Painting Inspection Report Summary

The document provides 3 paint inspection reports for different components of a wagon loading station project. It details the manufacturer, paint specifications, measurements of dry film thickness, and inspection results. The average dry film thickness for primer, intermediate, and final coats are reported for each component, with readings within specification. The reports were prepared, witnessed, and verified according to standard processes.

Uploaded by

siva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views139 pages

Painting Inspection Report Summary

The document provides 3 paint inspection reports for different components of a wagon loading station project. It details the manufacturer, paint specifications, measurements of dry film thickness, and inspection results. The average dry film thickness for primer, intermediate, and final coats are reported for each component, with readings within specification. The reports were prepared, witnessed, and verified according to standard processes.

Uploaded by

siva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Tail Frame Inspection
  • Frame Guard Inspection
  • Deck Plate Inspection
  • Non Std Short Support Stringer DTS(DTS1) Inspection
  • Non Std Short Support Stringer DTS(DTS2) Inspection
  • Non Std Stringer DTS(DTS3) Inspection
  • Non Std Stringer DTS(DTS4) Inspection
  • Non Std Stringer DTS(DTS5) Inspection
  • Non Std Stringer DTS(DTS6) Inspection
  • Non Std Stringer DTS(DTS7) Inspection
  • Non Standard Stringer Details Inspection
  • Non Standard Stringer Details NSTD2 Inspection
  • Non Standard Stringer Details NSTD3 Inspection
  • Non Standard Stringer Details NSTD4 Inspection
  • Non Standard Stringer Details N51 Inspection
  • Head Frame Inspection
  • Vertical Take Up Guide Details Inspection
  • Bend Pulley Supporting Structure Inspection
  • Standard Stringer Details STD-2 Inspection
  • Trestle Assembly Inspection

PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 18/03/2017 &
Item Description:TAIL FRAME Date : 19/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2000 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 18/03/2017 18/03/2017 19/03/2017 19/03/2017 ACC
10.00 AM 03.50 PM 9.30 AM 11.35
*** Refer attached annexure AM
for DFT ***
01 TO 14 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2000 TAIL FRAME


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 14 65 65 56 65 60 62.2 170 175 178 174 170 173.4 51 52 52 51 51 51.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 02/04/2017 &
Item Description:TAIL FRAME GUARD Date : 04/04/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2001 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 02/04/2017 02/04/2017 02/04/2017 04/04/2017 ACC


11.30 AM 01.30 PMRefer attached
*** 04.30 PM
annexure11.35 AM
for DFT ***
01 TO 13 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2001 TAIL FRAME GUARD


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 13 63 65 65 65 66 64.8 170 170 170 174 170 170.8 51 51 54 51 54 52.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:DECK PLATE DETAILS Date :

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2002 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 09/04/2017 09/04/2017 09/04/2017 10/04/2017 ACC
10.30 AM 01.30***
PMRefer attached
04.30 PM 11.35
annexure AM
for DFT ***
01 TO 03 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2002 DECK PLATE DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 03 62 65 65 61 61 62.8 172 172 172 170 170 171.2 52 51 54 54 55 53.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 05/02/2017 &
Item Description:NON STD SHORT SUPPORT STRINGER DTLS(NSTD-1) Date : 06/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2005 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/02/2017 05/02/2017 05/02/2017 06/02/2017 ACC


10.00 AM 12.00 PM 04.30 PM 10.35
*** Refer attached annexure for DFT AM
readings ***
01 TO 07 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2005 NON STD SHORT SUPPORT STRINGER DTLS(NSTD-1)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 07 63 54 59 55 68 59.8 165 175 173 173 172 171.6 52 52 54 54 55 53.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:NON STD SHORT SUPPORT STRINGER Inspection 05/02/2017 &
DTLS(NSTD-2) Date : 06/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2006 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/02/2017 05/02/2017 05/02/2017 06/02/2017 ACC


