cycle Cost Analysis, Building
Heating and Cooling Loads, and ASHRAE 90.1 Compliance Calculations as required by
UFC 3-410-01.
15-6.4.1
Energy Analysis.
Provide an Adobe PDF copy of the computerized energy analysis that includes input
and output data in their entirety.
15-6.4.2
Submit the computerized LCC analysis utilizing the latest edition of the NIST Building
Life-Cycle Cost Program.
15-6.4.3
Provide an Adobe PDF copy of the computerized load calculations with input and output
data in their entirety.
15-6.4.4
Plumbing Calculations.
97
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
15-6.5
Electrical.
15-6.6
Load Analysis.
Service size.
Feeder size.
Submit all calculations supporting all fire suppression and fire alarm/detection systems
for the project. Calculations for systems, features, or elements other than fire
suppression or detection will be required as applicable. Fire suppression system
calculations must be prepared using commercially available computer software.
15-6.7
Environmental Report.
98
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 16 PHASE: PRE-FINAL DESIGN SUBMITTALS (100%)
16-1
GENERAL.
The intent of the Pre-Final submittal is to provide a complete set of design deliverables.
The following are the minimum requirements of a Pre-Final submittal:
16-2
BASIS OF DESIGN.
Geotechnical.
The Geotechnical Report, if modified during the previous review, must be re-submitted
as an appendix to the Basis of Design; otherwise, do not submit.
16-2.2
Sustainability.
DRAWINGS.
Drawings must be 100% complete, minus final signatures, and incorporate all
responses to the previous review comments. The drawings must be complete to the
extent that they may be released for bid or constructed as submitted. Provide a
complete set of construction drawings organized by discipline as described in this
document and the Core UFCs. Upon submittal of the Pre-Final package, request
NAVFAC Drawing Numbers from the Government. For Design-Build projects, follow the
requirements of the RFP when shop drawings are used as design drawings.
Provide drawings updated from the previous submittal level, drawings specified in the
Core UFCs, and the following, as a minimum:
16-3.1
Civil.
Provide updated drawings from the previous submittal and the following:
16-3.2
Provide updated drawings from the previous submittal to substantiate design level, and
the following in accordance with UFC 3-501-01:
99
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
16-3.3
Site Plan.
Lighting Plan(s).
Power Plan(s).
Additional Plans/Risers.
Load Analysis.
Service size.
Feeder size.
Fire Alarm Riser Diagram: Include only when separate Fire Protection
Drawings are not required to be included in the design.
Panel Schedules.
SPECIFICATIONS.
100
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Provide edited, \2\marked-up specification sections, using the SpecsIntact Show
Revisions function when editing and printing, to show deletions from and additions to
the UFGS master sections. Use the default settings in SpecsIntact that displays
deletions lined out and additions underlined./2/ Run all verification reports when
printing. Print project specification sections\2\, using the SpecsIntact Show Section
Dates function, /2/to display the official date of release of the master guide specification
and version of the specification used. This date appears immediately below the
specification section title.
Design submittal must be complete at this stage and require only minor corrections if
any. Organize specifications in accordance with Chapter 8. Provide a submittal register
with the specifications.
16-5.1
Sustainability.
Environmental Specifications.
Provide additional requirements for Environmental specifications as required by UFC 3800-10N (DRAFT).
16-5.3
\2\Provide the source file (Excel format) of the eOMSI FDW in a separate file folder.
Provide the PDF of the completed Model & Facility Data Matrix tab of the eOMSI FDW
attached to UFGS 01 78 24.00 20/1//2/
16-6
CONTRACT SOLICITATION.
Provide a PIF, which includes the Bid Schedule as specified in Chapter 10, and a
complete scope for use in the project Synopsis.
16-7
INTERIOR DESIGN.
16-7.1
101
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
16-7.2
FF&E Summary List corresponding to the FF&E Plan with estimated item
costs.
FF&E.
