Gantt Chart for Infrastructure Upgrade

This Gantt chart outlines the timeline for a 4-year project to upgrade infrastructure facilities at the National College of Arts in Lahore, Pakistan. It involves renovating and constructing several buildings, upgrading labs, installing solar panels and LED lights, improving services, and boosting faculty capacity. Key activities include procuring equipment, retrofitting windows, re-laying pipes and wires, building a boys' hostel and parking structure, restoring a historic building, and hiring project staff. The project aims to modernize the college's facilities through 2024.

Uploaded by

xahidlala
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
240 views1 page

Gantt Chart for Infrastructure Upgrade

This Gantt chart outlines the timeline for a 4-year project to upgrade infrastructure facilities at the National College of Arts in Lahore, Pakistan. It involves renovating and constructing several buildings, upgrading labs, installing solar panels and LED lights, improving services, and boosting faculty capacity. Key activities include procuring equipment, retrofitting windows, re-laying pipes and wires, building a boys' hostel and parking structure, restoring a historic building, and hiring project staff. The project aims to modernize the college's facilities through 2024.

Uploaded by

xahidlala
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Activity Details
  • Project Plan Overview

NATIONALCOLLEGEOFARTS,LAHORE

GANTTCHART/WORKPLANFORTHEPROJECT"UPGRADATIONOFINFRASTRUCTUREFACILITIESNCA"
YEAR01 YEAR02 YEAR03 YEAR04
Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4
a Equip.&UpgradationofLabs
1 TenderProcess
2 ProcurementProcess
3 Installation&Commissioning
b Furniture&Elevators
1 Designingoffurniture
2 TenderProcess
3 ProcurementProcess
4 Installation&Commissioning
c RetrofittingofWindows
1 TenderProcess
2 RemovalofExistingWindows
3 FabricationofNewWindow
4 FixingofNewWindows
5 FabricationofGlassRetrofit
6 FixingofGlassRetrofit
d ReLayingofServices
1 HiringofConsultant
2 PreparationofTenderDocuments
3 TenderProcess
4 Relayingofservices
5 Pavement&Repairofwalkways
6 ConstructionofOHWT
e SolarSystem
1 Survey&PreparationofTender
2 TenderProcess
3 RetrofittingofLEDLights&Fans
4 ConstructionofParkingStructure
5 Constructionofmountingstructures
6 InstallationofPVModules
7 InstallationofBatteries
8 InstallationofHybridInverter
9 Commissioningofthesystem
f RestorationofHistoricBuilding
1 HiringofConsultant
2 PreparationofTender
3 TenderProcess
4 EvacuationoftheBuilding
5 Alternateaccomodationarrangement
6 FixingStructuralproblems
7 FixingRoofproblems
8 Layingofservices
9 Flooring
10 FaadeTreatment
11 Commissioningofbuilding
g Const.ofBoysHostelNewBuilding
1 HiringofConsultant
2 PreparationofTender
3 TenderProcess
4 Foundationofthebuilding
5 Superstructure
6 Services
7 Flooring&Tiling
8 SurfacerenderingInternal&external
9 FixingofDoors&Windows
10 Commissioningofbuilding
h ModelMaking&EnvironmentLab
1 TenderProcess
2 ProcurementProcess
3 Installation&Commissioning
i FacultyCapacityBuilding
1 ConstitutionofCommittees
2 SelectionofCandidates(PhD)
3 Admissionofthecandidates
4 StartingPhD
5 CourseCompletion
6 SelectionofCandidates(Masters)
7 AdmissionofthecandidatesPhaseI
8 StartingMasters
9 CourseCompletion
10 AdmissionofthecandidatesPhaseII
11 StartingMasters
12 CourseCompletion
13 SelectionofCandidates(Prof.Courses)
14 CourseBegin
15 CourseCompletion
j ProjectExecutionStaff
1 HiringofStaff
2 ProjectDirector
3 CivilEngineer
4 SiteSupervisor
5 ComputerOperator
6 QuantitySurveyor
7 NaibQasid