PVC Pipeline Design Manual
PVC Pipeline Design Manual
Guide
for
PVC
Water Pipe
January 1999 Edition
Preface
This booklet is intended for use by installers, supervisors, and inspectors responsible for the installation of
PWEagles PVC water pipe. It is not a design manual. Rather
it is intended as a guide for the proper handling, installation,
and testing of PVC pressure water pipe. If used properly,
this information can maximize product performance and minimize the possibility of field problems.
This guide is not intended to assume the authority of
the engineer. Because system requirements and actual field
conditions may vary significantly, the sole responsiblity for
all design and installation decisions lies with the project
engineer.
THIS
PAGE
IS
BLANK
Table of Contents
Chapter I
General Information
Chapter II
5
Receiving, Unloading, Storage,
and Handling
Chapter III
Trench Construction
13
Chapter IV
Pipe Assembly
29
Chapter V
Testing
43
Chapter VI
Service Connections
49
Chapter VII
Special Considerations
67
Index
79
THIS
PAGE
IS
BLANK
Chapter I
General Information
Specifications
PWEagle produces PVC municipal water (Cast Iron Pipe
Size) pipe in conformance with AWWA C900 and C905,
IPS (Iron Pipe Size) pipe in conformance with ASTM D 2241
and D 1785 and PIP (Plastic Irrigation Pipe) in conformance ASAE and SCS specifications. PWEagle recommends
that pipe be installed according to this guide, AWWA C605,
AWWA Manual M23, and ASTM D 2774.
Warranty
PWEagle warrants that its PVC pipe products were
manufactured in accordance with applicable materials and
product specifications, and that the pipe is free from all defects in materials and workmanship using the applicable
specifications as a standard.
Every claim under this warranty shall be deemed waived
unless presented in writing and received by PW Eagle within
sixty (60) days of the date the defect was, or should have
been discovered or within two (2) years of the date of
PWEagles shipment of the product, whichever occurs sooner.
PWEagle makes no other warranty or representation of any kind, expressed or implied, in fact or in law,
including without limitation the warrant of merchantability or fitness for a particular purpose, other than the
limited warranty set forth above.
Limitation of Liability
It is expressly agreed that the limit of PWEagles liability
is the replacement of defective product with the same quantity of non-defective product, and that PWEagle shall have
no such liability unless the claim results solely from breach
of PWEagles warranty.
In no event shall PWEagle be liable for any incidental or consequential damages of any kind, including
without limitation, any expense or removal or reinstallation resulting from any defect.
Some states do not allow the exclusion or limitation of
incidental or consequential damages, so the above limitation or exclusion may not apply to you. This warranty gives
you specific legal rights, and you may have other rights which
vary from state to state.
Chapter II
Receiving,
Unloading,
Storage, and
Handling
Receiving
When receiving a pipe shipment, the contractor or
purchaser should exercise established precautions. Each
pipe shipment should be inventoried and inspected upon
arrival. The pipe was inspected and loaded with due
care at the factory using methods acceptable to the carrier. It is the carriers responsibility to deliver the shipment in good condition, and it is the receivers responsibility to ensure that there has been no loss or damage.
Unloading
The means by which the pipe is unloaded in the field is
the decision and the responsibility of the receiver. These
recommendations should be followed:
1. Remove restraints from the top unit loads. These may
be either straps, ropes, or chains with padding.
2. Remove any boards on the top or sides of the load which
are not part of the pipe packaging.
3. Using a fork lift with thin chisel forks (or a front-end loader
equipped with forks), remove the top units one at a time
from the truck.
4. If a fork lift is not available, use a spreader bar with fabric
straps capable of carrying the load. Space straps ap-
5.
6.
7.
8.
9.
10. Protect units with packing materials the same way they
were protected while on the truck.
11. To unload lower units, repeat the unloading process described above.
12. Do not unload by hand.
13. WARNING: DO NOT STAND OR CLIMB ON CRATES
OR CONTAINERS.
Storage
The following procedures are recommended to prevent
damage to the pipe:
1. Store the pipe at the site in unit packages.
2. Avoid compression, deformation or damage to bell ends
of the pipe.
3. When unit packages are stacked, ensure that the weight
of upper units does not cause deformation to pipe in lower
units.
4. Support pipe unit packages on wood blocking to prevent
damage to the bottom surfaces during storage. Space
supports to prevent pipe bending.
5. Store solvent cement in tightly sealed containers away
from excessive heat.