Provide Preliminary FF&E to include the following, and present to the Activity and
NAVFAC personnel:
16-8
Cover Title Page (project name, project #, submittal date, submittal title).
Provide calculations, updated from previous submittal, to substantiate design level and
to reflect resolution of all previous government review comments, and in accordance
with the Core UFCs. Provide design analysis that is 100% complete. In addition,
provide the following:
16-8.1
Mechanical.
Submit calculations to support the plumbing and mechanical systems and the major
equipment comprising those systems. Submittals must include, but not be limited to,
cooling loads, heating loads, air balance, and outside air calculations.. Update the
energy analysis, provided at the Design Development phase, with the equipment
efficiencies scheduled on the drawings.
16-8.2
Electrical.
Provide updated and complete calculations required by Core UFCs, and include
photometric calculations for interior and exterior lighting.
16-9
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
3-301-01 01 and the International Existing Building Code as modified by UFC 3-301-01..
The generic schedule of special inspections is maintained on the WBDG at the following
location: http://www.wbdg.org/ccb/browse_cat.php?c=6./1/
16-10
Provide a Draft DD Form 1354, Transfer and Acceptance of Military Real Property, in
accordance with UFC 1-300-08. A blank, editable form is available for download at
http://www.dtic.mil/whs/directives/forms/eforms/dd1354.pdf.
Break out all assets by construction categories, provided on the form, and by the Navyspecific Category Codes for Military Real Property found in NAVFAC P-72.
Coordinate the identification of appropriate asset construction categories with the
Governments Real Property Accounting Officer. Include all quantities and units of
measure; however, cost breakdown is not required.
16-11
Design for and specify a professionally designed and manufactured recognition plaque
commemorating the opening of the facility and recognizing the leadership participants of
the project. \1\Coordinate the location with the Third Party Certification plaque (where
applicable). Provide design details for wall blocking to support the weight of hanging the
plaque(s)./1/ If multiple facilities are in the project, design a plaque for each major
facility. Indicate requirements of plaque on drawings and specify in UFGS 10 14 00.20,
Interior Signage. Include the following information:
16-12
Facility Name
Identify any recognition applied to the facility or person for which the
facility has been dedicated
Prime Contractor
Provide edited, red-lined RFP, showing deletions from and additions to the DB template
and UFGSs. Follow Specifications requirements in Chapter 8 for prescriptive
specifications provided in Part 5 of the RFP.
103
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
RFP submittal must be complete at this stage and require only minor corrections if any.
Organize Part 2 specifications in accordance with Chapter 11.
16-13
OVERSEAS TRANSLATIONS.
104
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 17 PHASE: FINAL DESIGN SUBMITTALS
17-1
GENERAL REQUIREMENTS.
The Final Submittal provides a complete and final set of contract documents ready for
bid solicitation by the Government, or in the case of Design-Build, ready for construction
by the Contractor. All previous government review comments must have been
addressed.
Unless specified otherwise by the Contract, provide final submittals in electronic format
in accordance with Chapter 12. Update deliverables from the previous submittal stages,
and in addition to requirements from the Core UFCs, provide the following, as a
minimum, for the Final Submittal:
17-2
BASIS OF DESIGN.
Sustainability.
Sustainability Notebook.
No later than 60 days after providing the Final Design Submittal, provide Sustainability
Notebook.
17-2.3
For projects that require TPC certification, submit TPC requirements for Design Review
to TPC organization, no later than 60 days after Final Design Submittal.
17-3
DRAWINGS.
Plotstamp Record.
Provide a Plotstamp Record for each contract drawing. This history begins with the final
design submittal and continues with subsequent submissions and modifications of that
drawing. Maintain this record and make it available at the jobsite for review.
17-3.1.1
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
a) DOR signed Final Critical Path Submittal or the Final Design Submittal.
b) Government approved Final Critical Path Submittal or the Final Design
Submittal. This development stage may be combined with "c." below,
if issued at the same time.
c) Incorporation of the Final Critical Path or Final Design drawings in the
contract by modification.
d) Submissions to Government and modifications of the Final Critical
Path or Final Design drawings incorporating variations in the contract.
