0 ratings0% found this document useful (0 votes) 467 views14 pages020 JMS Piping
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
MELAKA REFINERY PSR-2 REVAMP PROJECT
LMS FOR PIPING FIELD FABRICATION AND
‘©C-3080-008-FF-020
INSTALLATION
‘JMS FOR PIPING FIELD FABRICATION AND INSTALLATION
Cc-3080-009-FFI-020
FOR
c¢-2080-009
MECHANICAL AND MAINTENANCE WORKS (PACKAGE A2)
t
aera a=
Pick
eae eed
a a Le [as
2 [eae [vero [wun - fe ageea
i
| eaiecieommtnteteeee eee
“TSFOR PPG FELD
HISTORICAL REVISION SHEET
Revo Rov-t
| Change Tile
‘Comment from CONSULTANT
and shall be revised Revised as per comment
CONSULTANT.
Rev Rev2
|conmerttomconsuiranT | eved specu
ease conse
BRICATION AND NSTALLATION|
TOUGH FFTOLOara
HANICAL AND MAINTENANCE WORK (AREA AZ)
"DNS FOR PIPING FIELD FABRGATION AND INSTALLATION
‘TABLE OF CONTENTS
4. SCOPE
2, REFFERANCE
3. DEFINISION
10.
PREPARATION
[Link] Receipt and Storing
4.2Matorial Traceability
[Link] Tolerances
[Link] Roquiromont
FABRICATION
INSTALLATION
REPAIR PROCEDURE (FOR WELDING DEFECT)
7.4. General
7.2, Ropalring for Stainless Stoo!
7.3. Repairing for Dissimilar Material
7.4. Base Metal Defect
PAINTING WORK
INSPECTION AND TESTING
9.1, WELD INSPECTION
9.2, PRESSURE TEST, CLEANING & DRYING FOR PIPING.
DOCUMENTATION
TOSS DOSFFT OIDCHANICAL AND MAINTENANCE WORK (AREA A2)
a
{WS FOR PING FELD FABRICATION AND INSTALLATION
1. SCOPE
This procedure describes the method for field piping fabrication and installation work
tobe applied for PSR2 REVAMP PROJECT. This method covers the following steps:
> Preparation
> Fabrication
> Installation
> Repair Procedure
> Painting
> Inspection and testing
> Documentation
2. REFERENCE
‘All works shall be carried out in accordance wth the procedures, Spectcation and /\,
Document Contract n Part B ofthe Contract Requisition including but no ited othe
following:
> APIRP 582 Welding Guitolnes or the Chemica, Ot and Gas
industries,
> ASME 831.3, Process Piping
> ASME SEC. IX Welding and Brazing Qualifications
> ASME SEC. V Non Destructive Examination
> ASME 8165 Pipe Flanges and Flanged Fiting
> ASME B109 Factory Made Wrought Steel Butt Welding Fiting
> PTS31.38.01. 11 Piping General Requirements
> PTS 30.1060. 18 ‘Welding of Metals
> PTS31.38.01.91 ‘Shop and Field Fabrication of Piping
> CC-8080-008:WCP-001 Welder Control Procedure For Construction
> CC-3080-008:WRP-002 Welding Consumable Controt Procedure
> [Link].003 Welding Procedure Specification
> CC-8080.000-PHT-004 PWT Procedure For Piping
> CC-3080-009-PEP.008 Project Execution Plan
> CC-3080-008-SCP-017 Site Construction Plan
> CC-8080-009-0A6-005 Project Quality Plan
‘CC-3080-009-PIP-018 Piping Spool Receiving Inspection Procedure
TOOT VOT FFTOLToS SR? MECHANCAL AND MANTENANCE WOR (AREA A2)
D FABRIOATION AND INSTALLATION aa
WS FOR PING
> CC-3080-008-+HST-012 Hydrostatic Test Procedure For Piping installation
> 3080-8280-00-SP-0007 Piping Material Specification
> P1S61.1006.11 Field Inspection Pir To Commissioning of Mechanical
Equipment
> 3080-8440.00-SP.0003 PM of Aloy Materia
> 3080-8440-00-SP.0004 Shep and Field Fabrication of Pipe Work A
> 3080-8710-00-PR-0001 Construction HSE Plan
3080-8710-00-PR-0012 Lift Classification Procedure
DEFINITIONS.
