Hilti HIT-RE 500
post-installed rebars
Hilti HIT-RE 500 post-installed rebars
Injection mortar system
Benefits
Hilti
HIT-RE 500
330 ml foil pack
(also available
as 500 ml
and 1400 ml
foil pack)
Static mixer
- suitable for non-cracked concrete
C 20/25 to C 50/60
- high loading capacity
- suitable for dry and water
saturated concrete
- under water application
- large diameter applications
- high corrosion resistant
- long working time at elevated
temperatures
- odourless epoxy
Rebar
Concrete
Fire
resistance
European
Technical
Approval
DIBt approval
Drinking
water
appoved
Corossion
tested
PROFIS
Rebar
design
software
Service temperature range
Temperature range: -40C to +80C (max. long term t emperature +50C, max. short term temperature +80C) .
Approvals / certificates
Description
European technical approval
European technical approval
DIBt approval
Fire test report
Assessment report (fire)
810
Authority / Laboratory
DIBt, Berlin
DIBt, Berlin
DIBt, Berlin
IBMB Braunschweig
Warringtonfire
No. / date of issue
ETA-08/0105 / 2008-07-30
ETA-04/0027 / 2009-05-20
Z-21.8-1790 / 2009-03-16
3357/0550-5 / 2002-07-30
WF 166402 / 2007-10-26
09 / 2012
Hilti HIT-RE 500
post-installed rebars
Materials
Reinforcmenent bars according to EC2 Annex C Table C.1 and C.2N.
Properties of reinforcement
Product form
Class
Characteristic yield strength f yk or f 0,2k (MPa)
Bars and de-coiled rods
B
400 to 600
Minimum value of k = (ft/fy)k
1,08
Characteristic strain at maximum force, uk (%)
5,0
Bendability
Maximum deviation from
nominal mass
(individual bar) (%)
Bond:
Minimum relative rib area,
fR,min
C
1,15
< 1,35
7,5
Bend / Rebend test
Nominal bar size (mm)
8
>8
Nominal bar size (mm)
8 to 12
> 12
6,0
4,5
0,040
0,056
Setting details
For detailed information on installation see instruction for use given with the package of the product.
Curing time for general conditions
Data according ETA-08/0105, issue 2008-06-30
Temperature
Initial curing time
Working time in which
of the
rebar can be inserted and
tcure,ini
base material
adjusted tgel
2h
18 h
5 C TBM <
10 C
90 min
12 h
10 C TBM < 15 C
30
min
9h
15 C TBM < 20 C
20 min
6h
20 C TBM < 25 C
20 min
5h
25 C TBM < 30 C
12
min
4h
30 C TBM < 40 C
TBM = 40 C
12 min
4h
Curing time before rebar
can be fully loaded tcure
72 h
48 h
24 h
12 h
12 h
8h
4h
For dry concrete curing times may be reduced according to the following table. For installation temperatures below
+5 C all load values have to be reduced according to the load reduction factors given below.
Curing time for dry concrete
Temperature
of the
base material
TBM = -5 C
TBM = 0 C
TBM = 5 C
TBM = 10 C
TBM = 15 C
TBM = 20 C
TBM = 30 C
TBM = 40 C
09 / 2012
Additional Hilti technical data
Working time in which
Initial curing
rebar can be inserted and
time
adjusted tgel
tcure,ini
4h
36 h
3h
25 h
2h
18 h
2h
12 h
1h
9h
30 min
6h
20 min
4h
12 min
2h
Reduced curing time
before rebar can be
fully loaded tcure
72 h
50 h
36 h
24 h
18 h
12 h
8h
4h
Load
reduction
factor
0,6
0,7
1
1
1
1
1
1
811
Hilti HIT-RE 500
post-installed rebars
Dry and water-saturated concrete, hammer drilling
a)
) Note: Manual cleaning for element sizes d 16mm and embedment depth hef 20 d only!
812
09 / 2012
Hilti HIT-RE 500
post-installed rebars
Dry and water-saturated concrete, diamond coring drilling; Hilti technical information only
a)
Note: Manual cleaning for element sizes d 16mm and embedment depth hef 20 d only!
