Master Specifications
Master Specifications
Release 1.0
[March] 2017
Released by:
Northwestern University
Facilities Management Operations
2020 Ridge Avenue, Suite 200
Evanston, IL 60208-4301
** End of List **
NORTHWESTERN UNIVERSITY
PROJECT NAME FOR:
JOB # ISSUED: 03/29/2017
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
B. [It is intended this project pursue a LEED [“SILVER"] ["Gold”] rating. LEED criteria will
be followed for the installation of building systems. This Contractor shall be responsible
for the following items to ensure the Facility achieves LEED certification:
1.3 DEFINITIONS
A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred
spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings,
unexcavated spaces, crawlspaces, and tunnels.
B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied
spaces and mechanical equipment rooms.
D. Concealed, Interior Installations: Concealed from view and protected from physical contact by
building occupants. Examples include above ceilings and chases.
E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions
and physical contact by building occupants but subject to outdoor ambient temperatures.
Examples include installations within unheated shelters.
A. The editions recognized by latest [City of Chicago Codes and Standards] [City of Evanston
Codes and Standards] of the following are hereby included in and made a part of Division 23:
1.5 SUBMITTALS
B. Welding certificates.
C. For any equipment/components used by the contractor during construction, submit preventative
maintenance records for same.
A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural
Welding Code--Steel."
B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure
Vessel Code: Section IX, "Welding and Brazing Qualifications."
1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."
2. Certify that each welder has passed AWS qualification tests for welding processes
involved and that certification is current.
D. Meet all in-force University, OSHA, state, and local safety requirements.
E. To meet the University goals of safety, reliability, serviceability, and efficient operation, all
contractors shall use the burn permit procedure Burn permits are issued b the Facilities
Management Operations Engineering Department. The respective trades that are performing
any hot work must pick up a Burn Permit prior to commencing any work. Prior to the Burn
Permit being picked up, the respective contractor will provide and indicate on the Burn Permit
the Northwestern University work order. All procedures indicated on the Burn Permit are to be
followed.
F. All work to meet in-force local plumbing code. In the case of discrepancies between the project
contract documents and the in-force local code, the most stringent shall govern.
I. Complete Project Closeout list, Pre-Occupancy checklist, and Project Turnover checklist prior to
project turnover to Owner.
A. Two weeks prior to shipment, the contractor shall submit three (3) bound copies (One copy for
archive, two for shop use. One to the actual shop location and one left on site.) of operating and
maintenance data on all equipment furnished (separated by individual unit) to include, but not
limited to, the following: Shop Drawings; Model, system/tag and serial numbers of all
equipment; Performance data/curves; Fan curves for fans with variable frequency drives shall
show fan performance at various percentages of frequency/speed from 100% to 0% in 10%
increments; Manufacturer's written instructions for the operation and maintenance of the
component equipment; Lubrication schedule indicating all equipment to be lubricated,
recommended lubrication interval, and type and quality of lubricant to be used; recommended
spare parts. And, submitter must obtain signed proof in writing that the University received this
information.
B. All of the above listed documents shall be provided in electronic format to each division in
addition to the Northwestern University archives.
C. All assets that are going to be added to the University system will be submitted via Excel
spreadsheet. A sample of the format with required information and format is located in Appendix
XX. This information will be provided electronically to the representative PM and University
Reliability Engineer.
FSI Data
Template'.xlsx
D. Two of the bound copies are to be distributed to the Evanston Engineer's Department. One
copy is to be located in the associated mechanical room and another to the shop. The
associated manuals will be stored on a project supplied book shelf. Prints are to be installed on
a vertical wall mounted print storage rack.
1. Two copies Single line, full size, piping and ventilation prints laminated and stored on the
respective print storage device. One copy is for the building and the other is for the shop
files.
2. Two copies of the piping print showing floor and branch isolation valves indicated by the
respective tag number.
3. Two copies of the ventilation print showing all smoke and fire dampers.
E. Provide verification with Northwestern University Engineering Department to make sure there is
record of them receiving Operation and Maintenance Manual.
A. For the Evanston campus, central steam is distributed at 150 (and/or at 90 psi, verify with NU
Evanston campus during design and specification and specify here properly!!) psig
(known as the "Campus Line"), and at 230 psig. These are distinct piping systems but they
both originate from the same high pressure header in the CUP. Steam is and needs to be
metered and reduced in pressure after entrance of each building as required. Condensate is
returned to the Central Utility plant via pumped or high pressure condensate return.
B. For the Chicago campus, central steam is distributed at 170 psig. Steam is and needs to be
metered and reduced in pressure after entrance of each building as required.
C. Both campus' utilize direct buried piping and piping run through tunnels.
A. Five years for new equipment and work, see Division 01.
B. Extended warranties for equipment/work utilized by contractor during construction, see Division
01.
A. Piping, duct, equipment, and associated accessories kept on-site should be stored off the
ground on skids, ends should be capped or sealed, and these items should be covered with
plastic to prevent fouling or contact with excessive moisture. Piping, duct, and equipment
should be cleaned of debris inside and out before installation and should be kept clean and
protected throughout construction.
B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.
A. All contractors are to fill out and submit University Notification of Work Forms, and coordinate
with the respective University Project Manager.
B. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of
construction, to allow for HVAC installations.
D. Coordinate requirements for access panels and doors for HVAC items requiring access that are
concealed behind finished surfaces. Access panels and doors are specified in Division 08
Section "Access Doors and Frames."
E. All shutdowns are to be requested with the respective University Project Manager. All
shutdowns must have a shutdown request filled out for the applicable trade and submitted to the
respective trades's shop calendar 48 hours in advance, they shall include Methods of
Procedure. Emergency situations will be addresses and a case by case basis.
PART 2 - PRODUCTS
A. All equipment and materials shall be furnished in strict accordance with the equipment named
and according to Specification requirements. Each bid shall be based upon one of the materials
or manufacturers specified.
B. Equipment and materials specified shall be considered to have prior approval, but submittal for
approval is required. Furnish construction drawings to other Contractors when required to
coordinate construction.
C. Where multiple manufacturers are named the drawings and specifications are based on the
requirements and layouts for the equipment of the first named manufacturer. Any change
required by the use of other named manufacturers such as revisions to foundations, bases,
piping, controls, wiring, openings, and appurtenances shall be made by the Contractor at no
additional cost to the Owner. Changes must be submitted to the University for approval.
2.2 GROUT
A. Description: ASTM C 1107, Grade B, non-shrink and nonmetallic, dry hydraulic-cement grout.
3.1 DEMOLITION
A. Refer to Division 01 Section covering cutting and patching" and Division 02 Section covering
demolition for general demolition requirements and procedures.
B. Disconnect, demolish, and remove HVAC systems, equipment, and components indicated to be
removed.
B. All materials and equipment provided under this contract shall be new (except where otherwise
noted) and shall be listed, labeled or certified by Underwriters Laboratories, Inc., or other
acceptable entity.
C. All materials, products, and equipment being installed which fall into a category covered by the
®
ENERGY STAR program must be labeled as such.
E. Where any device or part of equipment is referred to in these specifications in the singular
number (e.g., "the diffuser"), this reference shall be deemed to apply to as many such devices
as are required to complete the installation as shown on the drawings.
F. During construction the contractor shall at all times maintain HVAC utilities of the building
without interruption. Should it be necessary to interrupt any HVAC service or utility, the
contractor shall secure permission in writing from the University for such interruption at least
seven days in advance. Any interruption shall be made with minimum amount of inconvenience
to the University and any shut-down time shall have to be on a premium time basis and such
time to be included in the contractor's bid. Arrange to provide and pay for temporary HVAC if
required by project conditions.
G. Measure indicated mounting heights to bottom of units/work for suspended items and to center
of items of work for wall-mounted items.
H. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange
and install components and equipment to provide maximum possible headroom consistent with
these requirements.
I. Working clearance around equipment shall not be less than that specified by the in-force codes,
standards, and the equipment manufacturer's instructions.
J. The locations of sensors, grilles, registers, diffusers, equipment, piping, ductwork, etc. shown
are approximate. The contractor shall use good judgment in placing the preceding items to
eliminate all interference with lights, cabinetry, sprinklers, etc. The contractor shall check all
furniture plans so that wall mounted sensors, panels, etc., are not located behind same.
Relocate same as required, with approval from the Architect and Engineer. The University may
direct relocation of sensors before installation, up to five (5) feet from the position indicated on
the Drawings, without additional cost.
1. Where the University determines that the Contractor has installed equipment not
conveniently accessible for operations and maintenance, the equipment shall be
removed and reinstalled as directed at no additional cost to the University.
2. “Conveniently Accessible” is defined as being capable of being
reached/serviced/maintained without climbing or crawling over or under obstacles such
as ductwork, large conduits or banks of conduits, large piping or banks of piping, or
similar.
L. Coordinate work with all other trades. This is to include coordinating to eliminate interference to
allow proper access to equipment doors, access to valves, and to not interrupt equipment or
devices proper operation.
M. Firestopping shall be applied to HVAC penetrations of fire-rated floor and wall assemblies to
restore/create the required fire-resistance rating of the assembly according to appropriate
Division 07 and 09 Sections and the University Fire Protection Group. All floor or wall
penetrations will be sleeved with the same or compatible material and appropriately firestopped.
N. Owner Furnished Equipment: Equipment furnished by the University shall be received, stored,
protected, uncrated, moved into position, and installed by the Contractor with all appurtenances
required to place the equipment in operation, ready for use. The Contractor shall be responsible
for the equipment as if he had purchased the equipment himself/herself.
3.3 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS
A. Install equipment to allow maximum possible headroom unless specific mounting heights are
not indicated.
B. Install equipment level and plumb, parallel and perpendicular to other building systems and
components in exposed interior spaces, unless otherwise indicated.
E. Minimum service access size for HVAC equipment/components above ceilings shall be 24"
cubed.
F. Install equipment to allow right of way for piping installed at required slope.
G. Install equipment to allow for proper access to all ancillary devices that are part of the
equipment. This includes valves, circuit setters, building automation system controllers.
1. If valves are not readily accessible for proper isolation, adequate pipe spacing needs to
be allowed with consideration given to insulation that will be installed.
2. Valves that are located in areas where access is difficult will be installed at the three or
nine o'clock position to allow for service. If this any question about the serviceability, the
owner’s appropriate representative will be consulted for review.
1. Construct concrete bases of dimensions indicated, but not less than 4 inches larger in
both directions than supported unit. Install dowel rods to connect concrete base to
concrete floor.
2. Unless otherwise indicated, install dowel rods on 18-inch centers around the full
perimeter of the base.
3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete
base, and anchor into structural concrete floor.
4. Place and secure anchorage devices. Use supported equipment manufacturer's setting
drawings, templates, diagrams, instructions, and directions furnished with items to be
embedded.
5. Install anchor bolts to elevations required for proper attachment to supported equipment.
6. Install anchor bolts according to anchor-bolt manufacturer's written instructions.
7. Use 3000-psi, 28-day compressive-strength concrete and reinforcement as specified in
Division 03 Section “Cast-in-Place Concrete” unless otherwise noted on the drawings.
A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support, and anchor
HVAC materials and equipment.
B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or
will receive finish materials. Tighten connections between members. Install fasteners without
splitting wood members.
D. All wood used to be fire retardant/treated wood, to be approved by the Architect, and is to be
used minimally.
3.7 GROUTING
A. Mix and install grout for HVAC equipment base bearing surfaces, pump and other equipment
base plates, and anchors.
F. Place grout on concrete bases and provide smooth bearing surface for equipment.
PART 1 - GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 COORDINATION
A. Coordinate features of motors, installed units, and accessory devices to be compatible with the
following:
A. Comply with FM Global requirements for motors and VFD's and for monitoring and diagnosis of
vibration in rotating machinery.
PART 2 - PRODUCTS
2.1 MANUFACTURERS/MODELS
MOTORS 23 0513 - 1
2. Reliance Type XE.
3. US Electric Motors Type UTE or CE.
4. General Electric Type E4.
5. Marathon Electric XRI Blue Chip.
A. Comply with requirements in this Section except when stricter requirements are specified in
HVAC equipment schedules or Sections.
C. Motor efficiencies shall at a minimum comply with the most recent editions of the International
Energy Conservation Code and ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise
Residential Buildings.
D. Motors shall be selected such that the brake horsepower (bhp), including drive losses of the
driven equipment, does not exceed 90% of the motor nameplate at design conditions.
A. Duty: Continuous duty at ambient temperature of 40 deg C and at altitude of 3300 feet above
sea level.
B. Capacity and Torque Characteristics: Sufficient to start, accelerate, and operate connected
loads at designated speeds, at installed altitude and environment, with indicated operating
sequence, and without exceeding nameplate ratings or considering service factor.
1. For motors with 2:1 speed ratio, consequent pole, single winding.
2. For motors with other than 2:1 speed ratio, separate winding for each speed.
E. Bearings: Regreasable, shielded, antifriction ball bearings suitable for radial and thrust loading.
G. Insulation: Class F.
I. Enclosure Material: Cast iron for motor frame sizes 324T and larger; rolled steel for motor
frame sizes smaller than 324T.
A. Motors Used with Reduced-Voltage and Multispeed Controllers: Match wiring connection
requirements for controller with required motor leads. Provide terminals in motor terminal box,
suited to control method.
B. Motors Used with Variable Frequency Controllers: (Ratings, characteristics, and features
coordinated with and approved by controller manufacturer.)
1. Windings: Copper magnet wire with moisture-resistant insulation varnish, designed and
tested to resist transient spikes, high frequencies, and short time rise pulses produced by
pulse-width modulated inverters.
2. Energy- and Premium-Efficient Motors: Class B temperature rise; Class F insulation.
3. Inverter-Duty Motors: Class F temperature rise; Class H insulation.
4. Thermal Protection: Comply with NEMA MG 1 requirements for thermally protected
motors.
5. Motors driven by a VFD shall not operate in their service factor.
6. Motors driven by a VFD shall be provided with shaft grounding brushes/rings similar to
AEGIS SGR's to prevent bearings from shaft currents.
7. See 2.7-F herein also.
A. Motors larger than 1/20 hp shall be one of the following, to suit starting torque and requirements
of specific motor application:
1. Permanent-split capacitor.
2. Split phase.
3. Capacitor start, inductor run.
4. Capacitor start, capacitor run.
C. Bearings: Pre-lubricated, antifriction ball bearings or sleeve bearings suitable for radial and
thrust loading.
E. Thermal Protection: Internal protection to automatically open power supply circuit to motor
when winding temperature exceeds a safe value calibrated to temperature rating of motor
insulation. Thermal-protection device shall automatically reset when motor temperature returns
to normal range.
A. Motors within air handling unit air streams shall be totally enclosed fan cooled (TEFC).
B. HVAC motors outdoors, not in an airstream, shall be totally enclosed fan cooled (TEFC) and
shall have epoxy sealed windings using vacuum and pressure with rotor and stator surfaces
protected with epoxy enamel. Bearings shall be double shielded with waterproof non-washing
grease.
C. HVAC motors indoors, and not in an airstream, shall be open drip proof (ODP).
D. All motors over 5 hp shall have rigging fixtures for easy removal and installation.
E. All "critical" motors shall have vibration analysis monitoring tied into the BAS system.
Coordinate with the University during bidding and construction.
1. Critical is defined as any location that is serving a research location or a process that is
essential to "day to day" operations of the University.
F. Additional Requirements for Three Phase Motors Used with Variable Frequency Drives:
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes separately enclosed, pre-assembled, combination VFDs, rated 600 V and less,
for speed control of three-phase, squirrel-cage induction motors.
B. Harmonic analysis.
1.3 DEFINITIONS
A. AO - Analog Output.
C. BI - Binary Input.
D. BO - Binary Output.
A. Product Data: For each type and rating of VFD indicated. Include features, options,
performance, electrical ratings, operating characteristics, shipping and operating weights, and
furnished specialties and accessories.
A. Shop Drawings: For each VFD indicated. Include dimensioned plans, elevations, and sections;
and conduit entry locations and sizes, mounting arrangements, and details, including required
clearances and service space around equipment.
1. Show tabulations of installed devices, equipment features, and ratings. Include the
following:
2. Schematic and Connection Wiring Diagrams: For power, signal, and control wiring.
B. Coordination Drawings: Floor plans, drawn to scale, showing dimensioned layout, required
working clearances, and required area above and around VFDs. Show VFD layout and
relationships between electrical components and adjacent structural and mechanical elements.
Show support locations, type of support, and weight on each support. Indicate field
measurements.
C. Qualification Data: For qualified testing agency.
H. Load-Current and Overload-Relay Heater List: Compile after motors have been installed, and
arrange to demonstrate that selection of heaters suits actual motor nameplate, full-load
currents.
I. Load-Current and List of Settings of Adjustable Overload Relays: Compile after motors have
been installed and arrange to demonstrate that switch settings for motor-running overload
protection suit actual motors to be protected.
A. Operation and Maintenance Data: For VFDs to include in emergency, operation, and
maintenance manuals. In addition to items specified in Section 01 7000 "Execution and
Closeout Requirements," include the following:
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Power Fuses: Equal to 10 percent of quantity installed for each size and type, but no
fewer than three of each size and type.
2. Control Power Fuses: Equal to 10 percent of quantity installed for each size and type,
but no fewer than two of each size and type.
3. Indicating Lights: Two of each type and color installed.
4. Auxiliary Contacts: Furnish one spare(s) for each size and type of magnetic controller
installed.
5. Power Contacts: Furnish three spares for each size and type of magnetic contactor
installed.
1.8 QUALITY ASSURANCE
A. Factory Testing: Each drive, and all features of same, shall be factory tested under motor or
other similar torque load that simulates the project duty.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
a. UL508
b. UL508A
c. UL508C
G. Harmonic Analysis: The VFD manufacturer shall perform a harmonic analysis at no cost to the
University. The maximum allowable Total Harmonic Distortion (THD) imparted to the facility
electrical system shall be 5% for current and voltage per IEEE-519. The University "may" be
able to provide certain assistance/information for this analysis, but verify during bidding. The
project provided VFD's shall be outfitted to limit the THD to the final, coordinated, harmonic
analysis results.
H. IEEE Analysis: The VFD supplier shall, with the aid of the Owner's detailed electrical power
single line diagram showing all impedances in the power path to the VFD's, perform an analysis
to initially demonstrate that the supplied drives will meet the IEEE recommendations after
installation. If, as a result of the analysis, it is determined that additional filtering, isolation, or
reactor equipment is required to meet IEEE recommendations, then the cost of such equipment
shall be included in the drive supplier's quotation.
I. Qualifications:
1. VFDs and options shall be UL508 listed as a complete assembly. The base VFD shall be
UL listed for 100 kA SCCR without the need for input fuses. Base VFDs with red label UL
stickers requiring additional branch circuit protection are not acceptable.
2. CE Mark – The base VFD shall conform to the European Union Electromagnetic
Compatibility directive, a requirement for CE marking. The VFD shall meet product
standard EN 61800-3 for the First Environment restricted level (Category C2). Base
drives that only meet the Second Environment (Category C3, C4) shall be supplied with
external filters to bring the drive in compliance with the First Environment levels.
A. Environmental Limitations: Rate equipment for continuous operation, capable of driving full load
without derating, under the following conditions unless otherwise indicated:
1. Ambient Temperature: Not less than 14 deg F (minus 10 deg C) and not exceeding 104
deg F (40 deg C).
2. Ambient Storage Temperature: Not less than minus 4 deg F (minus 20 deg C) and not
exceeding 140 deg F (60 deg C)
3. Humidity: Less than 95 percent (noncondensing).
4. Altitude: Not exceeding 3300 feet (1005 m).
1. Notify the University no fewer than seven days in advance of proposed interruption of
electrical systems.
2. Indicate method of providing temporary electrical service.
3. Do not proceed with interruption of electrical systems without the University's written
permission.
