0% found this document useful (0 votes)
182 views5 pages

Lesson 7 - Earned Value Management

Earned value management (EVM) is a technique that integrates project scope, time, and cost by tracking planned value, actual cost, and earned value. Variances and indexes are calculated to measure performance and estimate project completion costs and timeline. EVM graphs allow managers to quickly see if projects are over or under budget and behind or ahead of schedule so corrective actions can be taken if needed. While estimates are used throughout EVM, the process provides an important method for controlling costs and evaluating progress.

Uploaded by

Abid Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
182 views5 pages

Lesson 7 - Earned Value Management

Earned value management (EVM) is a technique that integrates project scope, time, and cost by tracking planned value, actual cost, and earned value. Variances and indexes are calculated to measure performance and estimate project completion costs and timeline. EVM graphs allow managers to quickly see if projects are over or under budget and behind or ahead of schedule so corrective actions can be taken if needed. While estimates are used throughout EVM, the process provides an important method for controlling costs and evaluating progress.

Uploaded by

Abid Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

PROJECT MANAGEMENT

Lesson 7

EARNED VALUE MANAGEMENT

Earned value management (EVM) is a project performance measurement technique that


integrates scope, time, and cost data. Given a cost performance baseline, project managers and
their teams can determine how well the project is meeting scope, time, and cost goals by
entering actual information and then comparing it to the baseline. A baseline is the figure in the
original project plan plus approved changes. Actual information includes whether or not a
WBS item was completed, approximately how much of the work was completed, when the
work actually started and ended, and how much the completed work actually cost. In the past,
earned value management was used primarily on large government projects. Today, however,
more and more companies are realizing the value of using this tool to help control costs.
Earned value management involves calculating three values for each activity or summary
activity from a projects WBS.

Planned Value: The planned value (PV), also called the budget, is the portion of the approved
total cost estimate planned to be spent on an activity during a given period. Suppose that a
project included a summary activity of purchasing and installing a computer and according to
the plan, it would take one week and cost a total of Rs. 40,000 for the labor hours, hardware,
and software. The planned value (PV) for the activity that week is Rs. 40,000.

Actual Cost: The actual cost (AC) is the total direct and indirect costs incurred in
accomplishing work on an activity during a given period. For example, suppose that it actually
took two weeks and cost Rs. 60,000 to purchase and install the computer. Assume that Rs.
30,000 of these actual costs were incurred during Week 1 and Rs. 30,000 was incurred during
Week 2. These amounts are the actual cost (AC) for the activity each week.

Earned Value: The earned value (EV) is an estimate of the value of the physical work actually
completed. EV is based on the original planned costs for the project or activity and the rate at
which the team is completing work on the project or activity to date. The rate of performance
(RP) is the ratio of actual work completed to the percentage of work planned to have been
completed at any given time during the life of the project or activity. For example, suppose that
the computer installation was halfway completed by the end of Week 1. The rate of
performance would be 50 percent because by the end of Week 1, the planned schedule reflects
that the task should be 100 percent complete but only 50 percent of the work has been
completed.

Cost variance (CV): Cost variance (CV) is the earned value minus the actual cost. If cost
variance is a negative number, it means that performing the work cost more than planned. If
cost variance is a positive number, performing the work cost less than planned.

1
Schedule variance (SV): Schedule variance (SV) is the earned value minus the planned value.
A negative schedule variance means that it took longer than planned to perform the work, and a
positive schedule variance means that the work took less time than planned to perform.

The cost performance index (CPI): The cost performance index (CPI) is the ratio of earned
value to actual cost; it can be used to estimate the projected cost of completing the project. If
the CPI is equal to one, or 100 percent, then the planned and actual costs are equalthe costs
are exactly as budgeted. If the CPI is less than one or less than 100 percent, the project is over
budget. If the CPI is greater than one or more than 100 percent, the project is under budget.