(OWNER shail mean Malaysia Refining Company Sdn Bhd. (MRC)
CONSULTANT Foster Wheeler E&C [Link]. (FWM) in the role of Engineering
Procurement and Construction Management CONSULTANT
CONTRACTOR shall mean Pre Engineering Sdn. Bhd,
SUBCONTRACTOR shall moan a fim which is carrying out on behalf of the
CONTRACTOR but under CONTRACTOR Management and Contrl
PREPARATION
44. Material receipt and storing
1) CONTRACTOR and SUBCONTRACTOR shall inspect all material upon
receipt and ensure that identification, dimensions, material quality and
preparations are in accordance with the approved piping spool drawing, and
receiving material report shall be submitted to CONSULTANT including back
up evidence.
Material damaged or incorrectly marked, shall be immediately brought to the
attention of CONSULTANT and subsequently placed in storage area separate
quarantined area from acceptance material with sufficient safeguard to
2
preclude its being used
3) Physical separation of different material placed into storage shall be enforced
and each batch of material shall be marked in such @ manner that it can be
related to the original specification of material and advice note.
“SOEODOSFPTOTTsea!
{NS FOR PING FELD FABRIGATION AND INSTALLATION sas
4) Carbon steel, ow temperature steel, stainless steel, piping materials shall not
be transported or stored in such a way as to cause cross contamination ofthe
materials,
5) All Pipe flanges require careful
{ull face protection at all times,
6) Allmaterial, whether loose or prefabricated, shall be stored at minimum 30 om
iandiing and storage and shall be fited wit
above ground on flat surfaces, platform type skids or other similar approved
‘supports in a manner that can prevent deterioration. Materials shall be kept
free from dit, grease, paint spray, and other foreign matter. Intemals of pipe
fitings and water senstive components of other material stored outdoors shall
be protected with plastic cover.
4.2. Material Tracoability
1) The identification and marking requirements and techniques for all materials
shall be in accordance with applicable specification of identification for piping
material. Heat number transfer of identification of this information shall be
cartied out before sections of material are removed for use,
2
IF at any time during installation or. fabrication, any piece of material is not
readily identifiable, it shall be segregated and subject reported to
‘CONSULTANT.
Fabricated spools shall be clearly and permanently marked with the spoo!
‘dentifcation. Markings shall be located and repested, it necessary, in such a
‘manner thatthe spool can be identified without lifting oF turning
The spool identification shal include individual spool sequence number, Care
shall be taken to ensure that these marks do not obliterate other identification
marks, and CONTRACTOR should consider Tracking Register for
Traceability and material matching
3
4.3. Dimensional Tolerances
In addition to the tolerances specified in the referenced codes and standards,
the folowing shall apply
TOTO DUST FTOMTsz | T
“JS FOR PING FIELD FABRIGATION AND INSTALLATION eats
Linear dimensions for the relative position of branches, bosses, instrument
tapings, flanged or but-welded ends and changes in direction, each to other,
shail not exceed +3.0 mm and tolerances shall not be cumulative.
2) Flange bolt holes shall straddle the vertical centerine of the pipe end.
Rotation of the flange from the true centerline pesiton shall nt exceed 1.8
‘mm measured at the outside edge of the flange.
83) The gasket contact surfaces of flanges shall be flat and true within 0.8 mm
measure across any diameter. If warping occurs in the fabrication proces,
the flange shall be re-faced to the original surface finish with accuracy
Provided thatthe flange thickness is not reduced below the minimum allowed
by the flange manufacturing specication. This shall be checked after re-
facing.
4.4 Welding Work Requirement
1) Welding Procedure Specification (WPS) and welder performance
{ualifcation test to be applied for constuction shall be qualified in
accordance with ASME section IK and shall be approved by
CONSULTANT. Before starting to work Contractor shal submit those
documents to CONSULTANT for review.
2) No welding works shall be carried until welding procedure specification
and the welder are qualified in accordance with project specification and
approved by Consultant.