4. Comply with NFPA 70E.
C. Product Selection for Restricted Space: Drawings indicate maximum dimensions for VFDs,
including clearances between VFDs, and adjacent surfaces and other items.
1.11 COORDINATION
A. Coordinate features of motors, load characteristics, installed units, and accessory devices to be
compatible with the following:
C. Coordinate sizes and locations of roof curbs, equipment supports, and roof penetrations with
actual equipment provided.
D. Verify during bidding, and again prior to construction, the required communication protocol
required for the drives and provide the required drive electronics for proper communication with
other devices/systems on the job.
1.12 WARRANTY
PART 2 - PRODUCTS
A. The VFD's to be purchased by local contractor from a local representative, factory authorized
for start-up and service.
B. The VFD package as specified herein shall be enclosed in a UL Listed Type enclosure,
exceeding NEMA enclosure design criteria (enclosures with only NEMA ratings are not
acceptable), completely assembled and tested by the manufacturer in an ISO 9001 facility.
Enclosure shall be determined by the environment where the VFD's are being installed.
C. The VFD's shall be minimum 12 pulse inverter types, providing full rated output from a line of
±10% of nominal voltage. The VFD shall continue to operate without faulting from a line of
+30% to -35% of nominal voltage.
1. VFDs shall be capable of continuous full load operation under the following
environmental operating conditions:
1. Three (3) programmable critical frequency lockout ranges to prevent the VFD from
operating the load continuously at an unstable speed. The lockout range must be fully
adjustable, from 0 to full speed.
2. Two (2) PID Set point controllers shall be standard in the drive, allowing pressure or flow
signals to be connected to the VFD, using the microprocessor in the VFD for the closed-
loop control. The VFD shall have 250 ma of 24 VDC auxiliary power and be capable of
loop powering a transmitter supplied by others. The PID set point shall be adjustable
from the VFD keypad, analog inputs, or over the communications bus. There shall be
two independent parameter sets for the PID controller and the capability to switch
between the parameter sets via a digital input, serial communications or from the keypad.
The independent parameter sets are typically used for night setback, switching between
summer and winter set points, etc.
3. There shall be an independent, second PID loop that can utilize the second analog input
and modulate one of the analog outputs to maintain the set point of an independent
process (i.e. valves, dampers, etc.). All set points, process variables, etc. to be
accessible from the serial communication network.
4. Two (2) programmable analog inputs shall accept current or voltage signals.
5. Two (2) programmable analog outputs (0-20ma or 4-20 ma). The outputs may be
programmed to output proportional to Frequency, Motor Speed, Output Voltage, Output
Current, Motor Torque, Motor Power (kW), DC Bus voltage, Active Reference, Active
Feedback, and other data. Drives that have only one (1) analog output must provide an
option card that provides additional analog outputs.
6. Six (6) programmable digital inputs for maximum flexibility in interfacing with external
devices. All digital inputs shall be programmable to initiate upon an application or
removal of 24VDC or 24VAC.
7. Three (3) programmable, digital Form-C relay outputs. The relay outputs shall include
programmable on and off delay times and adjustable hysteresis. The relays shall be
rated for maximum switching current 8 amps at 24 VDC and 0.4 A at 250 VAC; Maximum
voltage 300 VDC and 250 VAC; continuous current rating of 2 amps RMS. Outputs shall
be true Form-C type contacts; open collector outputs are not acceptable. Drives that
have only two (2) relay outputs must provide an option card that provides additional relay
outputs.
8. Run Permissive Circuit - There shall be a run permissive circuit for damper or valve
control. Regardless of the source of a run command (keypad, input contact closure, time-
clock control, or serial communications), the VFD shall provide a dry contact closure that
will signal the damper to open (VFD motor does not operate). When the damper is fully
open, a normally open dry contact (end-switch) shall close. The closed end-switch is
wired to a VFD digital input and allows VFD motor operation. Two separate safety
interlock inputs shall be provided. When either safety is opened, the motor shall be
commanded to coast to stop and the damper shall be commanded to close. The keypad
shall display “start enable 1 (or 2) missing”. The safety input status shall also be
transmitted over the serial communications bus.
9. The VFD control shall include a programmable time delay for VFD start and a keypad
indication that this time delay is active. A Form C relay output provides a contact closure
to signal the VAV boxes open. This will allow VAV boxes to be driven open before the
motor operates. The time delay shall be field programmable from 0 – 120 seconds. Start
delay shall be active regardless of the start command source (keypad command, input
contact closure, time-clock control, or serial communications), and when switching from
drive to bypass.
10. Seven (7) programmable preset speeds.
11. Two independently adjustable accel and decel ramps with 1 – 1800 seconds adjustable
time ramps.
12. The VFD shall include a motor flux optimization circuit that will automatically reduce
applied motor voltage to the motor to optimize energy consumption and reduce audible
motor noise. The VFD shall have selectable software for optimization of motor noise,
energy consumption, and motor speed control.
13. The VFD shall include a carrier frequency control circuit that reduces the carrier
frequency based on actual VFD temperature that allows higher carrier frequency settings
without derating the VFD.
14. The VFD shall include password protection against parameter changes.
F. The Keypad shall include a backlit LCD display. The display shall be in complete English words
for programming and fault diagnostics (alpha-numeric codes are not acceptable). All VFD faults
shall be displayed in English words. The keypad shall include a minimum of 14 assistants
including:
1. Start-up assistant
2. Parameter assistants
a. PID assistant
b. Reference assistant
c. I/O assistant
d. Serial communications assistant
e. Option module assistant
f. Panel display assistant
g. Low noise set-up assistant
3. Maintenance assistant
4. Troubleshooting assistant
5. Drive optimizer assistants
G. All applicable operating values shall be capable of being displayed in engineering (user) units.
A minimum of three operating values from the list below shall be capable of being displayed at
all times. The display shall be in complete English words (alpha-numeric codes are not
acceptable):
1. Output Frequency
2. Motor Speed (RPM, %, or Engineering units)
3. Motor Current
4. Motor Torque
5. Motor Power (kW)
6. DC Bus Voltage
7. Output Voltage
H. The VFD shall include a fireman’s override input. Upon receipt of a contact closure from the fire
/ smoke control station, the VFD shall operate in one of two modes: 1) Operate at a
programmed predetermined fixed speed ranging from -500Hz (reverse) to 500Hz (forward). 2)
Operate in a specific fireman’s override PID algorithm that automatically adjusts motor speed
based on override set point and feedback. The mode shall override all other inputs
(analog/digital, serial communication, and all keypad commands), except customer defined
safety run interlocks, and force the motor to run in one of the two modes above. “FIREMODE”
shall be displayed on the keypad. Upon removal of the override signal, the VFD shall resume
normal operation, without the need to cycle the normal digital input run command.
I. Serial Communications
1. The VFD shall have an EIA-485 port as standard. The standard protocols shall be
Modbus, Johnson Controls N2, Siemens Building Technologies FLN, and BACnet.
Optional protocols for LonWorks, Profibus, EtherNet, BACnet IP, and DeviceNet shall be
available, and be provided as required for the project. Each individual drive shall have
the protocol in the base VFD. The use of third party gateways and multiplexers is not
acceptable. All protocols shall be “certified” by the governing authority (i.e. BTL Listing
for BACnet). Use of non-certified protocols is not allowed.
2. The BACnet connection shall be an EIA-485, MS/TP interface operating at 9.6, 19.2,
38.4, or 76.8 Kbps. The connection shall be tested by the BACnet Testing Labs (BTL)
and be BTL Listed. The BACnet interface shall conform to the BACnet standard device
type of an Applications Specific Controller (B-ASC). The interface shall support all BIBBs
defined by the BACnet standard profile for a B-ASC including, but not limited to:
3. If additional hardware is required to obtain the BACnet interface, the VFD manufacturer
shall supply one BACnet gateway per drive. Multiple VFDs sharing one gateway shall
not be acceptable.
4. Serial communication capabilities shall include, but not be limited to; run-stop controls,
speed set adjustment, and lock and unlock the keypad. The drive shall have the
capability of allowing the BAS to monitor feedback such as process variable feedback,
output speed / frequency, current (in amps), % torque, power (kW), kilowatt hours
(resettable), operating hours (resettable), and drive temperature. The BAS shall also be
capable of monitoring the VFD relay output status, digital input status, and all analog
input and analog output values. All diagnostic warning and fault information shall be
transmitted over the serial communications bus. Remote VFD fault reset shall be
possible.
5. Serial communication in bypass (if bypass is specified) shall include, but not be limited to;
bypass run-stop control, the ability to force the unit to bypass, and the ability to lock and
unlock the keypad. The bypass shall have the capability of allowing the BAS to monitor
feedback such as, current (in amps), kilowatt hours (resettable), operating hours
(resettable), and bypass logic board temperature. The BAS shall also be capable of
monitoring the bypass relay output status, and all digital input status. All bypass
diagnostic warning and fault information shall be transmitted over the serial
communications bus. Remote bypass fault reset shall be possible.
6. The VFD / bypass shall allow the BAS to control the drive and bypass digital and analog
outputs via the serial interface. This control shall be independent of any VFD function.
The analog outputs may be used for modulating chilled water valves or cooling tower
bypass valves, if applicable. The drive and bypass’ digital (Form-C relay) outputs may be
used to actuate a damper, open a valve or control any other device that requires a
maintained contact for operation. In addition, all of the drive and bypass’ digital inputs
shall be capable of being monitored by the BAS system. This allows for remote
monitoring of which (of up to 4) safeties are open.
7. The VFD shall include an independent PID loop for customer use. The independent PID
loop may be used for cooling tower bypass value control, chilled water value / hot water
valve control, etc. Both the VFD PID control loop and the independent PID control loop
shall continue functioning even if the serial communications connection is lost. As
default, the VFD shall keep the last good set point command and last good DO & AO
commands in memory in the event the serial communications connection is lost and
continue controlling the process.
J. EMI / RFI filters. All VFD’s shall include EMI/RFI filters. The onboard filters shall allow the VFD
assembly to be CE Marked and the VFD shall meet product standard EN 61800-3 for the First
Environment restricted level (Category C2) with up to 100 feet of motor cable. Second
environment (Category C3, C4) is not acceptable, no Exceptions. Certified test reports shall be
provided with the submittals confirming compliance to EN 61800-3, First Environment (C2).
K. DRIVE OPTIONS – Options shall be furnished and mounted by the drive manufacturer as
defined by the VFD schedule. All optional features shall be UL Listed by the drive manufacturer
as a complete assembly and carry a UL508 label.
1. Fieldbus adapters – The following optional fieldbus adapters shall be available as a plug
in modules, and provided as required for the project.
a. LonWorks
b. DeviceNet
c. Ethernet IP
d. BACnet IP
e. Profibus
L. BYPASSES AND/OR REDUNDANT (Drives with primary and backup drives in same enclosure)
DRIVES
1. [Based on duty (critical, non-critical, supply, return, exhaust, or other air, pumps,
involved with smoke control or not, etc.), the design AE must select and fully
specify here, either no bypass required, mechanical ATL bypass, redundant drives,
or electronic (Smart) bypasses. Electronic bypasses are generally preferred by the
University but may not be the right choice for all applications. Coordinate with the
University and the Electrical Shop when final specifying.]
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, surfaces, and substrates to receive VFDs, with Installer present, for compliance
with requirements for installation tolerances, and other conditions affecting performance.
B. Examine VFD before installation. Reject VFDs that are wet, moisture damaged, or mold
damaged.
C. Examine roughing-in for conduit systems to verify actual locations of conduit connections before
VFD installation.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Coordinate layout and installation of VFDs with other construction including conduit, piping,
equipment, and adjacent surfaces. Maintain required workspace clearances and required
clearances for equipment access doors and panels.
B. Wall-Mounting Controllers: Install VFDs on walls with tops at uniform height and with
disconnect operating handles not higher than 79 inches above finished floor unless otherwise
indicated, and by mounting units on lightweight structural-steel channels bolted to wall. For
controllers not on walls, provide freestanding racks complying with Section 26 0529 "Hangers
and Supports for Electrical Systems."
C. Floor-Mounting Controllers: Install VFDs on 4-inch nominal thickness concrete base. Comply
with requirements for concrete base specified in
1. Install dowel rods to connect concrete base to concrete floor. Unless otherwise
indicated, install dowel rods on 18-inch centers around the full perimeter of concrete
base.
2. For supported equipment, install epoxy-coated anchor bolts that extend through concrete
base and anchor into structural concrete floor.
3. Place and secure anchorage devices. Use setting drawings, templates, diagrams,
instructions, and directions furnished with items to be embedded.
4. Install anchor bolts to elevations required for proper attachment to supported equipment.
D. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and
temporary blocking of moving parts from enclosures and components.
G. Install heaters in thermal-overload relays. Select heaters based on actual nameplate full-load
amperes after motors have been installed.
H. Install, connect, and fuse thermal-protector monitoring relays furnished with motor-driven
equipment.
3.3 IDENTIFICATION
A. Identify VFDs, components, and control wiring. Comply with requirements for identification
specified in Section 26 0553 "Identification for Electrical Systems."
B. Operating Instructions: Frame printed operating instructions for VFDs, including control
sequences and emergency procedures. Fabricate frame of finished metal, and cover
instructions with clear acrylic plastic. Mount on front of VFD units.
A. Install wiring between VFDs and remote devices and facility's central-control system. Comply
with requirements in Section 26 0523 "Control-Voltage Electrical Power Cables."
C. Connect selector switches and other automatic control devices where applicable.
1. Connect selector switches with control circuit in both manual and automatic positions for
safety-type control devices such as low- and high-pressure cutouts, high-temperature
cutouts, and motor overload protectors.
A. Testing Agency: The University will engage a qualified testing agency to perform tests and
inspections.
1. Test insulation resistance for each VFD element, bus, component, connecting supply,
feeder, and control circuit.
2. Test continuity of each circuit.
1. Inspect VFD, wiring, components, connections, and equipment installation. Test and
adjust controllers, components, and equipment.
2. Test insulation resistance for each VFD element, component, connecting motor supply,
feeder, and control circuits.
3. Test continuity of each circuit.
4. Verify that voltages at VFD locations are within 10 percent of motor nameplate rated
voltages. If outside this range for any motor, notify the University before starting the
motor(s).
5. Test each motor for proper phase rotation.
6. Perform each electrical test and visual and mechanical inspection stated in
NETA Acceptance Testing Specification. Certify compliance with test parameters.
7. Correct malfunctioning units on-site, where possible, and retest to demonstrate
compliance; otherwise, replace with new units and retest.
8. Perform the following infrared (thermographic) scan tests and inspections and prepare
reports:
a. Initial Infrared Scanning: After Substantial Completion, but not more than 60 days
after Final Acceptance, perform an infrared scan of each VFD. Remove front
panels so joints and connections are accessible to portable scanner.
b. Follow-up Infrared Scanning: Perform an additional follow-up infrared scan of
each VFD 11 months after date of Substantial Completion.
c. Instruments and Equipment: Use an infrared scanning device designed to
measure temperature or to detect significant deviations from normal values.
Provide calibration record for device.
9. Test and adjust controls, remote monitoring, and safeties. Replace damaged and
malfunctioning controls and equipment.
F. VFDs will be considered defective if they do not pass tests and inspections.
G. Prepare test and inspection reports, including a certified report that identifies the VFD and
describes scanning results. Include notation of deficiencies detected, remedial action taken,
and observations made after remedial action.
3.7 ADJUSTING
A. Program microprocessors for required operational sequences, status indications, alarms, event
recording, and display features. Clear events memory after final acceptance testing and prior to
Substantial Completion.
B. Set field-adjustable switches, auxiliary relays, time-delay relays, timers, and overload-relay
pickup and trip ranges.
C. Adjust the trip settings of MCPs and thermal-magnetic circuit breakers with adjustable,
instantaneous trip elements. Initially adjust to six times the motor nameplate full-load amperes
and attempt to start motors several times, allowing for motor cool-down between starts. If
tripping occurs on motor inrush, adjust settings in increments until motors start without tripping.
Do not exceed eight times the motor full-load amperes (or 11 times for NEMA Premium Efficient
motors if required). Where these maximum settings do not allow starting of a motor, notify the
University before increasing settings.
3.8 PROTECTION
B. Replace VFDs whose interiors have been exposed to water or other liquids prior to Substantial
Completion.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
A. Compatibility: Products shall be suitable for piping service fluids, materials, working pressures,
and temperatures.
B. Capability: Products to absorb 200 percent of maximum axial movement between anchors.
B. Delegated-Design Submittal: For each anchor and alignment guide indicated to comply with
performance requirements and design criteria, including analysis data signed and sealed by the
qualified professional engineer responsible for their preparation.
A. Welding certificates.
PART 2 - PRODUCTS
2. Standards: ASME Boiler and Pressure Vessel Code: Section II, "Materials"; and
ASME B31.9, "Building Services Piping," for materials and design of pressure-containing
parts and bolting.
3. Material: Carbon-steel assembly with asbestos-free composition packing.
4. Design: For 360-degree rotation and angular deflection.
5. Minimum Pressure Rating: 250 psig at 400 deg F (1725 kPa at 204 deg C).
6. Angular Deflection for NPS 6 (DN 150) and Smaller: 30 degree minimum.
7. Angular Deflection for NPS 8 (DN 200) and Larger: 15 degree minimum.
8. End Connections for NPS 2 (DN 50) and Smaller: Threaded.
9. End Connections for NPS 2-1/2 (DN 65) and Larger: Flanged.
D. Nipples: Galvanized, ASTM A 53/A 53M, Schedule 40, Type E or S, steel pipe with grooved
ends.
E. Couplings: Multiple (as required), flexible type for steel-pipe dimensions. Include ferrous
housing sections, with EPDM gasket suitable for project fluids, and bolts and nuts.
1. Metraflex, Inc.
2. Flexhose
3. Flexicraft
B. Description: Manufactured assembly with inlet and outlet elbow fittings and two flexible-metal-
hose legs joined by long-radius, 180-degree return bend or center section of flexible hose.
D. Expansion Joints for Copper Tubing NPS 2 (DN 50) and Smaller: Copper-alloy fittings with
solder-joint end connections.
1. Bronze hoses and double-braid bronze sheaths with 700 psig at 70 deg F (4830 kPa at
21 deg C) and 500 psig at 450 deg F (3450 kPa at 232 deg C) ratings.
E. Expansion Joints for Copper Tubing NPS 2-1/2 to NPS 4 (DN 65 to DN 100): Copper-alloy
fittings with threaded end connections.
1. Stainless-steel hoses and double-braid, stainless-steel sheaths with 420 psig at 70 deg F
(2890 kPa at 21 deg C) and 315 psig at 450 deg F (2170 kPa at 232 deg C) ratings.
F. Expansion Joints for Steel Piping NPS 2 (DN 50) and Smaller: Carbon-steel fittings with
threaded end connections.
1. Stainless-steel hoses and double-braid, stainless-steel sheaths with 700 psig at 70 deg F
(4830 kPa at 21 deg C) and 515 psig at 600 deg F (3550 kPa at 315 deg C) ratings.
G. Expansion Joints for Steel Piping NPS 2-1/2 to NPS 6 (DN 65 to DN 150): Carbon-steel fittings
with flanged end connections.
1. Stainless-steel hoses and double-braid, stainless-steel sheaths with 275 psig at 70 deg F
(1900 kPa at 21 deg C) and 200 psig at 600 deg F (1380 kPa at 315 deg C) ratings.
H. Expansion Joints for Steel Piping NPS 8 to NPS 12 (DN 200 to DN 300): Carbon-steel fittings
with flanged end connections.
1. Stainless-steel hoses and double-braid, stainless-steel sheaths with 165 psig at 70 deg F
(1130 kPa at 21 deg C) and 120 psig at 600 deg F (830 kPa at 315 deg C) ratings.