6. Do not store pipe where gaskets may be exposed to
ozone, grease or oil.
7. Protect pipe interior and sealing surfaces from dirt and
foreign matter.
8. When unit packages are stacked, ensure that the stack
remains stable.
Handling
The following procedures are recommended:
1. When using mechanical equipment, exercise care to prevent damage to the pipe.
2. Lower pipe carefully from trucks and into trenches. Do
not drop pipe.
3. In subfreezing temperatures, use caution to prevent impact damage. Handling methods considered acceptable
for warm weather may be unacceptable during very cold
weather.
10
11
12
Chapter III
Trench
Construction
13
14
General
1. Trench excavation should comply with all applicable laws
and regulations.
2. Excavated material such as debris and removed pavement is not suitable for trench backfill.
3. Where dewatering is necessary, water should be removed
until the pipe has been installed and the backfill has been
placed to a sufficient height to prevent flotation of the
pipeline.
4. The maximum earth load on flexible pipe is the weight of
the material directly over the pipe (prism load). Unlike
rigid pipe, the width of the excavated trench does not
affect pipe loading. Trench width is based solely on practical and economical construction.
5. See Figure 3.1 for trench terminology.
FIGURE 3.1
TRENCH CROSS-SECTION SHOWING
TERMINOLOGY
15
Narrow,
Unsupported,
Vertical-Walled
Trench
1. See Figure 3.1 for unsupported vertical-walled trench
cross-section.
2. The width of narrow trenches is the minimum working room required for a worker to place haunching
material. See Table 3.1.
3. In narrow trenches, pipe embedment should be
compacted all the way to the trench wall.
TABLE 3.1
NARROW TRENCH WIDTHS, MINIMUM
NOMINAL
PIPE SIZE
Diameter
(Inches)
No. of Pipe
Diameters
Inches
4
6
8
10
12
15
18
21
24
4.3
2.9
2.9
2.5
2.4
2.0
1.8
1.6
1.5
18
18
24
26
30
30
32
34
36
16
Sub-Ditch
Trench
The width of the subditch below the top of the pipe should
meet the minimum dimensions of Table 3.1.
Wide
Trench
17
Supported Trench
1. This type of trench is used where unstable or flowing soil
conditions are present in the trench walls.
2. Methods of support include sheeting, bracing, trench
jacks, or trench box.
3. If conditions are extremely severe, it may be necessary
to grout the soil adjacent to the trench to prevent migration between pipe embedment materials and trench wall
soils.
4. See Table 3.2 for minimum trench widths.
TABLE 3.2
SUPPORTED TRENCH WIDTHS, MINIMUM
NOMINAL
TRENCH WIDTH, MINIMUM
PIPE SIZE
Diameter
(Inches)
4
6
8
10
12
15
18
21
24
No. of Pipe
Diameters
8.5
5.7
4.3
4.0
3.4
3.1
2.7
2.4
2.2
Inches
36
36
36
42
42
48
48
50
52
18
Trench Depth
1. Where frost depth is a consideration, pipe burial should
be 6 inches deeper than the record frost penetration.
2. Where frost is not a concern and live loads are not anticipated, a minimum cover of 12 inches is adequate.
3. Where live loads are significant, the design engineer
should consider such factors as size and type of equipment, impact, type of soil, and soil compaction in determining cover requirements.
19
Trench Bottom
1. The trench bottom should provide a uniform, stable support for the pipe.
2. The soil surface at the bottom of the trench should be
free of any irregularities that could cause point loads on
the pipe or bell.
3. Where an unstable trench bottom condition occurs, special foundations may be required. A layer of bedding
material should be placed between foundation and pipe.
4. Where rock subgrade or stones larger than 1-1/2 inches
are encountered, a minimum of 4 inches of bedding
should be placed under the pipe above the rock.
Embedment Materials
1. See Table 3.3 for soil classifications.
2. The high void ratio of Class I material limits its use to
areas where side support will not be lost due to migration of fines from the trench walls and bottoms. Where
such migration is possible, the minimum size range
should be reduced and the gradation designed to limit
void size.
3. Class II material should be well graded (not uniformly
graded or gap graded) to prevent loss of side support as
described in item 2.
4. For Class IV materials, caution should be exercised in
the design and method of compaction due to difficulty in
controlling moisture content in field conditions.
5. Class V materials are not recommended for bedding,
haunching, or initial backfill.
