Assignment 1

To assemble 30 units of the end item, 30 additional units each of items E and F are needed. The latest week an order for the end item can be started and still ship on time in week 11 is week 8. A material requirements plan is developed for component H. Sixty units of A are needed in week 8. There are currently 15 units of B, 130 units of E, and 200 units of H on hand. 50 units of H will be completed in week 2. The plan is developed using lot for lot ordering except for H which has a lot size of 100.

Uploaded by

Nada Abbady
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
165 views4 pages

Assignment 1

To assemble 30 units of the end item, 30 additional units each of items E and F are needed. The latest week an order for the end item can be started and still ship on time in week 11 is week 8. A material requirements plan is developed for component H. Sixty units of A are needed in week 8. There are currently 15 units of B, 130 units of E, and 200 units of H on hand. 50 units of H will be completed in week 2. The plan is developed using lot for lot ordering except for H which has a lot size of 100.

Uploaded by

Nada Abbady
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Deadline:

The German University in Cairo (GUC) Sunday 3rd of March, 2019


Faculty of Management Technology
Operations Management Department at 4:00

Assignment 1
(Only hard copies are accepted)
Problem 1
The following table lists the components needed to assemble an end item, lead times, and
quantities on hand.

Item End B C D E F G H

Lead time (week) 1 2 3 3 1 2 1 2

Amount on hand 0 15 6 20 40 0 5 0

a. If 30 units of the end item are to be assembled, how many additional units of items E and F
are needed?

b. An order for the end item is scheduled to be shipped at the start of week 11. What is the
latest week that the order can be started and still be ready to ship on time?
Deadline:
The German University in Cairo (GUC) Sunday 3rd of March, 2019
Faculty of Management Technology
Operations Management Department at 4:00

Problem 2
Develop a material requirements plan for component H.

 Lead times for the end item and each component except B are one week. The lead time
for B is three weeks.
 Sixty units of A are needed at the start of week 8.
 There are currently 15 units of B on hand, 130 of E on hand, and 200 of H on hand.
 50 units of H are in production and will be completed by the start of week 2.
 All items are ordered/produced using lot for lot except for item H with lot size of 100.
Deadline:
The German University in Cairo (GUC) Sunday 3rd of March, 2019
Faculty of Management Technology
Operations Management Department at 4:00
Beg. Inv. 1 2 3 4 5 6 7 8

Week

Item : LT =

Item : LT =

Item : LT =
Deadline:
The German University in Cairo (GUC) Sunday 3rd of March, 2019
Faculty of Management Technology
Operations Management Department at 4:00

Item : LT =

Item : LT =