Draft Punch List

This document is a draft punch list for the Chickasaw Nation Visitor Center project. It contains 63 items needing correction, organized by discipline. The items include repairs to masonry, metal cladding, curtain walls, lighting fixtures, electrical systems, fire suppression, and fire alarm systems. Once completed, test reports for fire alarm, suppression, and the backflow preventer will need to be submitted.

Uploaded by

opah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
344 views6 pages

Draft Punch List

This document is a draft punch list for the Chickasaw Nation Visitor Center project. It contains 63 items needing correction, organized by discipline. The items include repairs to masonry, metal cladding, curtain walls, lighting fixtures, electrical systems, fire suppression, and fire alarm systems. Once completed, test reports for fire alarm, suppression, and the backflow preventer will need to be submitted.

Uploaded by

opah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

LWR

09/23/13

A
A
A

X
X
X

LWR
LWR
LWR

09/23/13
09/23/13
09/23/13

5
6

Masonry lintels to be painted PT3.


Caulking at curtain wall needs to be cleaning, repaired, several
gaps at sills and head conditions are needing to be cleaned.

A
A

X
X

LWR
LWR

09/23/13
09/23/13

South entry columns are rough need, to be patched and


repainted.
Flat seam metal cladding has finish damage through out.
Finish damage and dents on curtain wall trim through out.
Large scratch in soffit at west end upper roof.
Repair finish at trim on north entry canopy.
Clean capstone along north elevation.
Repair scratched pergola steel at NE entry grid A/16
Install missing door hardware.
Install channels at lower level roller shades.

LWR

09/23/13

A
A
A
A
A
A
A
A

X
X
X
X
X
X
X
X

LWR
LWR
LWR
LWR
LWR
LWR
LWR
LWR

09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13

Cost

Item Still Open


Verification Date

Correction Date

Comment Date

Originator

Gutter has low spot in center between grid 11 and 15 along


grid Q.
Verify all reveals painted black.
Pen showing through paint at column grid 9&Q.
Downspouts to be sheet metal not PVC, upper and lower roof.

Comment

Discipline

FSB

Photographs

Room No.

Comment No.

9/23/2013

1
2
3
4

8
9
10
11
12l
13
14
15

Draft Punch [Link]

Page 1

9/24/2013

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

LWR
LWR
LWR
LWR
LWR
LWR
LWR
LWR
LWR
LWR
LWR

09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13

A
A
A
A

X
X
X
X

LWR
LWR
LWR
LWR

09/23/13
09/23/13
09/23/13
09/23/13

A
A
A
A
A
A
A

X
X
X
X
X
X
X

LWR
LWR
LWR
LWR
LWR
LWR
LWR

09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13
09/23/13

Cost

X
X
X
X
X
X
X
X
X
X
X

Item Still Open


Verification Date

A
A
A
A
A
A
A
A
A
A
A

Correction Date

Originator

Comment Date

FSB

Comment

Discipline

Photographs

Room No.

Comment No.

9/23/2013

16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37

Replace damaged ACT at open office area.


Men's 110, remove caulk at sprinkler cover.
Investigate water stain on ceiling tile at door 114A.
Clean glue on carpet in conf room.
Repair finish on interior portions of curtain wall through out.
Clean trim ring on lights at coffee bar.
Water connection for coffee maker missing.
Housing at coffee bar water cooler damaged.
Repair drywall in video room.
Elevator not operational, not punched.
Standards in gift shop millwork not flush with face of millwork.
Edge band missing at wood ceiling in gallery.
Install keyboard tray and monitor housing at info desk.
Sealant at gallery floor has gaps, repair.
Trim rings in the bottom of gallery lights not centered in fixture.
Overhead door at gift shop hits housing when moving.
Missing tile at diffuser, south wall gallery.
Edges of roller shades have roughly cut edges.
Roller shades have paint on them.
Display system missing from south wall in gallery.
North vestibule doors don't fully close.
Trim missing at inside corner curtain wall in north vestibule.