10.00 AM 12.00 PM 04.30 PM 10.35
*** Refer attached annexure AM
for DFT ***
01 TO 07 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2006 NON STD SHORT SUPPORT STRINGER DTLS(NSTD-2)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 10,15 64 64 64 65 66 64.6 178 178 173 172 170 174.2 54 51 51 54 58 53.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 05/02/2017 &
Item Description:NON STD STRINGER DTLS(NSTD-3) Date : 06/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2007 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/02/2017 05/02/2017 05/02/2017 06/02/2017 ACC


10.00 AM 12.00 PM 04.30 PM 10.35
*** Refer attached annexure for DFT AM
readings ***
01 TO 10,15 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2007 NON STD STRINGER DTLS(NSTD-3)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 10,15 69 56 54 55 66 60 168 178 174 170 170 172 50 54 54 52 52 52.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 05/02/2017 &
Item Description:NON STD STRINGER DTLS(NSTD-4) Date : 06/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2008 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/02/2017 05/02/2017 05/02/2017 06/02/2017 ACC


10.00 AM 12.00*** Refer attached annexure10.35
PM 04.30 PM AM
for DFT ***
01 TO 13,18 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2008 NON STD STRINGER DTLS(NSTD-4)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 13,18 65 65 65 62 62 63.8 170 170 170 174 171 171 51 51 54 58 55 53.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 05/02/2017 &
Item Description:NON STD STRINGER DTLS(NSTD-5) Date : 06/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2009 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/02/2017 05/02/2017 05/02/2017 06/02/2017 ACC


10.00 AM 12.00 PM 04.30 PM 10.35
*** Refer attached annexure AM
for DFT ***
01 TO 13,18 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2009 NON STD STRINGER DTLS(NSTD-5)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 13,18 50 51 52 58 58 53.8 168 170 178 174 170 172 50 50 52 54 54 52
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STD STRINGER DTLS(NSTD-6) Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2010 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.00 AM 12.00***PM 04.30 PMannexure
Refer attached 10.35 AM
for DFT ***
01 TO 13,18 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2010 NON STD STRINGER DTLS(NSTD-6)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 13,18 60 61 63 65 68 63.4 170 179 174 174 170 173.4 51 54 54 55 58 54.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STD STRINGER DTLS(NSTD-7) Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2011 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.00 AM 12.00***
PMRefer 04.30 PM 10.35
attached annexure AM
for DFT ***
01 TO 16,21,22 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2011 NON STD STRINGER DTLS(NSTD-7)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 16,21,22 64 64 64 65 68 65 175 170 171 171 170 171.4 54 54 54 54 55 54.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS Date : 07/02/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2012 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.00 AM 12.00
*** Refer attached annexure for10.35
PM 04.30 PM AM
DFT readings ***
01 TO 16,21,22 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2012 NON STANDARD STRINGER DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 16,21,22 62 62 65 62 62 62.6 174 174 178 174 170 174 54 51 51 50 50 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2013 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.00 AM 12.00 PM
*** 04.30 PMannexure10.35
Refer attached AM
for DFT ***
01 TO 16,21 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2013 NON STANDARD STRINGER DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 16,21 60 61 60 61 60 60.4 175 178 174 171 171 173.8 54 54 51 52 52 52.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2014 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.30 AM 12.30 PM 04.30 PM 11.35
*** Refer attached annexure for DFT AM
readings ***
01 TO 14 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2014 NON STANDARD STRINGER DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 14 63 63 62 61 61 62 170 171 174 178 174 173.4 51 51 50 50 52 50.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 03/01/2017 &
Item Description:NON STANDARD STRINGER DETAILS Date : 04/01/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2015 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 03/01/2017 03/01/2017 03/01/2017 04/01/2017 ACC


10.00 AM 12.00 PM 04.30 PM 11.35
*** Refer attached annexure for DFT AM
readings ***
01 TO 07 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2015 NON STANDARD STRINGER DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 07 60 60 61 64 64 61.8 172 172 170 171 170 171 50 51 57 50 55 52.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS Date : 07/02/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2016 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC
10.30 AM 12.30
*** Refer attached annexure for11.35
PM 04.30 PM AM
DFT readings ***
01 TO 13,20,21 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2016 NON STANDARD STRINGER DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 13,20,21 54 55 64 63 62 59.6 170 173 172 174 170 171.8 51 52 59 54 58 54.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS- NSTD12 Date : 07/02/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2017 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.30 AM 12.30 PM attached
*** Refer 04.30 PM
annexure for11.35 AM
DFT readings ***
01 TO 6 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2017 NON STANDARD STRINGER DETAILS-NSTD-12