I. Expansion Joints for Steel Piping NPS 14 (DN 350) and Larger: Carbon-steel fittings with
flanged end connections.
1. Stainless-steel hoses and double-braid, stainless-steel sheaths with 165 psig at 70 deg F
(1130 kPa at 21 deg C) and 120 psig at 600 deg F (830 kPa at 315 deg C) ratings.
A. Alignment Guides:
B. Anchor Materials:
a. Bonding Material: ASTM C 881/C 881M, Type IV, Grade 3, two-component epoxy
resin suitable for surface temperature of hardened concrete where fastener is to be
installed.
b. Stud: ASTM A 307, zinc-coated carbon steel with continuous thread on stud
unless otherwise indicated.
c. Washer and Nut: Zinc-coated steel.
PART 3 - EXECUTION
A. Install expansion joints of sizes matching sizes of piping in which they are installed.
B. Install packed-type expansion joints with packing suitable for fluid service.
C. Install metal-bellows expansion joints according to EJMA's "Standards of the Expansion Joint
Manufacturers Association, Inc."
A. Connect risers and branch connections to mains with at least five pipe fittings including tee in
main.
B. Connect risers and branch connections to terminal units with at least four pipe fittings including
tee in riser.
C. Connect mains and branch connections to terminal units with at least four pipe fittings including
tee in main.
A. Install alignment guides to guide expansion and to avoid end-loading and torsional stress.
B. Install two guide(s) on each side of pipe expansion fittings and loops. Install guides nearest to
expansion joint not more than four pipe diameters from expansion joint.
D. Install anchors at locations to prevent stresses from exceeding those permitted by ASME B31.9
and to prevent transfer of loading and stresses to connected equipment.
E. Anchor Attachments:
1. Anchor Attachment to Steel Pipe: Attach by welding. Comply with ASME B31.9 and
ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing
Qualifications."
2. Anchor Attachment to Copper Tubing: Attach with pipe hangers. Use MSS SP-69,
Type 24, U-bolts bolted to anchor.
F. Fabricate and install steel anchors by welding steel shapes, plates, and bars. Comply with
ASME B31.9 and AWS D1.1/D1.1M.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Sleeves.
2. Sleeve-seal systems.
3. Sleeve-seal fittings.
4. Grout.
PART 2 - PRODUCTS
2.1 SLEEVES
A. Cast-Iron Wall Pipes: Cast or fabricated of cast or ductile iron and equivalent to ductile-iron
pressure pipe, with plain ends and integral waterstop unless otherwise indicated.
B. Galvanized-Steel Wall Pipes: ASTM A 53/A 53M, Schedule 40, with plain ends and welded
steel collar; zinc coated.
C. Galvanized-Steel-Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc
coated, with plain ends.
E. Molded-PE or -PP Sleeves: Removable, tapered-cup shaped, and smooth outer surface with
nailing flange for attaching to wooden forms.
B. Description: Modular sealing-element unit, designed for field assembly, for filling annular space
between piping and sleeve.
1. Sealing Elements: EPDM-rubber or NBR interlocking links shaped to fit surface of pipe.
Include type and number required for pipe material and size of pipe.
2. Pressure Plates: Carbon steel or Stainless steel.
3. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, or Stainless
steel of length required to secure pressure plates to sealing elements.
1. Presealed Systems.
2.4 GROUT
PART 3 - EXECUTION
A. Install sleeves for piping passing through penetrations in floors, partitions, roofs, and walls.
B. For sleeves that will have sleeve-seal system installed, select sleeves of size large enough to
provide 1-inch (25-mm) annular clear space between piping and concrete slabs and walls.
C. Install sleeves in concrete floors, concrete roof slabs, and concrete walls as new slabs and
walls are constructed.
1. Permanent sleeves are not required for holes in slabs formed by molded-PE or -PP
sleeves.
2. Cut sleeves to length for mounting flush with both surfaces.
3. Using sealant, seal the space outside of sleeves in slabs and walls without sleeve-seal
system.
E. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at
pipe penetrations. Seal pipe penetrations with firestop materials. Comply with requirements for
firestopping specified in Section 078413 "Penetration Firestopping."
A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at service
piping entries into building.
B. Select type, size, and number of sealing elements required for piping material and size and for
sleeve ID or hole size. Position piping in center of sleeve. Center piping in penetration,
assemble sleeve-seal system components, and install in annular space between piping and
sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make
a watertight seal.
A. Install sleeve-seal fittings in new walls and slabs as they are constructed.
B. Assemble fitting components of length to be flush with both surfaces of concrete slabs and
walls. Position waterstop flange to be centered in concrete slab or wall.
A. Use sleeves and sleeve seals for the following piping-penetration applications:
a. Piping Smaller Than NPS 6 (DN 150): Cast-iron wall sleeves, Galvanized-steel-
pipe sleeves, or Sleeve-seal fittings.
b. Piping NPS 6 (DN 150) and Larger: Cast-iron wall sleeves or Galvanized-steel-
pipe sleeves.
a. Piping Smaller Than NPS 6 (DN 150): Cast-iron wall sleeves with sleeve-seal
system, galvanized-steel-pipe sleeves with sleeve-seal system, or sleeve-seal
fittings.
1) Select sleeve size to allow for 1-inch (25-mm) annular clear space between
piping and sleeve for installing sleeve-seal system.
b. Piping NPS 6 (DN 150) and Larger: Cast-iron wall sleeves with sleeve-seal
system or Galvanized-steel-pipe sleeves with sleeve-seal system.
1) Select sleeve size to allow for 1-inch (25-mm) annular clear space between
piping and sleeve for installing sleeve-seal system.
3. Concrete Slabs-on-Grade:
a. Piping Smaller Than NPS 6 (DN 150): Cast-iron wall sleeves with sleeve-seal
system, Galvanized-steel-pipe sleeves with sleeve-seal system, or Sleeve-seal
fittings.
1) Select sleeve size to allow for 1-inch (25-mm) annular clear space between
piping and sleeve for installing sleeve-seal system.
b. Piping NPS 6 (DN 150) and Larger: Cast-iron wall sleeves with sleeve-seal
system, Galvanized-steel-pipe sleeves with sleeve-seal system, or Galvanized-
steel-pipe sleeves.
1) Select sleeve size to allow for 1-inch (25-mm) annular clear space between
piping and sleeve for installing sleeve-seal system.
5. Interior Partitions:
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Escutcheons.
2. Floor plates.
PART 2 - PRODUCTS
2.1 ESCUTCHEONS
A. One-Piece, Cast-Brass Type: With polished, chrome-plated finish and setscrew fastener.
B. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with chrome-plated finish and
spring-clip fasteners.
D. Split-Casting Brass Type: With polished, chrome-plated finish and with concealed hinge and
setscrew.
E. Split-Plate, Stamped-Steel Type: With chrome-plated finish, concealed hinge, and spring-clip
fasteners.
3.1 INSTALLATION
A. Install escutcheons for piping penetrations of walls, ceilings, and finished floors.
B. Install escutcheons with ID to closely fit around pipe, tube, and insulation of piping and with OD
that completely covers opening.
a. Piping with Fitting or Sleeve Protruding from Wall: One-piece, deep-pattern type.
b. Chrome-Plated Piping: One-piece, cast-brass type with polished, chrome-plated
finish.
c. Insulated Piping: One-piece, stamped-steel type or split-plate, stamped-steel type
with concealed hinge.
d. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece, cast-
brass or split-casting brass type with polished, chrome-plated finish.
e. Bare Piping at Ceiling Penetrations in Finished Spaces: One-piece, cast-brass
type with polished, chrome-plated finish.
f. Bare Piping in Unfinished Service Spaces: One-piece, cast-brass or split-casting
brass type with polished, chrome-plated finish.
g. Bare Piping in Equipment Rooms: One-piece, cast-brass or split-casting brass
type with polished, chrome-plated finish.
D. Install floor plates with ID to closely fit around pipe, tube, and insulation of piping and with OD
that completely covers opening.
A. Replace broken and damaged escutcheons and floor plates using new materials.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Filled-system thermometers.
2. Thermowells.
3. Dial-type pressure gages.
4. Gage attachments.
5. Test plugs.
6. Test-plug kits.
7. Sight flow indicators.
8. Electromagnetic flowmeters.
B. Related Sections:
A. Product Certificates: For each type of meter and gage, from manufacturer.
A. Operation and Maintenance Data: For meters and gages to include in operation and
maintenance manuals.
a. Trerice, H. O. Co.
b. Weksler Instrument Corporation.
a. Trerice, H. O. Co.
b. Weksler Instrument Corporation.
A. Description: Flanged bracket with screw holes, for attachment to air duct and made to hold
thermometer stem.
2.3 THERMOWELLS
A. Thermowells:
A. Snubbers: ASME B40.100, brass; with NPS 1/4 (DN 8), ASME B1.20.1 pipe threads and piston
or porous-metal-type surge-dampening device. Include extension for use on insulated piping.
B. Siphons: Loop-shaped section steel pipe with NPS 1/4 (DN 8) pipe threads.
C. Valves: Brass ball, with NPS 1/4 (DN 8), ASME B1.20.1 pipe threads.
B. Description: Test-station fitting made for insertion into piping tee fitting.
C. Body: Stainless steel with core inserts and gasketed and threaded cap. Include extended stem
on units to be installed in insulated piping.
D. Thread Size: NPS 1/4 (DN 8) or NPS 1/2 (DN 15), ASME B1.20.1 pipe thread.
E. Minimum Pressure and Temperature Rating: 500 psig at 200 deg F (3450 kPa at 93 deg C).
1. Low-Range Thermometer: Small, bimetallic insertion type with 1- to 2-inch- (25- to 51-
mm-) diameter dial and tapered-end sensing element. Dial range shall be at least 25 to
125 deg F (minus 4 to plus 52 deg C).
2. High-Range Thermometer: Small, bimetallic insertion type with 1- to 2-inch- (25- to 51-
mm-) diameter dial and tapered-end sensing element. Dial range shall be at least 0 to
220 deg F (minus 18 to plus 104 deg C).
3. Pressure Gage: Small, Bourdon-tube insertion type with 2- to 3-inch- (51- to 76-mm-)
diameter dial and probe. Dial range shall be at least 0 to 200 psig (0 to 1380 kPa).
4. Carrying Case: Metal or plastic, with formed instrument padding.
C. Construction: Bronze or stainless-steel body, with sight glass and ball, flapper, or paddle wheel
indicator, and threaded or flanged ends.
G. End Connections for NPS 2-1/2 (DN 65) and Larger: Flanged.
2.9 FLOWMETERS
A. Electromagnetic Flowmeters:
a. Design: Electromagnetic type measurement for water, in-line or insertion type, and
bi-directional, as called for on drawings.
b. Body Construction: Primed and painted or coated carbon steel, or stainless steel.
Internal flow tube on in-line model to be stainless steel.
c. Maximum Operating Pressure Rating: 230 to 400 psig.
d. End Connections for In-Line Meters: Flanged.
e. Accuracy of In-Line Models: +/- 2% of reading from 1.6 to 33 ft/s.
f. Accuracy of Insertion Models: +/- 1% of reading from 2 to 20 ft/s.
g. Power Supply Requirements: 18-45 VAC for in-line type, 20-28 VAC for insertion
type.
h. Output Requirements: 4 - 20 mA analog output.
i. Insertion Type Insertion Design: "Simplified", with insertion and removal by hand
without a system shutdown.
5. Permanent Indicators: Meter suitable for wall or bracket mounting, calibrated for
connected flowmeter element, and having 6-inch- diameter, or equivalent, dial with
fittings and copper tubing for connecting to flowmeter element.
6. Display: Shows rate of flow, with register to indicate total volume in gallons (liters).
7. Conversion Chart: Flow rate data compatible with sensor.
8. Operating Instructions: Include complete instructions with each flowmeter.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install thermowells with socket to center of pipe and in vertical position in piping tees.
E. Install direct-mounted thermometers in thermowells and adjust vertical and tilted positions.
F. Install remote-mounted thermometer bulbs in thermowells and install cases on panels; connect
cases with tubing and support tubing to prevent kinks. Use minimum tubing length.
G. Install duct-thermometer mounting brackets in walls of ducts. Attach to duct with screws.
H. Pack thermometers in a thermal conductive compound. Preferred products are: Honeywell Part
No. 107408; Jonson Controls F-1000-182; York 013-00898-000.
I. Install direct-mounted pressure gages in piping tees with pressure gage located on pipe at the
most readable position.
K. Install valve and snubber in piping for each pressure gage for fluids (except steam).
L. Install valve and syphon fitting in piping for each pressure gage for steam.
N. Install flow indicators in piping systems in accessible positions for easy viewing.
O. Assemble and install connections, tubing, and accessories between flow-measuring elements
and flowmeters according to manufacturer's written instructions.
P. Install flowmeter elements in accessible positions in piping systems, and per manufacturer's
requirements.
U. Mount thermal-energy meters on wall if accessible; if not, provide brackets to support meters.
3.2 CONNECTIONS
A. Install meters and gages adjacent to machines and equipment to allow service and
maintenance of meters, gages, machines, and equipment.
B. Connect flowmeter-system elements to meters.
3.3 ADJUSTING
B. Adjust faces of meters and gages to proper angle for best visibility.
B. Scale Range for Heating and Glycol, Hot-Water Piping: 30 to 250 deg F or 30 to 300 deg F.
A. Scale Range for Hydronic Water Piping: As best suited for final project conditions.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes Valves and Valve Accessories for Hydronic Systems, Not Steam Systems:
B. Related Sections:
1. Section 230553 "Identification for HVAC Piping and Equipment" for valve tags and
schedules.
1.3 DEFINITIONS
A. Source Limitations for Valves: Obtain each type of valve from single source from single
manufacturer.
B. ASME Compliance:
1. ASME B16.10 and ASME B16.34 for ferrous valve dimensions and design criteria.
2. ASME B31.1 for power piping valves.
3. ASME B31.9 for building services piping valves.
C. Use sling to handle large valves; rig sling to avoid damage to exposed parts. Do not use
handwheels or stems as lifting or rigging points.
PART 2 - PRODUCTS
B. Valve Pressure and Temperature Ratings: Not less than indicated and as required for system
pressures and temperatures.
1. Gear Actuator: For quarter-turn valves NPS 8 (DN 200) and larger.
2. Handwheel: For valves other than quarter-turn types.
3. Handlever: For quarter-turn valves NPS 6 (DN 150) and smaller.
4. Chainwheel: Device for attachment to valve handwheel, stem, or other actuator; of size
and with chain for mounting height, as indicated in the "Valve Installation" Article.
E. Valves in Insulated Piping: With 2-inch stem extensions and the following features:
1. Ball Valves: With extended operating handle of non-thermal-conductive material, and
protective sleeve that allows operation of valve without breaking the vapor seal or
disturbing insulation.
2. Butterfly Valves: With extended neck.
F. Valve-End Connections:
2. Description:
a. Pratt Groundhoug
b. Approved equal
2. Description:
2. Description:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller.
2. Description:
A. Class 125, Bronze Horizontal Swing Check Valves with Bronze Disc:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller.
2. Description:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller
2. Description:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller
2. Description:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller
2. Description:
a. Nibco
b. Crane Co.; Crane Valve Group; Crane Valves.
c. Mueller
2. Description:
2.9 CHAINWHEELS
B. Description: Valve actuation assembly with sprocket rim, brackets, and chain.
1. Brackets: Type, number, size, and fasteners required to mount actuator on valve.
2. Attachment: For connection to valve stems.
3. Sprocket Rim with Chain Guides: Ductile iron, of type and size required for
valve. Include zinc coating.
4. Chain: Hot-dip, galvanized steel, of size required to fit sprocket rim.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove
special packing materials, such as blocks, used to prevent disc movement during shipping and
handling.
B. Operate valves in positions from fully open to fully closed. Examine guides and seats made
accessible by such operations.
C. Examine threads on valve and mating pipe for form and cleanliness.
D. Examine mating flange faces for conditions that might cause leakage. Check bolting for proper
size, length, and material. Verify that gasket is of proper size, that its material composition is
suitable for service, and that it is free from defects and damage.
A. Install valves with unions or flanges at each piece of equipment arranged to allow service,
maintenance, and equipment removal without system shutdown.
B. Locate valves for easy access and provide separate support where necessary.
E. Install chainwheels on operators for butterfly valves NPS 4 (DN 100) and larger and more than
96 inches above floor. Extend chains to 60 inches above finished floor.
3.3 ADJUSTING
A. Adjust or replace valve packing after piping systems have been tested and put into service but
before final adjusting and balancing. Replace valves if persistent leaking occurs.
3.4 GENERAL REQUIREMENTS FOR VALVE APPLICATIONS
1. Shutoff Service:
a. NPS 2 (DN 50) and Smaller: Bronze swing check valves with bronze disc.
b. NPS 2-1/2 (DN 65) and Larger: Iron swing check valves with lever and weight or
with spring or iron, center-guided, metal or resilient-seat check valves.
B. If valves with specified SWP classes or CWP ratings are not available, the same types of valves
with higher SWP classes or CWP ratings may be substituted.
C. Select valves, except wafer types, with the following end connections:
1. For Copper Tubing, NPS 2 (DN 50) and Smaller: Threaded ends except where solder-
joint valve-end option is indicated in valve schedules below.
2. For Copper Tubing, NPS 2-1/2 to NPS 4 (DN 65 to DN 100): Flanged ends except where
threaded valve-end option is indicated in valve schedules below.
3. For Copper Tubing, NPS 5 (DN 125) and Larger: Flanged ends.
4. For Steel Piping, NPS 2 (DN 50) and Smaller: Threaded ends.
5. For Steel Piping, NPS 2-1/2 to NPS 4 (DN 65 to DN 100): Flanged ends except where
threaded valve-end option is indicated in valve schedules below.
6. For Steel Piping, NPS 5 (DN 125) and Larger: Flanged ends.
7. For Grooved-End Copper Tubing and Steel Piping except Steam and Steam Condensate
Piping: Valve ends may be grooved.
1. Bronze Valves: May be provided with solder-joint ends instead of threaded ends.
2. Ball Valves: Two piece, full port, bronze with stainless-steel trim.
3. Bronze Swing Check Valves: Class 150, bronze disc.
1. Iron, Grooved-End Butterfly Valves, NPS 2-1/2 to NPS 12 (DN 65 to DN 300): 175
CWP.
2. High-Performance Butterfly Valves: Class 300, single flange.
3. Iron Swing Check Valves: Class 250, metal seats.
4. Iron, Grooved-End Check Valves, NPS 3 to NPS 12 (DN 80 to DN 300): 300 CWP.
3.6 HEATING-WATER VALVE SCHEDULE
1. Bronze Valves: May be provided with solder-joint ends instead of threaded ends.
2. Ball Valves: Two piece, full port, bronze with stainless-steel trim.
3. Bronze Swing Check Valves: Class 150, bronze disc.
1. Iron, Grooved-End Butterfly Valves, NPS 2-1/2 to NPS 12 (DN 65 to DN 300): 175
CWP.
2. High-Performance Butterfly Valves: Class 300, single flange.
3. Iron Swing Check Valves: Class 250, metal seats.
4. Iron, Grooved-End Check Valves, NPS 3 to NPS 12 (DN 80 to DN 300): 300 CWP.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
B. Related Sections:
1. Section 05 5000 "Metal Fabrications" for structural-steel shapes and plates for trapeze
hangers for pipe and equipment supports.
2. Section 23 0516 "Expansion Fittings and Loops for HVAC Piping" for pipe guides and
anchors.
3. Section 23 3114 "Ductwork" for duct hangers and supports.
1.3 DEFINITIONS
A. MSS: Manufacturers Standardization Society of The Valve and Fittings Industry Inc.
A. Delegated Design: Design trapeze pipe hangers and equipment supports, including
comprehensive engineering analysis by a qualified professional engineer, using performance
requirements and design criteria indicated.
