Saigon M&C Tower Project
Method Statement For Ductworks
General
Aim
Scope of works
Methodology
I. Duct Installation Works
1. Air Duct Connection
2. Air Duct Seal
3. Air Duct Insulation
II. Air Devices Installation Works
1. Volume Dampers (VD), Volume Control Dampers (VCD), Fire Dampers (FD).
2. Diffuser, Grille
3. Plenum Chamber, Silencer Chamber
4. Flexible Duct, Canvas Joints
5. Louver, Access Door, Outdooor Hood
A 12/03/09 FIRST ISSUE C.T.P N.A.K L.Q.K J.R.P
Page 2
Saigon M&C Tower Project
Method Statement For Ductworks
General:
Items: - The Method Statement for Air Distribution Installation Works.
Aim:
The aim of works is to describe mechanical works associated with installation of Air
Distribution Installation Works and to ensure compliance with contract requirements,
specification and quality control.
Scope of Works:
The scope of work for this method statement shall include all the Ductworks for the
SAIGON M&C TOWER Project.
Methodology:
I. Duct Installation Works:
Table1: Rectangular Duct Thickness Schedule
Largest Dimension (mm)
Duct Size (L max) Up to 400 600 800 ~ 1250 1600 ~ 2500 Above 2500
Steel Sheet Thickness 0.5 0.6 0.8 1.0 1.2
1. Air Duct Connection:
Table 2: Regulation for air duct connection Schedule
Corner Angle Duct
Companion Angle Duct
Connection
Less than 600 (mm) C , TDC NA
Duct size
largest 601 to 1500 (mm) TDC NA
dimension 1501 to 2500 (mm) NA Flange-40x40x3.0mm
(mm)
Over 2500 (mm) NA Flange-40x40x4.0mm
Maximum Spacing (mm) 1100 1200
Size of Bolt & Nut (mm) 8 mm 8 mm
Diameter (mm) 3.2 mm 3.2 mm
Rivet Maximum Spacing on
65 mm 65 mm
Center (mm)
Page 3
Saigon M&C Tower Project
Method Statement For Ductworks
Table 3: Support, hanger, spacing schedule
Less than 2000 ~
Duct size 400 ~ 999 1000 ~1999 Over 2500
400 2500
V- U-
Angle steel V-30x30x2.5 V30x30x2.5 V-40x40x3
50x50x3.5 80x38x3.5
Hanger
Round bar 2 x Φ8 2 x Φ10 2 x Φ10 2 x Φ10 2 x Φ12
Max. pitch L 3000 3000 2500 2500 2500
V- U-
Vertical Angle steel V-30x30x2.5 V30x30x2.5 V-40x40x3
50x50x3.5 80x38x3.5
support
Max. pitch L One point for each floor
1.1 Duct size over 1500mm:
) For duct size largest dimension over 1500mm show be as Figure 01:
Anchor bolt Concrete slab
Hanger rod M10
Air flow Air Duct Air flow
W
Angle steel
(see table 3)
Detail A L ≤ 1200
Figure 01: Typical duct connection detail (using flange joint)
) Detail A show be as Figure 02, Figure 03:
100 100
100
Angle steel flange Sealed
(see table 02)
Bolt hole 8mm
Figure 02: Detail of bolt spacing for flange joint
Page 4
Saigon M&C Tower Project
Method Statement For Ductworks
5mm thk
Washer Rubber gasket
Bolt & Nut 8mm Width: 25mm, 5mm thk
Air Duct Rivet 3.2mm
Angle steel flange
(see table 02)
Figure 03: Detail of connection angle for flange
1.2 Duct size under 1500mm:
) For duct size largest dimension under 1500mm show be as Figure 04
Air flow
Air flow Main duct
L Change between section
Detail B
Branch duct W
L = 0.25W; L≥150mm
Air flow
Figure 4: Branch duct connection detail (using Transverse Duct Connector (TDC) joint)
) Detail B show be as Figure 05, Figure 06, Figure 07
Cross aim brace
A C B C
4 hole Φ10
A
Air duct
C
B
A ≤ 150 mm
B ≤ 200 mm
C
100 mm ≤ C ≤ 150 mm
Figure 05: Detail of Cross Aim Brace Spacing
Page 5
Saigon M&C Tower Project
Method Statement For Ductworks
Cross Aim Brace
(see table 4) Rubber gasket (see figure 08)
TDC Corner (see table 4)
Air Duct
Figure 06: Cross Aim Brace detail
Table 4: Size, Thickness and Spacing of TDC Joint Schedule
Duct Size largest dimension (mm) Less than 700 700~1200 1200~1500
Size of TDC Duct End (minimum) (mm) 30 30 30
Thickness of TDC Corner (minimum) (mm) 1.2 1.2 1.2
Thickness of Cross Arm Brace (minimum)(mm) 1.0 1.0 1.0
Maximum Spacing (mm) 1100 1100 1100