Draft Punch [Link]

Page 2

9/24/2013

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

LWR
LWR
LWR

09/23/13
09/23/13
09/23/13

LWR

09/23/13

A
A

X
X

LWR
LWR

09/23/13
09/23/13

A
A
A

X
X
X

LWR
LWR
LWR

09/23/13
09/23/13
09/23/13
09/23/13

X NOG

Cost

X
X
X

Item Still Open


Verification Date

A
A
A

Correction Date

Originator

Comment Date

FSB

Comment

Discipline

Photographs

Room No.

Comment No.

9/23/2013

38
39
40
41
42
43
44
45
46
47

48
49
50
51

Kiosk floor boxes not correctly located.


Conceal sprinkler pipe above north vestibule.
Flat seam metal cladding not correctly installed in south
vestibule.
Flat seam metal cladding not correctly installed at exterior
corner grid B.4/8.5
South entry exterior needs to be re-painted.
Joints at AESS very rough inside and outside of south
vestibule, repair.
Rotate lights at north entry to be vertical.
Stripe parking stalls.
Provide mini blind in receiving room.
Verify that the installation (fittings) of the low voltage
transformer serving the sign lighting is suitable for outdoor. If
not, install the transformer in a NEMA 3R enclosure.
Complete installation of the storm water/irrigation system
pump wiring.
Verify that the roof mounted air terminals are not painted.
All electrical equipment shall have identification label with
name and voltage rating information.
All interior lighting automatic controls (except rooms 106 and
107) wiring shall be corrected, so that the light fixtures could
be turned off manually using the single pole switch.

Draft Punch [Link]

Page 3

09/23/13

E
E

X NOG
X NOG 09/23/13
09/23/13

X NOG
09/23/13

X NOG
9/24/2013

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

Cost

Item Still Open


Verification Date

Correction Date

Comment Date

Originator

FSB

Comment

Discipline

Photographs

Room No.

Comment No.

9/23/2013

52
53
54

55
56
57
58
59
60
61
62
63

Provide a copy of the lightning protection system UL master


label certification report.
Hide sprinkler piping located above vestibule 201.
Provide head guards on sprinklers in gray water storage area
and verify head guards are on every sprinkler in mechanical
space 113B. Missing on at least one sprinkler.
Complete installation of fire department connection (FDC).
Provide notification devices in men 110 and women 111 as
required by NFPA 72.
Provide notification device in break 215.
Patch and paint ceiling around fire protection equipment in
rooms 106 and 107 where hole was not cut correctly.
Provide device in shower 109 as required by NFPA 72.
Fire alarm system is currently in trouble alarm. Correct
deficiencies causing the trouble condition.
Incorporate all changes from PR #014.
Architect must witness all testing for fire suppression and fire
alarm per the spec.
Once completed, submit all test reports for fire alarm and fire
suppression. Include backflow preventer forward flow test, and
Contractor's Underground Material and Test Certificate among
others.

Draft Punch [Link]

Page 4

09/23/13

E
FP

X NOG
X CAN 09/23/13

FP
FP

X
X

CAN 09/23/13
CAN 09/23/13

FA
FA

X
X

CAN 09/23/13
CAN 09/23/13

FA
FA

X
X

CAN 09/23/13
CAN 09/23/13

FA
FA

X
X

CAN 09/23/13
CAN 09/23/13

FA, FP

CAN 09/23/13

FA, FP

CAN 09/23/13

9/24/2013

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

Cost

Item Still Open


Verification Date

Correction Date

Comment Date

Originator

FSB

Comment

Discipline

Photographs

Room No.

Comment No.

9/23/2013

Draft Punch [Link]

Page 5

9/24/2013

Frankfurt-Short-Bruza Architects Engineers Planners

PUNCH LIST

DRAFT / IN PROGRESS

Chickasaw Nation Visitor Center

Cost

Item Still Open


Verification Date

Correction Date

Comment Date

Originator

FSB

Comment

Discipline

Photographs

Room No.

Comment No.

9/23/2013

Draft Punch [Link]

Page 6

9/24/2013

You might also like