B. Structural Performance: Hangers and supports for HVAC piping and equipment shall withstand
the effects of gravity loads and stresses within limits and under conditions indicated according
to ASCE/SEI 7.
1. Design supports for multiple pipes, including pipe stands, capable of supporting
combined weight of supported systems, system contents, and test water.
2. Design equipment supports capable of supporting combined operating weight of
supported equipment and connected systems and components.
A. Welding certificates.
B. Shop Drawings: Signed and sealed by a qualified professional engineer. Show fabrication and
installation details and include calculations for the following; include Product Data for
components:
B. Pipe Welding Qualifications: Qualify procedures and operators according to ASME Boiler and
Pressure Vessel Code.
C. Hangers and Supports for mechanical and plumbing piping shall be in accordance with MSS
Standards.
1. MSS SP-58 – Pipe Hangers and Supports – Materials, Design and Manufacturer
2. MSS SP-69 – Pipe Hangers and Supports – Selection and Application
3. MSS SP-89 – Pipe Hangers and Supports – Fabrication and Installation Practices
D. Hangers and Supports for fire protection piping shall be in accordance with NFPA Standards.
Provide products which are UL listed and FM approved.
PART 2 - PRODUCTS
A. Description: MSS SP-69, Type 59, shop or field-fabricated pipe-support assembly made from
structural hot-dip galvanized, carbon-steel shapes with MSS SP-58 hot-dip galvanized or
electro-coated zinc, carbon-steel hanger rods, nuts, saddles, and U-bolts. If used, they cannot
impede serviceability of equipment.
B. Insulation-Insert Material for Cold Piping: ASTM C 552, Type II cellular glass with 100-psig
(688-kPa) or ASTM C 591, Type VI, Grade 1 polyisocyanurate with 125-psig (862-kPa)
minimum compressive strength and vapor barrier.
C. Insulation-Insert Material for Hot Piping: Water-repellent treated, ASTM C 533, Type I calcium
silicate with 100-psig (688-kPa) ASTM C 552, Type II cellular glass with 100-psig (688-kPa)
minimum compressive strength.
D. For Trapeze or Clamped Systems: Insert and shield shall cover entire circumference of pipe.
E. For Clevis or Band Hangers: Insert and shield shall cover lower 180 degrees of pipe.
F. Insert Length: Extend 2 inches beyond sheet metal shield for piping operating below ambient
air temperature.
B. Compact Pipe Stand: One-piece plastic unit with integral-rod roller, pipe clamps, or V-shaped
cradle to support pipe, for roof installation without membrane penetration.
C. Low-Type, Single-Pipe Stand: One-piece stainless-steel base unit with plastic roller, for roof
installation without membrane penetration.
1. Description: Assembly of base, vertical and horizontal members, and pipe support, for
roof installation without membrane penetration.
2. Base: Stainless steel.
3. Vertical Members: Two or more cadmium-plated-steel or stainless-steel, continuous-
thread rods.
4. Horizontal Member: Cadmium-plated-steel or stainless-steel rod with plastic or stainless-
steel, roller-type pipe support.
E. High-Type, Multiple-Pipe Stand:
1. Description: Assembly of bases, vertical and horizontal members, and pipe supports, for
roof installation without membrane penetration.
2. Bases: One or more; plastic.
3. Vertical Members: Two or more protective-coated-steel channels.
4. Horizontal Member: Protective-coated-steel channel.
5. Pipe Supports: Galvanized-steel, clevis-type pipe hangers.
F. Curb-Mounted-Type Pipe Stands: Shop- or field-fabricated pipe supports made from structural-
steel shapes, continuous-thread rods, and rollers, for mounting on permanent stationary roof
curb.
A. Description: Welded, shop- or field-fabricated equipment support made from structural carbon-
steel shapes, with hot dip galvanized coating.
A. Structural Steel: ASTM A 36/A 36M, carbon-steel plates, shapes, and bars; black and hot dip
galvanized.
B. Grout: ASTM C 1107, factory-mixed and -packaged, dry, hydraulic-cement, non-shrink and
nonmetallic grout; suitable for interior and exterior applications.
a. Hangers are required to be specific to pipe and ductwork independently and not
shared.
PART 3 - EXECUTION
A. Metal Pipe-Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Install hangers,
supports, clamps, and attachments as required to properly support piping from the building
structure.
B. Metal Trapeze Pipe-Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Arrange for
grouping of parallel runs of horizontal piping, and support together on field-fabricated trapeze
pipe hangers. Multiple, stacked trapeze's are not allowed.
1. Pipes of Various Sizes: Support together and space trapezes for smallest pipe size or
install intermediate supports for smaller diameter pipes as specified for individual pipe
hangers.
2. Field fabricate from ASTM A 36/A 36M, carbon-steel shapes selected for loads being
supported. Weld steel according to AWS D1.1/D1.1M.
C. Metal Framing System Installation: Arrange for grouping of parallel runs of piping, and support
together on field-assembled metal framing systems.
D. Thermal-Hanger Shield Installation: Install in pipe hanger or shield for insulated piping.
1. Install powder-actuated fasteners for use in lightweight concrete or concrete slabs less
than 4 inches (100 mm) thick in concrete after concrete is placed and completely cured.
Use operators that are licensed by powder-actuated tool manufacturer. Install fasteners
according to powder-actuated tool manufacturer's operating manual.
2. Install mechanical-expansion anchors in concrete after concrete is placed and completely
cured. Install fasteners according to manufacturer's written instructions.
1. Pipe Stand Types except Curb-Mounted Type: Assemble components and mount on
smooth roof surface. Do not penetrate roof membrane.
2. Curb-Mounted-Type Pipe Stands: Assemble components or fabricate pipe stand and
mount on permanent, stationary roof curb. See Section 077200 "Roof Accessories" for
curbs.
G. Install hangers and supports complete with necessary attachments, inserts, bolts, rods, nuts,
washers, and other accessories.
J. Install hangers and supports to allow controlled thermal movement of piping systems, to permit
freedom of movement between pipe anchors, and to facilitate action of expansion joints,
expansion loops, expansion bends, and similar units.
K. Install lateral bracing with pipe hangers and supports to prevent swaying.
L. Install building attachments within concrete slabs or attach to structural steel. Install additional
attachments at concentrated loads, including valves, flanges, strainers, and at changes in
direction of piping. Install concrete inserts before concrete is placed; fasten inserts to forms and
install reinforcing bars through openings at top of inserts.
M. Load Distribution: Install hangers and supports so that piping live and dead loads and stresses
from movement will not be transmitted to connected equipment.
N. Pipe Slopes: Install hangers and supports to provide indicated pipe slopes and to not exceed
maximum pipe deflections allowed by ASME B31.9 for building services piping.
O. Insulated Piping:
a. Piping Operating above Ambient Air Temperature: Clamp may project through
insulation.
b. Piping Operating below Ambient Air Temperature: Use thermal-hanger shield
insert with clamp sized to match OD of insert.
c. Do not exceed pipe stress limits allowed by ASME B31.9 for building services
piping.
2. Install MSS SP-58, Type 39, protection saddles if insulation without vapor barrier is
indicated. Fill interior voids with insulation that matches adjoining insulation.
3. Install MSS SP-58, Type 40, protective shields on cold piping with vapor barrier. Shields
shall span an arc of 180 degrees.
a. NPS 1/4 to NPS 3-1/2 (DN 8 to DN 90): 12 inches long and 0.048 inch thick.
b. NPS 4 (DN 100): 12 inches long and 0.06 inch thick.
c. NPS 5 and NPS 6 (DN 125 and DN 150): 18 inches long and 0.06 inch thick.
d. NPS 8 to NPS 14 (DN 200 to DN 350): 24 inches long and 0.075 inch thick.
5. Pipes NPS 8 (DN 200) and Larger: Include wood or reinforced calcium-silicate-insulation
inserts of length at least as long as protective shield.
6. Thermal-Hanger Shields: Install with insulation same thickness as piping insulation.
7. Un-insulated Piping:
a. Where insulation is not required, use similar metal hangers such as copper
hangers for copper piping, stainless steel for stainless steel piping, etc.
B. Grouting: Place grout under supports for equipment and make bearing surface smooth.
A. Cut, drill, and fit miscellaneous metal fabrications for trapeze pipe hangers and equipment
supports.
B. Fit exposed connections together to form hairline joints. Field weld connections that cannot be
shop welded because of shipping size limitations.
C. Field Welding: Comply with AWS D1.1/D1.1M procedures for shielded, metal arc welding;
appearance and quality of welds; and methods used in correcting welding work; and with the
following:
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. Finish welds at exposed connections so no roughness shows after finishing and so
contours of welded surfaces match adjacent contours.
5. Re-galvanize if galvanizing affected.
3.4 ADJUSTING
A. Hanger Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve
indicated slope of pipe.
B. Trim excess length of continuous-thread hanger and support rods to 1-1/2 inches (40 mm).
3.5 PAINTING
A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas
immediately after erecting hangers and supports. Use same materials as used for shop
painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.
1. Apply paint by brush or spray to provide a minimum dry film thickness of 2.0 mils (0.05
mm).
B. Touchup: Cleaning and touchup painting of field welds, bolted connections, and abraded areas
of shop paint on miscellaneous metal are specified in Section 099100 "Painting"."
C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply
galvanizing-repair paint to comply with ASTM A 780.
A. Specific hanger and support requirements are in Sections specifying piping systems and
equipment.
B. Comply with MSS SP-69 for pipe-hanger selections and applications that are not specified in
piping system Sections.
C. Use hangers and supports with galvanized metallic coatings for piping and equipment that will
not have field-applied finish.
D. Use coated carbon-steel pipe hangers and supports, metal trapeze pipe hangers and metal
framing systems and attachments for general service applications.
E. Use copper pipe hangers and copper attachments for copper piping and tubing. Likewise for
stainless steel piping and tubing, use stainless steel hangers.
H. Horizontal-Piping Hangers and Supports: Unless otherwise indicated and except as specified in
piping system Sections, install the following types:
1. Adjustable, Steel Clevis Hangers (MSS Type 1): For suspension of non-insulated or
insulated, stationary pipes NPS 1/2 to NPS 30 (DN 15 to DN 750).
2. Yoke-Type Pipe Clamps (MSS Type 2): For suspension of up to 1050 deg F, pipes
NPS 4 to NPS 24 (DN 100 to DN 600), requiring up to 4 inches of insulation.
3. Carbon- or Alloy-Steel, Double-Bolt Pipe Clamps (MSS Type 3): For suspension of pipes
NPS 3/4 to NPS 36 (DN 20 to DN 900), requiring clamp flexibility and up to 4 inches of
insulation.
4. Steel Pipe Clamps (MSS Type 4): For suspension of cold and hot pipes NPS 1/2 to
NPS 24 (DN 15 to DN 600) if little or no insulation is required.
5. Pipe Hangers (MSS Type 5): For suspension of pipes NPS 1/2 to NPS 4 (DN 15 to DN
100), to allow off-center closure for hanger installation before pipe erection.
6. Adjustable, Swivel Split- or Solid-Ring Hangers (MSS Type 6): For suspension of non-
insulated, stationary pipes NPS 3/4 to NPS 8 (DN 20 to DN 200).
7. Adjustable, Steel Band Hangers (MSS Type 7): For suspension of non-insulated,
stationary pipes NPS 1/2 to NPS 8 (DN 15 to DN 200).
8. Adjustable Band Hangers (MSS Type 9): For suspension of non-insulated, stationary
pipes NPS 1/2 to NPS 8 (DN 15 to DN 200).
9. Adjustable, Swivel-Ring Band Hangers (MSS Type 10): For suspension of non-insulated,
stationary pipes NPS 1/2 to NPS 8 (DN 15 to DN 200).
10. Split Pipe Ring with or without Turnbuckle Hangers (MSS Type 11): For suspension of
non-insulated, stationary pipes NPS 3/8 to NPS 8 (DN 10 to DN 200).
11. Extension Hinged or Two-Bolt Split Pipe Clamps (MSS Type 12): For suspension of non-
insulated, stationary pipes NPS 3/8 to NPS 3 (DN 10 to DN 80).
12. U-Bolts (MSS Type 24): For support of heavy pipes NPS 1/2 to NPS 30 (DN 15 to
DN 750).
13. Clips (MSS Type 26): For support of insulated pipes not subject to expansion or
contraction.
14. Pipe Saddle Supports (MSS Type 36): For support of pipes NPS 4 to NPS 36 (DN 100 to
DN 900), with steel-pipe base stanchion support and cast-iron floor flange or carbon-steel
plate.
15. Pipe Stanchion Saddles (MSS Type 37): For support of pipes NPS 4 to NPS 36 (DN 100
to DN 900), with steel-pipe base stanchion support and cast-iron floor flange or carbon-
steel plate, and with U-bolt to retain pipe.
16. Adjustable Pipe Saddle Supports (MSS Type 38): For stanchion-type support for pipes
NPS 2-1/2 to NPS 36 (DN 65 to DN 900) if vertical adjustment is required, with steel-pipe
base stanchion support and cast-iron floor flange.
17. Single-Pipe Rolls (MSS Type 41): For suspension of pipes NPS 1 to NPS 30 (DN 25 to
DN 750), from two rods if longitudinal movement caused by expansion and contraction
might occur.
18. Adjustable Roller Hangers (MSS Type 43): For suspension of pipes NPS 2-1/2 to
NPS 24 (DN 65 to DN 600), from single rod if horizontal movement caused by expansion
and contraction might occur.
19. Complete Pipe Rolls (MSS Type 44): For support of pipes NPS 2 to NPS 42 (DN 50 to
DN 1050) if longitudinal movement caused by expansion and contraction might occur but
vertical adjustment is not necessary.
20. Pipe Roll and Plate Units (MSS Type 45): For support of pipes NPS 2 to NPS 24 (DN 50
to DN 600) if small horizontal movement caused by expansion and contraction might
occur and vertical adjustment is not necessary.
21. Adjustable Pipe Roll and Base Units (MSS Type 46): For support of pipes NPS 2 to
NPS 30 (DN 50 to DN 750) if vertical and lateral adjustment during installation might be
required in addition to expansion and contraction.
I. Vertical-Piping Clamps: Unless otherwise indicated and except as specified in piping system
Sections, install the following types:
1. Extension Pipe or Riser Clamps (MSS Type 8): For support of pipe risers NPS 3/4 to
NPS 24 (DN 24 to DN 600).
2. Carbon- or Alloy-Steel Riser Clamps (MSS Type 42): For support of pipe risers NPS 3/4
to NPS 24 (DN 20 to DN 600) if longer ends are required for riser clamps.
J. Hanger-Rod Attachments: Unless otherwise indicated and except as specified in piping system
Sections, install the following types:
1. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches for heavy loads.
2. Steel Clevises (MSS Type 14): For 120 to 450 deg F piping installations.
3. Swivel Turnbuckles (MSS Type 15): For use with MSS Type 11, split pipe rings.
4. Malleable-Iron Sockets (MSS Type 16): For attaching hanger rods to various types of
building attachments.
5. Steel Weldless Eye Nuts (MSS Type 17): For 120 to 450 deg F piping installations.
K. Building Attachments: Unless otherwise indicated and except as specified in piping system
Sections, install the following types:
1. Steel or Malleable Concrete Inserts (MSS Type 18): For upper attachment to suspend
pipe hangers from concrete ceiling.
2. Top-Beam C-Clamps (MSS Type 19): For use under roof installations with bar-joist
construction, to attach to top flange of structural shape.
3. Side-Beam or Channel Clamps (MSS Type 20): For attaching to bottom flange of beams,
channels, or angles.
4. Center-Beam Clamps (MSS Type 21): For attaching to center of bottom flange of beams.
5. Welded Beam Attachments (MSS Type 22): For attaching to bottom of beams if loads
are considerable and rod sizes are large.
6. C-Clamps (MSS Type 23): For structural shapes.
7. Top-Beam Clamps (MSS Type 25): For top of beams if hanger rod is required tangent to
flange edge.
8. Side-Beam Clamps (MSS Type 27): For bottom of steel I-beams.
9. Steel-Beam Clamps with Eye Nuts (MSS Type 28): For attaching to bottom of steel I-
beams for heavy loads.
10. Linked-Steel Clamps with Eye Nuts (MSS Type 29): For attaching to bottom of steel I-
beams for heavy loads, with link extensions.
11. Malleable-Beam Clamps with Extension Pieces (MSS Type 30): For attaching to
structural steel.
12. Welded-Steel Brackets: For support of pipes from below or for suspending from above
by using clip and rod. Use one of the following for indicated loads:
13. Side-Beam Brackets (MSS Type 34): For sides of steel or wooden beams.
14. Plate Lugs (MSS Type 57): For attaching to steel beams if flexibility at beam is required.
15. Horizontal Travelers (MSS Type 58): For supporting piping systems subject to linear
horizontal movement where headroom is limited.
L. Saddles and Shields: Unless otherwise indicated and except as specified in piping system
Sections, install the following types:
1. Steel-Pipe-Covering Protection Saddles (MSS Type 39): To fill interior voids with
insulation that matches adjoining insulation.
2. Protection Shields (MSS Type 40): Of length recommended in writing by manufacturer to
prevent crushing insulation.
3. Thermal-Hanger Shield Inserts: For supporting insulated pipe.
M. Spring Hangers and Supports: Unless otherwise indicated and except as specified in piping
system Sections, install the following types:
1. Restraint-Control Devices (MSS Type 47): Where indicated to control piping movement.
2. Spring Cushions (MSS Type 48): For light loads if vertical movement does not exceed 1-
1/4 inches (32 mm).
3. Spring-Cushion Roll Hangers (MSS Type 49): For equipping Type 41, roll hanger with
springs.
4. Spring Sway Braces (MSS Type 50): To retard sway, shock, vibration, or thermal
expansion in piping systems.
5. Variable-Spring Hangers (MSS Type 51): Preset to indicated load and limit variability
factor to 25 percent to allow expansion and contraction of piping system from hanger.
6. Variable-Spring Base Supports (MSS Type 52): Preset to indicated load and limit
variability factor to 25 percent to allow expansion and contraction of piping system from
base support.
7. Variable-Spring Trapeze Hangers (MSS Type 53): Preset to indicated load and limit
variability factor to 25 percent to allow expansion and contraction of piping system from
trapeze support.
8. Constant Supports: For critical piping stress and if necessary to avoid transfer of stress
from one support to another support, critical terminal, or connected equipment. Include
auxiliary stops for erection, hydrostatic test, and load-adjustment capability. These
supports include the following types:
N. Comply with MSS SP-69 for trapeze pipe-hanger selections and applications that are not
specified in piping system Sections.
O. Comply with MFMA-103 for metal framing system selections and applications that are not
specified in piping system Sections.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
a. Isolation pads.
b. Isolation mounts.
c. Restrained elastomeric isolation mounts.
d. Restrained spring isolators.
e. Elastomeric hangers.
f. Spring hangers.
g. Spring hangers with vertical-limit stops.
1.3 DEFINITIONS
A. Wind-Restraint Loading:
1. For Basic Wind Speed and Building Classification Category, please refer to the project
Structural Drawings.
2. Project design value in lb/sq. ft. (kg/sq. m) multiplied by the maximum area of the HVAC
component projected on a vertical plane that is normal to the wind direction, and 45
degrees either side of normal.
A. All vibration isolation products and wind restraints must be by a single manufacturer.
1. Include rated load, rated deflection, and overload capacity for each vibration isolation
device.
2. Illustrate and indicate style, material, strength, fastening provision, and finish for each
type and size of seismic-restraint component used.
a. Tabulate types and sizes of seismic restraints, complete with report numbers and
rated strength in tension and shear as evaluated by an evaluation service member
of ICC-ES or an agency acceptable to authorities having jurisdiction.
b. Annotate to indicate application of each product submitted and compliance with
requirements.
