DSC Workflows
Home
Supplemental Cultural
Resource Studies 3.0 Design Development (DBB)
Design
3.1 Prepare Design Development Documents
Design-Bid-Build
(DBB)
Based on the Final Schematic Design Documents, and the Response Memorandum to the DAB review
0.0 General
questions, prepare the following:
1.0 Predesign
2.0 Schematic Design Design Development Drawings
Division 1 Specifications
3.0 Design
Development
Divisions 2 through 49 Outline Specifications
Product File
4.0 Construction
Draft Statement of Structural Tests and Special Inspections (STSI)
Documents
Draft Profit Calculator
Design-Build (DB)
Templates:
Construction
Information Division 1 Specifications MF04
Macros must be enabled to edit specifications. Refer to instructions included in the Division 1
Specifications download.
Tools Statement of Structural Tests and Special Inspections (STSI)
Profit Calculator
FAQs
Contact Us Guidelines:
Site Index
Design Deliverables - Content and Format Requirements for Design Development Documents
CAD Standards
Guide for Writing Outline Specifications
3.2 Initiate Constructability Analysis
Initiate Constructability Analysis utilizing the Constructability Checklist template.
Template: Constructability Checklist
3.3 Draft Contract Price Schedule
Prepare a draft Contract Price Schedule utilizing the Contract Price Schedule template.
Template: Contract Price Schedule
Guideline: Guide for Specifiers, December 2010
3.4 Complete NPS Project Sustainability Checklist (Design Development Portion)
www.nps.gov/dscw/dbbdesdevelop.htm 1/3
3/31/13 3.0 Design Development (DBB) - DSC Workflows
Working collaboratively within the integrated design team, complete the Design Development portion of the
NPS Project Sustainability Checklist.
Templates:
NPS Project Sustainability Checklist (based on LEED™ version 2.2)
NPS Project Sustainability Checklist (based on LEED™ version 2009)
3.5 Update Class B Construction Cost Estimate
Update the Class B Construction Cost Estimate based on the completed Design Development documents;
confirm that project cost is within available funds.
Template:
Class B Construction Cost Estimate Template
Refer to the Class B Construction Cost Estimate Template Instructions.
Sample: Class B Construction Cost Estimate Sample (pdf)
Guidance: Cost Estimating Requirements Handbook (pdf)
3.6 Conduct Design Development Value Based Decision-Making
Conduct a Design Stage Value Analysis (DSVA) study to analyze the Design Development Documents to
improve project's performance, reliability, quality, and value.
Prepare the DSVA Report utilizing the Value Analysis (VA) Report template.
Templates:
VA Report
VA Templates
3.7 Design Development Deliverables
3.7.1 Submit Design Development Documents
Submit the following Design Development Documents for review:
Design Development Documents
Design Development Drawings
Division 1 Specifications
Divisions 2 through 49 Outline Specifications
Product File
Draft Statement of Structural Tests and Special Inspections (STSI)
Draft Profit Calculator
Draft Constructability Analysis
Draft Contract Price Schedule
NPS Project Sustainability Checklist
Updated Class B Construction Cost Estimate
Design Stage Value Analysis Report
3.7.2 Resolve Design Development Review Comments
Resolve all review comments. Submit written responses to review comments, utilizing the NPS review
form, within 15 calendar days of receipt of comments.
3.8 Compliance Deliverables
www.nps.gov/dscw/dbbdesdevelop.htm 2/3
3/31/13 3.0 Design Development (DBB) - DSC Workflows
3.8.1 Compliance Drawings and Supporting Narrative
3.8.1.1 When required, prepare and submit drawings and supporting narrative for SHPO/THPO
review and other compliance activities, as required. Incorporate resolution of SHPO/THPO review
comments into Draft Design Development Documents, as required.
3.8.1.2 When required, prepare and submit drawings and supporting narrative for obtaining
Section 404, National Pollutant Discharge Elimination System (NPDES), and other permits as
required.
Resolve reviewing agencies comments, as required.
3.8.2 Submit FONSI or ROD
When required, submit FONSI or ROD.