Document Reference
PROJECT No.: DPC-DN-Z1B-2016-33 kV-3 JARZIZ/E/3015/A4
CONSTRUCTION OF 2X20 MVA, 33/11KV PSS DESIGNATED AS
Rev No 0
JARZIZ (DPC/TENDER/2016/201)
Rev Date 21.05.2017
PROJECT COMPANY DHOFAR POWER COMPANY
OWNER’S ENGINEER HAMED ENGINEERING SERVICES LLC
CONTRACTOR SHARIKAT FANNIYA OMANIYA LLC
METHOD OF STATEMENT
JARZIZ - ELECTRICAL WORKS
Prepared /Reviewed by SFO Approved by SFO Approved by HES
TITLE
Electrical Engineer Site Manager Electrical Engineer
NAME
SIGNATURE
DATE
Page 1
Document Reference
PROJECT No.: DPC-DN-Z1B-2016-33 kV-3 JARZIZ/E/3015/A4
CONSTRUCTION OF 2X20 MVA, 33/11KV PSS DESIGNATED AS
Rev No 0
JARZIZ (DPC/TENDER/2016/201)
Rev Date 21.05.2017
PROJECT COMPANY DHOFAR POWER COMPANY
OWNER’S ENGINEER HAMED ENGINEERING SERVICES LLC
CONTRACTOR SHARIKAT FANNIYA OMANIYA LLC
METHOD STATEMENT: -33kV POWER CABLE PLUG-IN AND TESTING
- RELAY TESTING AND CABLE STABILITY
DOCUMENT REFERENCE NUMBER: AL SAADA II/SFO/CO443/MS/E/14
Page 2
Document Reference
PROJECT No.: DPC-DN-Z1B-2016-33 kV-3 JARZIZ/E/3015/A4
CONSTRUCTION OF 2X20 MVA, 33/11KV PSS DESIGNATED AS
Rev No 0
JARZIZ (DPC/TENDER/2016/201)
Rev Date 21.05.2017
PROJECT COMPANY DHOFAR POWER COMPANY
OWNER’S ENGINEER HAMED ENGINEERING SERVICES LLC
CONTRACTOR SHARIKAT FANNIYA OMANIYA LLC
POWER CABLE TESTING AND PLUGGING AND RELAY TESTING INSIDE AS SAADA GSS
The following activities shall be ensured by the Electrical Engineer /Testing Engineer/ QC Engineer at site:
1.0 PURPOSE
The purpose of this method statement is to provide the guidelines for activities carried out during plug-in and testing of
33kv power cable and relay testing.
2.0 APPLICABLE SPECIFICATIONS, REFERENCE STANDARDS & APPROVED DRAWINGS
Scope of work
Volume 2, Section 4, 11
Method Statement
3.0 JOB SAFETY PLAN
3.1 HAZARD IDENTIFICATION
Stored energy
Hand and power tools
Slipping and Tripping Hazard
Electrical hazard
Physical hazard
Weather condition
Live apparatus
3.2 ACTION BY THE EXECUTION TEAM.
Identification and barricading of live panels
Use Proper Personnel Protective Equipment during working.
Tripping hazard to be mechanically removed.
4.0 RESPONSIBILITY
The Electrical Engineer / Testing engineer shall be the responsible person in supervising the above activities at site.
The Quality Control Engineer shall monitor the activities for the compliance of the Specifications.
The Safety steward shall be all time available at site to monitor the safety aspects during the activity at site.
5.0 TOOLS AND EQUIPMENTS
Cutting tools
Hand tools
Drilling machine
Hipot test kit.
Multimeter
Megger 5kV
Gas torch
Page 3
Document Reference
PROJECT No.: DPC-DN-Z1B-2016-33 kV-3 JARZIZ/E/3015/A4
CONSTRUCTION OF 2X20 MVA, 33/11KV PSS DESIGNATED AS
Rev No 0
JARZIZ (DPC/TENDER/2016/201)
Rev Date 21.05.2017
PROJECT COMPANY DHOFAR POWER COMPANY
OWNER’S ENGINEER HAMED ENGINEERING SERVICES LLC
CONTRACTOR SHARIKAT FANNIYA OMANIYA LLC
Fire extinguisher
6.0 MANPOWER
a) 33kv cable Plug-in and testing
Cable jointers- 1 No.
Protection Engineer- 1 No.
Fabricator – 1 No.
Electrician – 1 No.
Helper – 1 No.
7.0 PROCEDURE
a) 33kv cable plug-in and power cable testing ( 1 DAY)
Upon receipt of necessary permit, conduct the tool box talk.
Work area shall be secured with signage’s and barricades.
The power cable of shall be identified properly.
33kv switchgear panels shall be identified and nameplates shall be provided as per DPC recommendation.
Cable plug in shall be done by competent person only.
Prior to cable plug in termination cable hipot test to be carried at the recommended voltage(68kV, 15 min)
Power cables shall be supported properly with cable clamps and supports shall be earthed to the nearest earth
bus.
33kv cable hipot shall be carried out after plug in and 33kv Circuit breaker in open condition. After proper tagging
and barricading at the GSS end, High voltage of 45kV shall be applied at the PSS end and leakage current shall be
noted down.
b) 33kv Relay testing and cable stability (1 DAY)
All necessary permits shall be obtained prior to commissioning of work.
Relay testing and cable stability testing shall be done by DCRP approved testing engineers only.
All the current injection during the relay testing and cable stability test shall be from the PSS end only.
All be testing activities will be witnessed by DPC/HES Protection Engineer.
8.0 DOCUMENTS & RECORDS.
Records shall include the following,
All quality records. (Check List)
As built Drawing.