Monitoring Programme Monitoring Programme: Outlet Works Outlet Works

This document outlines the monitoring programme for outlet works construction from September 2019 to December 2020. It details the activities, original durations, and planned start and finish dates for demolishing an existing basin, earthworks, laying foundations, erecting walls and slabs, and miscellaneous items. The critical path activities include demolition, rock excavation, concrete casting, and installing handrails.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views1 page

Monitoring Programme Monitoring Programme: Outlet Works Outlet Works

This document outlines the monitoring programme for outlet works construction from September 2019 to December 2020. It details the activities, original durations, and planned start and finish dates for demolishing an existing basin, earthworks, laying foundations, erecting walls and slabs, and miscellaneous items. The critical path activities include demolition, rock excavation, concrete casting, and installing handrails.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

MONITORING PROGRAMME Page 1 of 1

Activity ID Activity Name Original Start Finish 2019 2020


Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
MONITORING PROGRAMME 71 26-Sep-19 05-Dec-19

Outlet Works 71 26-Sep-19 05-Dec-19

Outlet Basins 71 26-Sep-19 05-Dec-19


New Basin 3B 71 26-Sep-19 05-Dec-19
Demolition 8 26-Sep-19 03-Oct-19
A2850 Demolition Portion of Existing Basin incl Disposal 8 26-Sep-19* 03-Oct-19 Demolition Portion of Existing Basin incl Disposal
Earthworks 57 04-Oct-19 29-Nov-19
A3170 Rock Excavation/Common Excavation 4 04-Oct-19 07-Oct-19 Rock Excavation/Common Excavation
A2830 Common Excavation/Base course material 4 04-Oct-19 07-Oct-19 Common Excavation/Base course material
A2840 Lean Concrete 2 08-Oct-19 09-Oct-19 Lean Concrete
A3180 Common Backfill 14 16-Nov-19 29-Nov-19 Common Backfill
Foundation 19 10-Oct-19 28-Oct-19
Lower Portion 10 10-Oct-19 19-Oct-19
A2710 Rebar installation 6 10-Oct-19 15-Oct-19 Rebar installation
A2720 Forms installation 3 16-Oct-19 18-Oct-19 Forms installation
A2730 Concrete casting 1 18-Oct-19 18-Oct-19 Concrete casting
A2770 Formworks removal 1 19-Oct-19 19-Oct-19 Formworks removal
Upper Portion 10 19-Oct-19 28-Oct-19
A4680 Rebar installation 6 19-Oct-19 25-Oct-19 Rebar installation
A4690 Forms installation 3 25-Oct-19 27-Oct-19 Forms installation
A4700 Concrete casting 1 28-Oct-19 28-Oct-19 Concrete casting
A4710 Formworks removal 1 28-Oct-19 28-Oct-19 Formworks removal
Elevation/Wall 28 29-Oct-19 25-Nov-19
A3280 Forms installation (Internal) 4 29-Oct-19 01-Nov-19 Forms installation (Internal)
A2740 Rebar installation 8 02-Nov-19 09-Nov-19 Rebar installation
A2750 Forms installation (External) 5 10-Nov-19 14-Nov-19 Forms installation (External)
A2760 Concrete casting 1 15-Nov-19 15-Nov-19 Concrete casting
A3600 Forms removal 3 16-Nov-19 18-Nov-19 Forms removal
A4750 Cantilever slab construction 7 19-Nov-19 25-Nov-19 Cantilever slab construction
Miscellaneous Items 38 29-Oct-19 05-Dec-19
A3920 Ladder rung 4 29-Oct-19 01-Nov-19 Ladder rung
A3660 Handrail 10 26-Nov-19 05-Dec-19 Handrail

Actual Level of Effort Milestone NEW BASIN 3B CONSTRUCTION


Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work