17-3.2
For Design-Build projects, follow the requirements of the RFP when shop drawings are
used as design drawings.
17-4
Provide Clash Detection Report, Visual Review Report, and Final BIM Model in
accordance with Chapter 12 and PxP. There must be zero clashes./2/
17-5
Provide a quality control review. Evaluate both technical accuracy and discipline
coordination. With the final submittal, provide a single set of 100% prints and
specifications highlighted to validate that the review was performed, and that the
corrections were made. Provide a stamp on the cover page of the drawing set and
specifications as shown in Figure 17-1. Mark and verify correctness of such items as
section, detail, and note references to other sheets, major dimensions, and equipment
locations. Verify that all equipment is correctly identified the same way on all sheets and
in the specifications. Ensure that all work as indicated on the drawings is fully and
consistently specified.
Figure 17-1 Quality Review Block.
QUALITY CONTROL REVIEW
Signature
17-5.1
Date
For Design-Build projects, this review must be a coordinated effort between the
Contractor and their DOR.
106
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
17-6
SPECIFICATIONS.
Provide complete, final specifications with redlines executed. Organize and compile the
package as detailed in Chapter 8.
17-7.1
Provide complete Model & Facility Data Matrix tab of the eOMSI FDW, and attach to
UFGS 01 78 24.00 20. In addition, provide the native Excel file of the FDW with the
electronic files./1/
17-7.2
Sustainability.
Environmental Specifications.
For Design-Build projects, follow the requirements of the RFP when manufacturers
catalog data \1\ are used with the UFGS during design.
17-7.4.1
For Fire Protection systems, combine design and construction submittal information on
the design documents. In addition to the UFGS specification, provide proprietary
information, such as catalog cuts and manufacturers data that demonstrates
compliance with the RFP. Fire protection systems include fire suppression systems, fire
pumps, fire alarm and detection systems, fire-stopping, and spray-applied
fireproofing./1/
17-7.5
As part of the Final submittal of the specifications, provide the source files of Reports
included in the specifications.
17-8
CONTRACTING DOCUMENTS.
Provide a final, completed PIF, including Bid Schedule. Provide final scope for Project
Synopsis.
107
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
17-9
INTERIOR DESIGN.
17-9.1
Update deliverables for Interior Design from Pre-Final. Include Interior and Exterior
Material and Finish samples submitted in presentation board or binder format.
17-9.2
FF&E.
Provide the final FF&E submittal with final submittal package. Present to NAVFAC and
to the Activity. Update FF&E deliverables from Pre-Final.
17-10
Cover Title Page (project name, project #, submittal date, submittal title)
Revise design analysis and calculations as required to reflect resolution of all previous
government review comments and as required by this document and the core UFCs.
17-11
RFP.
108
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Provide complete, final RFP with redlines executed. Organize and compile the package
as detailed in Chapter 11.
17-13.1
As part of the Final submittal, provide source file of Reports included in the RFP, in
either Word or SpecsIntact.
17-14
Comparisons of Host Nation requirements with NFPA Codes, UFC 1-20001, and UFC 1-200-02
Translate the Geotechnical Report into English. Unless stated otherwise in the contract,
the boring logs must be shown in two languages, English and the local language of
country of bidding and construction.
17-14.1
Design of all disciplines must comply with the applicable U.S. & Host Nation norms,
regulations and all applicable U.S. Military criteria. Plans and Specifications must be
certified by a Host Nation architect or engineer, registered on the countrys professional
rolls, for compliance with all applicable codes and laws.
Provide this certification on the cover sheet of project drawings and specifications, in
dual languages. If the specifications coversheet does not have sufficient space for this
certification, provide directly behind the coversheet on a separate page, including the
project information from the coversheet. The code compliance certification must be
provided as indicated below, and dated, signed and stamped in accordance with the
requirements set forth in Chapter 7 of this document.