The schedule performance index (SPI): The schedule performance index (SPI) is the ratio of
earned value to planned value; it can be used to estimate the projected time to complete the
project. Similar to the cost performance index, an SPI of one, or 100 percent, means the project
is on schedule. If the SPI is greater than one or 100 percent, then the project is ahead of
schedule. If the SPI is less than one or 100 percent, the project is behind schedule.

After you total the EV, AC, and PV data for all activities on a project, you can use the CPI and
SPI to project how much it will cost and how long it will take to finish the project based on
performance to date. Given the budget at completion and original time estimate, you can divide
by the appropriate index to calculate the estimate at completion (EAC) and estimated time to
complete, assuming that performance remains the same.

Estimate at Completion (EAC): The cost performance index can be used to calculate the
estimate at completion (EAC)an estimated cost of completing a project based on
performance to date. You can graph earned value information to track project performance.
Figure below shows an earned value chart for a one-year project after five months. Note that
the actual cost and earned value lines end at five months because the data was collected or
estimated at that point. The chart includes three lines and two points, as follows:
Planned value (PV), the cumulative planned amounts for all activities by month. Note that the
planned value line extends for the estimated length of the project and ends at the BAC point.
Actual cost (AC), the cumulative actual amounts for all activities by month.
Earned value (EV), the cumulative earned value amounts for all activities by month.

2
Budget at completion (BAC), the original total budget for the project, or $100,000 in this
example. The BAC point is plotted on the chart at the original time estimate of 12 months.
Estimate at completion (EAC), estimated to be $122,308 in this example. This number is
calculated by taking the BAC, or $100,000 in this case, and dividing by the CPI, which was
81.761 percent. This EAC point is plotted on the chart at the estimated time to complete of
12.74 months. This number is calculated by taking the original time estimate, or 12 months in
this case,
and dividing by the SPI, which in this example was 94.203 percent.

Table below summarizes the formulas used in earned value management. Note that the
formulas for variances and indexes start with EV, the earned value. Variances are calculated by
subtracting the actual cost or planned value from EV, and indexes are calculated by dividing
EV by the actual cost or planned value.

Term Formula
Rate of Performance (RP) RP = %Complete / %Planned
Earned Value (EV) EV = PV (to date) x RP
Schedule Variance SV = EV PV
Cost Variance CV = EV AC
Schedule Performance Index (SPI) SPI = EV / PV
Cost Performance Index (CPI) CPI = EV / AC
Estimate At Completion (EAC) EAC = BAC/CPI
Estimated Time to Complete (ETC) Original Time Estimate / SPI

3
Earned value charts allow you to see quickly how projects are performing. If there are serious
cost and schedule performance problems, top management may decide to terminate projects or
take other corrective action. The EACs are important inputs to budget decisions, especially if
total funds are limited. Earned value management is an important technique when used
effectively, because it helps top management and project managers evaluate progress and make
sound management decisions. It is important to remember that the heart and soul of EVM are
estimates. The entire EVM process begins with an estimate; when the estimate is off, all the
calculations will be off. Before an organization attempts to use EVM, it must learn to develop
good estimates. Earned value management is the primary method available for integrating
performance, cost, and schedule data. It can be a powerful tool for project managers and top
management to use in evaluating project performance. Project management software, such as
MS Project, includes tables for collecting earned value data and reports that calculate variance
information.

4
Example

RP
EV= SPI= CPI= ETAC =
Activities (%Complt/ SV= CV= BAC EAC=
PV PV*RP AC (EV/PV) (EV/AC) BAC/SPI
%Schdld) EV-PV EV-AC BAC/CPI

A 2000 1 2000 2300 0 -300 100.00% 86.96%


B 2500 1 2500 2500 0 0 100.00% 100.00%
C 3000 0.7 2100 2500 -900 -400 70.00% 84.00%
D 2400 1 2400 2200 0 200 100.00% 109.09%
E
F
G
9900 9000 9500 -900 -500 90.91% 94.74% 20900 22061.11 12.10

You might also like