Fitness for use
Some creep tests have been conducted in accordance with ETAG guideline 001 part 5 and TR 023 in the following
conditions : in dry environnement at 50 C during 90 days.
These tests show an excellent behaviour of the post-installed connection made with HIT-RE 500: low
displacements with long term stability, failure load after exposure above reference load.
09 / 2012
813
Hilti HIT-RE 500
post-installed rebars
Resistance to chemical substances
Categories
Chemical substances
Drilling dust slurry pH = 12,6
Alkaline products
Potassium hydroxide solution (10%) pH = 14
Acids
Solvents
Products from job site
Environnement
resistant
+
Non resistant
Acetic acid (10%)
Nitric acid (10%)
Hydrochloric acid (10%)
Sulfuric acid (10%)
Benzyl alcohol
Ethanol
Ethyl acetate
Methyl ethyl keton (MEK)
Trichlor ethylene
Xylol (mixture)
Concrete plasticizer
Diesel
Engine oil
Petrol
Oil for form work
Sslt water
De-mineralised water
Sulphurous atmosphere (80 cycles)
Electrical Conductivity
HIT-RE 500 in the hardened state does not conduct electrically. Its electric resistivity is 661012 .m
(DIN IEC 93 12.93). It is adapted well to realize electrically insulating anchorings (ex: railway applications,
subway).
814
09 / 2012
Hilti HIT-RE 500
post-installed rebars
Drilling diameters
Drill bit diameters d0 [mm]
Rebar (mm)
8
10
Hammer drill (HD)
a)
12 (10 )
a)
14 (12 )
a)
Compressed air
drill (CA)
-
Diamond coring
Wet (DD)
Dry (PCC)
a)
a)
a)
12 (10 )
14 (12 )
12
16 (14 )
17
16 (14 )
14
18
17
18
16
20
20
20
18
22
22
22
20
25
26
25
22
28
28
28
24
32
32
32
35
25
32
32
32
35
26
35
35
35
35
28
35
35
35
35
30
37
35
37
35
32
40
40
40
47
34
45
42
42
47
36
45
45
47
47
40
55
57
52
52
a) Max. installation length I = 250 mm.
09 / 2012
815
Hilti HIT-RE 500
post-installed rebars
Basic design data for rebar design according to rebar ETA
Bond strength in N/mm according to ETA 08/0105 for good bond conditions
for hammer drilling, compressed air drilling, dry diamond core drilling
Rebar (mm)
Concrete class
C12/15
C16/20
C20/25
C25/30
C30/37
C35/45
C40/50
C45/55
C50/60
8 - 32
1,6
2,0
2,3
2,7
3,0
3,4
3,7
4,0
4,3
34
1,6
2,0
2,3
2,6
2,9
3,3
3,6
3,9
4,2
36
1,5
1,9
2,2
2,6
2,9
3,3
3,6
3,8
4,1
40
1,5
1,8
2,1
2,5
2,8
3,1
3,4
3,7
4,0
Bond strength in N/mm according to ETA 08/0105 for good bond conditions
for wet diamond core drilling
Rebar (mm)
Concrete class
C12/15
C16/20
C20/25
C25/30
C30/37
C35/45
C40/50
C45/55
C50/60
8 - 25
1,6
2,0
2,3
2,7
3,0
3,4
3,7
4,0
4,3
26 - 32
1,6
2,0
2,3
2,7
2,7
2,7
2,7
2,7
2,7
34
1,6
2,0
2,3
2,6
2,6
2,6
2,6
2,6
2,6
36
1,5
1,9
2,2
2,6
2,6
2,6
2,6
2,6
2,6
40
1,5
1,8
2,1
2,5
2,5
2,5
2,5
2,5
2,5
Pullout design bond strength for Hit Rebar design
Design bond strength in N/mm according to ETA 04/0027 (values in table are
design values, fbd,po = Rk/Mp
Hammer or compressed air drilling.
Water saturated, water filled or submerged hole.
Uncracked concrete C20/25.