6. See Table 3.4 for degree of compaction information for
various compaction methods and embedment materials.
7. For PVC pipes 6 inches in diameter and greater, limit
particle size in the embedment zone to 1-1/2 inches or
less. For pipe diameters less than 6 inches, limit particle
size in the embedment zone to 3/4 inch or less.
20
TABLE 3.3
Description of Embedment Material Classifications
SOIL
TYPE
CLASS II SOILS**
CLASS III SOILS***
DESCRIPTION OF
MATERIAL CLASSIFICATION
Manufactured angular, granular material,
1/4 to 1 1/2 inches (6 to 40 mm) size,
including materials having regional
significance such as crushed stone or
rock, broken coral, crushed slag, cinder or
crushed shells.
CLASS I
SOILS*
SOIL
GW
GP
SW
SP
GM
GC
SM
SC
21
CLASS V SOILS
CLASS IV SOILS
SOIL
CLASS
SOIL
TYPE
DESCRIPTION OF
MATERIAL CLASSIFICATION
ML
CL
MH
CH
CL
CH
PT
22
Compaction
1. Saturation If saturation methods are used for compaction, the following recommendations should be followed:
a. Prevent flotation of the pipeline.
b. Do not use saturation during freezing temperatures.
c. Exercise care to prevent erosion at pipe sides and
bottom caused by water jetting.
d. Apply only enough water to provide complete saturation.
e. Allow each layer to dewater and solidify until it will
support the weight of workers.
2. Compaction equipment
a. Avoid contacting the pipe with compaction equipment.
b. Do not use compaction equipment directly over the
pipe until sufficient backfill has been placed to prevent damaging or disturbing the pipe.
23
24
Compact by power
tamper or rammer
95 - 100
__
9 - 18
Mixed-Grain
Soils
III
95 - 100
95 - 100
9 - 12
Manufactured
Granular Materials
MATERIAL DESCRIPTION
II
CLASS OF EMBEDMENT
TABLE 3.4
90 - 100
6 - 30
Fine Grain
Soils
IV
25
60 - 80
Place by hand
60 - 80
60 - 80
60 - 80
__
80 - 95
80 - 95
60 - 80
60 - 80
__
__
80 - 95
Note: This table serves as an approximate guide defining average Proctor densities attained through
various methods of soil consolidation in different classes of soil. The table is intended to
provide guidance and is not recommended for design use. Actual design values should be
developed by the engineer for specific soils at specific moisture contents.
Dump
__
80 - 95
Consolidate by saturation
Tamp by hand
80 - 95
Densify by
by portable
portable vibrators
vibrators
Density
60 - 75
60 - 75
__
__
75 - 90
Bedding
1. Bedding is required to bring the trench bottom up to grade
and to provide longitudinal support under the pipe. Blocking must not be used to bring the pipe to grade.
2. Bell holes are necessary at each joint to maintain continuous support for the pipe.
3. Bedding thickness of 4 to 6 inches of compacted material is usually adequate.
4. Use of well-graded material is recommended where
trench native soil is fine-grained.
26
Haunching
1. Haunching provides side support to the pipe. This area
is the most important for controlling pipe deflection.
2. Haunching material should be worked under the sides
of the pipe to ensure side support.
3. Where coarse materials have been used for bedding,
the same materials should be used for haunching.
4. Haunching should extend to the springline of the pipe.
Initial Backfill
1. Initial backfill is placed to protect the pipe from impact
damage during final backfill.
2. Since initial backfill provides little additional structural
support, special compaction is not required.
Final Backfill
1. Material - The material used for final backfill need not be
as carefully selected as material in the embedment zone,
but should not contain boulders, frozen clumps or rubble
which could damage the pipe.
2. Compaction - Under open fields, natural compaction
should be adequate. Under improved surfaces, special
compaction (as specified by the design engineer) is required.
27
28
Chapter IV
Pipe Assembly
29
30
Gasketed Pipe
PWEagle gasketed pipe is an integrally belled product.
All gaskets are installed at the factory.
The joint is engineered to provide problem-free service for the life of the pipe, but proper procedures must be
followed to ensure its effectiveness.
31
33
9. If the pipe must be field-cut, mark the entire circumference of the pipe to ensure a square cut. The pipe can be
cut with a hacksaw, handsaw, or portable powersaw with
a steel blade or abrasive disc.