3) __Allweiging material shall be stored in their orginal packets or cartoons in a
dry place and working welding material shall be Kept in dkyer equipment
land adequate protected fom weather effects. Low hydrogen (ype
electrodes shall be baked in accordance with the welding materials
‘manufacturer recommendation.
4) All welding joints to be executed shall have supporting steel work or
‘wooden, for anticipated of deflection,
5) Socket weld valves must be in the open position during welding. The weld
‘hall be alowed to cool between runs to provent overheating,
©) Where valves are butt-welded, consideration shall be given to the removal
‘of internals to avoid damage to seats and seal
SOFsre
LANA AND MAINTENANCE WORK (A
» |W
“TAS FOR PIPING FELD FABRICATION AND INSTALLATION To
7) For pipe sizeof 12 inch and targer, two welders shall be employed working
‘on the opposite sides of the pip.
8) Before installation, CONTRACTOR shall ensure all welding joints and
Painting shall be inspected
9) The classification and size of electrode or filer wie, are length, voltage,
‘and amperage shall be in accordance with the applicable welding
procedure and shall be suited to the thickness of material, type of grove,
‘welding position, and other circumstance at tending the work
10) Welding consumables that have been removed from the original package
shall be protected and stored so that the welding properties are not
affected
11) Allow hydrogen type electrodes shall be In hermetically sealed containers
or shall be backed by the user in conformance with AWS AS.1 and A5.S
prior to use,
12) Contractor shall fumish certification that the electrode of filer wire
conforms tothe requirements of the classification,
18) Surface on which weld metal is to be deposited shall be dry, smooth,
uniform, and free from fins, tears, crack, lamination, paint, and other
discontinuities which would be adversely affect the quality of strength of
the weld. And also shall be free from loose or thick scale, slag, rust,
moisture, grease, and other material that would be prevent proper welding,
14) Weld cleaning by brushing of other suitable means shall be applied not
nly on the finish weld surface but also to successive beads and the crater
area when welding on over previously deposited weld metal, Al slag shall
be removed.
15) Are stikes outside the area of permanent welds shall be avoided on any
base metal
16) Welds shail not be allowed to cool down until at least half the wall
thickness has been welded,
47) The root, fil, and cap of all pipe materials with diameter equal to or less
than DN 50 shall be welded using GTAW processes.
18) All GTAW machines shall be equipped with are starting devices
(high frequency, lft are).
SOBEL“INS FOR PING FELD FABRCGATION AND INSTALLATION 8013
19) The preheat temperature (if required) shall be applied throughout the
entire thickness ofthe weld and atleast 3 in on each side ofthe wel,
20) The preheat and inter pass temperature shall be checked by temperature
ingicating crayons, pyrometers or by other suitable method
21) All welding will be carried out and accordance with approved Weld
Procedures.
5. FABRICATION
1) Fabrication area
Fabrication of diferent materials, carbon steel, low temperature carbon steel,
stainless steel and support material shall be done on survey & marking of
location based on AFC drawing of piping arrangement drawing, isometric
rawing and spool drawing before execution work, segregated from each other
‘materia to prevent cross contamination during cutting & welding,
2) Proper storage and handling of piping material shall be observed to minimize
lost and damage, any damage shall be rectified and repaired before use for
fabrication & installation.
3) Cutter / blade of abrasive cutting machine for cutting austenitic stainless steel
shall be used only for austenitic stainless steel or free from ion content.
4) Thermal cutting can be used for un-alloyed or low-alloyed materials. If thermal
cutting is desired for stainless stee! (high alloy) only plasma flames cutting is
allowed. Thermally-cut surface edges shall be dressed back approximately 2
‘mm by machining or grinding to remove notch and scale.
