Solar Inverter Manual for Water Pumps
Solar Inverter Manual for Water Pumps
2.2KW/7.5KW/11KW
Solar Inverter for Water Pump
Version: 1.8
Table Of Contents
Purpose ............................................................................................................................................................ 1
Scope ............................................................................................................................................................... 1
SAFETY INSTRUCTIONS................................................................................................................................... 1
Inspection ......................................................................................................................................................... 1
Installation ........................................................................................................................................................ 1
Operation ......................................................................................................................................................... 2
Maintenance .................................................................................................................................................... 2
INTRODUCTION ................................................................................................................................................. 3
Features ........................................................................................................................................................... 3
Basic System Architecture ............................................................................................................................... 3
Product Overview ............................................................................................................................................. 4
INSTALLATION ................................................................................................................................................... 5
COMMISSIONING ............................................................................................................................................. 10
OPERATION ...................................................................................................................................................... 11
SPECIFICATIONS ............................................................................................................................................. 19
ABOUT THIS MANUAL
Purpose
This manual describes the assembly, installation, operation and troubleshooting of this unit. Please read
this manual carefully before installations and operations. Keep this manual for future reference.
Scope
This manual provides safety and installation guidelines as well as information on tools and wiring.
SAFETY INSTRUCTIONS
WARNING: This chapter contains important safety and operating instructions. Read and
keep this manual for future reference.
Inspection
If missing components or damaged inverter is found after receiving, please do NOT install or operate it.
Otherwise, it may cause human injury or equipment damage.
Installation
1. Before installation, please make sure if the voltage range of PV panel meets the requirement.
2. Check if all wires are firmly connected without short circuit. Otherwise, it will cause equipment damage.
3. Do NOT install this inverter under direct sunlight because high temperature may cause equipment damage.
4. Please install the inverter away from inflammable and explosive objectives. Please ensure no liquid can
enter the inverter.
5. Please install the inverter on metal non-combustible surface.
1. CAUTION!! Only qualified personnel can install and operate this inverter.
2. To reduce risk of electric shock, disconnect power source before making wire connection. Otherwise, it may
cause electrical shock.
3. To reduce risk of electric shock, NEVER touch any terminals on electric circuits.
4. If connection cable between inverter and water pump is more than 50m, please be sure to install a
three-phase AC reactor. Inductance value for each phase is about 1mH. Otherwise, water pump would be
easily to be damaged.
1
Operation
1. Only after wire connection is complete and put cover back to the inverter, it’s ok to do commissioning.
Otherwise, it will cause electric shock
2. If sunlight is sufficient but little water is pumped, maybe the wires on motor connection are reversely
connected. Please reverse any two wires of them.
3. When testing water pump, be sure to install water pump at appropriate water level. Never allow water
pump in dry running. Otherwise, the inverter will activate protection.
Maintenance
1. Only qualified personnel can maintain, repair, inspect the inverter and replace any components.
2. It may still contain energy after disconnecting power source for 10 minutes. Only service the unit after the
bus voltage is within safe range.
2
INTRODUCTION
Interest in renewable energy has increased over the past few years due to solar power becoming more cost
effective and eco-friendly. This is a solar inverter which allows power to be switched from the DC power
obtained from solar panels to the AC power needed to control the pump. With the renewable solar inverter,
pumps can adapt to solar power sources rather than traditional electrical supplies or generators.
This solar inverter is built-in with MPPT solar charger to maximize solar power. Besides, it is easy to install with
low maintenance cost. It becomes an eco-friendly solution for the rural areas where grid power is expensive
and unreliable.
Features
Built-in MPPT solar charger
Supports three-phase asynchronous motor
Built-in full protection and self-diagnosis
Soft start function prevents water hammer effect and extends system lifecycle
Comprehensive LCD and LEDs display real-time system status
Remote monitoring through RS-485
3
Product Overview
1. PV input
2. AC output
3. RS-485 communication port
4. RS-232 communication port
5. Signal control slot
6. Display screen (Refer to Operation and Display Panel for the details)
7. LED indicators (Refer to Operation and Display Panel for the details)
8. Operation buttons (Refer to Operation and Display Panel for the details)
4
INSTALLATION
Unpacking and Inspection
Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You should
have received the following items inside of package:
The unit x 1
User manual x 1
RJ45 cable x 1
RS-232 cable x 1
Preparation
Before connecting all wirings, please take off bottom cover by removing two screws as shown below.
5
1. Drill four holes in the marked locations with four 2. Install the unit by screwing four screws. It’s
screws. recommended to use M5 screws.
PV Connection
CAUTION: Before connecting to PV modules, please install separately a DC circuit breaker between inverter
and PV modules. The recommended spec of DC breaker is C8A/2P/1000VDC/25KA for 2.2KW,
C32A/2P/1000VDC/25KA for 7.5KW and C40A/2P/1000VDC/25KA for 11KW.
NOTE: It’s required to install PV combiner box when using several PV modules in parallel and series.
CAUTION: Important
Before making PV connection, be sure to do the following actions to prevent human injury or machine damage.
1. It’s required to turn off circuit breaker.
2. Make sure connect positive pole (+) of PV input connector in inverter to positive pole (+) of PV modules and
negative pole (-) of PV input connector in inverter to negative pole (-) of PV modules.
6
PV Module Selection:
When selecting proper PV modules, please be sure to consider below parameters:
1. Open circuit Voltage (Voc) of PV modules not exceeds max. DC voltage (800VDC).
2. Accumulated voltage of connected PV panels should be close to 560V for inverter with 380V output voltage.
To calculate PV module numbers in series (N) and in parallel (M), please follow below formula:
Imp>Po/(Kvo x 0.9 x M)
Po represents the rated output power.
Kvo is equal to 560V/585/606V/642V for 380V/400V/415V/440V output voltage respectively.
Maximum PV module numbers in series (N) > 560 / Vmp
We strongly recommend the total PV Vmp is around 560Vdc to get the optimum MPPT output.
7
NOTE: To reverse the direction of motor rotation, reverse any two wires.
US Black (BLK) Red (RED) Yellow (YEL) Ground (GND)
International Gray (GRY) Black (BLK) Brown (BRN) Ground (GND)
International standards for motor lead wire
Final Assembly
After connecting all wirings, please put bottom cover back by screwing two screws as shown below.
8
Control Signal Connection (Optional)
There are 7 ports in control signal connection. 2-port on the right side is to power supply for remote panel.
5-port on the left side is to detect water level to prevent water pump from dry running and water tank from
overflow/underflow.
9
Remote float switch (2):
It’s to prevent the water pump dry running by connecting to remote float switch. The length of connecting wire
should not longer than 50m. If the water level is normal in the well, COM1 and DI3 (S3) is kept in normal close
status. If the water level is low in the well, COM1 and DI3 (S3) will be open status. If this port is not connected
to water level probe, be sure to connect COM1 and DI3 together. It’s default setting from factory.
COMMISSIONING
Step 1: Check the following requirements before commissioning:
Ensure all wires are firmly and correctly connected
Use a megger to check insulation of motor and wires
Check if the open circuit DC voltage of PV module meets requirement
Step 2: Switch on DC breaker and provide power to the inverter. Then, LCD screen will show 0.00. Please set up
the parameters of the inverter such as rated power, rated frequency, rated current and rated voltage. For the
detailed setting, please check “Parameter setting” section in Operation chapter.
Step 3: Press “RUN” button to activate the inverter. If the output frequency or water yield is low, it may be
wrong for output wire connection. Please exchange any two wires connected to the motor. Please be sure the
output frequency and water yield are normal. It means the wire connection is correct and complete.
10
OPERATION
Power ON/OFF
Once the unit has been properly installed, simply press “RUN” button (located on the button area) to turn
on the unit.
LED indicators
Display screen
Function buttons
LED Indicator
LED Indicator Messages
Hz Green Solid On Output frequency value is displayed on the LCD screen.
A Green Solid On Output current value is displayed on the LCD screen.
V Green Solid On Output voltage value is displayed on the LCD screen.
A and V Green Solid on Output power value is displayed on the LCD screen.
Green Solid on The inverter is running.
STOP/RUN
Green OFF The inverter stops.
NOTE: After the inverter is turned on, LED display will show following information in turns: current output
frequency, current output voltage, current output current, current PV voltage and current output
power. After the inverter is turned off, LED display will still show output frequency until it’s 0.
11
Function Buttons
Function Button Description
ESC/PROG To enter or exit setting mode.
ENTER To confirm the selection/value in setting mode.
RUN To turn on the unit, press this button for at least 1 second.
To turn off the unit, press this button for at least 1 second.
STOP/RST
To reset fault message, press this button for at least 1 second.
To increase the setting value.
To decrease the setting value.
and ENTER Press these two buttons at the same time to move cursor location.
Parameter Setting
The entire display setting program structure is demonstrated as below chart.
12
Parameter setting procedure for water pump
Operation steps Screen Display
1. Press “ESC/PROG” button for 500ms. Then, it will display “P0” in
display screen.
2. Press “ENTER” button for 500ms, display screen will show as in the
right chart.
3. Press “ENTER” button again to start to set up rated power of the water
pump. Press “ENTER” and “DOWN” buttons to switch cursor location.
