Renovation Proposal for Markandeya Temple

This document is a letter from an Assistant Executive Engineer to a Deputy Executive Engineer regarding a proposed temple renovation project. It summarizes that the approved project estimated to cost Rs. 5 lakhs is not aligned with what needs to be done according to the temple trustees. Specifically, the DPR proposed adding iron grills and a ticket counter, but the trustees said the grills are already installed and few devotees visit to require a ticket counter. Instead, the trustees requested constructing a new building for a different temple on site that is old with a leaking roof. The Assistant Engineer inspected and agreed the trustees' proposal is genuine. Thus, there is no relevance between the approved DPR and actual work
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
355 views2 pages

Renovation Proposal for Markandeya Temple

This document is a letter from an Assistant Executive Engineer to a Deputy Executive Engineer regarding a proposed temple renovation project. It summarizes that the approved project estimated to cost Rs. 5 lakhs is not aligned with what needs to be done according to the temple trustees. Specifically, the DPR proposed adding iron grills and a ticket counter, but the trustees said the grills are already installed and few devotees visit to require a ticket counter. Instead, the trustees requested constructing a new building for a different temple on site that is old with a leaking roof. The Assistant Engineer inspected and agreed the trustees' proposal is genuine. Thus, there is no relevance between the approved DPR and actual work
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Formal Letter from Panchayat Raj Engineering Department

GOVERNMENT OF ANDHRAPRADESH

PANCHAYAT RAJ ENGINEERING DEPARTMENT

From:- To,
D.V.Srinivasa Rao, Dy.Executive Engineer,
Asst.Executive Engineer, PRI Sub Division,
PRI Sub division, Eluru
Eluru

Lr.Rc.No.108-I/AEE/Tourism Dept./2013 Dt.25.11.13

Sir,

Sub:-Works-Deposit Grant-Archeology Dept.-"Proposed Renovation&Restoration


works of Sri Markandeya Swamy Temple@ Eluru",Est.Cost.Rs.5.00 lakhs-
No correlation between DPR and the work needs to be executed-
Report submitted-Regarding

Ref:-1)DPR of Archeology Department


2)Instructions of the higher authorities
3)GO Rt.No.213 of YAT&C(PMU) Dept.Dt.15.03.2013

******

I submit that the work"Proposed Renovation&Restoration works of Sri


Markandeya Swamy Temple@ Eluru",Est.Cost.Rs.5.00 lakhs was sanctioned under vide
reference 3rd cited.In this connection,I submit that DPR prepared for the above work was also
furnished to the PR Department,so that any deviation with reference to the DPR can be brought to
the notice of the higher authorities.

The following items are proposed in the DPR:-

1)Supply and fixing of Iron Grill to the Mukhamandapam

2)Construction of ticket counter at entrance

In this connection,I submit that the Chairman,Sri.M.Srinivasa Rao and other


trustees of the temple informed that there are no considerable no of devotees visiting the temple on
regular basis,hence construction of ticket counter is not needed.They further informed that the
grills were already fixed in Mukhamandapam.

They further informed that AMMAVARI TEMPLE(Plan &Photo enclosed)


is very old and roof is also leaking.As such,they requested to construct new building for the above
said temple.After inspection of the temple,it is found the proposal of the trustees is genuine .

In this connection,I submit that there is relevance between the DPR of


archeology department and the actual work necessary for the temple.As such,it is not possible
to take up the without deviating the DPR.

This is submitted for favour of information and necessary action.

Yours faithfully

Encl:As above Asst Executive Engineer,


PRI Sub division,
Eluru