34
10. Bevel the cut end using a pipe beveling tool or a portable sander or abrasive disc. Round off any sharp edges
on the leading edge of the bevel with a pocket knife or
a file. Mark cut end with an insertion line similar to
uncut pipe.
Bevel requirements may vary with different joint types:
Joint
a. PVC pipe Bell
b. PVC push-on fitting
c. Other pipe bell/pushon fitting
d. Mechanical joint fitting
Bevel
Same as factory bevel
Same as factory bevel
Shorter bevel length
No bevel
35
Solvent-Cemented Pipe
1. Specifications
Solvent-cemented joints should be made in accordance
with ASTM D 2855 Standard Recommended Practice
for Making Solvent-Cemented Joints with Polyvinyl Chloride (PVC) Pipe and Fittings. The solvent cement should
conform to ASTM D 2564 Standard Specification for Solvent Cements for Polyvinyl Chloride (PVC) Plastic Pipe
and Fittings, and the primer should conform to ASTM F
656 Specification for Primers for Use in Solvent Cement
Joints of PVC Plastic Pipe and Fittings. The handling of
solvent cements should be in accordance with ASTM F
402 Standard Recommended Practice for Safe Handling
of Solvent Cements Used for Joining Thermoplastic Pipe
and Fittings.
2. Basic principles of solvent-cemented joints:
a. The joining surfaces must be clean and dry.
b. The joining surfaces must be softened and made semifluid.
c. Sufficient cement must be applied to fill the gap between male and female ends.
36
37
inserted. Insert the pipe into the fitting and check that the
interference occurs about 1/3 to 2/3 of the socket depth.
Sometimes, when the pipe and fittings are at their tolerance extremes, it may be possible to fully insert the dry
pipe into the fitting socket until it bottoms. If this occurs,
extra care must be taken to apply sufficient cement to fill
the gap between pipe and fitting in order to obtain a strong
leak-free joint.
38
39
40
After assembly, wipe excess cement from the pipe at the end
of the socket. Any gaps in the cement bead around the pipe
perimeter may indicate a defective assembly.
h. Set Time Handle the newly assembled joints carefully
until after the set period as follows:
Temperature Range
F
C
60 to 100
15 to 40
40 to 60
5 to 15
20 to 40
-5 to 5
0 - 20
-20 to -5
i. Weather Precautions
a. High humidity Quick application of primer and cement is essential to minimize condensation of moisture.
b. High temperatures Temperature of PVC surfaces
should not exceed 110 F (45 C) at the time of assembly.
c. Low temperatures At temperatures below freezing,
solvents penetrate the PVC surfaces more slowly than
in warmer weather. Testing on scrap pipe is recommended.
d. Store cements and primers between 40 F (5 C) and
70 F (21 C) when not in use.
e. Allow for adequate expansion and contraction with proper
shading methods or with expansion couplings.
6. Installation
After the set period, the pipe may be carefully laid in a prepared ditch. For temperature considerations see page 71,
Thermal Expansion and Contraction.
7. Cure Period
The cure period before testing depends on the specific cement, the size of the pipe, the ambient temperature, and the
joint tightness. Cure time may vary from minutes to days.
Consult cement manufacturer for information.
8. Safe Handling of Primers and Solvent Cements
a. Keep solvent cements and primers away from all sources
of ignition.
b. Provide adequate ventilation to reduce fire hazard and
to minimize breathing of vapors.
c. Avoid contact with skin and eyes.
d. Refer to ASTM F 402 for more information.
41
42
Chapter V
Testing
43
44
General
This chapter gives PWEagles recommendations for project
testing, but the final authority on testing requirements is the
project engineer.
Water pipe installations are tested for pressure and leakage. PWEagle recommends simultaneous pressure and leakage tests. If the tests are to be done separately, the pressure
test should be done first.
It is good installation practice to test portions of a line as
they are completed. Sections that fail to pass testing should be
located, repaired, and retested until tests are passed.
Prior to the start of testing, the following steps are required:
[Link] pipe to be tested should be backfilled to prevent movement while under test pressures. Where possible, leave
joints uncovered during testing to allow for easier inspection.
2. At fittings, permanent thrust restraint is required sufficient
to withstand test pressures. If concrete thrust blocks are
used, the concrete must be allowed to cure before testing
begins.
[Link] ends are to be capped and braced to withstand forces
developed by test pressures.
