Form INSPECTION & TEST PLAN
Project Name: Rev 0
Main Activity: Installation,Testing Commissioning of Escalators Date: 7-Jun-15
W = Witness
CONTROL
QUALITY
H = Hold Point
TYPES:
T = Test
` R = Random
Quality control type by:
Activity
Third Party
Consultant
Contractor
Reference Quality Characteristics/acceptance criteria
Supplier
no.
Activity Works by Remarks
Client
SC /
doc. to be verified Records
Check levels and centreline of the setting out as
Setting Out / Survey per the Grid line provided by Maincontractor
1 SPI Shop Drawings H H W R Survey record
2 Mechanical Installation SPI Shop Drawings H H W R Check sheets
As per the Method statement/Schindler standards
3 Electrical Installation SPI Shop Drawings As per the Method statement/Schindler standards H H W R Check sheets
As per the Method statement/Schindler
4 Testing commissiong SPI Shop Drawings standards/ Local Third party Inspections H H W R T DM Approved Third
party Certificate
SUBMITTED BY: REVIEWED BY MAIN CONTRACTOR APPROVED BY CONSULTANT
SCHINDLER ELEVATORS KELE HYDER
NAME : NAME : NAME :
SIGN : SIGN : SIGN :
DATE: DATE: DATE:
Page 1 of 1