3. Interlocking Snubbers: Include ratings for horizontal, vertical, and combined loads.
C. Delegated-Design Submittal: For vibration isolation and restraint details indicated to comply
with performance requirements and design criteria, including analysis data signed and sealed
by the qualified professional engineer responsible for their preparation.
1. Design Calculations: Calculate static and dynamic loading due to equipment weight and
operation, and wind forces required to select vibration isolators, and wind restraints, and
for designing vibration isolation bases.
a. Coordinate design calculations with wind load calculations required for equipment
mounted outdoors. Comply with requirements in other Sections for equipment
mounted outdoors.
2. Riser Supports: Include riser diagrams and calculations showing anticipated expansion
and contraction at each support point, initial and final loads on building structure, spring
deflection changes, and seismic loads. Include certification that riser system has been
examined for excessive stress and that none will exist.
3. Vibration Isolation Base Details: Detail overall dimensions, including anchorages and
attachments to structure and to supported equipment. Include auxiliary motor slides and
rails, base weights, equipment static loads, power transmission, component
misalignment, and cantilever loads.
4. Wind Restraint Details:
A. Coordination Drawings: Show coordination of required clearances and bracing for HVAC duct
and equipment with other systems and equipment in the vicinity, including other supports, wind
restraints, housekeeping pads, and roof curbs.
B. Qualification Data: For professional engineer, manufacturer, installer, and testing agency.
C. Welding certificates.
A. Testing Agency Qualifications: An independent agency, with the experience and capability to
conduct the testing indicated, that is a nationally recognized testing laboratory (NRTL) as
defined by OSHA in 29 CFR 1910.7, and that is acceptable to authorities having jurisdiction.
B. Comply with wind design/restraint requirements in the IBC unless requirements in this Section
are more stringent.
C. Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding
Code - Steel."
PART 2 - PRODUCTS
2.1 General
A. Metal parts of vibration isolation units installed out-of-doors shall be hot-dipped galvanized,
cadmium-plated, or Neoprene-coated after fabrication. Galvanizing shall meet ASTM 44 “Salt
Spray Test Standards and Federal Test Standard.”
B. Spring elements shall be powder coated and tested in salt spray fog test per ASTM B117
standards
C. Spring elements shall have a lateral stiffness greater than 0.8 times the rated vertical stiffness
and shall be designed to provide up to 50% overload capacity before solid state is reached.
Spring shall be safe at solid state.
D. Spring elements shall be color coded or otherwise identified to indicate load capacity.
F. Vibration Isolators shall be selected by the manufacturer for each specific application to comply
with deflection requirements as shown on the vibration isolation schedule listed in this
specification.
B. Pads <TYPE 1>: Arranged in single or multiple layers of sufficient stiffness for uniform loading
over pad area, molded with a nonslip pattern and galvanized-steel baseplates, and factory cut
to sizes that match requirements of supported equipment. Minimum static deflection .25”
C. Mounts <TYPE 2>: Double-deflection type, with molded, oil-resistant rubber, hermetically
sealed compressed fiberglass, or neoprene isolator elements with factory-drilled, encapsulated
top plate for bolting to equipment and with baseplate for bolting to structure. Color-code or
otherwise identify to indicate capacity range. Minimum static deflection .25”
1. Materials: Cast-ductile-iron or welded steel housing containing two separate and
opposing, oil-resistant rubber or neoprene elements that prevent central threaded
element and attachment hardware from contacting the housing during normal operation.
2. Neoprene: Shock-absorbing materials compounded according to the standard for bridge-
bearing neoprene as defined by AASHTO.
D. Restrained Spring Isolators <Type 3>: Freestanding, steel, housed (Type C mounting),
isolators with limit-stop restraint.
1. Housing: Steel with resilient vertical-limit stops to prevent spring extension due to weight
being removed; factory-drilled baseplate bonded to 1/4-inch- (6-mm-) thick, neoprene or
rubber isolator pad attached to baseplate underside; and adjustable equipment mounting
and leveling bolt that acts as blocking during installation. A minimum clearance of ½”
shall be maintained around restraining bolts and between the housing and the spring so
as not to interfere with the spring action. Housing shall be designed to resist all wind
forces as applicable per building codes.
2. Restraint: Limit stop as required for equipment and authorities having jurisdiction.
Restraining bolts shall have a neoprene busing between the bolt and the housing. Limit
stops shall be out of contact during normal operation.
3. Outside Spring Diameter: Not less than 80 percent of the compressed height of the
spring at rated load.
4. Minimum Additional Travel: 50 percent of the required deflection at rated load.
5. Lateral Stiffness: More than 80 percent of rated vertical stiffness.
6. Overload Capacity: Support 200 percent of rated load, fully compressed, without
deformation or failure.
E. Elastomeric Hangers <Type 4>: Single or double-deflection type, fitted with molded, oil-
resistant elastomeric isolator elements bonded to steel housings with threaded connections for
hanger rods. Color-code or otherwise identify to indicate capacity range.
F. Spring Hangers <Type 5>: Combination coil-spring and fiberglass-insert hanger with spring
and insert in compression.
1. Frame: Steel, fabricated for connection to threaded hanger rods and to allow for a
maximum of 30 degrees of angular hanger-rod misalignment without binding or reducing
isolation efficiency.
2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the
spring at rated load.
3. Minimum Additional Travel: 50 percent of the required deflection at rated load.
4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.
5. Overload Capacity: Support 200 percent of rated load, fully compressed, without
deformation or failure.
6. Fiberglass Element: Molded, oil-resistant fiberglass. Steel-washer-reinforced cup to
support spring and bushing projecting through bottom of frame.
7. Self-centering hanger rod cap to ensure concentricity between hanger rod and support
spring coil.
G. Spring Hangers with Vertical-Limit Stop <Type 6>: Combination coil-spring and fiberglass-
insert hanger with spring and insert in compression and with a vertical-limit stop.
1. Frame: Steel, fabricated for connection to threaded hanger rods and to allow for a
maximum of 30 degrees of angular hanger-rod misalignment without binding or reducing
isolation efficiency.
2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the
spring at rated load.
3. Minimum Additional Travel: 50 percent of the required deflection at rated load.
4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.
5. Overload Capacity: Support 200 percent of rated load, fully compressed, without
deformation or failure.
6. Fiberglass Element: Molded, oil-resistant fiberglass.
7. Adjustable Vertical Stop: Steel washer with neoprene washer "up-stop" on lower
threaded rod.
8. Self-centering hanger rod cap to ensure concentricity between hanger rod and support
spring coil.
B. Steel Base <Type A>: Factory-fabricated, welded, structural-steel bases and rails.
1. Design Requirements: Lowest possible mounting height with not less than a 2-inch
clearance above the floor. Include equipment anchor bolts and auxiliary motor slide
bases or rails.
2. Include supports for suction and discharge elbows for pumps.
3. Structural Steel: Steel shapes, plates, and bars complying with ASTM A 36/A 36M.
Bases shall have shape to accommodate supported equipment.
4. Support Brackets: Factory-welded steel brackets on frame for outrigger isolation
mountings and to provide for anchor bolts and equipment support.
5. All vibration isolated structural frame base equipment shall have flexible connectors on all
attached piping, duct, conduit, etc. as to fully isolate the unit.
C. Inertia Base <Type B>: Factory-fabricated, welded, structural-steel bases and rails including
placement of cast-in-place concrete.
1. Design Requirements: Lowest possible mounting height with not less than a 2-inch
clearance above the floor. Include equipment anchor bolts and auxiliary motor slide
bases or rails.
2. Include supports for suction and discharge elbows for pumps.
3. Structural Steel: Steel shapes, plates, and bars complying with ASTM A 36/A 36M.
Bases shall have shape to accommodate supported equipment.
4. Support Brackets: Factory-welded steel brackets on frame for isolation mountings and to
provide for anchor bolts and equipment support.
5. Fabrication: Fabricate steel templates to hold equipment anchor-bolt sleeves and
anchors in place during placement of concrete. Obtain anchor-bolt templates from
supported equipment manufacturer.
6. All vibration isolated concrete inertia base equipment shall have flexible connectors on all
attached piping, duct, conduit, etc as to fully isolate the unit.
7. Cast-In-Place Concrete: Fill base with concrete per bas manufacturer's instructions,
using concrete meeting concrete specs.
2.4 ROOFTOP EQUIPMENT VIBRATION ISOLATION <Type C>
B. General Requirements
1. Factory-assembled, fully enclosed, insulated, air- and watertight curb rail designed to
resiliently support equipment and to withstand project wind forces.
2. All components within the final product and including the final product are to be
manufactured within the United States of America.
3. Complete curb and isolation assembly shall be stamped by a Professional Engineer
licensed in the jurisdiction of the project.
4. Provide sloped and/or extended height curb assemblies as necessary to coordinate with
roof slope and buildup.
5. All vibration isolated structural frame base equipment shall have flexible connectors on all
attached piping, duct, conduit, etc. as to fully isolate the unit.
1. Lower Support Assembly: Formed sheet-metal section containing steel springs that
support upper frame. Upper frame shall provide continuous support for equipment and
shall be captive to resiliently resist seismic and wind forces. Lower support assembly
shall have a means for attaching to building structure and a wood nailer for attaching roof
materials, and shall be insulated with a minimum of 2 inches (50 mm) of rigid, glass-fiber
insulation on inside of assembly.
2. Spring Isolators: restrained spring isolators shall be mounted on 1/4-inch- (6-mm-) thick,
elastomeric vibration isolation pads and shall have access ports, for level adjustment,
with removable waterproof covers at all isolator locations. Isolators shall be located so
they are accessible for adjustment at any time during the life of the installation without
interfering with the integrity of the roof.
3. Snubber Bushings: All-directional, elastomeric snubber bushings at least 1/4 inch (6 mm)
thick.
4. Water Seal: EPDM or Galvanized sheet metal weather seal attached to upper support
frame, extending down past wood nailer of lower support assembly, and counterflashed
over roof materials.
A. Split seals shall consist of pipe halves with minimum 3/4" thick neoprene sponge cemented to
the inner faces. The seal shall be tightened around the pipe to eliminate clearance between the
inner sponge face and the piping. Concrete may be packed in around the seal to make it
integral with the floor, wall, or ceiling if the seal is not in place prior to the construction of the
building surface or member.
B. Seals shall project a minimum of 1" past either face of walls. Where temperatures exceed
240°F, 10 pound density fiberglass may be used in lieu of the sponge.
A. Guides shall consist of a telescopic arrangement of two sizes of steel tubing separated by a
minimum of 1/2" thickness of 60 durometer or softer neoprene. The height of the guides shall
be preset with a set screw/bolt to allow vertical motion due to pipe expansion or contraction.
Guides shall be capable of +/- 1.625" motion, or to meet location requirements.
A. Guides shall consist of f two sizes of steel tubing separated by a minimum of 1/2" thickness of
60 durometer or softer neoprene. Vertical restraint shall be provided by similar material
arranged to prevent up or down vertical travel. Allowable loads on the isolation material shall
not exceed 500 psi and the design shall be balanced for equal resistance in any direction.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and equipment to receive vibration isolation and wind-control devices for
compliance with requirements for installation tolerances and other conditions affecting
performance.
B. Examine roughing-in of reinforcement and cast-in-place anchors to verify actual locations before
installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 APPLICATIONS
A. Multiple Pipe Supports: Secure pipes to trapeze member with clamps approved for application
by an evaluation service member of ICC-ES or an agency acceptable to authorities having
jurisdiction.
B. Hanger Rod Stiffeners: Install hanger rod stiffeners where indicated or scheduled on Drawings
to receive them and where required to prevent buckling of hanger rods due to seismic forces.
C. All rotating equipment shall have vibration isolation from building structure.
D. Ducts within 50' of fan discharges shall be isolated by spring hangers with neoprene cups.
E. The first three hangers and floor supports from equipment (i.e. pumps, etc.) shall be isolated by
spring hangers with neoprene cup for pipe and spring isolated concrete inertia base mounts
respectively.
F. Pipes passing through equipment room walls, floors, or ceilings shall have all directional
acoustical pipe seals.
G. Pipe risers shall bne suspended from or supported by all directional acoustical pipe anchors
and telescoping type guides.
H. All supply fans and pumps are to have at least four isolation springs located at the corners of
the equipment.
A. Comply with requirements in Section 077200 "Roof Accessories" for installation of roof curbs,
equipment supports, and roof penetrations.
B. Equipment Restraints:
1. Install resilient bolt isolation washers on equipment anchor bolts where clearance
between anchor and adjacent surface exceeds 0.125 inch (3.2 mm).
C. Piping Restraints:
D. Install bushing assemblies for anchor bolts for floor-mounted equipment, arranged to provide
resilient media between anchor bolt and mounting hole in concrete base.
E. Install bushing assemblies for mounting bolts for wall-mounted equipment, arranged to provide
resilient media where equipment or equipment-mounting channels are attached to wall.
G. Drilled-in Anchors:
1. Identify position of reinforcing steel and other embedded items prior to drilling holes for
anchors. Do not damage existing reinforcing or embedded items during coring or drilling.
Notify the structural engineer if reinforcing steel or other embedded items are
encountered during drilling. Locate and avoid prestressed tendons, electrical and
telecommunications conduit, and gas lines.
2. Do not drill holes in concrete or masonry until concrete, mortar, or grout has achieved full
design strength.
3. Wedge Anchors: Protect threads from damage during anchor installation. Heavy-duty
sleeve anchors shall be installed with sleeve fully engaged in the structural element to
which anchor is to be fastened.
4. Adhesive Anchors: Clean holes to remove loose material and drilling dust prior to
installation of adhesive. Place adhesive in holes proceeding from the bottom of the hole
and progressing toward the surface in such a manner as to avoid introduction of air
pockets in the adhesive.
5. Set anchors to manufacturer's recommended torque, using a torque wrench.
6. Install zinc-coated steel anchors for interior and stainless-steel anchors for exterior
applications.
A. Testing Agency: The Owner shall engage a qualified testing agency to perform tests and
inspections.
3.5 ADJUSTING
B. Adjust limit stops on restrained spring isolators to mount equipment at normal operating height.
After equipment installation is complete, adjust limit stops so they are out of contact during
normal operation.
D. Adjust restraints to permit free movement of equipment within normal mode of operation.
3.6 DEMONSTRATION
A. See drawing schedules but, the minimum mounting deflection for spring isolators shall be as
follows: 300 rpm, 3.5"; 500 rpm, 1.65"; 800 rpm, 1.00"; 1200 rpm and higher, 0.80".
B. All supply fans and HVAC pumps are to have at least (4) spring isolators located at the corners
of the fans/pumps.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Equipment labels.
2. Warning signs and labels.
3. Pipe labels.
4. Valve tags.
5. Duct labels.
6. Bar coding new equipment and components (see 3.7 at end of this section).
1.3 SUBMITTAL
PART 2 - PRODUCTS
1. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving,
1/8 inch thick, and having predrilled holes for attachment hardware.
2. Letter Color: White.
3. Background Color: Black.
4. Maximum Temperature: Able to withstand temperatures up to 160 deg F.
5. Minimum Label Size: Length and width vary for required label content, but not less than
2-1/2 by 3/4 inch.
6. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24
inches, 1/2 inch for viewing distances up to 72 inches, and proportionately larger lettering
for greater viewing distances. Include secondary lettering two-thirds to three-fourths the
size of principal lettering.
7. Fasteners: Stainless-steel rivets or self-tapping screws.
8. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.
A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/8 inch
thick, and having predrilled holes for attachment hardware.
F. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24 inches, 1/2
inch for viewing distances up to 72 inches, and proportionately larger lettering for greater
viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal
lettering.
H. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.
I. Label Content: Include caution and warning information, plus emergency notification
instructions.
A. General Requirements for Manufactured Pipe Labels: Preprinted, color-coded, with lettering
indicating service, showing flow direction, and area served (i.e. perimeter heating hot water).
B. Pre-tensioned Pipe Labels: Pre-coiled, semi-rigid plastic formed to cover full circumference of
pipe and to attach to pipe without fasteners or adhesive.
D. Pipe Label Contents: Include identification of piping service using same designations or
abbreviations as used on Drawings, pipe size, and an arrow indicating flow direction.
1. Flow-Direction Arrows: Integral with piping system service lettering to accommodate both
directions, or as separate unit on each pipe label to indicate flow direction, and visible all
around pipe.
2. Lettering Size: At least 1-1/2 inches high.
A. Valve tags shall be per University standards and according to project valve specification
section(s). Unless required differently in project valve specification section(s), valve tags to be
minimum 1.5" round brass, attached with metallic chains.
A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/8 inch
thick, and having predrilled holes for attachment hardware.
E. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2
by 3/4 inch.
F. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24 inches, 1/2
inch for viewing distances up to 72 inches, and proportionately larger lettering for greater
viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal
lettering.
H. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.
I. Duct Label Contents: Include identification of duct service using same designations or
abbreviations as used on Drawings, duct size, and an arrow indicating flow direction.
1. Flow-Direction Arrows: Integral with duct system service lettering to accommodate both
directions, or as separate unit on each duct label to indicate flow direction.
2. Lettering Size: At least 1-1/2 inches high.
1. Fire damper access panels shall be permanently identified on the exterior by labels not
less than 2" in height reading "FIRE DAMPER".
2. Smoke damper access panels shall be permanently identified on the exterior by labels
not less than 2" in height reading "SMOKE DAMPER".
3. Combination fire/smoke damper access panels shall be permanently identified on the
exterior by labels not less than 2" in height reading "RESETTABLE FIRE/SMOKE
DAMPER". Mark the other access panels "FIRE/SMOKE DAMPER."
4. Items listed in items 1-3 above, will also be listed on a full size, laminated print and left in
the main mechanical room as indicated above.
K. Duct static pressure sensors shall be permanently identified on the exterior by labels not less
than 2" in height reading "STATIC PRESSURE SENSOR".
1. Humidity sensors in ductwork shall be permanently identified on the exterior by labels not
less than 2" in height reading "HUMIDITY SENSOR".
2. Abbreviations: No abbreviations to be used.
3. All smoke and fire damper locations are to be posted as a pdf on the DDC system per fan
system. This information is also to be located in the fire command center for the building.
Coordinate with other trades to make sure this happens, and support as required via that
coordination.
a. STENCILING
1) Not allowed.
L. Barcoding New Equipment: Contractor to barcode any new equipment for the University, and in
coordination with their requirements.
PART 3 - EXECUTION
3.1 GENERAL
A. Refer to and adhere to "Northwestern University Pipe, Valve, and Fittings Standards" for work of
this section.
3.2 PREPARATION
A. Clean piping and equipment surfaces of substances that could impair bond of identification
devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and
encapsulants.
B. Locate pipe labels where piping is exposed or above accessible ceilings in finished spaces;
machine rooms; accessible maintenance spaces such as shafts, tunnels, and plenums; and
exterior exposed locations as follows:
A. Tag valves according to project valve specification section(s), and provide typed list (loose and
framed under glass) per same specification section(s).
1. A valve tag schedule is to be mounted in each mechanical room and on every floor (for
that respective floor) in a location to be determined by the Evanston Engineer shop.
2. Each valve tag schedule will have an associated architectural print showing each valve
location.
3. At project completion two additional hard copies are to be provided in addition to an
electronic copy. One for University Archive and one for the FMO Engineers shop.
4. Two copies of the mechanical piping flow diagram will be supplied. All prints that are
supplied that are located in mechancial rooms are to be laminated.
B. Pipe tags that are the first isolation for a utility in a mechanical room or building need to have
indicated where the next upstream valve is located and the associated valve number indicated
on the valve tag.
