Mobile Scaffold Tower Risk Assessment
Mobile Scaffold Tower Risk Assessment
1 Falls of persons X
2 Falls of materials X
3
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
The Work at Height Regulations 2005
HSE Guidance Booklets HS(G)33: Safety in Roofwork (out of print) and HS(G)130: Health and safety
for small construction sites
HSE Guidance Note GS25: Prevention of falls to window-cleaners
British Standard BS 1129:1990 Ladders, steps & lightweight staging
Planning:
Work is planned to ensure a safe means of access is provided.
See separate assessments for use of ladders, scaffolding, mobile elevating working platforms and mobile
scaffold towers.
All equipment is provided and maintained to required legal and other standards.
Physical:
Suitable signs and barriers will be positioned directly below works to warn of overhead operations.
Edge protection will be erected at all openings or edges where falls of more than 2m could occur.
Where edge protection is removed for access, or is not practicable, safety lines and harnesses will be
worn by operatives working at or near the edge.
Where there is likely to be debris falling, fans, chutes or full enclosures will be used to protect third
parties.
All operatives working below overhead operations will wear safety helmets.
Managerial/Supervisory:
All equipment used will be checked to ensure it is in good order, to correct specification, and in date for
inspection.
Work will be monitored to ensure that additional precautions and equipment is taken into use if edge
protection is removed.
Other relevant British Standards include:
BS 5845:1991 - Anchors for safety harnesses
BS 8213 Part 1:1991 - Code of Practice for cleaning of windows & doors
BS EN 355, 358, 361-365 - Personal protective equipment against falls from a height
Training:
Training and instruction must be provided to all operatives and supervisory staff involved in the use of
lines and harnesses, and how to inspect and assess PPE of this type before use.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
GENERIC RISK ASSESSMENT
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
1 Falls of persons X
2 Falls of materials X
3 Collapse of tower X
4 Overturning of tower X
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
The Work at Height Regulations 2005
HSE Guidance Note GS42 - Tower scaffolds
British Standards: BS 5973:1993 - Access and working scaffolds
BS 1139:Part 3:1994 - Prefabricated mobile access and working towers
Planning:
Only authorised personnel will erect, modify or dismantle scaffolding towers.
Towers should not be specified for use in the vicinity of overhead power lines.
Specification for use of tower scaffolds will take into account the site ground conditions expected,
height restrictions and obstructions.
Work will be tendered for taking into account relevant standards.
Physical:
Towers will be erected by trained personnel in accordance with relevant standards and manufacturer's
instructions.
Ladder access should be internal and fixed to the narrowest side.
Maximum height to base ratios will not be exceeded: 3.5:1 inside use and 3:1 external use without ties.
Ties will be used in exposed or windy conditions.
All tower platforms will be fully boarded and fitted with toeboards and guardrails.
Wheels will be braked or locked when the tower is in use.
Personnel and materials will be removed before a tower is moved.
Manufacturer's advice on maximum loadings will be adhered to.
Managerial/Supervisory:
All scaffolding will be inspected on handover to or from other contractors.
After alteration or adverse weather conditions scaffolds must be inspected by management.
Towers over 2m in height must be inspected every seven days and the results entered in Form F91 Part 1
section A.
All scaffold inspections will be carried out by a competent person.
Scaffolds will be checked regularly to ensure their correct use and that unauthorised adaptations have
not been made.
Training:
Persons erecting scaffolding must be adequately trained. Training may be provided by manufacturers or
hirers, but some proof should be obtained.
Inspections of scaffolding will be carried out only by those trained and competent to do so.
This generic assessment must be completed by the File Ref:
addition of specific site details on the reverse GRA. 4 ( 10.7)
SITE-SPECIFIC ASSESSMENT
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
1 Falls of persons X
2 Falls of materials X
3 Collapse of structure X
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
The Work at Height Regulations 200HSE Guidance Note GS15 - General access scaffolds
British Standard BS 5973:1993 - Code of Practice
Planning:
Only authorised personnel will erect, modify or dismantle scaffolding.
For structures over 5m in height, CITB certification of erectors will be required and checked.
Design drawings will be produced for load-bearing scaffolds and non-standard structures.