Bar diameter
temperature
range
8
I: 40C/24C
II: 58C/35C
Hilti tech data
Data according to ETA 04/0027
10
12
7,1
14
16
20
22
24
6,7
5,7
III: 70C/43C
3,3
0,1
Increasing factor in non-cracked concrete: f B,p=(fcck/25)
25
26
28
30
6,2
5,2
4,8
32
36
40
5,2
4,8
4,3
3,8
3,1
2,9
2,4
(fcck: characteristic compressive strength on cube)
Additional Hilti Technical Data:
If the concrete is dry (not in contact with water before/during installation and curing), the pullout design bond
strength may be increased by 20%.
If the hole was produced by wet diamond coring, the pullout design bond strength has to be reduced by 30%.
Reduction factor for splitting with large concrete cover: = 0,306 (Hilti additional data)
816
09 / 2012
Hilti HIT-RE 500
post-installed rebars
Fire Resistance according to DIBt Z-21.8-1790
a) fire situation anchorage
linst
Maximum force in rebar in conjunction with HIT-RE 500 as a function of embedment depth for the fire
a)
resistance classes F30 to F180 (yield strength fyk = 500 N/mm) according EC2 .
Drill hole
Max. Fs,T
Fire resistance of bar in [kN]
Bar
linst
[mm]
[mm]
[kN]
[mm]
R30
R60
R90
R120
R180
80
2,4
1,0
0,5
0,3
0
95
3,9
1,7
0,3
0,6
0,1
115
7,3
3,1
1,7
1,1
0,4
150
16,2
8,2
4,6
3,1
1,4
8
10
16,19
180
16,2
10,0
6,7
2,9
205
16,2
12,4
5,1
220
16,2
7,0
265
16,2
100
5,7
2,5
1,3
0,8
0,2
120
10,7
4,4
2,5
1,7
0,7
140
17,6
7,8
4,4
3,0
1,3
165
25,3
15,1
8,5
5,8
2,6
10
12
25,29
195
25,3
17,6
12,2
5,1
220
25,3
20,7
8,7
235
25,3
11,8
280
25,3
120
12,8
5,3
3,0
2,0
0,8
150
25,2
12,2
6,9
4,7
2,1
180
36,4
24,3
15,0
10,1
4,4
12
16
36,42
210
36,2
27,4
20,6
8,5
235
36,4
31,0
14,2
250
36,4
19,1
295
36,4
140
24,6
10,9
6,1
4,2
1,9
170
39,1
23,5
13,5
9,2
4,1
195
49,6
35,6
24,7
17,1
7,2
14
18
49,58
225
49,6
39,2
31,3
13,5
250
49,6
43,4
22,3
265
49,6
29,5
310
49,6
160
39,2
21,3
11,9
8,1
3,6
190
55,8
37,9
25,5
17,3
7,3
210
64,8
49,0
36,5
27,5
11,3
16
20
64,75
240
64,8
53,1
44,1
20,9
265
64,8
57,9
33,7
280
64,8
42,0
325
64,8
09 / 2012
817
Hilti HIT-RE 500
post-installed rebars
Bar
[mm]
Drill hole
[mm]
Max. Fs,T
linst
[mm]
R30
R60
R90
R120
R180
200
76,6
54,3
38,7
27,5
11,4
240
101,2
82,0
66,4
55,1
26,1
270
101,2
87,1
75,9
45,6
20
25
101,18
295
101,2
93,2
62,9
310
101,2
73,2
355
101,2
250
139,0
111,1
91,6
77,6
39,9
275
158,1
132,7
113,2
99,2
61,3
305
158,1
139,1
125,1
87,2
25
30
158,09
330
158,1
146,7
108,8
345
158,1
121,8
390
158,1
280
184,7
153,4
131,6
115,9
73,5
295
198,3
168,0
146,1
130,4
88,0
330
198,3
180,0
164,3
121,9
28
35
198.3
350
198,3
183,6
141,2
370
198,3
160,6
410
198,3
320
255,3
219,6
194,7
176,7
128,2
325
259,0
225,1
200,2
182,2
133,8
360
259,0
238,9
220,9
172,5
32
40
259,02
380
259,0
243,1
194,6
395
259,0
211,2
440
259,0
400
404,7
385,1
353,9
331,5
270,9
415
404,7
374,6
352,2
291,6
40
47
404,71
440
404,7
386,8
326,2
455
404,7
346,9
500
404,7
a)
For tables according the standards to DIN 1045-1988, NF-ENV 1991-2-2(EC2), sterreichische Norm B 47002000, British-, Singapore- and Australian Standards see Warringtonfire report WF 166402 or/and IBMB
Braunschweig report No 3357/0550-5.