HAVING PARTICIPATED IN THE DESIGN OF PROJECT No. (Identify project number,
project title, location), AND HAVING THOROUGHLY REVIEWED THE COMPLETED
PROJECT DOCUMENTS, I DECLARE THAT THE FACILITY DESIGN INCLUDED
HEREIN COMPLIES WITH ALL APPLICABLE (Identify Host Country) CODES AND
LAWS.
Date
Signature
(Professional Seal)
109
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
110
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 18 PHASE: POST-DESIGN OR POST-RFP DEVELOPMENT
SUBMITTAL REQUIREMENTS
18-1
GENERAL REQUIREMENTS.
Submissions after final design or RFP development include providing DOR and
Government responses to Contractor Pre-Proposal Inquiries (PPI), Pre-Bid Inquiries
(PBI), and Requests for Information (RFI), and providing amendments and contract
modification documents. Submissions may include sketches, additions or corrections to
drawings, specifications, or RFP, and a continuation sheet with an explanation of
changes.
Changes made to the drawings, specifications, or RFP after the Final Submission are
changes to the Contract Documents. Changes before contract award are amendments;
changes after contract award are contract modifications.
18-2
PRE-PROPOSAL/PRE-BID INQUIRIES AND REQUESTS FOR
INFORMATION.
Responses to Pre-Proposal/Pre-Bid Inquiries and Requests for Information must be
responded to as quickly as possible to prevent delay to bid opening or to construction of
contract. It is expected that the DOR will provide response to a PPI/PBI or RFI no later
than 3 working days after notification. Where the response to a PPI/PBI or RFI requires
additional time, the DOR must notify the Government Project Manager/Design Manager
or ROICC/PWD as to the expected date of response. In any case, the DOR should
indicate if an amendment or a contract modification is required in response to the
PPI/PBI or RFI.
18-3
CHANGE NUMBERS.
111
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
18-5
CHANGE FORMAT.
Provide a Continuation Sheet for an Amendment and a Proposed Change Sheet for a
contract modification with an explanation of the changes. Where drawings, sketches,
RFP sections, or specifications are replaced or added, attach the document PDF file
separately, and reference in the Continuation Sheet or Proposed Change Sheet in
accordance with guidance below. When multiple drawing, sketch, RFP section, or
specification files are replaced or added, combine the documents by type into a single
file, and bookmark each document; i.e. combine the drawings into a single file and
bookmark each drawing, and combine the specification sections into a single file and
bookmark each section. Follow file size limitations in accordance with Chapter \1\12/1/.
Prior to submittal of an amendment or contract modification, contact the Government
representative for the number of the amendment or contract modification.
18-5.1
Language Format.
Use Table 18-1 "Specifications or RFP Changes Format" and Table 18-2 "Drawing
Changes Format" for guidance on how to format the language for changes. Note that
any additions, deletions, or replacement of complete specification sections should be
done at the Table of Contents; do not list the section separately within the document by
Section number and title with note to add, delete, or replace the section. Note that
adding, deleting or replacing a drawing or sketch in its entirety is done at Section 00 01
15, List of Drawings; do not list each drawing or sketch separately with a note to add,
delete, or revise the entire drawing.
18-5.2
Continuation Sheet.
Use the Continuation Sheet for Amendments. A sample Continuation Sheet is provided
at Figure 18-1. Follow the specific guidance for drawing, specification, and RFP
changes.
18-5.3
Use a Proposed Change Sheet for contract modifications. A sample sheet is provided
at Figure 18-2. Use the guidance for amendments and changes for language and
format.
112
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Table 18-1 Specification or RFP Changes Format
Change
Change Format
Adding a
Specification
Section
Replacing an
Existing
Specification
Adding Paragraphs
or Sub-paragraphs
Making Word
Changes
Omitting
Paragraphs or Subparagraphs
113
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
18-5.4
Use Table 18-2, Drawing Changes Format, as a guide in preparing changes to the
Drawings.