Erection will be to BS 5973:1993.
Lighting arrangements will be referred to local authority for structures on the public highway or right of
way.
Physical:
Guardrails and toeboards removed for access will be replaced after access has been gained. Unused
ladder gaps will have them fitted.
Ties removed for any purposes will be replaced or alternative ties fitted, at once.
Debris guards, debris netting and fans will be considered for high-rise scaffolds and those close to public
areas.
Traffic movements will be restricted around scaffold bases.
Excavations adjacent to scaffold bases will be monitored to ensure the stability of the structure is not
affected.
Managerial/Supervisory:
All scaffolding will be inspected on handover to or from other contractors.
After alteration or adverse weather conditions scaffolds must be inspected by management.
Structures over 2m in height must be inspected every seven days and the results entered into Form F91
Part 1 Section A.
All scaffold inspections will be carried out by a competent person.
Scaffolds will be checked regularly to ensure their correct use and that unauthorised adaptations have
not been made.
Training:
Persons erecting scaffolding must be adequately trained. This will normally be verified by production of
a Scaffolder Certificate issued by the CITB.
Inspections of scaffolding will be carried out only by those trained and competent to do so.
This generic assessment must be completed by the File Ref:
addition of specific site details on the reverse GRA. 5 ( 10.7)
SITE-SPECIFIC ASSESSMENT
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
1 Falls of persons X
2 Falls of materials X
3 Unintentional lowering of platform X
4 Striking against overhead obstructions X
5 Platform overturning X
6 Vehicles or plant striking platform X
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
The Work at Height Regulations 2005 Construction (Lifting Operations) regulations 1961
HSE Guidance Booklet HS(G)19 - Safety in working with power-operated mobile working platforms
British Standard BS 7171:1989 - Specification for mobile elevating working platforms
Planning:
Control of traffic and pedestrians will be planned.
Platform capacity will be checked to ensure sufficient height and SWL for the work undertaken, before
use.
Where owned by the Company, this equipment is subject to the planned maintenance programme.
Where hired, proof of servicing will be required.
Physical:
The area of work is to be fenced off.
Platforms must not be operated outside limits set by the manufacturer.
The operating area will be firm and level. Stabilisers will be extended before the platform is raised;
platforms are not to be left unattended in the raised position.
Platforms must not be moved until they are clear of loose material.
Managerial/Supervisory:
Platforms require regular maintenance, which must be arranged at appropriate intervals.
Managers are responsible for ensuring that only trained and authorised personnel use the platforms.
Training:
All operatives must be trained in the safe use of these platforms as detailed in HS(G)19.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
Planning:
Mercury is an inherent component in instruments used.
Exposure to mercury occurs only in the event of breakage or spillage.
Physical:
Metallic mercury is a liquid which evaporates at room temperature - its tendency to disperse into infinite
numbers of tiny globules vastly increases the surface area.
In unventilated spaces concentrations of mercury vapour can rapidly exceed acceptable levels.
Ventilate the area and collect mercury by use of vacuum cleaner vented to atmosphere.
Managerial/Supervisory:
All instruments are checked by the Instrument Manager before issue.
All damaged instruments must be returned to Head Office for repair/replacement.
Training:
Personnel are instructed in the use of instrumentation.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
1 Electrocution X
2 Electrical burns X
3 Fire X
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
Management of Health and Safety at Work Regulations 1999
Electricity at Work Regulations 1989 (EAW)
BS 7671:2001 (latest edition)
IEE Wiring Regulations, 16th edition and guidance
HSE Booklets: HS(R)25 - Memorandum of guidance, EAW Regulations
HS(G)85 - EAW - safe working practices
HSE Guidance Notes: GS38 - Test equipment for use by electricians
GS27 - Protection against electric shock
GS47 - Safety of electrical distribution systems
Planning:
BS 6423:1983 - Code of practice for maintenance of switchgear & control gear up to 650 volts
Work is to be covered by a permit to work system where necessary.
Planning will include liaison with other contractors and those in control of the workplace to ensure that
all are aware of the work to be done.
Only competent persons with suitable test equipment, correctly calibrated, will be involved in the work.