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 6 60 64 62 68 65 63.8 175 178 174 170 170 173.4 54 54 51 53 52 52.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 07/02/2017 &
Item Description:NON STANDARD STRINGER DETAILS- NSTD13 Date : 08/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2018 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 07/02/2017 07/02/2017 07/02/2017 08/02/2017 ACC


11.30 AM 12.30 PM 05.30 PM 10.35
*** Refer attached annexure AM
for DFT ***
01 TO 9 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2018 NON STANDARD STRINGER DETAILS-NSTD-13


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 9 62 65 68 62 62 63.8 170 172 172 171 171 171.2 50 50 51 52 52 51
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:NON STANDARD STRINGER DETAILS- NSTD14 Date :

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2019 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 07/02/2017 07/02/2017 07/02/2017 08/02/2017 ACC


11.30 AM 12.30*** Refer attached annexure10.35
PM 05.30 PM AM
for DFT ***
01 TO 7 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2019 NON STANDARD STRINGER DETAILS-NSTD-14


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)-50 Min
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2 3 4 5 Avg.
01 TO 7 60 60 61 62 62 61 170 170 174 174 178 173.2 50 51 58 54 51 52.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:NON STANDARD STRINGER DETAILS- NSTD- Inspection
18,19,20 Date :

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2020 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 07/02/2017 07/02/2017 07/02/2017 08/02/2017 ACC


11.30 AM 12.30 PM 05.30 PM 10.35
*** Refer attached annexure AM
for DFT ***
01 TO 7 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2020 NON STANDARD STRINGER DETAILS-NSTD-18,19,20


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 14 60 62 65 62 66 63 172 172 175 175 170 172.8 48 55
DETAILS-NSTD-18,19,20
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
54 54 52 52.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:HEAD FRAME Date :

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2021 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time ACC


07/02/2017 07/02/2017 07/02/2017 08/02/2017
11.30 AM 12.30
*** Refer attached annexure10.35
PM 05.30 PM AM
for DFT ***
01 TO 09,16,17 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2021 HEAD FRAME


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 09,16,17 60 60 62 65 62 61.8 170 170 174 174 170 171.6 55 58
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
53 52 52 54
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 22/03/2017 &
Item Description:VERTICAL TAKE UP GUIDE DETAILS Date : 23/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2027 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 22/03/2017 22/03/2017 22/03/2017 23/03/2017 ACC


11.30 AM 12.30 PM 05.30 PM 10.35
*** Refer attached annexure for AM
DFT ***
01 TO 15 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2027 VERTICAL TAKE UP GUIDE DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 15 60 60 62 62 63 61.4 170 170 172 174 170 171.2 50 51
ETAILS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
50 50 55 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 12/03/2017 &
Item Description:BEND PULLEY SUPPORTING STRUCTURE Date : 13/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2029 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 12/03/2017 12/03/2017 13/03/2017 13/03/2017 ACC
10.00 AM 03.50
*** Refer attached annexure for 11.35
PM 9.30 AM AM
DFT readings ***
01 TO 7 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2029 BEND PULLEY SUPPORTING STRUCTURE


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 7 61 64 60 60 62 61.4 170 170 175 175 174 172.8 50 54
STRUCTURE
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
50 50 52 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:STANDARD STRINGER DETAILS STD -2 Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2039 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

Surface DFT Toatal DFT


Item / part No. preparati Avg(in Result
on Primer Coat Intermediate final Coat microns)
06/02/20 Coat
17 10.30 06/02/2017 06/02/2017 07/02/2017
Date / Time AM 12.30 PM attached
04.30 PM for DFT
11.35 AM *** ACC
*** Refer annexure readings
01 TO 7 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2039 STANDARD STRINGER DETAILS STD -2


