Waterproofing 101
1. Torch Applied Membrane
2. Polyurethane System (Solvent Based)
3. Polyurea System (Pure and Hybrid)
Prepared by:
Bernabe T. Salazar Jr.
Roof Management Committee
Roof Management Committee
Engineering
Design &
Development
Objectives
To have a common understanding on the application of
the three waterproofing system for concrete.
To know the common problems of exposed torch applied
membrane.
To present the waterproofing guide matrix
2 Roof Management Committee
Engineering
Design &
Development
TORCH APPLIED MEMBRANE (Exposed)
Surface covered with
bitumen primer
3 Roof Management Committee
Engineering
Design &
Development
TORCH APPLIED MEMBRANE (Exposed)
Application
Concrete deck (exposed)
Negotiated Cost
Php 441/sqm
Warranty
5 years
Traffic rating
Light traffic (Foot Traffic)
1.
2.
3.
4.
End lapping = 6
Side Lapping=4
4 Roof Management Committee
5.
6.
Surface Preparation
Surface should be sloped
Curing of Cement should be achieved (28days)
Loose concrete should be removed
Cracked should be repaired using epoxy
injection
Water blast cleaning
Drying 24 hrs.
Engineering
Design &
Development
TORCH APPLIED MEMBRANE (Embed)
5 Roof Management Committee
Engineering
Design &
Development
TORCH APPLIED MEMBRANE (Embed)
End lapping = 6
Side Lapping=4
6 Roof Management Committee
Application
Concrete deck, Gutter
Negotiated Cost
Php 441/sqm
Concrete Topping
Pho 250/sqm
Steel Matting
Php 200/sqm
+ Smooth Finish
Php 150/sqm
Warranty
10 years
1.
2.
3.
4.
5.
6.
Surface Preparation
Surface should be sloped
Curing of Cement should be achieved (28days)
Loose concrete should be removed
Cracked should be repaired using epoxy injection
Water blast cleaning
Drying 24 hrs.
Engineering
Design &
Development
POLYURETHANE SYSTEM Seamless, UV Stable, Light to Medium Traffic
7 Roof Management Committee
Engineering
Design &
Development
POLYURETHANE : 3 COAT SYSTEM (Exposed & Embed)
Application
Concrete deck, gutter , metal
roof, (exposed and embed)
Negotiated Cost
Php 600/sqm
Warranty
10 years
Traffic Rating
Light to Medium (not vehicle)
Foot Traffic and Cart wheeled
1.
2.
3.
DFT = 1.0 2.0 mm
Solvent Based
8 Roof Management Committee
4.
Surface Preparation
Surface should shot blasted
Loose concrete should be removed
Cracked should be repaired using epoxy
injection
Corner : sealant bonding
Engineering
Design &
Development
POLYUREA SYSTEM Seamless, UV Stable, Vehicle Traffic
9 Roof Management Committee
Engineering
Design &
Development
POLYUREA SYSTEM (Exposed & Embed)
Application
Concrete deck, gutter , metal
roof, planters, etc
(exposed and embed)
Cost/sqm
Php 1,500/sqm for pure
Php 1,300/sqm for hybrid
Warranty
10 years
Traffic Rating
High Traffic
Vehicle Traffic
1.
2.
3.
DFT = 1.0 1.5mm
10 Roof Management Committee
4.
Surface Preparation
Surface should shot blasted
Loose concrete should be removed
Cracked should be repaired using epoxy
injection
Corner : sealant bonding
Engineering
Design &
Development
EVALUATION OF THE 3 WATERPROOFING MATERIALS
Torch Applied
Polyurethane
Hybrid Polyurea
Repair & Maintenance
Easy
Easy
Easy
Fail point tracing
Hard
Easy
Easy
Surface adhesion
Poor
Good
Good
Termination
overlapping connection
Seamless
Seamless
UV Reaction
Good
Stable
Stable
Traffic Rating
Foot Traffic
Foot Traffic, cart wheeled
Vehicle Traffic
Poor
Good
Good
5 years exposed
10 years embed
10 years exposed
10 years embed
10 years exposed
10 years embed
Negotiated Price
441/sqm
600/sqm
1,500/sqm
Application
Concrete
Concrete, metal
Concrete, metal, etc.*
Water ponding
Warranty
11 Roof Management Committee
Engineering
Design &
Development
Common Problem of TORCH MEMBRANE
PHOTOS FOR
MEMBRANE
12 Roof Management Committee
Engineering
Design &
Development
PHOTOS FOR
MEMBRANE
13 Roof Management Committee
Engineering
Design &
Development
PHOTOS FOR
MEMBRANE
14 Roof Management Committee
Engineering
Design &
Development
PHOTOS FOR
MEMBRANE
15 Roof Management Committee
Engineering
Design &
Development
PHOTOS FOR MEMBRANE
WATERPONDING
WATERPONDING
16 Roof Management Committee
Engineering
Design &
Development
Waterproofing Selection Matrix
17 Roof Management Committee
Engineering
Design &
Development
Waterproofing Selection Matrix
Substrate
Roof, Deck and Parking
Concrete Deck or Roof
Concrete Gutter
Parking
Metal Roof
Wet Areas
CR
Kitchen
Sump pit
Cistern Tanks
Planters
Chiller, Cooling Tower Area
Spill Dike
Walkin Chillers
Walls
Parapet
Concrete Walls (above ground)
Concrete Walls (below ground)
Rust and protective coatings
Condenser Pipes, Hangers
Duct and goose neck
18 Roof Management Committee
Exposed
Polyurethane (Solvent Based)
Polyurethane (Solvent Based)
Polyurea
Elastomeric
Covered
Epoxy Coating
Cementitious; MB Torch Applied with topping
Cementitious, MB Torch Applied with topping
Cementitious
Cementitious and Tank Lining
Polyurea, PVC
MB Torch Applied Membrane with topping
MB Torch Applied Membrane with topping
Cementitious, MB Torch Applied with topping
Elastomeric
Elastomeric
Cementitious, MB Torch Applied with topping
Epoxy coating
Acrylic paint, rust inhibitor
Engineering
Design &
Development
End of Report