Physical:
Prior to the commencement of work a check will be made to verify that all switchrooms/control rooms
have been cleared of loose materials and that all temporary installations have been removed.
Equipment covers and doors are to be closed and guards refitted to machinery.
Any circuits to be worked on will be treated as live until verified dead. There are no
exceptions to this requirement; experience of employees is irrelevant.
ASSUMPTIONS KILL.
Managerial/Supervisory:
An authorised competent person is to ensure that all precautions and conditions of the permit to work
have been met before signing the clearance to work
Training:
Only authorised and competent electricians having been provided with all the information relevant to the
work will carry out testing and commissioning.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date Signature Name
CML International (Dubai)
1 Falls of persons X
2 Falls of materials X
3 Mobile & Static Plant X
4 Use of Machinery X
5 Electrical Plant & Equipment X
6
Actions already taken to reduce the risks
Persons Name
Persons D.o.B.
Job Description Trainee Commissioning Engineer
Compliance with:
The Health And Safety (Young Persons) Regulations 1997
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
The Work at Height Regulations 2005
Management of Health & Safety at Work Regulations 1999
All other relevant legislation and regulations covered by CML Risk Assessments and Method
Statements
Planning:
Assess risks to all young people between 16 and 18 years of age, before they start work.
Ensure the risk assessment takes into account their possible psychological or physical immaturity,
inexperience, and lack of awareness of existing or potential risks.
Introduce control measures to eliminate or minimise the risks, so far as is reasonably practicable.
Ensure the young persons parents/guardians are aware of the risk assessment and provide written
acceptance for the young person to take up employment.
Physical:
N/A
Managerial/Supervisory:
The young persons work will be monitored to ensure that additional precautions are provided if
necessary.
This Risk Assessment shall be regularly monitored and revised to suit any change in site conditions,
work requirements of the young person and training/experience gained by the young person.
Training:
All young persons will be fully trained in construction site health and safety procedures and
requirements by a competent, experienced and qualified supervisor prior to starting work.
Training shall be provided to the young person to enable them to become competent in the tasks which
they will be expected to perform
This generic assessment must be completed by the File Ref:
addition of specific site details on the following pages GRA. 10 (03.8)
SITE-SPECIFIC ASSESSMENT
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date: Signature: Name:
CML International (Dubai)
1 Dehydration X
2 Prickly Heat X
3 Fainting, Heat Cramp & Heat Exhaustion X
4 Heat Stroke X
5 Skin Cancer X
6 Eye Damage X
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
Management of Health & Safety at Work Regulations 1999
All other relevant legislation and regulations covered by CML Risk Assessments and Method
Statements
Planning:
Assess sun/heat exposure risks to all personnel before they start work.
Ensure the risk assessment takes into account their physical condition, health, permanent medication,
age, experience of working in a hot climate.
Introduce control measures to eliminate or minimise the risks, so far as is reasonably practicable.
Arrange work such that the most physically demanding tasks are carried out early in the morning or late
afternoon.
Arrange work such that outside tasks are not carried out during peak sunshine periods (12:00pm to
4:00pm). On most UAE sites all work ceases between 12:00pm to 3:00pm during July & August.
Ensure that all works in confined spaces are not carried out during extreme hot periods. Plan these
works to be carried out at night when it is cool. If not, ensure that suitable mechanical ventilation is
provided to cool down the work space.
Rotate physical work tasks to minimise prolonged periods of intense physical work.
Ensure that Rest Areas are shaded, ventilated and preferably cooled.
Ensure First Aiders are trained to deal with heat related illness.
Physical:
Where possible provide temporary shading in areas of long term activity, e.g. more than one hour in the
same location.
Managerial/Supervisory:
This Risk Assessment shall be regularly monitored and revised to suit any change in site conditions or
work requirements.
Training:
There are no specific training requirements. However all personnel must be regularly advised against the
effects of over exposure to extreme heat and UV. Ensure awareness of sun protection measures and
identification of early signs of skin cancer. Emphasise the need for self examination and early medical
treatment.