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 7 60 64 65 65 68 64.4 170 178 174 171 171 172.8 51 50
LS STD -2
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
55 51 52 51.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 06/02/2017 &
Item Description:STANDARD STRINGER DETAILS STD -3 Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2040 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.30 AM 12.30 PM 04.30 PM 11.35
*** Refer attached annexure AM
for DFT ***
01 TO 7 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2040 STANDARD STRINGER DETAILS STD -3


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 7 60 60 60 65 66 62.2 172 173 174 170 170 171.8 50 54
LS STD -3
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
51 52 50 51.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:NON STANDARD STRINGER DETAILS NSTD Inspection 06/02/2017 &
-21&22 Date : 07/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2041 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.30 AM 12.30 PM 04.30 PM 11.35
*** Refer attached annexure AM
for DFT ***
01 TO 8 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2041 NON STANDARD STRINGER DETAILS NSTD -21&22


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 8 60 64 62 65 66 63.4 178 170 175 174 170 173.4 54 52
DETAILS NSTD -21&22
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
54 54 55 53.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:NON STANDARD STRINGER DETAILS NSTD Inspection 06/02/2017 &
-23,24,25 Date : 07/02/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2042 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 06/02/2017 06/02/2017 06/02/2017 07/02/2017 ACC


10.30 AM 12.30 PM attached
*** Refer 04.30annexure
PM for11.35 AM
DFT readings ***
01 TO 9 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2042 NON STANDARD STRINGER DETAILS NSTD -23,24,25


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
01 TO 9 61 61 62 62 60 61.2 173 173 170 172 170 171.6 49 60
DETAILS NSTD -23,24,25
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
58 50 51 53.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 16/02/2017 &
Item Description:24.101 M GANTRY DETAILS Date : 17/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2101 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38.8 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 16/02/2017 16/02/2017 16/02/2017 17/02/2017 ACC
10.30 AM 12.30
*** Refer attached annexure for 11.35
PM 04.30 PM AM
DFT readings ***
24.101 M GANTRY SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2101 24.101 M GANTRY DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
24.101 M
GANTRY 60 61 62 68 66 63.4 170 174 176 174 170 172.8 56 55
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

48 45 52 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 16/02/2017 &
Item Description:24.101 M GANTRY DETAILS Date : 17/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2101 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38.8 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 16/02/2017 16/02/2017 16/02/2017 17/02/2017 ACC
10.30 AM 12.30
*** Refer attached annexure for 11.35
PM 04.30 PM AM
DFT readings ***
24.101 M GANTRY SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2101 24.101 M GANTRY DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
24.101 M
GANTRY 60 61 62 68 66 63.4 170 174 176 174 170 172.8 56 55
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

48 45 52 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 09/03/2017 &
Item Description:24.086 M OPEN BEND GANTRY DETAILS Date : 11/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2104 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 09/03/2017 09/03/2017 11/03/2017 11/03/2017 ACC
10.00 AM 04.50 PM 9.30 AM 11.35 AM ***
24.086 M OPEN BEND SA 2 1/2 *** Refer attached annexure for DFT
GANTRY readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2104 24.086 M OPEN BEND GANTRY DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

24.086 M OPEN
BEND GANTRY 60 61 68 62 62 62.6 170 174 175 170 170 171.8 51 53
RY DETAILS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

52 52 55 52.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 18/03/2017 &
Item Description:STANDARD GANTRY DETAILS 30 MTS Date : 19/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2108 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 18/03/2017 18/03/2017 19/03/2017 19/03/2017 ACC
10.00 AM 03.50 PM 9.30 AM 11.35 AM ***
STANDARD GANTRY 30 SA 2 1/2 *** Refer attached annexure for DFT readings
MTS ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2108 STANDARD GANTRY DETAILS 30 MTS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

STANDARD
GANTRY 30
MTS 58 62 62 62 63 61.4 172 170 170 174 170 171.2 50 54
S 30 MTS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

53 52 52 52.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 11/02/2017 &
Item Description:TWO LEGGED TRESTLE (2.342 MTS) Date : 12/02/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2125 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 11/02/2017 11/02/2017 11/02/2017 12/02/2017 ACC
10.30 AM 12.30 PM 02.30 PM 10.35 AM ***