5) If plasma gas cutting is used, bevel ends shall also be flame cut or by beveling
machine to make no deep grooves and teeth marks are visible,
6) Beveled end of pine to be welded shall be thoroughly cleaned from rust, dust, oil
tc, edge of the beveled pipe shall not be re-prepared unless the edge damage
lor the angle of bevel is diferent from as required,
7) Edge preparation (Vor flat end pipe or other) shall be done as required in
‘epproved drawing and can be proceed by grinding machine, or flame cut and
surface shall be ground smoothly and stag shall be removed from the surface
8) Tack weld shall be carried out by qualified welder, and shall be in such a way
that tacks welding must not touch the root gap or root face of the joint to be
SOOOPSR2 MECHANECAL AND MA
JIMS FOR PIPNG FELD FABRIOATION AND STALLATION oa,
‘welded. Temporary tack welds shall be smoothly removed by grinding or
chipping without reduction of wall thickness, folowed by MT or PT inspection to
confirm the linior of indication
10) Fit up shall be given with dimensions (root gap, root face etc.) as mentioned in
approved Welding Procedure Specification
11) Alljoints during fi-up shall be given at least three tack welds separated equally
‘around the diameter.
12) All field weld shall be identified by application of a box adjacent to the weld
containing: Date of welding, Joint no, Welder Stamp, Weld Procedure used,
Final inspector name,
13) For large diameter pipes and small thickness pipes, jigs used for ft up shall nat
bbe removed unless atleast 1/3 ofthe root bead has been welded,
8. INSTALLATION
1) CONTRACTOR shall inspect all prefabricated pipe work, valves, piping specials,
tc, before instalation to ensure that protective packing, covers and wrappings
are removed and intemal protective such as siica gel bags, pallets, and other
foreign matter and removed, Protective covers of pipe and equipment shall not
bbe removed until immediately prior to installation,
2) Piping shall be supported as indicated on the piping drawings. Where supports
required to faciitate
installation, they shall be of the removable type, Temporary supports shall not
transfer detrimental reactions to piping, structural members or equipment.
Welding to pipe as a temporary support measure during installation is not
permite.
3) Where pipe support attachments are to be permanenty welded tothe pipe work,
other than those shown on the piping drawings are
the welding shall be in accordance with applicable specication, employing only
Welder qualified in accordance with that specification. Galvanized material shall
not be welded to stainless stee! under any circumstances,
4) CONTRACTOR shall check all closing dimensions to equipment and make field
adjustments as necessary to assomble pipe work. All modifications other than
OBIT OO—_|__
8)
”
3
9
10)
1)
12)
13)
“TiS FOR PIPINS FELD FABRIGATION AND INSTALLATION oH
the “Field ft weld” designated on piping drawing shall be notified to
CONSULTANT as proposal for rectification before work is commenced,
Pipe work shall be carefully and accurately fabricated and installed without the
use of force to connect closing pieces. Connections to pumps, vessels,
‘compressors, ec., shall not be made until the foundation bolting is completed.
When connecting pipe work to equipment, CONTRACTOR shall ensure that
equipment manufacturers instructions are carefully observed as to removal of
‘external and internal protective devices and that the opening is clean and free
‘rom obstruction and foreign matter.
Flange faces shall be cleaned of protective coatings, ete, and checked for
‘mechanical or corrosion damage to the gasket contact surfaces.
Flange bolts shall be tightened evenly and sequentially to impose even pressure
cn gaskets and to avoid distorton or overstressing of equipment, The use of bolt
tensioning torque equipment shall be used where specified in the procedure
documents,
Flange bolting shall be made up such that the minimum required bott stresses to
achieve the desired joint requirements are met,
CONTRACTOR shall ensure that gaskets or foreign materials do net protrude
inside pipe bore,
Spiral wound gaskets shall not be re-used. Ifa flanged joint must be opened, ©.g
for system pressure testing, line flushing, removal of temporary binds or
strainers, etc., the joint shall be re-made with new gaskets and with the bolt
lubricant replenished
Flanged joints at equipment of valves employing tapped holes shall have the
thread depth checked prior to assembly to ensure that cap screws of the correct
length are used.
Flange connections to pumps, compressor and other equipment shall be the
final connection in the line minimize the period in which the equipment covers
are removed before commissioning and to enable the final closure to be made
Without subsequent force or moment from the rest of the line. Temporary
strainers (where specified) shal be included when connections are frst made up
and cleaned and should be assembled under clean conditions, in all cases
TOTO OUTFIT14)
18)
16)
ore
HANICAL AND MAINTENAW
NORK (AREA Aa)
{INS FOR PIPING FELD FABROGATION AND INSTALLATION
extreme care shall be taken to ensure no foreign matter, dt, etc, enters the
equipment.