45
46
WARNING:
DO NOT USE AIR
PRESSURE FOR TESTING PVC
WATER PIPE. INJURY OR DEATH
MAY RESULT
DUE
TO THE
CATASTROPHIC NATURE OF
PIPE FAILURE SHOULD FAILURE
OCCUR. (RAPID EXPANSION OF
COMPRESSED AIR COULD EXPEL
SHARP FRAGMENTS OF PIPE
MATERIAL AT HIGH VELOCITY.)
47
48
Chapter VI
Service
Connections
49
50
General
Service connections range in size from 5/8-inch lines
for single-family homes to large lines for fire service or industrial use. Connections may be made by tapping directly
into the wall of the pipe, by tapping through service saddles,
or by using tapping sleeves.
Much of the information in this chapter is taken from the
Uni-Bell PVC Pipe Associations Tapping Guide for PVC
Pressure Pipe. Contact PWEagle for a copy of the guide.
Another source of information is a short video made by Uni
Bell titled Tapping PVC Pressure Pipe.
The illustrations used in this chapter depict specific tooling for the sake of clarity. It is not the intent of PWEagle to
promote specific types of equipment or the equipment of a
particular manufacturer.
51
52
Direct Tapping
General
Direct tapping involves the tapping of threads into the
pipe wall and the insertion of a corporation stop. Direct tapping is recommended for PVC water distribution pipe manufactured in accordance with AWWA C900 in nominal sizes
6 inch through 12 inch (150 mm through 305 mm) in pressure classes 150 (DR 18) and 200 (DR 14).
Direct tapping is not recommended for 4 inch pressure
class 150 or 200 pipe. In these cases, service clamps or
saddles should be used.
Equipment
1. Tapping Machine: Mechanical device used to install the
direct tapped connection into water mains. The tapping
machine may vary in design and operation depending
on the specific machine manufacturer. The machine must
operate with a cutting/tapping tool which is classified as
a core cutting tool (either with internal teeth or with double
slots) of the shell design which retains the coupon cut
while penetrating the wall of the water main. The tapping
53
Procedures
1. Planning the Direct Tap:
a. Only AWWA C900 Class 150 and 200 PVC pipes 6
(150 mm) through 12 (305 mm) can be direct tapped.
b. Taps up to 1 inch max. can be made directly (i.e. 5/8,
3/5 and 1).
c. Wet taps (pipe filled) or dry taps (pipe empty) are allowed. Wet taps are preferred.
d. The maximum allowable pressure in the pipe at the
time the wet tap is being completed is the rated pressure class of the pipe (i.e. DR 18, PC 150; DR 14, PC
200).
e. Corporation stops must have AWWA C800 thread. Iron
pipe threads are not recommended for the pipe wall.
f. Use a combination core drill and tap when tapping
direct. Do not use twist drills designed for tapping hard
wall pipes.
g. Recommended temperature limits:
Dry taps: 0 F (-18 C) to 100 F (38 C)
Wet taps: 32 F (0 C) to 90 F (32 C)
These temperatures refer to the temperature of the
pipe itself, which is closely related to air temperature
in most cases.
h. Placement
- Tap no closer than 24 inches (600 mm) from the
ends of the pipe.
- Stagger multiple taps and keep them at least 18
inches (450 mm) apart lengthwise.
- Avoid tapping into a discolored surface.
55
Nominal
Pipe Size
10
12
A (inches)
14.0
11.0
8.5
7.0
RIGHT
Pipe O.D.
(inches)
6.90
9.05
11.10
13.20
57
58
RIGHT
If the cutter is fed too fast, a
plug of material is pushed out
of the I.D. of the pipe where
the tool emerges. The condition of the coupon provides
a check of correct tapping procedures.
At the first sign of a crown on
the coupons, the tapping procedure or the condition of the
tools should be re-examined
and corrected before more
taps are attempted.
59
60
61
Saddle Tapping
General
The use of saddles to make taps in PVC pressure pipe
is recommended for any size or class of pipe. Service connections may be made using a service clamp or saddle.
Maximum outlet size recommended with service clamps or
saddles is 2 inches (50 mm). When making this type of connection, equipment is used which attaches to the corpora-
tion stop permitting a cutting tool to be fed through the corporation stop to cut a hole in the pipe. No tapping of the pipe
wall is required since the corporation stop is threaded into
the service clamp.
Equipment
1. Service Clamps or Saddles
a. Service clamps or saddles used for attaching service connections to PVC water pipe should:
Provide full support around the circumference of
the pipe.