TWO LEGGED TRESTLE SA 2 1/2 *** Refer attached annexure for DFT
(2.342 MTS) readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2125 TWO LEGGED TRESTLE (2.342 MTS)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TWO LEGGED
TRESTLE (2.342
MTS) 60 64 62 62 66 62.8 169 165 178 170 170 170.4 51 53
2 MTS)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

52 53 52 52.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 09/02/2017 &
Item Description:TWO LEGGED TRESTLE (3.838 MTS) Date : 10/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2126 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 09/02/2017 09/02/2017 09/02/2017 10/02/2017 ACC
10.30 AM 12.30 PM 04.30 PM 2.35 PM ***
TWO LEGGED TRESTLE SA 2 1/2 *** Refer attached annexure for DFT readings
(3.838 MTS) ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2126 TWO LEGGED TRESTLE (3.838 MTS)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TWO LEGGED
TRESTLE (3.838
MTS) 60 60 61 69 62 62.4 170 170 174 178 175 173.4 50 51
8 MTS)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

59 53 52 53
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:TRESTLE CD-2.15 AND GCD-2.15 Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2127 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 11/02/2017 11/02/2017 11/02/2017 12/02/2017 ACC


10.30 AM 12.30 PM 02.30 PM 10.35 AM ***
TRESTLE CD-2.15 AND SA 2 1/2 *** Refer attached annexure for DFT readings
GCD-2.15 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2127 TRESTLE CD-2.15 AND GCD-2.15


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE CD-
2.15 AND GCD-
2.15 58 62 61 62 66 61.8 169 170 174 172 170 171 60 58
2.15
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

51 51 51 54.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 14/04/2017 &
Item Description:TRESTLE ASSEMBLY CD-2.17/2.18 Date : 15/04/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2130 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 14/04/2017 14/04/2017 15/04/2017 15/04/2017 ACC
11.30 AM 2.30 PM 10.30 AM 2.35 PM ***
TRESTLE ASSEMBLY CD- SA 2 1/2 *** Refer attached annexure for DFT readings
2.17/2.18 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2130 TRESTLE ASSEMBLY CD-2.17/2.18


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE
ASSEMBLY CD-
2.17/2.18 60 60 62 65 61 61.6 170 172 171 178 170 172.2 58 53
/2.18
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

50 51 52 52.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 12/01/2017 &
Item Description:TRESTLE DETAILS AT FDN CD-2.19 AND GCD-2.19 Date : 13/01/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2134 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 12/01/2017 12/01/2017 12/01/2017 30/01/2017 ACC


11.30 AM 1.30 PM 03.30 PM 11.35 AM ***

TRESTLE DETAILS AT
FDN CD-2.19 AND SA 2 1/2 *** Refer attached annexure for DFT
GCD-2.19 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE
DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2134 TRESTLE DETAILS AT FDN CD-2.19 AND GCD-2.19


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE -CD-
2.19 AND GCD-
2.19 59 55 60 61 68 60.6 168 170 171 174 177 172 53 58
-2.19 AND GCD-2.19
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

54 52 52 53.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 21-01-2017 &
Item Description:TRESTLE CD 2.20&GCD 2.20 DETAILS Date : 22/01/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2136 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 37.5 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 21/01/2017 21/01/2017 21/01/2017 22/01/2017 ACC


11.30 AM 2.30 PM 04.30 PM 11.35 AM ***

TRESTLE CD 2.20&GCD SA 2 1/2 *** Refer attached annexure for DFT


2.20 DETAILS readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE
DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2136 TRESTLE CD 2.20&GCD 2.20 DETAILS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE CD
2.20&GCD 2.20 59 55 68 62 63 61.4 171 169 180 174 170 172.8 51 50
DETAILS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

51 52 53 51.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:: TWO LEGGED TRESTLE(27M) Date :

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2137 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

Surface DFT Toatal DFT


Item / part No. preparati Avg(in Result
on Primer Coat Intermediate final Coat microns)
Coat
Date / Time *** ACC