When drawings are revised and replaced, use a cloud to highlight the change. For
amendments, place a triangle with a sequential number in it, next to the cloud or the
item(s) changing for each sheet. For modifications, use a triangle with a sequential
letter instead of a number. Also provide this triangle with the number or the letter in the
revisions block. Under description, describe what the change is; listing the amendment
or contract modification number is not appropriate. Insert the date that the change was
made. This date and revision block distinguishes the revised drawing from the original
drawing. Do not change sheet numbers or sheet designations for revised drawings.
Table 18-2 Drawing Changes Format
Change
Change Format
Adding
Drawings
DOCUMENT 00 01 15
LIST OF DRAWINGS
Title
4265191
4265192
Revising
Drawings
DOCUMENT 00 01 15
LIST OF DRAWINGS
Title
4265191
4265192
Making Text
Changes to
Drawings
DOCUMENT 00 01 15
LIST OF DRAWINGS
114
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Figure 18-1 Sample Amendment
CONTINUATION SHEET
DOCUMENT 00 01 15 LIST OF DRAWINGS
1.2 CONTRACT DRAWINGS
NAVFAC Dwg. Nos. 14376950 and 14376951 are added to the list of drawings and accompany this
amendment.
NAVFAC Dwg. Nos. 14376308, 14376309, 14376310, 14376311, 14376312, 14376313, 14376314, 14376315,
and 14376316 are revised as of March 17, 2012. These revised drawings accompany this amendment.
On NAVFAC Dwg. No. 4376290 (T-1)
General Notes: Delete Note 1 in its entirety and replace with the following: 1. One lane of Williamsburg Road
must remain open at all times."
PROJECT TABLE OF CONTENTS
Section 03 37 13, SHOTCRETE, is added to the Table of Contents and accompanies this amendment.
Delete sections 26 00 00.00 20 and 33 71 02.00 20 in their entirety and replace with Sections 26 00 00.00 20,
BASIC ELECTRICAL MATERIALS AND METHODS, dated July 4, 2012 and 33 71 02.00 20,
UNDERGROUND ELECTRICAL WORK, dated July 4, 2012. Sections 26 00 00.00 20 and 33 71 02.00 20,
dated July 4, 2012, accompany this amendment.
SECTION 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
1.3 CONSTRUCTION SITE PLAN
Delete this paragraph in its entirety.
1.4 STORAGE AREAS
At the beginning of this paragraph add the following: Contractor is responsible for security of their own
property.
1.4.1 Storage in Existing Buildings
Delete this paragraph in its entirety and replace with the following:
1.4.1 Laydown Area
The enclosed site available for storage must be located at the North side of the building near the Lobbys North
entrance
.
1.4.2 Material Storage
The Contractor will be working in and around an occupied building. The storage of materials, unless approved
by the Contracting Officer, will not be allowed in the building.
115
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
2
SECTION 26 20 00 INTERIOR DISTRIBUTION SYSTEM
2.2.1 Surface Non-metallic Raceway
After the text snap cover type, add color must be white.
3.1.3.1 Workmanship
After this paragraph, add the following:
3.2 FIELD QUALITY CONTROL
Furnish test equipment and personnel, and submit written copies of test results. Give Contracting Officer five
working days notice prior to each test.
3.2.1 Devices Subject to Manual Operation
Operate each device subject to manual operation at least five times, demonstrating satisfactory operation five
out of five times.
-- End of Amendment --
116
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
Figure 18-2 Sample Contract Modification
N62470-96-C-6042
NAVFAC
WORK ORDER NUMBER
555555
PROPOSED CONTRACT
MODIFICATION
TACTICAL SUPPORT VAN PAD
AT THE
MARINE CORPS AIR STATION, NEW RIVER
JACKSONVILLE, NORTH CAROLINA
117
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
118
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CHAPTER 19 PHASE: POST-CONSTRUCTION DOCUMENTS
19-1
PROJECT CLOSE-OUT.