Provide a bearing area of sufficient width along
the axis of the pipe, 2 inch (50 mm) minimum,
insuring that the pipe will not be distorted when
the saddle is tightened.
62
63
Procedure
1. Evenly tighten the saddle to the pipe. Do not overtighten
the bolts. (If the bolts are overtightened, stresses will
be introduced into the wall of the pipe.) The torque required is generally approximately 20 ft. lb.
2. Screw the inlet side of the main stop into the saddle
threads. Retain the stop hardware as supplied.
3. Open the main stop.
4. Using the appropriate adapter and gasket, attach the
drilling machine to the main stop outlet threads. Use a
machine with an operator-controlled feed rate. Be sure
to follow the machine manufacturers instructions.
5. The use of a core drill is essential. The key to tapping
PVC pipe lies in advancing the feed nut slowly enough
to allow the core drill to cut the pipe rather than forcing
it through the pipe wall.
6. Lower the boring bar to the main and rotate the cutter
while exerting finger-pull on the feed handle. Rotate the
ratchet handle one complete turn for every 1/8 turn of
the feed yoke.
7. After the cutter has penetrated the pipe wall, withdraw
the cutter, close the main stop, and remove the drilling
machine.
8. After the machine has been removed, tighten the saddle
bolts to ensure that the saddle gasket will seal.
64
Tapping Sleeve
and Valve
General
Tapping sleeves and valves are used when service connections larger than 2 inches (50 mm) must be made in PVC
water mains. Tapping sleeves may be used for making large
taps under pressure. The use of tapping sleeves and valves to
make taps in PVC pressure pipe is recommended for any size
or class of pipe. When making this type of connection, equipment is used which attaches to the valve permitting a cutting
tool to be fed through the valve to cut a hole in the pipe. No
tapping of the pipe wall is required since the valve is attached to
the tapping sleeve.
Equipment
1. Tapping Sleeves and Valves:
a. When tapping sleeves are ordered from the manufacturer, the outside diameter of the pipe being tapped,
the size of the outlet desired and the working pressure
(or test pressure, if higher) should be specified to insure that the sleeve furnished will be satisfactory. Leadjoint sleeves should not be used.
b. Tapping sleeves should:
Provide full support around the circumference of the
pipe.
c. Tapping sleeves should not:
Distort the pipe when tightened.
Have lugs that will dig into the pipe when the sleeve
is tightened.
Have a clamping arrangement which is not fully contoured to the outside diameter of the pipe.
d. When ordering tapping valves, dimensions and attaching mechanisms consistent with the tapping sleeves
should be specified.
2. Cutting Tool: A toothed core cutter which retains the coupon, similar to those used for other materials, should be
65
Procedures
1. The tapping sleeve should be assembled on the pipe in
accordance with the manufacturers directions, insuring that no pipe distortion occurs. The tapping valve is
then connected to the sleeve.
2. Tapping sleeves should be well supported independently
from the pipe during the tapping. Support used should
be left in place after tapping. Thrust blocks should be
used as with any other fitting or appurtenance.
3. Attach the drilling machine and adaptor to the valve
outlet flange. Position the necessary support blocks.
Open the tapping valve, advance the cutter and cut the
hole into the main through the sleeve. Retract the cutter
and then close the tapping valve. Remove the drilling
machine and attach the new line or lateral.
66
Chapter VII
Special
Considerations
67
68
Longitudinal
Bending
1. The ability of PVC pipes to bend is a signficant advantage over rigid pipes.
2. Longitudinal bending may be done deliberately during
construction or may be the result of changes that occur
in the pipe-soil system after construction.
69
70
Thermal Expansion
and Contraction
1. All materials expand and contract with changes in temperature. Linear expansion of pipe in the longitudinal
direction is dependent on:
a. Variation in temperature.
b. Coefficient of thermal expansion of the material. It is
important to note that the rate of thermal expansion
and contraction is not dependent on pipe size or wall
thickness.
2. The coefficient of thermal expansion for PVC is 3.0 x
10-5 in/in/ F ( 5.4 x 10-5 mm/mm/ C).
3. Allowance for the movement:
a. 0.36 inch of length variation for every 100 feet of
pipe for each 10 F change in temperature.
b. 5.4 mm of length variation for every 10 meters of
pipe for each 10 C change in temperature.
71
4. Gasketed Joints When gasketed joints are used, thermal movement is not a significant design factor as long
as:
a. Pipe temperatures are kept within accepted limits for
PVC pipe.
b. Joints are properly installed with the pipe spigots inserted into the bells to the insertion line.