TWO LEGGED SA 2 1/2 *** Refer attached annexure for DFT readings
TRESTLE(27M) ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2137 TWO LEGGED TRESTLE(27M)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
TWO LEGGED
TRESTLE(27M) 59 64 60 62 66 62.2 170 165 174 172 170 170.2 50 58
)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

55 52 52 53.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 29/01/2017 &
Item Description:: TRESTLE DETAILS (31.51 MTS) Date : 30/01/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2140 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 36 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 29/01/2017 29/01/2017 29/01/2017 30/01/2017 ACC
10.30 AM 2.30 PM 04.30 PM 1.35 PM ***
TRESTLE DETAILS SA 2 1/2 *** Refer attached annexure for DFT
(31.51 MTS) readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2140 TRESTLE DETAILS (31.51 MTS)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE
DETAILS (31.51
MTS) 60 61 64 68 62 63 170 175 163 168 165 168.2 45 54
S)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

53 52 52 51.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 13/03/2017 &
Item Description:: TWO LEGGED TRESTLE DETAILS (35.678 MTS) Date : 14/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2143 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 36.8 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 13/03/2017 13/03/2017 13/03/2017 14/03/2017 ACC
10.30 AM 12.30 PM 03.30 PM 11.35 AM ***

TWO LEGGED TRESTLE SA 2 1/2 *** Refer attached annexure for DFT
DETAILS (35.678 MTS) readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2143 TWO LEGGED TRESTLE DETAILS (35.678 MTS)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TWO LEGGED
TRESTLE -
(35.678 MTS) 55 60 68 63 62 61.6 168 172 175 170 170 171 62 56
ILS (35.678 MTS)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

54 55 50 55.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: TRESTLE DETAILS AT FDN CD2-2.24 AND GCD2- Inspection 09/02/2017 &
2.24 Date : 10/02/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2145 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38.5 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 09/02/2017 09/02/2017 09/02/2017 10/02/2017 ACC


10.30 AM 12.30 PM 04.30 PM 2.35 PM ***

TRESTLE DETAILS AT
FDN CD2-2.24 AND SA 2 1/2 *** Refer attached annexure for DFT
GCD2-2.24 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE
DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2145 TRESTLE DETAILS AT FDN CD2-2.24 AND GCD2-2.24


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE
DETAILS AT FDN
CD2-2.24 AND
GCD2-2.24 65 55 68 62 65 63 165 175 172 173 172 171.4 50 51
2-2.24 AND GCD2-2.24
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

52 65 55 54.6
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 05/03/2017 &
Item Description:: TRESTLE CD2-2.25 AND GCD2-2.25 Date : 06/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2148 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat
Date / Time 05/03/2017 05/03/2017 05/03/2017 06/03/2017 ACC
10.30 AM 11.30 AM 03.30 PM 11.50 AM ***
TRESTLE CD2-2.25 AND SA 2 1/2 *** Refer attached annexure for DFT
GCD2-2.25 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2148 TRESTLE CD2-2.25 AND GCD2-2.25


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE CD2-
2.25 AND
GCD2-2.25 55 64 68 62 60 61.8 168 165 170 178 175 171.2 50 55
2-2.25
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

60 50 52 53.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 03/03/2017 &
Item Description:: STANDARD GANTRY DETAILS 23.65 MTS Date : 04/03/2017

Paint Spec 19260008-PRC-ME-GNR-


[Link]/Documents 192-60-001-DRW-ME-CD2-2155 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 03/03/2017 03/03/2017 04/03/2017 04/03/2017 ACC


10.00 AM 3.50 PM 010.30 AM 10.35 AM ***
STANDARD GANTRY SA 2 1/2 *** Refer attached annexure for DFT
DETAILS 23.65 MTS readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2155 STANDARD GANTRY DETAILS 23.65 MTS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

STANDARD
GANTRY
DETAILS 23.65
MTS 50 55 60 62 66 58.6 169 172 170 765 175 290.2 50 52
S 23.65 MTS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

54 50 55 52.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 17/04/2017 &
Item Description:: NON STANDARD GANTRY DETAILS 11.244 MTS Date : 18/04/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2162 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 17/04/2017 17/04/2017 18/04/2017 18/04/2017 ACC


10.00 AM 3.50 PM 09.30 PM 04.35 AM ***

NON STANDARD
GANTRY DETAILS SA 2 1/2 *** Refer attached annexure for DFT readings
11.244 MTS ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE
DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2162 NON STANDARD GANTRY DETAILS 11.244 MTS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

NON
STANDARD
GANTRY
-11.244 MTS 66 65 68 69 62 66 175 178 174 175 178 176 55 58
ETAILS 11.244 MTS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

54 57 56 56
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection
Item Description:: NON STANDARD GANTRY DETAILS 23.65 MTS 7/05/2017 & 9/05/2017
Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2167 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 7/05/2017 7/05/2017 08/05/2017 9/05/2017 ACC


11.00 AM 4.10 PM 10.30 PM 9.35 AM ***
NON STANDARD SA 2 1/2 *** Refer attached annexure for DFT readings
GANTRY ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2167 NON STANDARD GANTRY DETAILS 23.65 MTS


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

NON
STANDARD
GANTRY -23.65
MTS 62 64 65 67 63 64.2 175 178 175 176 172 175.2 58 57
ETAILS 23.65 MTS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

56 54 55 56
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: STANDARD GANTRY WALK WAY ASSLY & Inspection 23/03/2017 &
DETAILS Date : 24/03/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2156 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 23/03/2017 23/03/2017 24/03/2017 24/03/2017 ACC


10.00 AM 3.10
*** Refer attached annexure for02.35
PM 11.30 AM PM
DFT readings ***
05 TO 07 SA 2 1/2 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2156 STANDARD GANTRY WALK WAY ASSLY & DETAILS
PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
05 TO 07 63 65 64 69 68 65.8 178 174 172 170 170 172.8 54 54
WAY ASSLY & DETAILS
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
55 56 52 54.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 11/08/2017 &
Item Description:: STANDARD GANTRY DETAILS-5.743 Date : 12/08/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2158 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 11/08/2017 11/08/2017 12/08/2017 11/08/2017 ACC


10.00 AM 4.10 PM 11.30 AM 05.35 PM ***
STANDARD GANTRY SA 2 1/2 *** Refer attached annexure for DFT readings
DETAILS-5.743 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2158 STANDARD GANTRY DETAILS-5.743


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

STANDARD
GANTRY
DETAILS-5.743 63 60 62 61 60 61.2 170 171 174 172 170 171.4 52 54
S-5.743
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

58 59 57 56
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 27/06/2017 &
Item Description:: TRESTLE CD2-2.26 AND GCD2-2.26 Date : 28/06/2017

[Link]/Documents 192-60-001-DRW-ME-CD2-2158 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 27/06/2017 27/06/2017 28/06/2017 28/06/2017 ACC


10.00 AM 3.40 PM 10.30 AM 03.35 PM ***
TRESTLE CD2-2.26 SA 2 1/2 *** Refer attached annexure for DFT readings
AND GCD2-2.26 ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2152 TRESTLE CD2-2.26 AND GCD2-2.26


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2

TRESTLE CD2-
2.26 AND
GCD2-2.26 65 64 68 67 62 65.2 174 172 173 175 174 173.6 54 58
2-2.26
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

57 59 54 56.4
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: TRESTLE STOOL DETAILS AT FDN CD2/GCD2-2.24 Inspection 8/5/2017
Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2146 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/08/2017 05/08/2017 05/08/2017 05/08/2017 ACC


10.00 AM 12.40 PM 02.30 PM 05.35 PM ***

SA 2 1/2 *** Refer attached annexure for DFT readings


TRESTLE STOOL ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2146 TRESTLE STOOL DETAILS AT FDN CD2/GCD2-2.24


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
TRESTLE
STOOL 63 64 68 67 62 64.8 175 178 172 174 175 174.8 56 54
FDN CD2/GCD2-2.24
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

52 58 54 54.8
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: TRESTLE STOOL DETAILS AT FDN CD2/GCD2-2.25 Inspection 8/5/2017
Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2149 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/08/2017 05/08/2017 05/08/2017 05/08/2017 ACC