Press “UP” or “DOWN” button to change value for rated power. Until it
shows correct rated power, please press “ENTER” button to confirm the
setting.
13
7. Press “ENTER” button to be able to set up nominal voltage of the water
pump. Press “ENTER” and “DOWN” buttons at the same time to switch
cursor. Then, press “UP” or “DOWN” button to change value for
nominal voltage. Until it shows correct nominal voltage, please press
“ENTER” button to confirm the setting.
10. Then, all parameters of water pump are set up completely. Press
“ESC/PROG” button to return to P0 level. Please press “ESC/PROG”
button again for 1 second to return to main interface.
11. Turn on the inverter by pressing “RUN” button. Then, RUN/STOP LED
will light up and display screen will show inverter information in turns.
NOTE: If it’s requested to have the inverter is automatically turned on every morning, please set up program
P4.01 as “1” in standby mode.
14
Parameter Setting Table
〇: This parameter can be modified no matter the inverter is in operation or off status.
◎: This parameter can be modified only when inverter is turned off and it shows 0.00 Hz in display screen.
Program # Description Setting Range Unit Default Value Note
P0 Parameter settings for the motor
15
Program # Description Setting Range Unit Default Value Note
P3 Protection setting for the inverter of the water pump
Sleep mode while PV
P3.00 10-3600 S 120 〇
energy is weak
Sleep mode for dry
P3.01 10-7200 S 1200 〇
running
Allow dry pumping
P3.02 1-3600 S 5 〇
duration
Over-temperature fault
P3.03
on inverter
60-100 ℃ 85 ◎
Over-temperature 10 – setting value
P3.04 ℃ 75 〇
warning on inverter in P3.02
Acceleration time for
P3.05
motor
1-3600 S 20 ◎
Deceleration time for
P3.06
motor
1-3600 S 20 ◎
Over-temperature
P3.07 10-60 ℃ 45 〇
warning for environment
P4 Inverter operation mode setting
0:Disable.
Control PV
MPPT function
P4.00
enable/disable
voltage in setting None 1 ◎
value of P2.02
1:Enable
0:Disable
P4.01 Auto turn-on
1:Enable
None 0 ◎
Dry-pumping protection 0:Disable
P4.02 None 1 〇
enable/disable 1:Enable
P5 User password setting and restore to default setting
P5.00 User password setting 0-9999 None 0 〇
Remote monitored device
P5.01 1-247 None 1 〇
ID setting
0:No
P5.02 Restore to default setting
1:Yes
None 0 ◎
16
Fault and Warning Code
All fault and warning codes can be reset by pressing “RST” button except for A07 and A11. When faults or
warning occur, press “RST” button and the inverter will enter standby mode. Please press “RUN” button to turn
on the inverter for operation again.
After A02 or A03 warning occurs, the inverter will auto restart operation after a period of sleep mode. If
pressing “RST” button during sleep mode, please be sure to press “RUN” button again for operation.
17
Warning Reference Codes
Warning code Warning type Possible Cause
A01 PV input voltage is too low. 1. PV input voltage is too low.
2. Sunlight is too weak.
A02 Weak sunlight Sunlight is too weak
A03 Dry running 1. Water level in the well is low.
2. Nominal power of motor is not setting.
A04 Overload 1. The motor is suddenly locked.
2. The pump head is too high.
3. Wrong current setting on the motor.
A05 Over current 1. The motor is suddenly locked.
2. Wrong current setting on the motor.
A06 EEPROM error There is something wrong with EEPROM circuit.
A07 IGBT over temperature warning Over temperature on IGBT.
A08 Over-temperature warning for Over temperature warning. The default warning
environment point is 45°C.
A09 Over-temperature fault for 1. Environment temperature is beyond the upper
environment limit (60°C).
2. The wire of environment temperature
detection is not connected.
A10 Wrong parameter setting in the Wrong parameter setting in the motor.
motor.
A11 Water tank is full. Water tank is full.
A12 Water tank is dry. No water or water in low level in the water tower.
A13 Well is dry. No water or water in low level in the well.
A14 Password verification is not No password is set up.
complete.
18
SPECIFICATIONS
MODEL 2.2KW 7.5KW 11KW
PV INPUT (DC)
Nominal DC Voltage / Maximum
540 VDC / 800 VDC
DC Voltage
Start-up Voltage 250 VDC
OUTPUT
PROTECTION
Phase lost, dry pumping, motor locked, weak sunlight, over-voltage,
Full Protection under-voltage, over-current, surge, over-temperature and short circuit
protection
PHYSICAL
INTERACE
Communication Port RS-232/RS-485
ENVIRONMENT
Humidity < 95% RH (No condensing)
Operating Temperature -20°C~45°C at 100% full load, 46°C~60°C power derating
19