PDA Form

This document contains a preliminary detailed abstract (PDA) with cost estimates for construction of new buildings. It includes a breakdown of estimated costs for items like preliminaries, piling/foundation, building works, ancillary buildings, mechanical and electrical services, infrastructure works, and a provisional sum. The total estimated construction cost and cost per square meter are provided. An additional section covers turnkey elements that are part of the total estimated cost of the project.

Uploaded by

mohamad ashmuni
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views1 page

PDA Form

This document contains a preliminary detailed abstract (PDA) with cost estimates for construction of new buildings. It includes a breakdown of estimated costs for items like preliminaries, piling/foundation, building works, ancillary buildings, mechanical and electrical services, infrastructure works, and a provisional sum. The total estimated construction cost and cost per square meter are provided. An additional section covers turnkey elements that are part of the total estimated cost of the project.

Uploaded by

mohamad ashmuni
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

PRELIMINARY DETAILED ABSTRACT (PDA)

Head Subhead Year Total Provision RM -


Provision for Construction RM -
BRIEF DESCRIPTION OF BUILDINGS
ITEM BUILDING Frame Wall Roof Floor Ceiling Window Door
All Building

BREAKDOWN OF PRELIMINARY COST ESTIMATE COST (RM)


1 PRELIMINARIES (5% of Items 2 - 7) RM

2 PILING/SPECIAL FOUNDATION
RM

SUB TOTAL FOR ITEM 2 RM -


Floor Area Total Floor
BUILDING ` (m2)
Cost/m2 Blok/Unit
Area (m2) COST (RM)
3 BUILDING WORKS

SUB TOTAL FOR ITEM 3 RM -


4 ANCILLARY BUILDINGS & MISCELLANEOUS Quantity Unit Rate

SUB TOTAL FOR ITEM 4 RM -


5 MECHANICAL & ELECTRICAL SERVICES
RM -

SUB TOTAL FOR ITEM 5 RM -


6 INFRASTRUCTURE WORKS Quantity Unit Rate

RM
RM
RM
RM
RM
RM
RM
RM
RM

SUB TOTAL FOR ITEM 6 RM -


7 PROVISIONAL SUM
1) RM

SUB TOTAL FOR ITEM 8 RM -

TOTAL CONSTRUCTION COST RM

ALL IN UNIT RATES (ITEM 1 TO 7)


TOTAL FLOOR AREA m2 COST/m2 RM

8 TURNKEY ELEMENT
RM
RM -
RM
RM

SUB TOTAL FOR TURNKEY ELEMENT RM -

TOTAL ESTIMATED COST OF PROJECT RM -