China Harbour Engineering Co.L.L.C.
INSPECTION REQUEST FORM
CONTRACTOR: Construction General Contracting House Ltd Request No.: ________________
Project No.: ____________________________________ Date: _____________________
Previous Request No.: ___________
TO: The Consultant
The following items are ready for your inspection on (Date): ____________________ at (time) ________________
Location ______________________________________ Level ____________________ Axis __________________
Drawing ref.: __________________________________________________________________________________
Description:
We certify that the above items have been coordinated with the following Subcontractors and other relevant projects
Electrical __________________ Mechanical _________________ Elevators ________________ Others _________________
All requests must be submitted at least 24 hours prior to the required inspection and approval.
Request Date ______________________ Time ____________________ Project Manager ______________________________
(Contractor)
2222
Received Date ________________ Time _______________ Consultant (Stamp & Sign) ________________
Consultant’s Inspection Report
*Shuttering *Steel / Openings *Concreting
Dimension / Stability ____ Edges / chamfers _____ Brand _________ Cage Stability______ Class & Type _____ Amb Temp ________
Cleanliness ___________ Release Agent _______ Size Spacing ____ Box Out __________ Slump __________ No. of Cubes ______
Straightness ___________ Lifting Accessories ____ Conc. Cover ____ Dowel Bars _______ Conc. Temp _____ Vibration _________
Inspector Signature & Date
Surveyor
Material Engineer
Electrical / Mechanical Engineer
ARE
Consultant’s Approval / Comments: Approved Approved as Noted Revise & Resubmit Rejected
PM / RE
Sign & Date
Received Date ____________________________________________ Time ___________________ Contractor’s Rep ___________________________________
cc: Consultant ( ), Contractor, ( ) Other, ( )