Valve in horizontal piping shall be installed with the actuator in the upright
Position unless shown otherwise on the drawings
Wafer type check valves in horizontal piping shall be installed withthe hinge pin
in a vertical positon,
AA intine instruments and equipment shall be installed in strict conformance with
the manufacturer's instruction and recommendation.
Pipe Support installation
(@) Al supports shall be installed and accordance with the project support |
standard and shall be completed with the coating in accordance with the
painting specification.
‘Spring support shall be installed withthe stop in pasttion prominently flagged
towarn ofthe necessity for emoval ater completion of testing of the line
(©) Temporary support shal be limited to the unavoidable minimum. They shall
bbe designed and manufactured to take all loadings that they wil be
subjected to, They shall be painted a suitable color to warn of the necessity
of removal before plant start up.
(@) Temporary support shall not be attached to equipment or steel work unless.
shown on drawing
)
7. REPAIR PROCEDURE (for DEFECT WELDING)
7
GENERAL
Weld repairs! rework shall be made before any required PWHT (Post Weld
Heat Treatment) it specified
Unacceptable discontinuities shall be completely removed by chipping
gouging, grinding or other authorized method. The excavated area shall be
examined as a minimum visually to assure the discontinuity is removed
compietely
TO BOST OTF POLOPSR2 MECHANICAL AND MANTENANCE WORK (AREA A}
“JS FOR PIPING FELD FABRIGATION AND INSTALLATION.
Wold repairs shail be made using the same as with original the qualified WPS
(Welding Procedure Specification) and shall be in accordance in accordance
with ASME Ix
‘After welding, the repaired areas shall be re-examined using the same
inspection method which detected the original defect.
7.2 REPAIRING FOR STAINLESS STEEL
4) Special grind disc type and stainless steel brush shall be used to avoid
carbon inclusion and contamination.
) Are gouging shall be prohibited
7.3 REPAIRING FOR DISSIMILAR METAL
4} Special grind disc type shall be used for grinding on stainless stee!
surface.
8) Grind alse for stainless stool area shall be different from grind dise for
‘carbon steel area.
©) Stainless stee! brush shall be used for brushing on stainless steel surface,
4) Brush for stainless stee! shall be different from brush for carbon stee! area,
7.4 BASE METAL DEFECT
2) Ifdefects on the base material are found, they shall be removed by flame or
are gouging, grinding, chipping or machining
0) The excavated area shall be examined by penetrant test to make sure all
the defect is removed completely.
©) The excavated area shall be welded using the qualified WPS and the
qualified welder.
4) Weld surface defect will be visually examined, and for defect through inside
material and the root area wil be examined by Radiography,
©} The inspector shall make sure that the repairing is completed, accepted and
recorded.
8. PAINTING WORK
Painting work shall be cartied out in accordance with PTS 30.48,00.31 P. !
TOROS DOSFPTOETG
9.
INS FOR PIPING
INSPECTION AND TESTING
9a
92
10,
WELD INSPECTION
Inspection of welds shall be carried out after final heat treatment in accordance
with the inspection casses shown in see PWHT Procedure, Doc. No.
‘€C-3080-008-PHT-004 (Appendix B). The methods to be employed for
inspection, the aoceptance criteria for welds, and the progressive examination
shall all be in accordance with ASME B31.3, And Project Specification Standard,
PRESSURE TEST, CLEANING & DRYING FOR PIPING.
Pressure testing, cleaning and drying shall be carried out in accordance with ITP
for Fabrication and Pre-Commissioning and System Turnover Procedures and
documentation.
DOCUMENTATION
‘All QC documentation shall be complied In line with Project Quality Documents
and approved Inspection and Test Plans.
CONTRACTOR shall allocate sufficient personnel to compile populate and
handover QC documentation Packages for Pipe work and equipment.
‘All documents and reports shall be prepared and compiled in the Final Quality
Dossier including but not limited to:
‘Material traceabilly report
‘bWelding summary report
©. NDE report
[Link] report
2 Prossure Test report
{Painting report
[Link] Cleaning report
hAs-buit drawing
others
DFABRGATION AND INSTALLATION Bal
SORT DOS FROST