10.00 AM 12.40 PM 02.30 PM 05.35 PM ***

SA 2 1/2 *** Refer attached annexure for DFT readings


TRESTLE STOOL ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2149 TRESTLE STOOL DETAILS AT FDN CD2/GCD2-2.25


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
TRESTLE
STOOL 65 64 67 68 65 65.8 175 174 172 178 174 174.6 54 58
FDN CD2/GCD2-2.25
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

52 53 54 54.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: TTRESTLE STOOL DETAILS AT FDN CD2/GCD2- Inspection 8/5/2017
2.17 & 2.18 Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2132 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 05/08/2017 05/08/2017 05/08/2017 05/08/2017 ACC


10.00 AM 12.40 PM 02.30 PM 05.35 PM ***

SA 2 1/2 *** Refer attached annexure for DFT readings


TRESTLE STOOL ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2132 TRESTLE STOOL DETAILS AT FDN CD2/GCD2-2.17 & 2


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
TRESTLE
STOOL 68 64 62 60 60 62.8 178 172 173 174 175 174.4 55 55
FDN CD2/GCD2-2.17 & 2.18
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

59 58 54 56.2
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:: WALK WAY DETAILS FOR 24.086M OPEN BEND Inspection 9/18/2017
GANTRY Date :

[Link]/Documents 192-60-001-DRW-ME-CD2-2105 Paint Spec No: 19260008-PRC-ME-GNR-


0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal DFT


Surface
Item / part No. Avg(in Result
preparation microns)
Primer Coat Intermediate final Coat
Coat

Date / Time 19/09/2017 19/09/2017 19/09/2017 19/09/2017 ACC


10.00 AM 12.40 PM 02.30 PM 05.35 PM ***

SA 2 1/2 *** Refer attached annexure for DFT readings


WALKWAY ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME [Link] KUMAR [Link] KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD2-2105 WALK WAY DETAILS FOR 24.086M OPEN BEND GANT
PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
WALKWAY 60 62 65 59 65 62.2 174 170 170 174 165 170.6 55 65
086M OPEN BEND GANTRY
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
51 50 50 54.2

PAINTING INSPECTION REPORT
PROJECT
WAGON LOADING STATION PHASE -I
Manufacturer 
ARDEE ENGINEERING COMPANY
Report No :
Item De
WAGON LOADING STATION PHASE-I
ANNEXURE OF PAINTING  REPORT No:AEC/PIR/
DRAWING Nos 192-60-001-DRW-ME-CD2-2000
TAIL FRAME
PART
PAINTING INSPECTION REPORT
PROJECT
WAGON LOADING STATION PHASE -I
Manufacturer 
ARDEE ENGINEERING COMPANY
Report No :
Item De
WAGON LOADING STATION PHASE-I
ANNEXURE OF PAINTING  REPORT No:AEC/PIR/
DRAWING Nos 192-60-001-DRW-ME-CD2-2001
TAIL FRAME GUAR
PAINTING INSPECTION REPORT
PROJECT
WAGON LOADING STATION PHASE -I
Manufacturer 
ARDEE ENGINEERING COMPANY
Report No :
Item De
WAGON LOADING STATION PHASE-I
ANNEXURE OF PAINTING  REPORT No:AEC/PIR/
DRAWING Nos 192-60-001-DRW-ME-CD2-2002
DECK PLATE DETA
PAINTING INSPECTION REPORT
PROJECT
WAGON LOADING STATION PHASE -I
Manufacturer 
ARDEE ENGINEERING COMPANY
Report No :
Item De
WAGON LOADING STATION PHASE-I
ANNEXURE OF PAINTING  REPORT No:AEC/PIR/
DRAWING Nos 192-60-001-DRW-ME-CD2-2005
NON STD SHORT S
PAINTING INSPECTION REPORT
PROJECT
WAGON LOADING STATION PHASE -I
Manufacturer 
ARDEE ENGINEERING COMPANY
Report No :
Ref.DWG
WAGON LOADING STATION PHASE-I
ANNEXURE OF PAINTING  REPORT No:AEC/PIR/
DRAWING Nos 192-60-001-DRW-ME-CD2-2006
NON STD SHORT S