This generic assessment must be completed by the File Ref:
addition of specific site details on the following pages GRA. 11 (06.8)
SITE-SPECIFIC ASSESSMENT
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date: Signature: Name:
CML International (Dubai)
1 Fall of Persons X
2
3
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
Management of Health & Safety at Work Regulations 1999
All other relevant legislation and regulations covered by CML Risk Assessments and Method
Statements
Planning:
Work is planned to ensure a safe means of access is provided.
Introduce control measures to eliminate or minimise the risks, so far as is reasonably practicable.
Use controlled safe routes at all times.
Physical:
Suitable signs and barriers to be provided on designated safe routes.
Where small changes in level cannot be avoided provide ramps.
Ensure sufficient waste bins are provided to prevent waste being discarded and causing trip hazards.
Ensure all work areas are suitably lit.
Provide safety footwear with good grips on the soles.
Use cordless tools to minimise trailing cables.
Ensure all site temporary electrical and lighting cables are run at high level.
Managerial/Supervisory:
This Risk Assessment shall be regularly monitored and revised to suit any change in site conditions or
work requirements.
Training:
There are no specific training requirements. However all personnel must be regularly advised regarding
the risks associated with slip and trip hazards on construction sites.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date: Signature: Name:
CML International (Dubai)
1 Pedestrian Accident X
2 Vehicle Accident X
3 Mobile Plant Accident X
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
Management of Health & Safety at Work Regulations 1999
All other relevant legislation and regulations covered by CML Risk Assessments and Method
Statements
Planning:
Control of traffic and pedestrians will be planned.
Introduce control measures to eliminate or minimise the risks, so far as is reasonably practicable.
Use controlled safe routes at all times.
Physical:
Suitable signs and barriers to be provided on designated safe routes.
Where small changes in level cannot be avoided provide ramps.
Ensure sufficient waste bins are provided to prevent waste being discarded and causing trip hazards.
Ensure all work areas are suitably lit.
Provide safety footwear with good grips on the soles.
Use cordless tools to minimise trailing cables.
Ensure all site temporary electrical and lighting cables are run at high level.
Managerial/Supervisory:
This Risk Assessment shall be regularly monitored and revised to suit any change in site conditions or
work requirements.
Training:
There are no specific training requirements. However all personnel must be regularly advised regarding
the risks associated with slip and trip hazards on construction sites.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date: Signature: Name:
CML International (Dubai)
1 Hearing Loss X
2 ‘Vibration White Finger’ X
3
4
5
6
Actions already taken to reduce the risks
Compliance with:
Provision and Use of Work Equipment Regulations 1998
Construction (Working Places) Regulations
Construction (Design & Management) Regulations 2007
Management of Health & Safety at Work Regulations 1999
Control of Noise at Work Regulations 2005
Control of Vibration at Work Regulations 2005
Planning:
All otherofrelevant
Control legislation
noise will and regulations covered by CML Risk Assessments and Method
be planned.
Statements
Introduce control measures to eliminate or minimise the risks, so far as is reasonably practicable.
Physical:
Where eradication of noise is impractical, hearing protection shall be worn.
Managerial/Supervisory:
This Risk Assessment shall be regularly monitored and revised to suit any change in site conditions or
work requirements.
Training:
There are no specific training requirements. However all personnel must be regularly advised on the
correct use of hearing protection (Ear Defenders) and the ‘Noise Action Levels’.
Noise Action Levels
a) First action lower exposure level 80dB(A) - weekly or daily average
Hearing protection must be freely available to all those who request it.
b) Second action upper exposure level 85dB(A) - weekly or daily average
i) Try to reduce exposure by engineering control rather than hearing protection.
ii) Restrict entry to noise polluting areas through the use of clear recognisable signs
and marked zones.
iii) Provide hearing protection which must be worn in these areas if the noise cannot be
controlled by the above measures or whilst the measures are being carried out.
c) Peak Action level 87dB(A) - weekly or daily average
If all of the above measures do not reduce the noise to below the Peak Action Level then the
workers must be removed from the area of exposure until the noise levels have reduced.
On each site and each location, the generic assessment overleaf must be reviewed to
ensure that all significant hazards and their risks are identified and controlled. Completion
of this side will ensure that your assessment is both appropriate and complete.
On-site Assessment
Date: Signature: Name: