Co
oncrete
e Techno
ology an
nd Code
es
C t
Concrete
Thermal Control of
Overview
es
nd Code
Hot weather concreting
“External” influences
ology an
Mass concrete
“Internal” influences
e Techno
oncrete
Co
Hot Weather Concreting
Definition
ACI 305 Definition:
“Hot
Hot weather is any combination of:
- high air temperature
- high concrete temperature
- low relative humidity
- wind velocityy
- solar radiation
…that tends to impair the quality of
fresh or hardened concrete.”
Hot Weather
C t W
Concrete Workk
Questions You Ask Yourself
During Hot Weather ?
What are the effects of hot
weather on concrete ?
Why are these effects important to
the quality of the finished concrete
product?
Hot Weather Concreting Problems –
Fresh properties
Increased Water
Demand
Accelerated Slump Loss
Faster Set Times
Rapid Water
Evaporation
Plastic Shrinkage
Difficulties controllingg
entrained air
Increased potential for
thermal cracking
Hot Weather Concreting
Problems – Hardened Properties
Decreased strength
Drying Shrinkage
Decreased
Durability
Increased
Permeability
Evaporation
of Surface
Moisture
from
Concrete
When the rate of evaporation
exceeds 0.2 lb/ft2 per hour
precautionary measures
should be taken.
The use of supplementary
cementing materials may
lower this value.
Concrete Temperature
ACI 211.1 For every 100 lb
Cement expect approximately
10-15oF temperature rise from
Heat of Hydration.
Use tepidd water ffor curing.
After curing, let surface dry out
slowly
l l to t reduce
d th
the possibility
ibilit
of crazing or cracking.
Effect of Concrete Temperature on
Water Requirement
Effect of Concrete Temperature
S tti Ti
on Setting Time
Effect of Concrete Temperatures
on Strength
Strength vs. Curing Temperature
Adjust the mix for Hot Weather
Use of SCMs (fly ash, slag cement)
(Can be a double edged sword)
Retarders
Cool concrete materials
Moisten aggregates
Cool concrete
Add plastic fibers
Adjust Placement Practices
Dampen subgrade
Reduce the time of
transport, placing and
finishing
Erect temporary
windbreaks and
sunshades
Fog over the concrete
immediately after
placing
Cover concrete
Effect of Temperature of Materials on
Concrete Temperatures
p
0.22(TaMa + TcMc) + TwMw + TwaMwa
T=
0 22(Ma + Mc) + Mw + Mwa
0.22(M
T = temperature of the freshly mixed concrete
concrete, °C
C (°F)
( F)
Ta, Tc, Tw, and Twa = temperature in °C (°F) of aggregates,
cement,, added mixingg water,, and free water on
aggregates, respectively
Ma, Mc, Mw, and Mwa = mass, kg (lb), of aggregates,
cementing
i materials,
i l added
dd d mixing
i i water, andd ffree
water on aggregates, respectively
Effect of Ice on
Temperature of Concrete
0.22(TaMa + TcMc) + TwMw + TwaMwa – 80Mi
T (ºC) =
0.22(Ma + Mc) + Mw + Mwa + Mi
0.22(TaMa + TcMc) + TwMw + TwaMwa – 112Mi
T (ºF) =
0 22(Ma + Mc) + Mw + Mwa + Mi
0.22(M
Placing & Finishing Concrete in
Hot Weather
Cool equipment
Dampen/ cool
- subgrade
- forms
- rebar
Scheduling: evening or night time
construction
Windbreaks
Sunshades
Fogging
gg g
Questions on Hot Weather
Concreting?
What is Mass Concrete?
What is Mass Concrete?
“Any volume of concrete with dimensions
large enough to require that measures be
taken to cope with generation of heat from
hydration of the cement and attendant
volume change, to minimize cracking.” –
American Concrete Institute (ACI)
• Thick: Foundations, columns,
radiation shielding
shielding, etc
etc.
• Thin: High Performance (HPC),
Self Consolidating Concrete
(SCC), Grout, Patching material
W ki Definition
Working D fi i i
• Minimum Dimension (Thickness)
– No consensus (2½ ft to 7 ft)
– ACI 301-
301-09 will likely say ≥ 4 ft
• Cement Content
– Usually not considered
– ACI 301-
301-09 will likely recommend
a limit
Key Considerations
Maximum temperature
p
Can reduce strength and durability
Temperature
p difference
Can result in thermal cracking
Maximum Temperature
Often limited
No consensus between agencies
Safe limit: 160°F (70°C)
( )
Delayed Ettringite Formation (DEF)
Concrete mix
i ddesign
i
Cement (type and quantity)
Pozzolans
l ((type and
d percentage))
Delayed Ettringite Formation
(DEF)
Concrete cured at excessively
high temperatures may
develop p DEF because ettringiteg
decomposes – or does not
form at high temperature.
Later it forms/reforms after
the concrete is hard, and may
cause expansion.
DEF iis a tterm th
thatt iis properly
l
applied only to curing at
elevated temperatures. It
d
does nott apply
l tto ambient
bi t
curing.
Expansion of Paste away
from Aggregate
DEF potential?
The heat of hydration of cement can
p
raise the concrete temperature to
above 160°F
The critical temperature for DEF lies
somewhere between 160°F and 195°F
(depends on the cement)
This is particularly true for cements
with high fineness( > 400m2/kg), high
C3S, high
S hi h C3A,
A and high
d hi h alkali
lk li content.
t t
SO3/Al2O3 ratio > 0.7
Maximum Temperature
100% Cement
70/30
/ Blend
l d off
Cement and Fly Ash
25/75 Blend of
Cement and Slag
Maximum Temperature
Estimation
Max. Temp. = Initial Temp. + Temp. Rise - Loss
Initial Temperature
As low as economically practical (Payback of 1:1)
Temperature rise depends on mix design
Equivalent cement content
Loss (Early heat loss)
Minimal for placement >5 ft thick
2-6 F per day, depends on R value, dimensions, etc.
Equivalent Cement
Content
1lb/yd3 of cement = 1 lb/yd3 equiv. cement
1 lb/yd3 of Class F ash = 0.5 lb/yd3 equiv. cement
lb/ d3 off Cl
1 lb/yd Class C ash
h=00.8
8 lb/ d3 equiv.
lb/yd i cementt
1 lb/yd3 of Slag (50%) = 0.9 lb/yd3 equiv. cement
1 lb/yd3 of Slab (75%) = 0 8 lb/yd3 equiv.
0.8 equiv cement
Temperature
p Rise in Concrete
16°F per 100 lb/yd3 equiv. cement
For example
example…
Concrete Foundation
400 lb/yd3 cement and 200 lb/yd3 class F fly ash
70°F delivered concrete
6 ft thick
Equivalent cement = 400 + 0.5*200 = 500 lb/yd3
Temperature
p Rise = 500*16/100 = 80°F
Maximum Temperature = 80+70-0 = 150°F
Temperature Difference
Limited to minimize (or prevent) thermal cracking
Temperature difference between interior and surface
Crack width is a function of the temperature difference
Thermal Cracking
Undesirable, but sometimes unavoidable
Mostly a durability concern
Severe can be a structural issue
“Tolerable” limits in ACI 224R
E
Extreme Th
Thermall C ki
Cracking
More Extreme Thermal
Cracking
Somewhat Extreme Thermal
Cracking
T i l Th
Typical Thermall C ki
Cracking
More Typical Thermal
Cracking
Temperature Difference Limits
Often limited to a maximum of 35°F
Generalized “rule-of-thumb”
Worked for unreinforced dams in
E
Europe 75+ years ago
May not prevent thermal cracking
Extends construction time
Stepped limit
Steps up with age (35
(35-45-60°F)
45 60°F)
Shortens construction time
Can lead to thermal cracking
Tailored limit
Tailored Temperature
ff
Difference
Calculation based on ACI 207.2R
Performance-based approach
Acco nts for concrete’s ability
Accounts abilit to
withstand higher thermal stresses as
in-place strength increases
Based on concrete properties
Based on structure and design
Can be used to prevent cracking or
limit crack widths
Temperature Difference
(
(cont.)