1. This is applicable for all utility isolation valves for each mechanical room space.
A. Install self-adhesive duct labels with permanent adhesive on air ducts in the following color
codes:
B. Locate labels at maximum intervals of 10 feet, at every change in direction, and within 3' of wall
and floor penetrations on both sides of same.
C. Along with all other ducting on the job, label toxic exhaust.
A. Coordinate with University, and bar code all new Division 23 equipment and components for
them, according to their requirements. Requirements include, but not limited to, being iPad
compatible, have the ability to call up maps of the areas on bar code scans, must have
safeguards built in to flag missing items, and the devices on the maps need to be color coded
based on inspection status.
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes testing, adjusting and balancing HVAC systems to provide design
conditions as indicated by the associated drawings. This Section includes, but is not limited to
the following:
B. The testing, adjusting and balancing of the air and hydronic systems shall be performed by an
independent TAB contractor contracted directly by the University, and approved companies are
Arrow Testing and Balancing, CEPro, Hill Mechanical, and ITB (Independent Test and Balance).
1.2 DEFINITIONS
B. Adjust: To regulate fluid flow rates and air patterns at the system or terminal level. At the
system level an example would be reducing fan speed; at the terminal level an example would
be changing a damper position.
C. Balance: To proportion air or water flows within the distribution system, including submains,
branches and terminals with respect to design quantities.
D. Draft: A current of air, when referring to localized effect caused by one or more factors of high
air velocity, low ambient temperature, or direction of airflow, whereby more heat is withdrawn
from a person’s skin than is normally dissipated.
H. Report Forms: Test data sheets for recording test data in logical order.
J. Suction Head: The height of fluid surface above the centerline of the pump on the suction side.
K. System Effect: A phenomenon that can create undesired or unpredicted conditions that cause
reduced capacities in all or part of a system.
L. System Effect Factors: Allowances used to calculate a reduction of the performance ratings of
a fan when installed under conditions different from those presented when the fan was
performance tested.
O. Testing, Adjusting and Balancing (TAB) Agent: The entity responsible for performing and
reporting the TAB procedures.
P. Terminal: A point where the controlled medium (fluid or energy) enters or leaves the distribution
system.
A. TAB Conference: If requested by the Owner, conduct a TAB conference at project site after
approval of the TAB strategies and procedures plan to develop a mutual understanding of the
details. Provide a minimum of 14 days' advance notice of scheduled meeting time and location.
A. [LEED Submittals:
A. Qualification Data: Within [30] [60] [90] <Insert number> days of Contractor's Notice to
Proceed, submit documentation that the TAB specialist and this Project's TAB team members
meet the qualifications specified in "Quality Assurance" Article.
B. Contract Documents Examination Report: Within [30] [60] [90] <Insert number> days of
Contractor's Notice to Proceed, submit the Contract Documents review report as specified in
Part 3.
C. Strategies and Procedures Plan: Within [30] [60] [90] <Insert number> days of Contractor's
Notice to Proceed, submit TAB strategies and step-by-step procedures as specified in
"Preparation" Article.
D. System Readiness Checklists: Within [30] [60] [90] <Insert number> days of Contractor's
Notice to Proceed, submit system readiness checklists as specified in "Preparation" Article.
1. TAB Field Supervisor: Employee of the TAB specialist and certified by AABC or NEBB.
2. TAB Technician: Employee of the TAB specialist and certified by AABC or NEBB as a
TAB technician.
1. Review field data reports to validate accuracy of data and to prepare certified TAB
reports.
2. Certify that the TAB team complied with the approved TAB plan and the procedures
specified and referenced in this Specification.
A. Full Owner Occupancy: Owner will occupy the site and existing building during entire TAB
period. Cooperate with Owner during TAB operations to minimize conflicts with Owner's
operations.
B. Partial Owner Occupancy: Owner may occupy completed areas of building before Substantial
Completion. Cooperate with Owner during TAB operations to minimize conflicts with Owner's
operations.
1.8 WARRANTY
B. Guarantee shall include provisions that the certified TAB firm has tested and balanced systems
according to the Contract Document and that the systems are balanced to optimum
performance capabilities within design and installation limits.
PART 2 - PRODUCTS
A. To be Ventlock #699,
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine the Contract Documents to become familiar with Project requirements and to discover
conditions in systems' designs that may preclude proper TAB of systems and equipment.
B. Examine systems for installed balancing devices, such as test ports, gage cocks, thermometer
wells, flow-control devices, balancing valves and fittings, and manual volume dampers. Verify
that locations of these balancing devices are accessible.
D. Examine design data including HVAC system descriptions, statements of design assumptions
for environmental conditions and systems' output, and statements of philosophies and
assumptions about HVAC system and equipment controls.
E. Examine ceiling plenums and underfloor air plenums used for supply, return, or relief air to
verify that they meet the leakage class of connected ducts as specified in Division 23 Section
"Ductwork" and are properly separated from adjacent areas. Verify that penetrations in plenum
walls are sealed and fire-stopped if required.
F. Examine equipment performance data including fan and pump curves.
1. Relate performance data to Project conditions and requirements, including system effects
that can create undesired or unpredicted conditions that cause reduced capacities in all
or part of a system.
2. Calculate system-effect factors to reduce performance ratings of HVAC equipment when
installed under conditions different from the conditions used to rate equipment
performance. To calculate system effects for air systems, use tables and charts found in
AMCA 201, "Fans and Systems," or in SMACNA's "HVAC Systems - Duct Design."
Compare results with the design data and installed conditions.
G. Examine system and equipment installations and verify that field quality-control testing,
cleaning, and adjusting specified in individual Sections have been performed.
I. Examine HVAC equipment and filters and verify that bearings are greased, belts are aligned
and tight, and equipment with functioning controls is ready for operation.
J. Examine terminal units, such as variable-air-volume boxes, and verify that they are accessible
and their controls are connected and functioning.
K. Examine strainers. Verify that startup screens are replaced by permanent screens with
indicated perforations.
L. Examine three-way valves for proper installation for their intended function of diverting or mixing
fluid flows.
M. Examine heat-transfer coils for correct piping connections and for clean and straight fins.
N. Examine system pumps to ensure absence of entrained air in the suction piping.
P. Report deficiencies discovered before and during performance of TAB procedures. Observe
and record system reactions to changes in conditions. Record default set points if different from
indicated values.
3.2 PREPARATION
A. Perform testing and balancing procedures on each system according to the procedures
contained in AABC's "National Standards for Total System Balance" or NEBB's "Procedural
Standards for Testing, Adjusting, and Balancing of Environmental Systems" and in this Section.
B. Cut insulation, ducts, pipes, and equipment cabinets for installation of test holes and probes to
the extent necessary for TAB procedures, and duct test hole fittings shall be provided where
shown on the drawings or specified in the Data sheets. T&B instrument test holes to be
Ventlock #699.
1. After testing and balancing, install and join new insulation that matches removed
materials. Restore insulation, coverings, vapor barrier, and finish according to
Division 23 Section "Mechanical System Insulation."
C. Mark equipment and balancing devices, including damper-control positions, valve position
indicators, fan-speed-control levers, and similar controls and devices, with paint or other
suitable, permanent identification material to show final settings.
D. Take and report testing and balancing measurements in inch-pound (IP) units.
A. Prepare test reports for both fans and outlets. Obtain manufacturer's outlet factors and
recommended testing procedures. Crosscheck the summation of required outlet volumes with
required fan volumes.
D. Determine the best locations in main and branch ducts for accurate duct-airflow measurements.
E. Check airflow patterns from the outdoor-air louvers and dampers and the return- and exhaust-
air dampers through the supply-fan discharge and mixing dampers.
F. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.
G. Verify that motor starters are equipped with properly sized thermal protection.
A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by
fan manufacturer.
a. Measure outlet static pressure as far downstream from the fan as practical and
upstream from restrictions in ducts such as elbows and transitions.
b. Measure static pressure directly at the fan outlet or through the flexible connection.
c. Measure inlet static pressure of single-inlet fans in the inlet duct as near the fan as
possible, upstream from the flexible connection, and downstream from duct
restrictions.
d. Measure inlet static pressure of double-inlet fans through the wall of the plenum
that houses the fan.
3. Measure static pressure across each component that makes up an air-handling unit,
rooftop unit, and other air-handling and -treating equipment.
a. Report the cleanliness status of filters and the time static pressures are measured.
4. Measure static pressures entering and leaving other devices, such as sound traps, heat-
recovery equipment, and air washers, under final balanced conditions.
5. Review Record Documents to determine variations in design static pressures versus
actual static pressures. Calculate actual system-effect factors. Recommend adjustments
to accommodate actual conditions.
6. Obtain approval from Engineer for adjustment of fan speed higher or lower than indicated
speed. Comply with requirements in Division 23 Sections for air-handling units for
adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit
performance.
7. Do not make fan-speed adjustments that result in motor overload. Consult equipment
manufacturers about fan-speed safety factors. Modulate dampers and measure fan-
motor amperage to ensure that no overload will occur. Measure amperage in full-cooling,
full-heating, economizer, and any other operating mode to determine the maximum
required brake horsepower.
B. Adjust volume dampers for main duct, submain ducts, and major branch ducts to indicated
airflows within specified tolerances.
a. Where sufficient space in submain and branch ducts is unavailable for Pitot-tube
traverse measurements, measure airflow at terminal outlets and inlets and
calculate the total airflow for that zone.
2. Measure static pressure at a point downstream from the balancing damper, and adjust
volume dampers until the proper static pressure is achieved.
3. Remeasure each submain and branch duct after all have been adjusted. Continue to
adjust submain and branch ducts to indicated airflows within specified tolerances.
D. Adjust air outlets and inlets for each space to indicated airflows within specified tolerances of
indicated values. Make adjustments using branch volume dampers rather than extractors and
the dampers at air terminals.
1. Adjust each outlet in same room or space to within specified tolerances of indicated
quantities without generating noise levels above the limitations prescribed by the
Contract Documents.
2. Adjust patterns of adjustable outlets for proper distribution without drafts.
A. Compensating for Diversity: When the total airflow of all terminal units is more than the
indicated airflow of the fan, place a selected number of terminal units at a minimum set-point
airflow with the remainder at maximum airflow condition until the total airflow of the terminal
units equals the indicated airflow of the fan. Select the reduced-airflow terminal units so they
are distributed evenly among the branch ducts.
1. Set outdoor-air dampers at minimum, and set return- and exhaust-air dampers at a
position that simulates full-cooling load.
2. Select the terminal unit that is most critical to the supply-fan airflow and static pressure.
Measure static pressure. Adjust system static pressure so the entering static pressure
for the critical terminal unit is not less than the sum of the terminal-unit manufacturer's
recommended minimum inlet static pressure plus the static pressure needed to overcome
terminal-unit discharge system losses.
3. Measure total system airflow. Adjust to within indicated airflow.
4. Set terminal units at maximum airflow and adjust controller or regulator to deliver the
designed maximum airflow. Use terminal-unit manufacturer's written instructions to make
this adjustment. When total airflow is correct, balance the air outlets downstream from
terminal units the same as described for constant-volume air systems.
5. Set terminal units at minimum airflow and adjust controller or regulator to deliver the
designed minimum airflow. Check air outlets for a proportional reduction in airflow the
same as described for constant-volume air systems.
a. If air outlets are out of balance at minimum airflow, report the condition but leave
outlets balanced for maximum airflow.
6. Re-measure the return airflow to the fan while operating at maximum return airflow and
minimum outdoor airflow.
a. Adjust the fan and balance the return-air ducts and inlets the same as described
for constant-volume air systems.
7. Measure static pressure at the most critical terminal unit and adjust the static-pressure
controller at the main supply-air sensing station to ensure that adequate static pressure is
maintained at the most critical unit.
8. Record final fan-performance data.
C. Pressure-Dependent, Variable-Air-Volume Systems with Diversity: After the fan systems have
been adjusted, adjust the variable-air-volume systems as follows:
1. Set system at maximum indicated airflow by setting the required number of terminal units
at minimum airflow. Select the reduced-airflow terminal units so they are distributed
evenly among the branch ducts.
2. Adjust supply fan to maximum indicated airflow with the variable-airflow controller set at
maximum airflow.
3. Set terminal units at full-airflow condition.
4. Adjust terminal units starting at the supply-fan end of the system and continuing
progressively to the end of the system. Adjust inlet dampers of each terminal unit to
indicated airflow. When total airflow is correct, balance the air outlets downstream from
terminal units the same as described for constant-volume air systems.
5. Adjust terminal units for minimum airflow.
6. Measure static pressure at the sensor.
7. Measure the return airflow to the fan while operating at maximum return airflow and
minimum outdoor airflow. Adjust the fan and balance the return-air ducts and inlets the
same as described for constant-volume air systems.
A. Prepare test reports with pertinent design data, and number in sequence starting at pump to
end of system. Check the sum of branch-circuit flows against the approved pump flow rate.
Correct variations that exceed plus or minus 5 percent.
C. Prepare hydronic systems for testing and balancing according to the following, in addition to the
general preparation procedures specified above:
a. Measure discharge pressure directly at the pump outlet flange or in discharge pipe
prior to any valves.
b. Measure inlet pressure directly at the pump inlet flange or in suction pipe prior to
any valves or strainers.
c. Convert pressure to head and correct for differences in gage heights.
d. Verify pump impeller size by measuring the TDH with the discharge valve closed.
Note the point on manufacturer's pump curve at zero flow, and verify that the pump
has the intended impeller size.
e. With valves open, read pump TDH. Adjust pump discharge valve until design water
flow is achieved.
3. Monitor motor performance during procedures and do not operate motor in an overloaded
condition.
B. Adjust flow-measuring devices installed in mains and branches to design water flows.
C. Adjust flow-measuring devices installed at terminals for each space to design water flows.
1. Measure differential pressure and verify that it is within manufacturer's specified range.
2. Perform temperature tests after flows have been verified.
1. Measure and balance coils by either coil pressure drop or temperature method.
2. If balanced by coil pressure drop, perform temperature tests after flows have been
verified.
A. Balance systems with automatic two- and three-way control valves by setting systems at
maximum flow through heat-exchange terminals and proceed as specified above in section 3.7
for hydronic systems.
3.10 Systems installed with pressure independent control valves shall not require full hydronic
system balancing. Flow shall be verified for the pressure independent valve assembly (valve
and actuator combination) for field conditions using the pressure independent control valve
manufacturer’s documented procedure for [20%] [50%] [100%] of the total installed product.
Exact locations of tested product to be coordinated with the drawings.
B. Balance the secondary circuits after the primary circuits are complete.
a. Measure discharge pressure directly at the pump outlet flange or in discharge pipe
prior to any valves.
b. Measure inlet pressure directly at the pump inlet flange or in suction pipe prior to
any valves or strainers.
c. Convert pressure to head and correct for differences in gage heights.
d. Verify pump impeller size by measuring the TDH with the discharge valve closed.
Note the point on manufacturer's pump curve at zero flow and verify that the pump
has the intended impeller size.
e. With valves open, read pump TDH. Adjust pump discharge valve until design water
flow is achieved.
3. Monitor motor performance during procedures and do not operate motor in an overloaded
condition.
D. Adjust flow-measuring devices installed in mains and branches to design water flows.
E. Adjust flow-measuring devices installed at terminals for each space to design water flows.
1. Measure differential pressure and verify that it is within manufacturer's specified range.
2. Perform temperature tests after flows have been verified.
1. Measure and balance coils by either coil pressure drop or temperature method.
2. If balanced by coil pressure drop, perform temperature tests after flows have been
verified.
A. Measure and record upstream and downstream pressure of each piece of equipment.
B. Measure and record upstream and downstream steam pressure of pressure-reducing valves.
D. Check settings and operation of safety and relief valves. Record settings.
3.14 PROCEDURES FOR MOTORS
A. Motors 1/2 HP and Larger: Test at final balanced conditions and record the following data:
A. Balance total condenser-water flows to towers. Measure and record the following data:
A. Hydronic Boilers:
B. Steam Boilers:
A. Balance water flow through each evaporator and condenser to within specified tolerances of
indicated flow with all pumps operating. With only one chiller operating in a multiple chiller
installation, do not exceed the flow for the maximum tube velocity recommended by the chiller
manufacturer. Measure and record the following data with each chiller operating at design
conditions:
1. Evaporator-water entering and leaving temperatures, pressure drop, and water flow.
2. For water-cooled chillers, condenser-water entering and leaving temperatures, pressure
drop, and water flow.
3. Evaporator and condenser refrigerant temperatures and pressures, using instruments
furnished by chiller manufacturer.
4. Power factor if factory-installed instrumentation is furnished for measuring kilowatts.
5. Kilowatt input if factory-installed instrumentation is furnished for measuring kilowatts.
6. Capacity: Calculate in tons of cooling.
7. For air-cooled chillers, verify condenser-fan rotation and record fan and motor data
including number of fans and entering- and leaving-air temperatures.
A. Measure, adjust, and record the following data for each water coil:
B. Measure, adjust, and record the following data for each electric heating coil:
1. Nameplate data.
2. Airflow.
3. Entering- and leaving-air temperature at full load.
4. Voltage and amperage input of each phase at full load and at each incremental stage.
5. Calculated kilowatt at full load.
6. Fuse or circuit-breaker rating for overload protection.
C. Measure, adjust, and record the following data for each steam coil:
D. Measure, adjust, and record the following data for each refrigerant coil:
1. For most spaces, the total supply air quantity to each space of a system shall be within -
5% to +10% of design. Review project specific requirements with NU Project Manager.
2. The percent tolerance of each outlet within a space shall be per Table 23 0594-1.
Table 23 0594-1
System Number of Outlets in Space
1 2 3 or More
Single Zone, Mul- -5% ±10% ± 15%
tizone, VAV +10%
Heating and Venti- -5% ±15% ±15%
lating +10%
3. Air quantity of each return air grille and diffuser shall be within ±10% of design. The
design room pressurization must be maintained regardless of the tolerance at each
individual diffuser.
4. Vivariums: In general, these laboratories shall be under negative pressure. The design
should meet the current NIH Design Requirements Manual for Biomedical Laboratories
and Animal Research Facilities. Any reduction in airflow shall be presented by the project
Engineer of Record and reviewed by the NU Project Manager and Project Engineer.
5. Culture Rooms: These rooms shall be under positive pressure.
6. Hydronic Systems: Heating and cooling hydronic systems shall be balanced so that the
flow is from 0 to +5% of design at each coil.
7. Combination fire/smoke dampers in dynamic smoke control systems shall be tested for
closure under airflow conditions (International Mechanical Code – 2009, Section 607),
and to assure positive pressure of certain zones, and negative pressure for other zones.
Smoke dampers in dynamic smoke control systems must close under airflow conditions.
3.21 REPORTING
A. All test reports are to have an Executive Summary which shall state extent of system
compliance, system deficiencies, and recommended changes.
A. General: Prepare a certified written report; tabulate and divide the report into separate sections
for tested systems and balanced systems.
1. Include a certification sheet at the front of the report's binder, signed and sealed by the
certified testing and balancing engineer.
2. Include a list of instruments used for procedures, along with proof of calibration.
B. Final Report Contents: In addition to certified field-report data, include the following:
1. Pump curves.
2. Fan curves.
3. Manufacturers' test data.
4. Field test reports prepared by system and equipment installers.
5. Other information relative to equipment performance; do not include Shop Drawings and
product data.
C. General Report Data: In addition to form titles and entries, include the following data:
1. Title page.
2. Name and address of the TAB contractor.
3. Project name.
4. Project location.
5. Architect's name and address.
6. Engineer's name and address.
7. Contractor's name and address.
8. Report date.
9. Signature of TAB supervisor who certifies the report.
10. Table of Contents with the total number of pages defined for each section of the report.
Number each page in the report.
11. Summary of contents including the following:
D. System Diagrams: Include schematic layouts of air and hydronic distribution systems. Present
each system with single-line diagram and include the following:
A. Within 90 days of completing TAB, perform additional TAB to verify that balanced conditions are
being maintained throughout and to correct unusual conditions.
B. Seasonal Periods: If initial TAB procedures were not performed during near-peak summer and
winter conditions, perform additional TAB during near-peak summer and winter conditions.
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Insulation Materials:
a. Flexible elastomeric.
b. Mineral fiber.
B. Related Sections:
1.2 SUBMITTALS
B. ]LEED Submittal:
1. Product Data for Credit EQ 4.1: For adhesives and sealants, including printed
statement of VOC content.]
C. Shop Drawings:
1. Detail application of protective shields, saddles, and inserts at hangers for each type of
insulation and hanger.
B. Materials and installation in accordance with NFPA 255, UL 723, and MICA (Midwest Insulation
Contractors Association).
C. Insulation thickness shall meet the requirements of ASHRAE Standard 90.1 and Northwestern
University Standards and shall be selected to eliminate avoid condensation.
PART 2 - PRODUCTS
A. Comply with requirements in Part 3 schedule articles for where insulating materials shall be
applied.
C. Products that come in contact with stainless steel shall have a leachable chloride content of
less than 50 ppm when tested according to ASTM C 871.
D. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable
according to ASTM C 795.
E. Foam insulation materials shall not use CFC or HCFC blowing agents in the manufacturing
process.
F. Flexible Elastomeric: Closed-cell, sponge- or expanded-rubber materials. Comply with
ASTM C 534, Type I for tubular materials and Type II for sheet materials.
G. Mineral-Fiber Blanket Insulation: Mineral or glass fibers bonded with a thermosetting resin.
Comply with ASTM C 553, Type II and ASTM C 1290, Type III with factory-applied FSK jacket.
Factory-applied jacket requirements are specified in "Factory-Applied Jackets" Article.
H. Mineral-Fiber Board Insulation: Mineral or glass fibers bonded with a thermosetting resin.
Comply with ASTM C 612, Type IA or Type IB. For duct and plenum applications, provide
insulation with factory-applied FSK jacket. For equipment applications, provide insulation with
factory-applied ASJ. Factory-applied jacket requirements are specified in "Factory-Applied
Jackets" Article.
2. Type I, 850 deg F Materials: Mineral or glass fibers bonded with a thermosetting resin.
Comply with ASTM C 547, Type I, Grade A, with factory-applied ASJ. Factory-applied
jacket requirements are specified in "Factory-Applied Jackets" Article. Densities per
PART 3 schedules.
J. Mineral-Fiber, Pipe and Tank Insulation: Mineral or glass fibers bonded with a thermosetting
resin. Semi-rigid board material with factory-applied ASJ complying with ASTM C 1393, Type II
or Type IIIA Category 2, or with properties similar to ASTM C 612, Type IB. Nominal density is
2.5 lb/cu. ft. or more. Thermal conductivity (k-value) at 100 deg F is 0.29 Btu x in./h x sq. ft. x
deg F or less. Factory-applied jacket requirements are specified in "Factory-Applied Jackets"
Article.
B. Joint free, lightweight, non-asbestos, high temperature, inorganic foil encapsulated ceramic fiber
blanket duct wrap for use on commercial grease hood duct systems in accordance with
ASTM E2336.
C. A zero inch clearance to combustible construction and two (2) hour fire resistive rated enclosure
system shall be assured.
D. Adhesives: High performance filament tape, one inch wide, and aluminum foil tape to seal cut
edges of blankets.
E. Banding Material: Two (2) hour requirement, ¾” wide, no less than 0.015 inches thick, Type
304 stainless steel, (stainless steel hose clamps, ½ inch may be substituted for hanger
insulations only).
F. Insulation Pins: 10 gage, 4 inches to 5 inches long, copper coated steel no less than 1-1/2 inch
by 1-1/2 inch or 1-1/2 inch diameter galvanized steel speed clip.
G. Fire Stopping Materials: UL No R9464 classified noncombustible fiber with a flame spread of 0,
smoke development of 0 and fuel contribution of 0. Water based, mild chemical resistant putty
complying with ASTM E136-82 may be used.
2.4 ADHESIVES
A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding
insulation to itself and to surfaces to be insulated, unless otherwise indicated.
1. For indoor applications, use adhesive for Flexible Elastomeric, ASJ, and PVC
Jacket that has a VOC content of 50 g/L or less and for Mineral-Fiber Adhesive that
has a VOC content of 80 g/L or less when calculated according to 40 CFR 59,
Subpart D (EPA Method 24).]
2.5 MASTICS
2.6 SEALANTS
A. Joint Sealants:
C. ASJ Flashing Sealants, and Vinyl, PVDC, and PVC Jacket Flashing Sealants:
A. Field-applied jackets shall comply with ASTM C 921, Type I, unless otherwise indicated.
a. Johns Manville; Zeston (Preferred), 300 Series if outdoors, 2000 series if indoors.
b. P.I.C. Plastics, Inc.; FG Series.
c. Proto PVC Corporation; LoSmoke.
d. Speedline Corporation; SmokeSafe.
a. Shapes: 45- and 90-degree, short- and long-radius elbows, tees, valves, flanges,
unions, reducers, end caps, soil-pipe hubs, traps, mechanical joints, and P-trap
and supply covers for lavatories.
D. Aluminum Jacket: Comply with ASTM B 209, Alloy 3003, 3005, 3105 or 5005, Temper H-14.
A. Acceptable Manufacturers:
B. Removable ceramic blanket type with Velcro tabs and box-stitched, 1.5" wide, D-ring straps,
gussets, hot face inner jacketing, type 304 stainless steel tag with laser engraved data riveted to
body, outer jacketing, type 304 stainless steel quilting pins, specifically shaped and constructed
for insulated item.
2.10 TAPES
A. ASJ Tape: White vapor-retarder tape matching factory-applied jacket with acrylic adhesive,
complying with ASTM C 1136.
2. Width: 3 inches.
3. Thickness: 11.5 mils.
4. Adhesion: 90 ounces force/inch in width.
5. Elongation: 2 percent.
6. Tensile Strength: 40 lbf/inch in width.
7. ASJ Tape Disks and Squares: Precut disks or squares of ASJ tape.
B. FSK Tape: Foil-face, vapor-retarder tape matching factory-applied jacket with acrylic adhesive;
complying with ASTM C 1136.
2. Width: 3 inches.
3. Thickness: 6.5 mils.
4. Adhesion: 90 ounces force/inch in width.
5. Elongation: 2 percent.
6. Tensile Strength: 40 lbf/inch in width.
7. FSK Tape Disks and Squares: Precut disks or squares of FSK tape.
C. PVC Tape: White vapor-retarder tape matching field-applied PVC jacket with acrylic adhesive.
Suitable for indoor and outdoor applications.
1. Products: Subject to compliance with requirements, provide one of the following:
2. Width: 2 inches.
3. Thickness: 6 mils.
4. Adhesion: 64 ounces force/inch in width.
5. Elongation: 500 percent.
6. Tensile Strength: 18 lbf/inch in width.
2.11 SECUREMENTS
A. Aluminum Bands: ASTM B 209, Alloy 3003, 3005, 3105, or 5005; Temper H-14, 0.020 inch
thick, 1/2 inch wide with wing or closed seal.
a. Protect ends with capped self-locking washers incorporating a spring steel insert to
ensure permanent retention of cap in exposed locations.
A. PVC Corner Angles: 30 mils thick, minimum 1 by 1 inch, PVC according to ASTM D 1784,
Class 16354-C. White or color-coded to match adjacent surface.
B. Aluminum Corner Angles: 0.040 inch thick, minimum 1 by 1 inch, aluminum according to
ASTM B 209, Alloy 3003, 3005, 3105 or 5005; Temper H-14.
PART 3 - EXECUTION
3.1 PREPARATION
A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will
adversely affect insulation application.
B. Coordinate insulation installation with the trade installing heat tracing. Comply with
requirements for heat tracing that apply to insulation.
C. Mix insulating cements with clean potable water; if insulating cements are to be in contact with
stainless-steel surfaces, use demineralized water.
A. Install insulation materials, accessories, and finishes with smooth, straight, and even surfaces;
free of voids throughout the length of equipment, ducts and fittings, and piping including fittings,
valves, and specialties.
B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses required
for each item of equipment, duct system, and pipe system as specified in insulation system
schedules.
C. Install accessories compatible with insulation materials and suitable for the service. Install
accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or
dry state.
D. Install insulation with longitudinal seams at top and bottom of horizontal runs.
E. Install multiple layers of insulation with longitudinal and end seams staggered.
F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties.
H. Install insulation with tight longitudinal seams and end joints. Bond seams and joints with
adhesive recommended by insulation material manufacturer.
J. Where vapor barrier is indicated (all cold work at a minimum, and it shall be continuous), seal
joints, seams, and penetrations in insulation at hangers, supports, anchors, and other
projections with vapor-barrier mastic.
1. Install insulation continuously through hangers and around anchor attachments.
2. For insulation application where vapor barriers are indicated, extend insulation on anchor
legs from point of attachment to supported item to point of attachment to structure. Taper
and seal ends at attachment to structure with vapor-barrier mastic.
3. Install insert materials and install insulation to tightly join the insert. Seal insulation to
insulation inserts with adhesive or sealing compound recommended by insulation
material manufacturer.
4. Cover inserts with jacket material matching adjacent pipe insulation. Install shields over
jacket, arranged to protect jacket from tear or puncture by hanger, support, and shield.
K. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet
and dry film thicknesses.
M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its nominal
thickness.
N. Finish installation with systems at operating conditions. Repair joint separations and cracking
due to thermal movement.
O. Repair damaged insulation facings by applying same facing material over damaged areas.
Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches
similar to butt joints.
1. Vibration-control devices.
2. Testing agency labels and stamps.
3. Nameplates and data plates.
4. Manholes.
5. Handholes.
6. Cleanouts.
3.3 PENETRATIONS
D. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated):
Install insulation continuously through walls and partitions.
1. Duct: Install insulation continuously through floor penetrations that are not fire rated. For
penetrations through fire-rated assemblies, terminate insulation at fire damper sleeves
and externally insulate damper sleeve beyond floor to match adjacent duct insulation.
Overlap damper sleeve and duct insulation at least 2 inches.
2. Pipe: Install insulation continuously through floor penetrations.
3. Seal penetrations through fire-rated assemblies. Comply with requirements in
Division 07 Section "Penetration Firestopping."
1. Fabricate metal boxes lined with insulation. Fit boxes around pumps and coincide box
joints with splits in pump casings. Fabricate joints with outward bolted flanges. Bolt
flanges on 6-inch centers, starting at corners. Install 3/8-inch- diameter fasteners with
wing nuts. Alternatively, secure the box sections together using a latching mechanism.
2. Fabricate boxes from aluminum, at least 0.050 inch thick.
3. For below ambient services, install a vapor barrier at seams, joints, and penetrations.
Seal between flanges with replaceable gasket material to form a vapor barrier.
3.4 GENERAL PIPE INSULATION INSTALLATION
A. Requirements in this article generally apply to all insulation materials except where more
specific requirements are specified in various pipe insulation material installation articles.
1. Install insulation over fittings, valves, strainers, flanges, unions, and other specialties with
continuous thermal and vapor-retarder integrity, unless otherwise indicated.
2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made from same
material and density as adjacent pipe insulation. Each piece shall be butted tightly
against adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular
surfaces with insulating cement finished to a smooth, hard, and uniform contour that is
uniform with adjoining pipe insulation.
3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation of same
material and thickness as used for adjacent pipe. Cut sectional pipe insulation to fit. Butt
each section closely to the next and hold in place with tie wire. Bond pieces with
adhesive.
4. Insulate valves using preformed fitting insulation or sectional pipe insulation of same
material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe
insulation by not less than two times the thickness of pipe insulation, or one pipe
diameter, whichever is thicker. For valves, insulate up to and including the bonnets,
valve stuffing-box studs, bolts, and nuts. Fill joints, seams, and irregular surfaces with
insulating cement.
5. Insulate strainers using preformed fitting insulation or sectional pipe insulation of same
material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe
insulation by not less than two times the thickness of pipe insulation, or one pipe
diameter, whichever is thicker. Fill joints, seams, and irregular surfaces with insulating
cement. Insulate strainers so strainer basket flange or plug can be easily removed and
replaced without damaging the insulation and jacket. Provide a removable reusable
insulation cover. For below ambient services, provide a design that maintains vapor
barrier.
6. Insulate flanges and unions using a section of oversized preformed pipe insulation.
Overlap adjoining pipe insulation by not less than two times the thickness of pipe
insulation, or one pipe diameter, whichever is thicker.
7. Cover segmented insulated surfaces with a layer of finishing cement and coat with a
mastic. Install vapor-barrier mastic for below ambient services and a breather mastic for
above ambient services. Reinforce the mastic with fabric-reinforcing mesh. Trowel the
mastic to a smooth and well-shaped contour.
8. For services not specified to receive a field-applied jacket except for flexible elastomeric,
install fitted PVC cover over elbows, tees, strainers, valves, flanges, and unions.
Terminate ends with PVC end caps. Tape PVC covers to adjoining insulation facing
using PVC tape.
9. Label the outside insulation jacket of each union with the word "UNION." Match size and
color of pipe labels.
C. Insulate instrument connections for thermometers, pressure gages, pressure temperature taps,
test connections, flow meters, sensors, switches, and transmitters on insulated pipes, vessels,
and equipment. Shape insulation at these connections by tapering it to and around the
connection with insulating cement and finish with finishing cement, mastic, and flashing sealant.
D. Install removable insulation covers at locations indicated. Installation shall conform to the
following:
1. Make removable flange and union insulation from sectional pipe insulation of same
thickness as that on adjoining pipe. Install same insulation jacket as adjoining pipe
insulation.
2. When flange and union covers are made from sectional pipe insulation, extend insulation
from flanges or union long at least two times the insulation thickness over adjacent pipe
insulation on each side of flange or union. Secure flange cover in place with stainless-
steel or aluminum bands. Select band material compatible with insulation and jacket.
3. Construct removable valve insulation covers in same manner as for flanges except divide
the two-part section on the vertical center line of valve body.
4. When covers are made from block insulation, make two halves, each consisting of
mitered blocks wired to stainless-steel fabric. Secure this wire frame, with its attached
insulation, to flanges with tie wire. Extend insulation at least 2 inches over adjacent pipe
insulation on each side of valve. Fill space between flange or union cover and pipe
insulation with insulating cement. Finish cover assembly with insulating cement applied
in two coats. After first coat is dry, apply and trowel second coat to a smooth finish.
5. Unless a PVC jacket is indicated in field-applied jacket schedules, finish exposed
surfaces with a metal jacket.
A. Seal longitudinal seams and end joints with manufacturer's recommended adhesive to eliminate
openings in insulation that allow passage of air to surface being insulated.
1. Install preformed valve covers manufactured of same material as pipe insulation when
available.
2. When preformed valve covers are not available, install cut sections of pipe and sheet
insulation to valve body. Arrange insulation to permit access to packing and to allow
valve operation without disturbing insulation.
3. Install insulation to flanges as specified for flange insulation application.
4. Secure insulation to valves and specialties and seal seams with manufacturer's
recommended adhesive to eliminate openings in insulation that allow passage of air to
surface being insulated.
3.6 MINERAL-FIBER INSULATION INSTALLATION
1. Secure each layer of preformed pipe insulation to pipe with wire or bands and tighten
bands without deforming insulation materials.
2. Where vapor barriers are indicated, seal longitudinal seams, end joints, and protrusions
with vapor-barrier mastic and joint sealant.
3. For insulation with factory-applied jackets secure tabs with additional adhesive as
recommended by insulation material manufacturer and seal with vapor-barrier mastic and
flashing sealant.
1. Install preformed sections of same material as straight segments of pipe insulation when
available.
2. When preformed insulation elbows and fittings are not available, install mitered sections
of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure insulation
materials with wire or bands.
1. Install preformed sections of same material as straight segments of pipe insulation when
available.
2. When preformed sections are not available, install mitered sections of pipe insulation to
valve body.
3. Arrange insulation to permit access to packing and to allow valve operation without
disturbing insulation.
4. Install insulation to flanges as specified for flange insulation application.
E. Blanket and Board Insulation Installation on Ducts and Plenums: Secure with adhesive and
insulation pins.
a. On duct sides with dimensions 18 inches and smaller, place pins along longitudinal
centerline of duct. Space 3 inches maximum from insulation end joints, and 16
inches o.c.
b. On duct sides with dimensions larger than 18 inches, place pins 16 inches o.c.
each way, and 3 inches maximum from insulation joints. Install additional pins to
hold insulation tightly against surface at cross bracing.
c. Pins may be omitted from top surface of horizontal, rectangular ducts and
plenums.
d. Do not over-compress insulation during installation.
e. Impale insulation over pins and attach speed washers.
f. Cut excess portion of pins extending beyond speed washers or bend parallel with
insulation surface. Cover exposed pins and washers with tape matching insulation
facing.
4. For ducts and plenums with surface temperatures below ambient, install a continuous
unbroken vapor barrier. Create a facing lap for longitudinal seams and end joints with
insulation by removing 2 inches from 1 edge and 1 end of insulation segment. Secure
laps to adjacent insulation section. Install vapor barrier consisting of factory- or field-
applied jacket, adhesive, vapor-barrier mastic, and sealant at joints, seams, and
protrusions.
a. Repair punctures, tears, and penetrations with tape or mastic to maintain vapor-
barrier seal.
b. Install vapor stops for ductwork and plenums operating below 50 deg F at 18-foot
intervals. Vapor stops shall consist of vapor-barrier mastic applied in a Z-shaped
pattern over insulation face, along butt end of insulation, and over the surface.
Cover insulation face and surface to be insulated a width equal to 2 times the
insulation thickness but not less than 3 inches.
5. Overlap unfaced blankets a minimum of 2 inches on longitudinal seams and end joints.
At end joints, secure with steel bands spaced a maximum of 18 inches o.c.
6. For Blanket Insulation Install insulation on rectangular duct elbows and transitions with a
full insulation section for each surface. Install insulation on round and flat-oval duct
elbows with individually mitered gores cut to fit the elbow.
7. For Board Insulation, install insulation on rectangular duct elbows and transitions with a
full insulation section for each surface. Groove and score insulation to fit as closely as
possible to outside and inside radius of elbows. Install insulation on round and flat-oval
duct elbows with individually mitered gores cut to fit the elbow.
8. Insulate duct stiffeners, hangers, and flanges that protrude beyond insulation surface with
6-inch- wide strips of same material used to insulate duct. Secure on alternating sides of
stiffener, hanger, and flange with pins spaced 6 inches o.c.
B. Where PVC jackets are indicated, install with 1-inch overlap at longitudinal seams and end
joints; for horizontal applications, install with longitudinal seams along top and bottom of tanks
and vessels. Seal with manufacturer's recommended adhesive.
1. Apply two continuous beads of adhesive to seams and joints, one bead under lap and the
finish bead along seam and joint edge.
C. Where metal jackets are indicated, install with 2-inch overlap at longitudinal seams and end
joints. Overlap longitudinal seams arranged to shed water. Seal end joints with weatherproof
sealant recommended by insulation manufacturer. Secure jacket with stainless-steel bands 12
inches o.c. and at end joints.
3.8 FINISHES
A. Duct, Equipment, and Pipe Insulation with ASJ or Other Paintable Jacket Material: Paint jacket
with paint system identified below and as specified in Division 09 Painting Sections.
1. Flat Acrylic Finish: Two finish coats over a primer that is compatible with jacket material
and finish coat paint. Add fungicidal agent to render fabric mildew proof.
B. Flexible Elastomeric Thermal Insulation: After adhesive has fully cured, apply two coats of
insulation manufacturer's recommended protective coating.
C. Color: Final color as selected by Architect. Vary first and second coats to allow visual
inspection of the completed Work.