TDC joint
Corner plate
(see detail) Air duct
Max 1100
TDC flange
Bolt M10
TDC corner 1.2mm thk
TDC duct end
(see table 4)
Nut M10
Rubber gasket
(see figure 08)
Nut M10
Bolt M10
Rubber gasket
(see figure 08)
Figure 07: Typical TDC assembly detail
Page 6
Saigon M&C Tower Project
Method Statement For Ductworks
Rubber gasket
Width: 25mm 15-20mm
Thickness: 5mm
Bolt hole 8mm
Figure 08: Typical rubber gasket installation detail
) Note:
? Support, hanger will be concerned on method statement of M&E Support System Installation
Work: ME - REE - T+ - MS – G+ - GEN - 003
2. Air Duct Seal:
Bolt hole 10mm
TDC joint Seal
Air Duct 50
Figure 09: Position of Seal for TDC Joint
Seal
Angle flange joint
Bolt hole 8mm
50
Air Duct
Figure 10: Possition of Seal for Angle Flange Joint
Page 7
Saigon M&C Tower Project
Method Statement For Ductworks
Seal (Inside Only)
Seal
Air Duct
Figure 11: Possition of Sealant for Duct Seam
3. Air Duct Insulation:
Table 5: Duct Insulation Specification Schedule
Applicable scope Material Type Density Thickness
Supply air duct 48kg/m3 25mm
Glasswool Blanket
Return air duct 48kg/m3 25mm
Smoke exhaust duct Rockwool Board 60kg/m3 50mm
Supply air chambers
and sound Glasswool Blanket 48kg/m3 50mm
attenuation fittings
Attached Alu. Tape
Board insulation 50mm (Width 50mm)
(see table 5)
Seam
Pin Φ1.6mm
(see figure 15)
Alu. Sheet Cladding
Air duct (if any)
Metal clips
Adhesive
Figure 12: Typical smoke exhause duct insulation detail
Page 8
Saigon M&C Tower Project
Method Statement For Ductworks
Alu. foil facing
Metal clip
Alu. sheet cladding
Air (Non-flammable)
du
ct
Glasswool for AC duct
Rockwool for smoke exhaust duct
Pin Φ1.6mm
(see figure 15)
Figure 13: Ducting insulation layer detail
Glasswool 25mm thk Glass cloth
Air duct Metal clips
Pins Φ1.6mm
(see figure 14)
`
Figure 14: Insulation detail for supply air chambers and sound attenuation fitings
Page 9
Saigon M&C Tower Project
Method Statement For Ductworks
Max. 300mm
Max. 300mm
Pin Φ1.6mm
Metal clip
Insulated duct
Bare duct
Max. 300mm
Max. 300mm
Figure 15: Shape & distance of pins
Page 10
Saigon M&C Tower Project
Method Statement For Ductworks
Front view
Pin Φ 1.6mm
50mm
25mm
Flange joint
Metal slip
Glasswool 25mm thk
50mm
25mm
Attached alu. tape 25mm TDC joint
Glasswool 25mm thk TDC or Flange joint Alu. Tape 50mm
25mm
50mm Attached alu. tape 25mm
Plan view
Figure 16: Typical insulation menthod for TDC joint & flange joint
Glasswool 25mm thk
(outside duct)
Glasswool 25mm thk
(inside diffuser box) Chamber box
Air flow
Screw
Glasswool 25mm thk
(outside duct)
Aluminum tape 25mm
Ceiling
Figure 17: Detail of typical insulation for diffuser box
Page 11
Metal slip Attached alu. tape 25mm
Saigon M&C Tower Project
Method Statement For Ductworks
Screw Wall
Air duct Frame
Glasswool 25mm Tapping
thk (outside duct)
Figure 18: Detail of typical insulation for grille (VHS type)
II. Air Devices Installation Works:
1. Volume Dampers (VD), Volume Control Dampers (VCD), Fire Damer (FD):
TDC joint
VD
D Air flow
Air duct
L
VD
L = 8D
D: diameter of air duct
Air Fan
Concrete foundation Concrete slab
Figure 19: Detail of setting damper
Table 6: Quantity of hanger rods for Fire Damper
Rectangular Duct Spiral Duct
Duct size or Diameter (mm) Less than 300 Over 300 Less than 300 Over 300
Quantity of hanger rods (nos) 2 4 2 4
Page 12
Saigon M&C Tower Project
Method Statement For Ductworks
Branch duct Access door FD
Concrete floor slab
Fire damper
Wall
Anchor bolt
Angle steel
Bolt M8
Rubber pad Vertical duct Insulation 25mm
PLAN VIEW
Anchor bolt Wall
Rockwool 50mm
Concrete floor slab V-Angle steel
Hanger rod Bolt M8
Fire damper
Insulation 25mm
Vertical duct
VCD Access door FD Duct elbow
