Bus Coupler Interlocking Protocol

1. A test of the interlocking scheme was conducted on the 690V bus coupler and incoming feeders at the 3.0 MPTA Integrated Steel Plant in Nagarnar on October 10, 2017. 2. The test involved checking the operation of the interlocking scheme under manual, auto, and synchronizing modes of operation. 3. The results of the test confirmed that the interlocking scheme operated as expected in all test scenarios, allowing and restricting operations as designed.

Uploaded by

Prabagaran Prt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
67% found this document useful (3 votes)
9K views7 pages

Bus Coupler Interlocking Protocol

1. A test of the interlocking scheme was conducted on the 690V bus coupler and incoming feeders at the 3.0 MPTA Integrated Steel Plant in Nagarnar on October 10, 2017. 2. The test involved checking the operation of the interlocking scheme under manual, auto, and synchronizing modes of operation. 3. The results of the test confirmed that the interlocking scheme operated as expected in all test scenarios, allowing and restricting operations as designed.

Uploaded by

Prabagaran Prt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

PROJECT : 3.

0 MPTA INTEGRATED STEEL PLANT, NAGARNAR


OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

1. Single Line Diagram:

LINE 1 LINE 2

LPT-A LPT-B

Incomer-1 Incomer-2
ACB ACB

BUS A BUS B

Bus-coupler
ACB

BPT-A BPT-B

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

2. MANUAL MODE OPERATION


Initial PT & ACB status Action
M-A-P switch in Expected result Actual result
LPT -1 I/C -1 B/C I/C -2 LPT-2 manual mode
To close I/C-1 I/C-1 should get Ok& confirms
H OFF OFF OFF AS from TNC switch ‘ON’ expected result
To close I/C-2 I/C-2 should get Ok& confirms
AS OFF OFF OFF H from TNC switch ‘ON’ expected result
To close B/C from B/C should not Ok& confirms
H ON OFF ON H TNC switch get ‘ON’ expected result
To close B/C from B/C should get Ok& confirms
H ON OFF OFF AS TNC switch ‘ON’ expected result
To close B/C from B/C should get Ok& confirms
AS OFF OFF ON H TNC switch ‘ON’ expected result

To close I/C-2 I/C-2 should Ok& confirms


H ON ON OFF AS from TNC switch not get ‘ON’ expected result
To close I/C-1 I/C-1 should not Ok& confirms
AS OFF ON ON H from TNC switch get ‘ON’ expected result
To close I/C-2 I/C-2 should get Ok& confirms
H ON OFF OFF H from TNC switch ‘ON’ expected result
To close I/C-1 I/C-1 should get Ok& confirms
H OFF OFF ON H from TNC switch ‘ON’ expected result

To close B/C from B/C should not Ok& confirms


H TRIP OFF ON H TNC switch get ‘ON’ expected result
H To close B/C from B/C should not Ok& confirms
H ON OFF TRIP TNC switch get ‘ON’ expected result
H ON TRIP OFF H To close I/C-2 I/C-2 should Ok& confirms
from TNC switch not get ‘ON’ expected result
To close B/C from B/C should not Ok& confirms
H OFF OFF OFF H TNC switch get on expected result
To close I/C-1 I/C-1 should not Ok& confirms
H OFF TRIP ON H from TNC switch get ‘ON’ expected result

H- PT voltage healthy AS- Any state of PT voltage ON- ACB ON condition


OFF- ACB OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

3. AUTO MODE OPERATION

Initial PT & ACB status Action


M-A-P switch in Expected Actual result
LPT -1 I/C -1 B/C I/C -2 LPT-2 AUTO mode result
I/C-1 should
H ON OFF ON H Under voltage get ‘OFF’ Ok& confirms
made on LPT-1 & B/C should expected result
get ‘ON’
I/C-2 should
H ON OFF ON H Under voltage get ‘OFF’& Ok& confirms
made on LPT-2 B/C should get expected result
‘ON’

H- PT voltage healthy AS- Any state of PT voltage

ON- ACB ON condition OFF- ACB OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

4. SYNCHRO MODE OPERATION


The below mentioned conditions are only happen in same sequence of voltage
inline PT-1& line PT-2