)
80
Diff., °F
70
60
Alllowable Temp. D
50
40
30
20 Calculated (Example)
10 Specified 35°F
35 F
0
0 1000 2000 3000 4000 5000 6000 7000
In-Place Compressive Strength, psi
Temperature
p Difference and
Time Savings
180
160
Temperaturre, °F
140
120
Calculated dT
100
35°F dT
80
60
0 10 20 30 40 50 60
Time, Days
Temperature Control
Strategies - Use a Reduced
Heat Concrete
180 Type I with No Pozzolans
Type II with No Pozzolans
160
Type I/II, II or V Cement Type I with 25% Fly Ash
T e m p e r a tu r e , °F
Type II with 25% Fly Ash
140
Slag Cement 120
100
50% to 75% replacement 80
Fly Ash (Class F) 60
0 5 10 15 20 25 30
25% to 40% replacement Time, Days
Recall that:
1lb/yd3 of cement = 1 lb/yd3 equiv. cement
1 lb/yd3 of Class F ash = 0.5 lb/yd3 equiv. cement
lb/ d3 off Class
1 lb/yd l C ash h = 0.8 lb/ d3 equiv. cement
lb/yd
1 lb/yd3 of Slag (50%) = 0.9 lb/yd3 equiv. cement
1 lb/yd3 of Slab (75%) = 0.8 lb/yd3 equiv. cement
Temperature Control Strategies
l
– Place C
Concrete iin Lifts
if
Thick placements take a long time to cool
Multiple distinct placements
Thin lifts allow early heat loss
Reduced maximum temperature
Faster cooling
Temperature Control
Strategies – Precool the
Concrete
Precool aggregates
Evaporative cooling is a very low
cost solution
Chilled mix water
Low cost (need chiller plant)
Max. reduction of about 5°F
Substitute ice for mix water
More expensive
Can be labor intensive
Max. reduction of about 20°F
Temperature Control
Strategies – Precool the
Concrete (Cont.)
Liquid Nitrogen (LN2)
Can re-cool concrete
multiple times
Adds time and drum
rotations
Cool onsite or at batch
plant
Can be expensive
Can be dangerous
Temperature Control
l Pipes
Strategies – Cooling
Remove internal heat after
concrete placed
Reduces maximum temperature
p
Reduces cooling time
¾” plastic cooling pipes
Grouted afterwards
Temperature Control
l Pipes
Strategies – Cooling
Large supply of natural water
(river, lake, ocean, ground water)
Chiller
Temperature Control Strategies
– Insulation
Insulation retains surface
heat to control the
temperature difference
Necessary in summer
and winter
Things to Avoid
Water Curing
Improper Insulation
Early Removal of
Insulation
Example: 10 ft dia.
dia column
Performance specifications
674 pcy minimum cementitious
150°F maximum temperature
No thermal cracking
Tailored temperature
p difference
Example (cont
(cont.))
Specially designed
concrete
Tight Schedule
Used Cooling Pipes
Used Maturity
150
Ambient Air Centerline
Example
p ((cont.)) 130
Surface
Water Outlet
Water Inlet
Temperature, °F
110
Using Calculated temp. 90
d ff
difference, Columns
l
T
70
sufficiently cool in 5 to 6
50
y
days 0 1 2 3 4 5 6
Time, Days
• If 20°
20°C(35
C(35°°F) temp differential
specified…
– cooling time increased by 50%
– could not meet spec without cooling
pipes
Example:
C l
Column Analysis
A l i
Concrete at Top C
L
Full-height Cooling Pipe (4 total)
of Column
Concrete in the
Bottom Half of Hoop/Tie Reinforcing
the Column (not all shown)
Manifolds
C
L Supply
Pump
C
L
Discharge
Plan View of the Column
(not to scale)
Temperature, °F
155
150
145
140
135
130
125
120
115
110
105
100
95
90
85
80
75
70
Day = 0
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 137°F
S f
Surface Thermocouple
Th l = 123°F
Pipe Thermocouple = 117°F
Largest Temp. Diff. = 20°F Day = 1
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 150°F
S f
Surface Thermocouple
Th l = 129°F
Pipe Thermocouple = 124°F
Largest Temp. Diff. = 26°F Day = 2
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 146°F
S f
Surface Thermocouple
Th l = 123°F
Pipe Thermocouple = 121°F
Largest Temp. Diff. = 25°F Day = 3
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 139°F
S f
Surface Thermocouple
Th l = 116°F
