OCCUPANCY PERMIT
Source: Iloilo City Engineer’s Office
NAME OF PERMIT NO. OF COPY AGENCY
PURPOSE REQUIREMENTS CONCERNED FEE
3 copies
An Occupancy Building Permit
Permit is required 3 copies CITY
OCCUPANCY before any Electrical Permit ENGINEERING’S
building/structure 3 copies OFFICE
is used or Sanitary / Plumbing Permit TO BE ASSESSED
occupied. It is
3 copies
usually secured
Mechanical Permit
after the
completion of a 1 set
structure. It is also Issued/Approved Plan
required if there is 5 copies
any change in the Certificate of Occupancy
existing use or
occupancy Duly Accomplished Certificate Of 4 copies
classification of a Completion Forms (Building,
building, structure Plumbing/Sanitary, Electrical,
or any portion &Mechanical) signed and sealed by
thereof. duly registered Civil Engineer/Architect,
Master Plumber, Professional Electrical
Engineer, and Professional Mechanical
Engineer on their corresponding
discipline in-charge of construction
4 copies
Pictures of the building/structure
showing all sides (front, right, left,
& rear)
OTHER DOCUMENTS
Original and 2 photocopies
Fire Safety Inspection Certificate
Picture of the structure nearest to
PECO high tension line/wire for 2-
storey and above building
OCCUPANCY PERMIT
Source: Iloilo City Engineer’s Office
As built-Plan if there are significant
changes made during the
implementation stage in relation to
the issued plan
Any other requirements/documents
deemed necessary to support the
issuance of the permit