818
[kN]
09 / 2012
Hilti HIT-RE 500
post-installed rebars
b) fire situation parallel
Max. bond stress, T , depending on actual clear concrete cover for classifying the fire resistance.
It must be verified that the actual force in the bar during a fire, Fs,T , can be taken up by the bar connection of the
selected length, linst. Note: Cold design for ULS is mandatory.
Fs, T (linst cf) T where: (linst cf) ls;
ls
= lap length
= nominal diameter of bar
linst cf = selected overlap joint length; this must be at least ls,
but may not be assumed to be more than 80
T
= bond stress when exposed to fire
Critical temperature-dependent bond stress, c, concerning overlap joint for Hilti HIT-RE 500 injection
adhesive in relation to fire resistance class and required minimum concrete coverage c.
Clear concrete cover c
Max. bond stress, c [N/mm]
[mm]
R30
R60
R90
R120
R180
30
0,7
0
35
0,8
0,4
40
0,9
0,5
0
45
1,0
0,5
0
50
1,2
0,6
55
1,4
0,7
0,5
0
60
1,6
0,8
0,5
65
1,9
0,9
0,6
0,4
70
1,0
0,7
0,5
75
1,2
0,7
0,5
80
1,4
0,8
0,6
85
1,5
0,9
0,7
90
1,7
1,1
0,8
0,5
95
2,0
1,2
0,9
0,5
100
1,4
1,0
0,6
105
1,6
1,1
0,6
110
1,7
1,2
0,7
115
2,0
1,4
0,7
120
1,6
0,8
2,2
125
1,7
0,9
130
2,0
1,0
135
1,1
2,2
140
1,2
145
1,3
2,2
150
1,4
155
2,2
1,6
160
1,7
165
1,9
170
2,1
175
2,2
09 / 2012
819
Hilti HIT-RE 500
post-installed rebars
Minimum anchorage length
According to ETA-08/0105, issue 2008-06-30, the minimum anchorage length shall be increased by factor 1,5 for
wet diamond core drilling. For all the other given drilling methods the factor is 1,0.
Minimum anchorage and lap lengths for C20/25; maximum hole lengths (ETA
08/0105)
Hammer drilling,
Compressed air drilling,
Dry diamond coring drilling
Rebar
Diameter
ds
[mm]
fy,k
[N/mm]
Wet diamond coring
drilling
lb,min*
[mm]
l0,min *
[mm]
lb,min*
[mm]
l0,min *
[mm]
lmax
[mm]
500
113
200
170
300
1000
10
500
142
200
213
300
1000
12
500
170
200
255
300
1200
14
500
198
210
298
315
1400
16
500
227
240
340
360
1600
18
500
255
270
383
405
1800
20
500
284
300
425
450
2000
22
500
312
330
468
495
2200
24
500
340
360
510
540
2400
25
500
354
375
532
563
2500
26
500
369
390
553
585
2600
28
500
397
420
595
630
2800
30
500
425
450
638
675
3000
32
500
454
480
681
720
3200
34
500
492
510
738
765
3200
36
500
532
540
797
810
3200
616
621
925
932
3200
500
40
* lb,min (8.6) and l0,min (8.11) are calculated for good bond conditions with maximum utilisation of rebar yield
strength fyk = 500 N/mm and 6 = 1,0
820
09 / 2012
Hilti HIT-RE 500
post-installed rebars
09 / 2012
821