WARNING: IF PIPE SPIGOTS ARE INSERTED
PAST THE INSERTION LINE, THERMAL EXPANSION MAY CAUSE SIGNIFICANT
STRESSES IN THE PIPE BELLS.
5. Solvent Cemented Joints When solvent cemented
joints are used, thermal movement cannot be accommodated in the pipe joints. The following installation procedures are recommended (after the joints are properly cured):
a. Small diameter pipes (1/2 inch to 2 1/2 inch) When
installation temperature is substantially lower than operating temperature, the pipe should be installed with
straight alignment and brought up to operating temperature. This procedure will permit expansion of the
pipe to be accommodated by snaking action. When
installation temperature is substantially above operating temperature, the pipe should be installed by
snaking in the trench.
b. Large Diameter Pipes (3 inch and larger) Pipe
should be installed in straight alignment. Before backfill to the extent that restricts longitudinal movement,
the product temperature should be adjusted to within
15 F (8 C) of operating temperature.
6. Where the operating temperature cannot be closely controlled, the stresses resulting from extreme temperature variations must be considered in the design. The
design engineer should be consulted for guidance.
72
73
74
Appurtenances
1. Valve and fitting weights should not be carried by PVC
pipe. Most valves and fittings may be supported on properly compacted bedding, but in some soil conditions,
concrete cradles may be required for heavy valves.
2. AWWA C900 and C905 pressure pipe is produced in
cast-iron pipe size (CIPS). This means that ductile iron
valves and fittings are compatible with CIPS PVC pipe.
3. Similarly, iron pipe size (IPS) PVC pipe is compatible
with appurtenances used for steel pipe.
4. Butterfly valves may not function properly on some heavywalled PVC pipe because wall thickness may interfere
with disc movement. Special adapters may be required.
5. Most fittings do not allow as much spigot insertion depth
as do pipe bells and couplings. When assembling a PVC
pressure pipe to an iron fitting (push-on or mechanical
joint), remove all but 1/4 inch of the factory made bevel
from the spigot end of the pipe. Bottom the pipe in the
bell of the iron fitting.
75
Thrust Restraint
The large thrust forces exerted in water distribution
systems require thrust restraint designed to resist test pressures as well as peak operating pressures.
1. When concrete thrust blocks are used, the size and type
of blocking must be based on the maximum thrust force
expected and the load-bearing capacity of the soil.
THRUST BLOCKS
76
Application Precautions
1. Entrapped air During filling of pipe with water for testing or operation, air should be allowed to escape through
valves or corporation stops at the high points of the line.
Removal of entrapped air reduces surge pressures (water hammer) in the line.
2. Pressurized air PWEagles pressure water pipe is not
intended for air pressure testing or service.
WARNING: Do not use PWEagle products for pressurized air applications, as injury may result.
3. Safety All applicable federal, state, and local safety
regulations should be followed.
77
78
Index
Appurtenances 75
Backfill, final 27
Backfill, initial 27
Backhoe 32
Bedding 20, 21, 26
Bell holes 26
Bending 69
Bevel 35, 75
Compaction 17, 18, 23, 24
Cutting 34, 37, 38
Cutting Tool 34, 37
Dewatering 15
Direct Tapping 53-61
Embedment 20-22, 24
Entrapped air 77
Fittings 38, 75
Foundation 15, 20
Gasket 9, 31-33
Handling 8-10
Haunching 15, 27
Impact 8, 10, 27
Impact Strength 73, 74
Leakage, allowable 47
Leakage testing 45, 46
Lubricant 31
79
Minimum Cover 19
Moveable trench support 18, 19
Pipe assembly 2941
Pressurized air 44, 77
Primer 36, 39, 41
Prism load 15
Receiving 7
Reference mark 32, 33, 35
Saddles 62-64
Saturation 23
Service connections 51-66
Soil Classifications 21-22
Solvent cement 36, 37, 39
Specifications 3, 36
Stop line 32, 33, 35
Storage 9, 37
Stringing 11
Subditch 17
Supported trench 18, 19
Tapping sleeves 65, 66
Testing 4547
Thermal effects on PVC properties 73
Thermal expansion 71
Thrust restraint 45, 76
Trench width 1518
Ultraviolet radiation 74
Unloading 8
Valves 65, 66, 75
Warranty 4
80