Pipe Thermocouple = 116°F
Largest Temp. Diff. = 23°F Day = 4
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 131°F
S f
Surface Thermocouple
Th l = 109°F
Pipe Thermocouple = 111°F
Largest Temp. Diff. = 21°F Day = 5
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 123°F
S f
Surface Thermocouple
Th l = 104°F
Pipe Thermocouple = 106°F
Largest Temp. Diff. = 19°F Day = 6
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 116°F
S f
Surface Thermocouple
Th l = 99°F
Pipe Thermocouple = 101°F
Largest Temp. Diff. = 17°F Day = 7
Assumed Placement Conditions
Concrete Mix No. 1 with 330 pcy slag and 330 pcy cement Temperature, °F
Cooling Pipes Installed and Operated
Average Air Temperature = 70°F 155
Initial Concrete Temperature = 80°F 150
Cooling Water Temperature = 70°F
145
R-2.8 Surface Insulation
140
135
130
125
120
115
110
105
100
95
90
85
80
75
Predicted Temperatures (See Drawing No. 3 for Thermocouple Locations) 70
Center Thermocouple = 110°F
S f
Surface Thermocouple
Th l = 95°F
Pipe Thermocouple = 97°F
Largest Temp. Diff. = 15°F Day = 8
Inspector’s Guide to Mass
f
Concrete – Before l
Placement
Read contractor’s thermal control plan
Identify initial concrete temperature limit
Identify other rejection criteria
Verify cylinder storage area
Verify placement equipment
Schedule p personnel and duties
Verify installed temperature sensors
Verifyy operation
p of coolingg pipes
p p ((if used))
Thermal Control Plan
( )
(TCP)
Submittal item
Must be approved before placement
Demonstrates contractor’s methods to
Comply with mass concrete specifications
Ensure maximum temperature under 160°F (or
specified limit)
Minimize/prevent
Mi i i / thermal
h l cracking
ki ((states a
temperature difference limit)
Ensure proper curing
Contents of a TCP
Specification Requirements
Concrete Placements covered by TCP
Concrete Mix Design
Predicted Temperatures in Placements
Assumptions used
Temperature ranges (air, concrete, etc).
Prediction method
Anticipated results
(cont )
Contents of a TCP (cont.)
Construction Practices
Placement method (pump, etc.)
Rejection temperature for delivered concrete
Curing method
Insulation (materials and installation)
Cooling pipe details (if used)
Materials
Installation
Operation
(cont )
Contents of a TCP (cont.)
Construction practices (cont.)
Temperature monitoring
Equipment
Frequency
Reporting
R ti
Corrective measures
Completion criteria
riteria
Prepour Temperature Sensor
f
Verification
Correct equipment
q p and locations
Per the thermal control plan
Typically at center of mass of placement
2-3” below surface (top or side)
Away from pipes, piles, etc.
Backup sensors
Functioning (good data)
Wires protected
Prepour Cooling Pipe
f
Verification
Proper
p locations
Per the thermal control plan
Uniform layout
Water flows through all pipes
No leaks
Flow rate
Inspector’s Guide to Mass
l
Concrete – During Placement
Verify fresh properties
Verify concrete temperature within limit
Verify proper vibration
Form pressure issues?
Watch cooling pipes and temperature
sensors
Revibration
Finishing
Curing
Inspector’s Guide to Mass
Concrete – During Thermal
Control Period
Fully insulated concrete and formwork
Cooling pipes operating properly
All temperatures within limit
Temperature differences within limit
Contractor adjustments, if necessary
Inspector’s Guide to Mass
Concrete – After Thermal
Control is Complete
Cooling pipes grouted, cut below surface
and patched
No thermal cracking
Repairs (if necessary)
Summary
Concrete gets hot!!
Extra measures are needed to
prevent excessive temperatures
and temperature differences.
Many approaches to thermal
control
t l
Insulation always needed
Temperature sensors for
verification of thermal control
Questions on Mass
Concrete?