Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of April 30, 2019
WIDENING OF BUGTONG BR. (B00888LZ) ALONG CAMILING-WAWA-BAYAMBANG-
Name of Project : MALASIQUI-STA. BARBARA ROAD, MALASIQU, PANGASINAN
Station Limits :
PROJECT DESCRIPTION:
Widening of Bridge into more than two (2) lanes.
PROJECT IMPACT:
Widening of the bridge into more than two (2) lanes will help ease traffic congestion within the area.
CONTRACTUAL DATA : FINANCIAL STATUS :
Project Component : Bridges
Province : Pangasinan
Region : I Amount (P'000)
Location : Malasiqui, Pangasinan Allocation Releases Obligation Disbursement
Source of Funds : GAA 2018 FY2017
Mode of Contract : Competitive Bidding FY2018
Implementing Office : DPWH - Pangasinan IV District Total: -
Engineering Office
Date of Bidding :
Contractor :
Total Project Cost :
Revised Contract Amount : N/A
Start Date :
Contract Duration :
Revised Contract Duration :
Completion Date :
Revised Completion Date :
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment :
Actual Accomplishment :
Slippage :
PROJECT UPDATE: EQUIPMENT ON SITE:
MANPOWER ON SITE:
ACTIVITIES UNDERTAKEN:
PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:
Prepared by: Submitted by: Approved by:
_____________________ __________________________ ____________________________
Project Engineer I Chief, Construction Section District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of April 30, 2019
Name of Project : WIDENING OF BUGTONG BR. (B00888LZ) ALONG CAMILING-WAWA-
BAYAMBANG-MALASIQUI-STA. BARBARA ROAD, MALASIQU, PANGASINAN
Station Limits :
BENEFITS:
SOCIAL ECONOMIC ENVIRONMENTAL OTHER BENEFITS
1. Widening of the bridge 1. Widening of the bridge will 1. Widening the bridge results 1. Widening of the bridge will
will provide the public provide fast and easy in less noise and air result in cost of fuel
with transport transport of goods, pollution due to continuous savings due to fast and
convenience due to commodities and services to flow of traffic. improved travel of
improved and continuous their intended points of vehicles.
flow of traffic. destination, thereby,
improving the economic
viability of businesses.
PROGRESS PHOTOGRAPHS:
BEFORE: DURING: AFTER:
LOCATION MAP:
THIS SITE
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of October 31, 2017
Name of Project : Construction of Small Water Impounding Project, San Carlos City, Pangasinan
Station Limits :
PROJECT DESCRIPTION:
Construction of two (2) Small Water Impounding Project - Reinforced Concrete Structure with Rubble Concrete Slope
Protection on approaches at Downstream = 50.00 l.m. and Upstream = 200.00 l.m. (Brgy. Libas) and Downstream =
50.00 l.m. and Upstream = 100.00 l.m. (Brgy. Lilimasan); and Gabion Revetment of 60.00 l.m. at Brgy Libas.
PROJECT IMPACT:
Small Water Impounding Project provides supplemental irrigation water for intensified crop production which may
substantially increase farmer's income. In addition, it also contributes to the water requirements of livestock production,
aquaculture, power generation, and recreation.
CONTRACTUAL DATA : FINANCIAL STATUS :
Project Component : Small Water Impounding Construction
Province : Pangasinan
Region : I Amount (P'000)
Location : San Carlos City, Pangasinan Allocation Releases Obligation Disbursement
Source of Funds : GAA 2017 (LIP) FY2016
Mode of Contract : Competitive Bidding FY2017 25,000 25,000
Implementing Office : DPWH - Pangasinan IV District Total: 25,000 25,000 -
Engineering Office
Date of Bidding : April 25, 2017
Contractor : JASA BUILDERS
Total Project Cost : 23,636,319.32
Revised Contract Amount : N/A
Start Date : June 8, 2017
Contract Duration : 168 C.D.
Revised Contract Duration : 198 C.D.
Completion Date : November 22, 2017
Revised Completion Date : December 22, 2017
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 23.40% 23.40%
Project is totally suspended due to unworkable
Actual Accomplishment : 15.00% 15.00%
site condition/ high water level.
Slippage : -8.40% -8.40%
PROJECT UPDATE: EQUIPMENT ON SITE:
NONE
Project is totally suspended due to unworkable site condition/ high
water level (August 1, 2017 up to Present). MANPOWER ON SITE:
NONE
ACTIVITIES UNDERTAKEN:
NONE
PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:
Project is totally suspended due to unworkable site condition/ high Contract Time Suspension and Extension were
Project is totally suspended due to unworkable site condition/ high Contract Time Suspension and Extension were
water level caused by previous heavy rains. introduced to the project.
Prepared by: Submitted by: Approved by:
ELDRED M. MISLANG VIRGILIO B. ZAMUDIO SIMPLICIO D. GONZALES
Project Engineer Chief, Construction Section District Engineer