WATER TIGHTNESS TEST REPORT FOR WATER RETAINING
STRUCTURE
Name of Project :
:
:
Project Reference
No. :
1. Watertightness Test
Testing Date : Time :
Type of Reservoir :
Reservoir ID :
Reservoir Capacity :
A Reduced water level (in reservoir)
. i) Initial water level Date Time:
mm
:
ii) Final water level Date Time:
mm
:
B. Evaporation (in tray)*
Date Time:
iii) Initial water level mm
:
Date Time:
iv) Final water level mm
:
*Using tray size 0.4 sq.m containing not less than 75mm depth of water
Depth of water
(
v)
Allowable Leakage : 1x (mm)
500
Drop in water (After 72 Allowable
hours) Actual Leakage Leakage Result
(mm) (mm)
level A (i-ii) level B (i-ii) level A - level B (v) Pass √ Fail X
Result: Pass = If; Actual Leakage < Allowable Leakage
Fail = If; Actual Leakage > Allowable Leakage
Prepared By Checked By Approved By