SCHEDULE
The following Gantt chart outlines the plan of approximate time to be undertaken each week so as to obtain project data and knowledge for the
project as well as the methods used.
WEEKS
TASKS DURATION 21-Mar-11 28-Mar-11 04-Apr-11 11-Apr-11 18-Apr-11 25-Apr-11 02-May-11 09-May-11 16-May-11
PROJECT PROPOSAL 14 days
Investigation on existing design and 5 days
technology
Research design – 1. technical constraints 1 day
Research design – 2. technical possibilities 1 day
Technical design – 1. Design of sensors 5 days
Technical design – 2. Design of wireless 8 days
techniques
Technical design – 3. Design of SCADA 6 days
Technical design – 4. Design of installation 6 days
Design analysis – 1. Component analysis 5 days
Design analysis – 2. System analysis 1 day
Investigation on life cycle environmental 10 days
issue
Environmental impacts of manufacturing 8 days
process
Environmental impact of Irrigation in the 6 days
European Union
Suggestions for ameliorating the 6 days
environmental impact of irrigation
Presentations
Final Report