The DOR may be required to execute specific project tasks during project close-out.
These tasks may include preparing DD Form 1354, "Real Property Record," for
Government signature, attending project close-out meetings, verifying that the LID IMPs
were constructed as designed, or performing other tasks. Refer to the design contract
(if a Design-Bid-Build project) or the Design-Build RFP for project close-out related
tasks.
19-1.1
Update the Draft DD Form 1354 to include any additional assets, improvements or
alterations that occurred during construction. Identify costs. Submit completed form for
approval to the Government.
19-1.2
Record Drawings.
Sustainability.
119
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
120
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
APPENDIX A REFERENCES
AMERICAN SOCIETY OF HEATING, REFRIGERATION AND AIR CONDITIONING
ENGINEERS
http://www.ashrae.org/
ASHRAE 90.1, Energy Standards for Buildings, Except Low-Rise Residential Buildings
ASTM
http://www.astm.org
ASTM D1452, Standard Practice for Soil Exploration and Sampling by Auger Borings
ASTM D1586, Standard Test Method for Standard Penetration Test and Split-Barrel
Sampling of Soils
ASTM D2487, Standard Practice for Classification of Soils for Engineering Purposes
(Unified Soil Classification System)
ASTM D2488, Standard Practice for Description and Identification of Soils (VisualManual Procedure)
ASTM D3740, Standard Practice for Minimum Requirements for Agencies Engaged in
Testing and/or Inspection of Soil and Rock as Used in Engineering Design and
Construction
ASTM D5778, Standard Test Method for Electronic Friction Cone and Piezocone
Penetration Testing of Soils
FM GLOBAL
http://www.fmglobal.com
Property Loss Prevention Data Sheet 3-0, Hydraulics of Fire Protection Systems
GENERAL SERVICES ADMINISTRATION
FAR 52-236-21, Specifications and Drawings for Construction,
http://acquisition.gov/far/current/html/52_233_240.html#wp1113494
FAR 52-236-25, Requirements for Registration of Designers,
http://acquisition.gov/far/current/html/52_233_240.html#wp1113529
Standard Form (SF) 30, Amendment of Solicitation/ Modification of Contract,
http://www.gsa.gov/portal/forms/download/116158
121
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
122
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
UNITED STATES DEPARTMENT OF DEFENSE, UNIFIED FACILITIES CRITERIA
PROGRAM
http://dod.wbdg.org unless otherwise noted
FC 4-721-10N, Navy and Marine Corps Unaccompanied Housing
FC 4-722-01N, Navy and Marine Corps Dining Facilities
FC 4-740-02N, Navy and Marine Corps Fitness Centers
UFC 1-200-01, General Building Requirements
UFC 1-200-02 High Performance and Sustainable Building Requirements
UFC 1-300-02, Unified Facilities Guide Specifications (UFGS) Format Standard
UFC 3-101-01, Architecture
UFC 3-210-10, Low Impact Development
UFC 3-220-01, Geotechnical Engineering
UFC 3-250-01FA, Pavement Design for Roads, Streets, Walks, and Open Storage
Areas
UFC 3-260-02, Pavement Design for Airfields
UFC 3-260-03, Airfield Pavement Evaluation
\1\UFC 3-301-01, Structural Engineering/1/
UFC 3-340-01, Design and Analysis of Hardened Structures to Conventional Weapons
Effects (FOUO)
UFC 3-410-01, Heating, Ventilating, and Air Conditioning Systems
UFC 3-420-01, Plumbing Systems
UFC 3-501-01, Electrical Engineering
UFC 3-600-10N (DRAFT), Fire Protection, http://www.wbdg.org/ndbm
UFC 3-701-01, DoD Facilities Pricing Guide
UFC 3-730-01, Programming Cost Estimates for Military Construction
UFC 3-740-05, Handbook: Construction Cost Estimating
123
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
UFC 3-800-10N (DRAFT), Environmental Engineering for Facility Construction,
http://www.wbdg.org/ndbm
UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings
UFC 4-010-05, Sensitive Compartmented Information Facilities Planning, Design, and
Construction
UFC 4-020-01, Security Engineering Facilities Planning Manual
UFC 4-023-03, Design of Buildings to Resist Progressive Collapse
UFC 4-510-01, Design: Medical Military Facilities
UFC 4-610-01, Administrative Facilities
UFGS 00 01 15, List of Drawing
UFGS 00 22 13.00 20, Supplementary Instructions to Offerors
UFGS 01 11 00, Summary of Work
UFGS 01 33 00, Submittal Procedures
UFGS 01 33 00.05 20, Construction Submittal Procedures, http://dod.wbdg.org/ndbm
UFGS 01 33 10.05 20, Design Submittal Procedures, http://www.wbdg.org/ndbm
UFGS 01 33 29, Sustainability Reporting
\1\UFGS 01 45 00.00 20, Quality Control/1/
UFGS 01 45 00.05 20, Design and Construction Quality Control,
http://www.wbdg.org/ndbm
\1\UFGS 01 45 35, Special Inspections
UFGS 01 45 35.05 20, Special Inspections for Design-Build,
http://www.wbdg.org/ndbm/1/
\1\ UFGS 01 78 24.00 20, Facility Electronic Operation and Maintenance Support
Information (eOMSI)\1\
UFGS 02 82 16.00 20, Engineering Control of Asbestos Containing Materials
UFGS 10 14 00.20, Interior Signage
124
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
UNITED STATES NATIONAL CAD STANDARD
http://www.nationalcadstandard.org/
United States National CAD Standard for Architecture, Engineering, & Construction
(A/E/C)
UNITED STATES NAVY
Electronic Project Generator (EPG), Naval Facilities Engineering Command. Contact
Government administrator for Intranet address and access.
NAVFAC P-Pub 442, Economic Analysis Handbook,
http://wbdg.org/ccb/NAVFAC/PPUBB/p442.pdf
NAVFAC Acquisition Supplement, (NFAS) Part 6.304,
https://www.navfac.navy.mil/content/dam/navfac/Small%20Business/PDFs/Contracti
ng_with_NAVFAC/SB-NAVFAC_Naval_Facilities_ACQ_Supplement_NOV2012.pdf
NAVFAC Cost Engineering Policy and Procedures2,\1\
http://www.wbdg.org/ccb/browse_cat.php?c=273 /1/
NAVFAC DESIGN-BUILD MASTER WEBSITE
http://www.wbdg.org/ndbm
NAVFAC Instruction 11012.119, En-(Fac 04t) Preparation of Concept Plans and Final
Working Drawings and Specifications for Medical/Dental Facilities
OPNAVINST 11010.20G, Facilities Project Instruction Manual, Public Law 94-168,
http://doni.daps.dla.mil/Directives/11000%20Facilities%20and%20Land%20Manage
ment%20Ashore/1100%20Facilities%20and%20Activities%20Ashore%20Support/11010.20G%20w%20
CH-1.pdf
WHOLE BUILDING DESIGN GUIDE (WBDG)
http://www.wbdg.org
\2\eOMSI FDW, Electronic Operation and Maintenance Support Information (eOMSI),
Facility Data Workbook, http://www.wbdg.org/bim/navfac_bim.php /2/
125
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
126
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
APPENDIX B GLOSSARY OF ABBREVIATIONS
A-E
A/E/C
Architect/Engineer/Contractor
CAD
CATEX
Categorical Exclusion
CCB
CD
Compact Disk
CFA
CMC
CSI
CONUS
DB
Design-Build
DBB
Design-Bid-Build
DoD
Department of Defense
DOR
Designer of Record
DQC
DVD
EA
Environmental Assessment
EBS
EDD
EIS
FACP
FF&E
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
FOSSAC
HPSB
IFP
IP
Inch-Pound (English)
KTR
Contractor
LCC
Life-Cycle Cost
LEED
NAVFAC
NSEDRC
NCPC
NEHC
NFPA
NIST
PBI
Pre-Bid Inquiry
PCAS
PIF
PM
Project Manager
PPI
Pre-Proposal Inquiry
PROD
PWD
PTS
PxP
OSHA
OCONUS
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
RAC
RAMP
RFI
RFP
ROICC
RONA
Record of Non-Applicability
SAES
SHPO
SI
SPAWAR
TPC
UFC
UFGS
129
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
130
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
APPENDIX C SAMPLE DELIVERABLES
C-1
1.1
CONTRACT LINE ITEMS
The terms Offeror and Bidder and versions thereof (offer/bid) have the same
definition as used within this contract.