Initial PT & ACB status Action


Synchronic Trip M-A-P switch Expected Actual
LPT -1 I/C -1 B/C I/C -2 LPT-2 switch selector in parallel result result
switch mode
To close B/C B/C ‘ON’ Ok&
H ON OFF ON H ON I/C-1 from TNC & I/C-1 confirms
switch ‘OFF’ expected
result
To close I/C-1 I/C-1 ‘ON’ Ok&
H OFF ON ON H ON B/C from TNC & B/C confirms
switch ‘OFF’ expected
result
To close B/C B/C ‘ON’ Ok&
H ON OFF ON H ON I/C-2 from TNC & I/C-2 confirms
switch ‘OFF’ expected
result
To close I/C-2 I/C-2 ‘ON’ Ok&
H ON ON OFF H ON I/C-1 from TNC & I/C-1 confirms
switch ‘OFF’ expected
result
To close I/C-1 I/C-1 ‘ON’ Ok&
H OFF ON ON H ON I/C-2 from TNC & I/C-2 confirms
switch ‘OFF’ expected
result
To close I/C-2 I/C-2 ‘ON’ Ok&
H ON ON OFF H ON B/C from TNC & B/C confirms
switch ‘OFF’ expected
result

H- PT voltage healthy AS- Any state of PT voltage

ON- ACB ON condition OFF- ACB OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

5. CONTROL TRANSFORMER AUTO CHANGE OVER OPERATION

A. AUX SUPPLY FOR INCOMER/BUSCOUPLER

Initial voltage & control transformer status


Action Expected result Actual result
Line voltage-1 TRAFO-1 TRAFO-2 Line voltage-2
Control supply
H ON ON H U/V made change over Ok& confirms
in line from trafo- 1 to expected result
voltage-1 trafo-2

Control supply
H ON ON H U/V made change over Ok& confirms
in line from trafo-2 to expected result
voltage-2 trafo-1

Control trafo-
H OFF OFF AS Control 1feeds the Ok& confirms
trafo-1 supply to the expected result
MPCB bus
‘ON’
Control trafo-2
AS OFF OFF H Control feeds the Ok& confirms
trafo-2 supply to the expected result
MPCB bus
‘ON’

H- Line voltage healthy AS- Any state of line voltage

ON- control trafo ON condition OFF- control trafo OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

B. AUX SUPPLY FOR OUTGOING FEEDERS

Initial voltage & control transformer status


Action Expected Actual result
Bus voltage-1 TRAFO-3 TRAFO-4 Bus voltage-2 result
Control
H ON ON H U/V made in supply Ok&
bus voltage-1 change over confirms
from trafo- 3 expected
result
to trafo-4
Control
H ON ON H U/V made in supply Ok&
bus voltage-2 change over confirms
from trafo-4 expected
result
to trafo-3
Control trafo-
H OFF OFF AS Control trafo-1 3 feeds the Ok&
MPCB ‘ON’ supply to the confirms
bus expected
result
Control trafo-
AS OFF OFF H Control trafo-2 4 feeds the Ok&
MPCB ‘ON’ supply to the confirms
bus expected
result

H- Bus voltage healthy AS- Any state of Bus voltage

ON- control trafo ON condition OFF- control trafo OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE

FORMAT NO: ELE-TEST-PROTOCOL-017


PROJECT : 3.0 MPTA INTEGRATED STEEL PLANT, NAGARNAR
OWNER NAME : M/S NMDC Interlocking Scheme Checking
CONSULTANT : M/S MECON LTD.
CONTRACTOR : M/S TATA PROJECTS LIMITED Sheet 1 to 4
INCOMERS & BUSCOUPLER DATE OF TESTING LOCATION
690V B-B-LC 14-BF 10.10.2017 DRIVE HOUSE ECR EL: + 4.5mtr

C. AUX SUPPLY FOR HTMCC MOTOR SPRING CHARING

Initial voltage & control transformer status


Action Expected result Actual
Line voltage-1 TRAFO-5 TRAFO-6 Line voltage-2 result
Control supply
H ON ON H U/V made in change over Ok&
line voltage-1 from trafo- 1 to confirms
trafo-2 expected
result

Control supply
H ON ON H U/V made in change over Ok&
line voltage-2 from trafo-2 to confirms
trafo-1 expected
result

Control trafo-
H OFF OFF AS Control trafo-1 1feeds the Ok&
MPCB ‘ON’ supply to the confirms
bus expected
result
Control trafo-2
AS OFF OFF H Control trafo-2 feeds the Ok&
MPCB ‘ON’ supply to the confirms
bus expected
result

H- Line voltage healthy AS- Any state of line voltage

ON- control trafo ON condition OFF- control trafo OFF Condition

TESTED BY WITNESSED BY WITNESSED BY WITNESSED BY


REF
VOLTECH TATA PROJECTS Ltd MECON NMDC
NAME P. PRABAGARAN [Link] [Link]/[Link]
DESIGNATION Sr T & C ENGINEER [Link] SDE/DE
SIGNATURE
DATE