V-Angle steel
FRONT VIEW
Figure 20: Typical damper installation detail
Page 13
Saigon M&C Tower Project
Method Statement For Ductworks
2. Diffusers, Registers:
Connection with chamber box Connection with Duct
D H+50mm H+50mm
Flexible
W+50mm 100mm or over
Flexible Chamber box
D D+50mm Air duct
K K
Ceiling Ceiling
W×H W×H
H, W: Dimension of Diffusers opening size for ceiling (mm)
K = 150 ~ 300mm
d : Diameter of flexible duct (mm)
Figure 21: Example of connection with chamber & duct
SUPPLY AIR CHAMBER BOX
Insulation (inside)
Glasswool 25mm thk
Insulation (outside)
Opposed blade damper Glass wool 25mm thk
(if any) Insulation (outside)
Glass wool 25mm thk
Ceiling
Figure 22: Detail of typical installation for supply air diffuser
Page 14
Saigon M&C Tower Project
Method Statement For Ductworks
Insulation (inside)
RETURN AIR CHAMBER BOX
Glasswool 25mm thk
Insulation (outside)
Screw Glass wool 25mm thk
Ceiling
Figure 23: Detail of typical installation for return air grille
EXHAUST AIR CHAMBER BOX
Opposed blade damber
(if any)
Screw
Ceiling
Figure 24: Detail of typical connection for exhause air grille
3. Plenum Chamber, Silencer Chamber:
? Sound Absorber for Chamber shall be used glasswool 50mm thk, 48 kg/cm3 density.
Table 7: Galvanized steel sheet thickness for Chamber
Longest Dimension of Chamber (mm)
Chamber Size (L max) (mm) Less than 800 800 ~ 1500 1500 or Over
Steel Sheet Thickness (mm) 0.8 1.0 1.2
Page 15
Saigon M&C Tower Project
Method Statement For Ductworks
A Sound Absorber by
Silencer Elbow glasswool 50mm thk
R
A
L
Figure 25: Silencer Elbow Chamber Detail
Sound Absorber by
glasswool 50mm thk
B
Silencer Chamber
Detail D
Detail E A
Figure 26: Silencer Chamber Detail
Detail E
GI sheet cover
0.6mm thk
25~50mm
Air Pin Φ 1.6mm
Duct
Sound Absorber by
glasswool 50mm thk
Page 16
Saigon M&C Tower Project
Method Statement For Ductworks
Detail D
Sound Absorber by
glasswool 50mm thk
Pin Φ1.6mm
25~50mm
75mm 100~150mm
Figure 27: Chamber Jointing Detail
4. Flexible Duct, Canvas Joints
a) Flexible Duct:
Insulation (inside)
Steel band Bolt M6
Glasswool 25mm thk [Link] 0.6mm thk
FLEXIBLE DUCT AIR DUCT
SUPPLY AIR CHAMBER BOX
Steel band
Screw 3.2Ø
[Link] 0.6mm thk
Insulation (outside) Opposed blade damper
Glasswool 25mm thk (if any)
Insulation (outside)
Ceiling Glass wool 50mm thk
Figure 28: Detail of typical connection between flexible duct & chamber box
Page 17
Saigon M&C Tower Project
Method Statement For Ductworks
b) Canvas Joints:
Duct canvas
Detail F
Air duct Air duct
Flange joint L L = 200 ~ 250 (mm)
Figure 29: Canvas Joint Detail
Detail F
Rubber gasket (width:5mm)
Angle steel flange
Washer
Bolt and nut M8
Air duct Rivet 3.2mm
Canvas Joint
Cuff 5mm or more Galvanized steel sheet
( same as duct thickness)
Insulation (inside)
Glasswool 25mm thk
RETURN CHAMBER BOX AIR DUCT
Insulation (outside) Flange joint
Glasswool 25mm thk
Screw (refer to detail G)
Ceiling Canvas
Figure 30: Detail of typical connection between canvas & chamber box
Page 18
Saigon M&C Tower Project
Method Statement For Ductworks
5. Louver, Access door, Outdoor Hood:
a) Louver:
Concrete slab
Wall
Anchor bolt
Mortar Grout
Hanger rod
Louver Chamber
box Angle steel
500mm (see table 3)
Anchor bolt
Access door
(see figure 32)
Figure 31: Typical Louver Installation Detail
Page 19
Saigon M&C Tower Project
Method Statement For Ductworks
b) Access door:
Steel plate
Screw 3.2Ø Air duct
Aluminium Sach lock
Steel plate Aluminium
Sach lock
Figure 32: Typical Access Door Installation Detail
c) Outdoor Hood:
Mortar
Wall
Sealant
Rockwool 60kg/m3
Outdoor hood
Screw
Air duct
Insect Screen
(if any)
Chamber box
GI sheet cover
0.6 mm thk
.
Figure 33: Typical Outdoor Hood Installation Detail