MONITORING PROGRAMME Page 1 of 1
Activity ID Activity Name Original Start Finish 2019 2020
Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
MONITORING PROGRAMME 71 26-Sep-19 05-Dec-19
Outlet Works 71 26-Sep-19 05-Dec-19
Outlet Basins 71 26-Sep-19 05-Dec-19
New Basin 3B 71 26-Sep-19 05-Dec-19
Demolition 8 26-Sep-19 03-Oct-19
A2850 Demolition Portion of Existing Basin incl Disposal 8 26-Sep-19* 03-Oct-19 Demolition Portion of Existing Basin incl Disposal
Earthworks 57 04-Oct-19 29-Nov-19
A3170 Rock Excavation/Common Excavation 4 04-Oct-19 07-Oct-19 Rock Excavation/Common Excavation
A2830 Common Excavation/Base course material 4 04-Oct-19 07-Oct-19 Common Excavation/Base course material
A2840 Lean Concrete 2 08-Oct-19 09-Oct-19 Lean Concrete
A3180 Common Backfill 14 16-Nov-19 29-Nov-19 Common Backfill
Foundation 19 10-Oct-19 28-Oct-19
Lower Portion 10 10-Oct-19 19-Oct-19
A2710 Rebar installation 6 10-Oct-19 15-Oct-19 Rebar installation
A2720 Forms installation 3 16-Oct-19 18-Oct-19 Forms installation
A2730 Concrete casting 1 18-Oct-19 18-Oct-19 Concrete casting
A2770 Formworks removal 1 19-Oct-19 19-Oct-19 Formworks removal
Upper Portion 10 19-Oct-19 28-Oct-19
A4680 Rebar installation 6 19-Oct-19 25-Oct-19 Rebar installation
A4690 Forms installation 3 25-Oct-19 27-Oct-19 Forms installation
A4700 Concrete casting 1 28-Oct-19 28-Oct-19 Concrete casting
A4710 Formworks removal 1 28-Oct-19 28-Oct-19 Formworks removal
Elevation/Wall 28 29-Oct-19 25-Nov-19
A3280 Forms installation (Internal) 4 29-Oct-19 01-Nov-19 Forms installation (Internal)
A2740 Rebar installation 8 02-Nov-19 09-Nov-19 Rebar installation
A2750 Forms installation (External) 5 10-Nov-19 14-Nov-19 Forms installation (External)
A2760 Concrete casting 1 15-Nov-19 15-Nov-19 Concrete casting
A3600 Forms removal 3 16-Nov-19 18-Nov-19 Forms removal
A4750 Cantilever slab construction 7 19-Nov-19 25-Nov-19 Cantilever slab construction
Miscellaneous Items 38 29-Oct-19 05-Dec-19
A3920 Ladder rung 4 29-Oct-19 01-Nov-19 Ladder rung
A3660 Handrail 10 26-Nov-19 05-Dec-19 Handrail
Actual Level of Effort Milestone NEW BASIN 3B CONSTRUCTION
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work