Contractor:SEPCOIII Owner:Lucky Electric Power Consultant:FICHTNER GMBH
ELECTRIC POWER Company Limited & CO KG
CONSTRUCTION
CORPORATION., LTD.
CHECKLIST FOR WELDING VISUAL INSEPCTION
ITP No. Form No.
Location Page No.
SN Description Result Remarks
1 Check the weld map with full joint details
2 Ensure that all welding spatters and slag is removed from joint
3 Ensure that joints is defect free and visually acceptable
4 Cap size is accepted
5 Check the welder certification is available
Note:
Issued Sub-contractor Contractor Consultant/Owner
Singnature
Name
Designation
Date
Result Instruction: √-Accept ×-Reject Or fill your comments