Provide the Contract Line Item (CLIN) price for the following items:
CLIN 0001AA. Price for the entire work for the P136 TACAMO E-6B Hangar
complete to the 5 foot line outside of the building, in accordance with the
drawings and specifications, but excluding work described in CLIN 0001AB,
0001AC, 0001AD, 0002, and 0003.
CLIN
DESCRIPTION
PRICE
0001AA
$____________
CLIN 0001AB. Price for the entire project Site Work, outside the 5 foot
line of the E-6B Hangar facility complete in accordance with the drawings
and specifications, but excluding work described in CLIN 0001AA, 0001AC,
0001AD, 0002 and 0003.
CLIN
DESCRIPTION
PRICE
0001AB
$____________
ITEM
UNIT
0001AC Drilled
Linear
Concrete feet
Pier
Foundation
UNIT PRICE
$___________
131
50
$____________
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
CLIN 0001AD. Price for drilled concrete pier load test, complete in
accordance with the drawings and specifications and in accordance with the
following schedule:
CLIN
ITEM
UNIT
UNIT PRICE
0001AD
Pier Load
Test
Each
$____________
CLIN 0002
NO.
UNITS
50
DESCRIPTION
PRICE
0002
$__________________
ITEM
GOVERNMENT
FF&E ESTIMATE
HAR (NTE
5%)
PRICE FOR
ESTIMATED
HAR AMOUNT
(GOVT EST. x
HAR%)
TOTAL FF&E
ESTIMATED AMOUNT
FOR CLIN 0003
(GOVERNMENT FF&E
ESTIMATE +
ESTIMATED HAR
AMOUNT)
0003
FF&E
$300,000
_____%
$_________
$_____________
132
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
1.2
a.
b.
d.
e.
1.3
133
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
e. The Government is not obligated to award the Planned Modification line
item. Should the Government choose to award the Planned Modification,
the line item will be awarded as a negotiated modification to the
contract/task order. The contractor's proposed HAR will be applied to
all vendor/supplier costs for the FF&E.
f. If awarded, the FF&E modification will be awarded at least six months
prior to the contract completion date. A minimum of six months is
required for the Contractor to purchase, deliver and install the FF&E
without impacting the overall completion date of the project. The
Contractor's schedule must assume the award of the FF&E as a
modification. No schedule extensions will be granted if the
modification is awarded at least six months prior to the contract
completion date. If the Government decides to negotiate and award the
furniture modification with less than six months prior to the contact
completion date, the Contractor may be entitled to a contract extension
and extended field overhead. A contract extension and extended field
overhead will only be granted in those cases where the Contractor
demonstrates that an accepted Final FF&E package was submitted within
the approved schedule deadlines and sufficient lead time for the FF&E
is not available and the Government's award of the modification is in
the last six months of the contract.
134
FC1-300-09N
1 May 2014
Change 2, 21 Aug 2015
C-2
SAMPLE SYNOPSIS
135