C. All insulation applications will be considered defective Work if sample inspection reveals
noncompliance with requirements.
3.10 DUCT INSULATION SCHEDULE, GENERAL [EOR TO FINAL DETERMINE ALL]
A. Plenums and Ducts Requiring Insulation: [EDIT TO MATCH 3.11 AND BEYOND FOR EACH
JOB]
1. Metal ducts with duct liner of sufficient thickness to comply with energy code and
ASHRAE/IESNA 90.1.
2. Factory-insulated flexible ducts.
3. Factory-insulated plenums and casings.
4. Flexible connectors.
5. Vibration-control devices.
6. Factory-insulated access panels and doors.
3.11 INDOOR DUCT AND PLENUM INSULATION SCHEDULE [EOR TO FINAL DETERMINE
ALL]
A. Concealed, Supply-Air Duct and Plenum Insulation: Mineral-fiber blanket, 1-1/2 inches thick
and 0.75-lb/cu. ft. nominal density.
B. Exposed (in finished spaces), Supply-Air Duct and Plenum Insulation: Mineral-fiber blanket, 1-
1/2 inches thick and 0.75-lb/cu. ft. nominal density.
D. Concealed, Outdoor Air Duct and Plenum Insulation: Mineral-fiber blanket, 1-1/2 inches thick
and 0.75-lb/cu. ft. nominal density.
F. Concealed or Exposed Exhaust and Relief Between Isolation Damper and Penetration of
Building Exterior, and Within 20' of the Building Exterior: Mineral-fiber blanket, 2 inches thick
and 0.75-lb/cu. ft. nominal density.
G. Kitchen Hood exhaust ducts shall be insulated with minimum 2-hour rated grease duct wrap.
A. Insulation materials and thicknesses are identified below. If more than one material is listed for
a duct system, selection from materials listed is Contractor's option.
B. Exposed, Supply-Air and Return-Air Duct and Plenum Insulation: Mineral-fiber board, 3 inches
thick and 6-lb/cu. ft. nominal density.
3.13 EQUIPMENT INSULATION SCHEDULE [EOR TO FINAL DETERMINE ALL]
A. Insulation materials and thicknesses are identified below. If more than one material is listed for
a type of equipment, selection from materials listed is Contractor's option.
B. Insulate indoor and outdoor equipment in paragraphs below that is not factory insulated.
C. Circuit Setters: Insulate with pre-formed insulation sections specifically designed for the specific
circuit setters, and adjacent piping insulation and jacketing shall butt to same, and be sealed.
E. Heating-Hot-Water Pump Insulation: Mineral-Fiber Board/Pipe and Tank: 2 inches thick and 3-
lb/cu. ft. nominal density.
G. Re-heat Coils: VAV and FPVAV reheat coil sections shall have field installed insulation, coving
the exposed coil u-bends on both sides of the coil section, coil headers, and the entire reheat
section.
A. Acceptable preformed pipe and tubular insulation materials and thicknesses are identified for
each piping system and pipe size range. If more than one material is listed for a piping system,
selection from materials listed is Contractor's option.
B. Items Not Insulated: Unless otherwise indicated, do not install insulation on the following:
3.15 INDOOR PIPING INSULATION SCHEDULE [EOR TO FINAL DETERMINE ALL DEPENDING
ON CAMPUS, ETC]
A. Chilled Water and Refrigerant Suction: Insulation shall be one of the following:
1. Flexible Elastomeric
2. Mineral-Fiber, Preformed Pipe, Type I
3. Insulation Density (if Mineral-Fiber): XXX
4. Insulation Thickness
a. XXX
a. XXX
a. XXX
a. XXX
a. XXX
F. Pipe insulation subject to maintenance personnel traffic or within 60" of the floor in mechanical
type spaces shall be minimum 12 pcf density (with a maximum conductivity of 0.45 BTU -
inch/(hr-sf-F) at 100°F) and is to be PVC (30 mil thick Series 300) or metal jacketed with
waterproof seams and joints. Thicknesses to be as follows (thickness derived normally from
ASHRAE 90.1-2007/required thickness): (1"/2").
A. Install jacket over insulation material. For insulation with factory-applied jacket, install the field-
applied jacket over the factory-applied jacket.
B. Piping, Exposed:
A. Chilled Water and Refrigerant Suction: Insulation shall be one of the following:
1. Flexible Elastomeric
2. Mineral-Fiber, Preformed Pipe, Type I
3. Insulation Density (if Mineral-Fiber): XXX
4. Insulation Thickness
B. Heating-Hot-Water Supply and Return, 200 Deg F and below: Insulation shall be:
a. XXX
a. XXX
A. Install jacket over insulation material. For insulation with factory-applied jacket, install the field-
applied jacket over the factory-applied jacket. Installation to be waterproof.
B. If more than one material is listed, selection from materials listed is Contractor's option.
E. Piping, Exposed:
A. Use to cover steam valves, chilled water valves, heating hot water valves, steam expansion
joints, condensate pump package receivers, heat exchanger faces, flash tanks, hurling tanks
and similar vessels, and awkward surfaces not covered by insulation.
A. Each pump to be covered by minimum of 1" thick AP Armaflex (or thicker to eliminate
condensation) applied with a waterproof adhesive. Removable components shall use Velcro
applied to both the pump body and the insulation with waterproof adhesive such that pieces can
be removed for servicing and inspection and re-installed without damage.
A. Each pump to be covered by minimum of 1" thick fiberglass pipe and tank insulation applied
with a high temperature adhesive and finish jacketing and banding/wiring. Removable
components shall use Velcro applied to both the pump body and the insulation with high
temperature adhesive such that pieces can be removed for servicing and inspection and re-
installed without damage.
A. Each chiller to be covered by minimum of 1" thick AP Armaflex (or thicker to eliminate
condensation) applied with a waterproof adhesive. Removable components shall use Velcro
applied to both the pump body and the insulation with waterproof adhesive such that pieces can
be removed for servicing and inspection and re-installed without damage.
A. Each convertor to be covered by removable insulation covers such that pieces can be removed
for servicing and inspection and re-installed without damage (for heat exchanger face only).
C. High pressure steam and condensate return piping within buildings shall be insulated with
1200°F rated mineral wool piping insulation ASTM-C547 with factory vapor barrier jacket.
D. Provide stainless steel jacketing over factory vapor barrier covering for all piping in the vaults for
entire straight lengths and jacket over PVC elbow and valve covers. Refer to specification of
stainless steel coverings below. Insulation K factor shall be minimum of 0.23 at 75°F per ASTM
C335. Thickness shall be 1.5" for piping up to 4" and 2" thick for piping 5" and larger. Provide
calcium silicate 120° segment at points of support (under insulation protection shield). Insulation
protection shield shall be installed over stainless steel jacketing.
E. High pressure steam and condensate return piping within vaults shall be insulated using IIG
(Industrial Insulation Group, LLC) thermo-12 gold pre- formed, 1200°F rated pipe and block
insulation composed of hydrous calcium silicate which is inorganic, non-combustible, and meets
ASTM C533 and ASTM C411, Type 1. Thermal conductivity shall be 0.45 btu*in/(hr*ft*°f)at
300°F. Cover all insulated piping and fittings withing vault with stainless steel jacketing (see
below).
F. If physical constraints will not allow the above thicknesses to be installed, contractor shell
provide an equivalent insulating value thickness of Pyrogel XTF. Cover insulation with minimum
2 coats of wettable fabric.
G. Insulation shall be applied using manufacturer approved material and methods. Adhesives shall
be waterproof retardant type in compliance with ASTM E84, NFPA 255 and UL 723.
H. No insulation shall be applied until after the system has been properly tested in presence of
owner's representative. Ductwork shall be sealed, tested and proved air tight prior to insulation
application.
I. No piping shall be insulated until pressure testing has been completed and accepted by the
owner.
J. Insulate all valves and pipe fittings except omit insulation on the following: unions, traps and
strainer blow-off valves.
K. Pipe fittings shall be covered with same thickness of insulation as the pipe and wrapped with
wettable cloth fabric and sealed with approved adhesive.
L. Equipment to be insulated shall include all equipment which is a part of the piping system. Such
includes but is not limited to: flash tanks.
M. New and existing insulated piping within manholes shall be enclosed with 304 stainless steel
jacket with prefabricated stainless steel fitting covers. Jacket shall be provided with stainless
steel straps at 12" O.C. seams shall be arranged to shed water, shall overlap shall be caulked
with weather resistant industrial quality clear sealant. Jacket thickness shall be 0.16" up to 6"
O.D. (including insulation) and 0.20" thick for piping with O.D. greater than 6". Metal jacketing
shall be by ITW (ITWINSINSULATIONS.COM) or equal. Cover all valves and fittings located
outside with same insulation type and thickness as piping. Installed custom fabricated or pre-
fabricated valve jacketing covering entire valve and leaving only operating handle. Seal water
tight with mastiques and sealant such that no insulation can become wet. Aluminum jacketing
and PVC covers within manholes are not acceptable. Use of PVC covers within manholes is
prohibited.
O. PVC factory insulation fitting and straight pipe covers for pipe fittings and valves: proto
"Losmoke" fabricated of ASTM 1784 polyvinyl chloride. 160°F rated with 25/50 fire/smoke rating
per ASTM E-84, bright gloss white. Fitting covers shall be commercial grade thickness. "light
gauge" commercial thickness covers are not acceptable. Install covers using manufacturer-
furnished adhesive mastic and sealant. Contractor shall use cover manufacturer furnished
fiberglass insulation inserts for each specific application with fiberglass having k=0.26 at 75°F
per ASTM C177. All fitting covers shall be one-piece. Space between PVC covers and piping
shall be filled tightly with insulation.
Q. When connecting new piping to existing piping within manhole existing insulation covering
entire straight run of pipe to which new piping connects shall be stripped of the existing
insulation and new insulation and jacketing in accordance with the specification shall be
provided to the entire straight piece of existing pipe to which new pipe connects.
R. Where anchor is installed in the existing piping in the existing manhole, the straight run of pipe
to which anchor is installed shall be stripped of existing insulation and new insulation and
jacketing in accordance with the specification shall be provided to straight pipe.
S. Valves shall be insulated entirely leaving only stem and handle. Valves shall be operable
without disturbing insulation. Should the insulating contractor notice that the valves installed by
mechanical contractor cannot be properly insulated due to lack of extended handle, insulating
contractor shall not insulate such valves until proper size handle has been installed by
mechanical contractor. Do not insulate pipe unions and steam traps. Provide neat 45 degree
taper at each side of union or trap.
T. Insulation shall be sealed with manufacturer's approved sealant and shall have neat finished
appearance. No exposed insulation shall be visible.
U. At wall penetrations by high pressure steam piping provide calcium silicate ASTM C533 rigid
white insulation
GENERAL
1.1 SUMMARY
The purpose of this section is to specify the Division 23 responsibilities and participation in the
Commissioning Process.
Work under this contract shall conform to requirements of Division 01, General Requirements,
Conditions of the Contract, and Supplementary Conditions. This specification covers
commissioning of mechanical systems which are part of this project.
Commissioning work shall be a team effort to ensure that all mechanical equipment and
systems have been completely and properly installed, function together correctly to meet the
design intent, and document system performance. Commissioning shall coordinate system
documentation, equipment start-up, control system calibration, testing and balancing, and
verification and performance testing.
The Commissioning Team shall be made up of representatives from the owner, Design Team,
General Contractor (GC), manufacturers, and construction trades. The trades represented on
the Commissioning Team shall include, but not be limited to: sheet metal, piping and fitting,
controls, test and balance, and electrical. The lead person for each trade who will actually
perform or supervise the work is to be designated as the representative to the Commissioning
Team. Responsibility for various steps of the Commissioning Process shall be divided among
the members of the Commissioning Team, as described in this section.
The Commissioning Authority (CxA) shall have responsibility for coordinating and directing each
step of the Commissioning Process.
Mechanical system installation, start-up, testing, balancing, preparation of O&M manuals, and
operator training are the responsibility of the Division 23 Contractors, with coordination,
observation, verification and commissioning the responsibility of Division 01, Section 01 9113.
The 01 9113 Commissioning Process does not relieve Division 23 from the obligations to
complete all portions of work in a satisfactory and fully operational manner.
Refer to Division 01, Section 01 9113, for a full list of commissioning related definitions. A few
critical definitions are included below:
Individual Division 01, 21, 22, 23, 25, and 26 sections contain requirements related to the
commissioning process.
Refer to Section 01 9113 for Commissioning Authority, Owner, Architect, and General Contractor
roles and responsibilities.
Refer to Section 21 0800 for fire protection contractor roles and responsibilities.
Refer to Section 25 0800 for integrated automation contractor roles and responsibilities.
Design Team
1. Provide documentation of initial design concepts and Design Intent based on Owner’s
program.
2. Provide mechanical system design parameters and obtain approval of Owner.
3. Prepare contract documents incorporating Commissioning Specification requirements
and description of the electrical systems.
4. The Design Team shall specify and verify adequate maintenance accessibility for each
piece of equipment in shop drawings and the actual installation.
5. Periodic inspections as part of the Design Team’s contract with the Architect and/or Owner.
6. Review and approve submittals.
7. Participate in commissioning meetings.
8. Review Pre-functional Checklists and Functional Performance Test procedures submitted
by the Commissioning Authority.
9. Prepare punch lists.
10. Review as-built records as required by contract documents. Issue a report noting
deficiencies requiring correction to the Commissioning Authority.
11. Review and comment on final commissioning report.
Mechanical Contractor
1. Include cost to complete commissioning requirements for mechanical systems in the
contract price.
2. Include requirements for submittal data, O&M data, and training in each purchase order
or sub contract written.
3. Ensure cooperation and participation of all subcontractors.
4. Ensure participation of major equipment manufacturers in appropriate training and testing
activities.
5. Attend Construction Phase coordination meeting scheduled by the Commissioning
Authority.
6. Conduct mechanical system orientation and inspection when equipment is set.
7. Respond to (in writing) and address items documented in the Contractor Commissioning
Issues Log.
8. Notify the GC a minimum of two weeks in advance of system start-up and testing, so CxA
may be on site to witness.
9. Notify the GC a minimum of two weeks in advance, of the time for start of the TAB work.
Attend the initial TAB meeting for review of the TAB procedures.
10. Submit copies of all test results to the CxA.
11. Complete Pre-Functional Checklists for all equipment.
12. Assist the Commissioning Authority in all Pre-Functional Checklist verifications and
Functional Performance Tests.
13. Prepare preliminary schedule for mechanical system orientation and inspections, O&M
manual submission, training sessions, pipe and duct system testing, flushing and
cleaning, equipment start up, TAB, and task completion for use by the GC and
Commissioning Authority. Update schedule as appropriate throughout the construction
period.
14. Conduct mechanical system orientation and inspection when equipment is set in place.
15. Keep drawings updated as changes in the field are made, and review with the GC and
Commissioning Authority.
16. Gather O&M data on all equipment, and assemble in binders as required by the
Commissioning Specification. Submit to GC for review prior to the completion of
construction.
17. Participate in, and schedule vendors and Contractors to participate in the training
sessions as set up by the GC.
18. Provide written notification to the General Contractor and Commissioning Authority that
the following work has been completed in accordance with the contract documents, and
that the equipment, systems, and sub-systems are functioning as required.
a. HVAC equipment including all fans, air handling units, dehumidification units,
ductwork, dampers, terminals, and all Division 23 equipment.
b. Refrigeration equipment, pumping systems and heat rejection equipment.
c. Fire stopping in the fire rated construction, including fire and smoke damper
installation, caulking, gasketing and sealing of smoke barriers.
d. Dedicated smoke control systems including stairway pressurization and atrium
systems.
e. Non-dedicated systems using the air handling units for smoke control.
f. Fire detection and smoke detection devices furnished under other divisions of this
specification as they affect the operation of the smoke control systems.
g. That building control systems are functioning to control mechanical equipment and
smoke control systems.
1. Include cost for commissioning requirements in the contract price, including assisting the
Commissioning Authority with implementation of Functional Test Procedures and
reviewing control system operation with the Commissioning Authority.
2. Review design for controllability with respect to selected manufacturer’s equipment:
The work included in the Commissioning Process involves a complete and thorough evaluation
of the operation and performance of all components, systems, and sub-systems. The following
equipment and systems shall be evaluated:
Timely and accurate documentation is essential for the Commissioning Process to be effective.
Documentation required as part of the Commissioning Process shall include but not be limited to:
Detailed testing maybe performed on all installed equipment and systems to ensure that
operation and performance conform to contract documents. All tests shall be witnessed by the
Commissioning Authority. The following testing is required as part of the Commissioning
process:
1. Pre-Functional Checklists (PFC) are comprised of a full range of checks and tests to
determine that all components, equipment, systems, and interfaces between systems
operate in accordance with contract documents. Verification is completed by the Division
22, 23 and 26 contractors and documented using Pre-Functional Checklists.
2. Functional Performance Tests (FPT) shall determine if the HVAC system is operating in
accordance with the design intent. This includes all operating modes, interlocks, control
responses, and specific responses to abnormal or emergency conditions.
1.5 DOCUMENTATION
The Commissioning Authority shall oversee and maintain the development of the document
process. The GC shall facilitate project documentation through the web-based commissioning
software. The commissioning documentation shall include, but not be limited to, the following:
1. Commissioning Plan
2. Commissioning Schedule
3. Document Request Log
4. Commissioning RFIs
5. Commissioning Field Reports on the WCxS
6. Design Team Issues Log on the WCxS
7. Contractor Commissioning Issues Log on the WCxS
8. Pre-Functional Checklists on the WCxS
9. Functional Performance Tests on the WCxS
10. See 01 9113 for additional information on the commissioning documentation.
PRODUCTS
The appropriate Contractor(s) shall furnish all special tools and equipment required for testing
during the commissioning process. A list of all tools and equipment to be used during
commissioning shall be submitted to the Commissioning Authority for approval. The owner shall
furnish necessary utilities for the Commissioning Process.
Proprietary test equipment and software required by any equipment manufacturer for
programming and/or start-up, whether specified or not, shall be provided by the manufacturer of
the equipment. Manufacturer shall provide the test equipment, demonstrate its use, and assist
in the Commissioning Process as needed. Proprietary test equipment (and software) shall
become the property of the owner upon completion of the Commissioning Process.
EXECUTION
3.1 GENERAL
A pre-construction meeting of all Commissioning Team members shall be held at a time and
place designated by the owner. The purpose shall be to familiarize all parties with the
Commissioning Process, and to ensure that the responsibilities of each party are clearly
understood.
The Contractor shall complete all phases of work so the systems can be started, tested,
balanced, and commissioning procedures undertaken. This includes the complete installation of
all equipment, materials, pipe, duct, wire, insulation, controls, etc., per the contract documents
and related directives, clarifications, and change orders.
Acceptance procedures are normally intended to begin prior to completion of a system and/or
sub-systems, and shall be coordinated with the Division 23 contractor. Start of acceptance
procedures before system completion does not relieve the contractor from completing those
systems as per the schedule.
The Contractor shall provide skilled technicians to start-up and debug all systems within Division
15. These same technicians shall be made available to assist the Commissioning Authority in
completing the commissioning program. Work schedules, time required for testing, etc., shall be
requested by the Commissioning Authority and coordinated by the contractor. Contractor shall
ensure that the qualified technician(s) are available and present during the agreed upon
schedules and of sufficient duration to complete the necessary tests, adjustments, and/or
problem resolutions.
System performance problems and discrepancies may require additional technician time,
Commissioning Authority time, reconstruction of systems, and/or replacement of system
components. The additional technician time shall be made available for subsequent
commissioning periods until the required system performance is obtained.
The Commissioning Authority reserves the right to question the appropriateness and
qualifications of the technicians relative to each item of equipment, system, and/or sub-system.
Qualifications of technicians shall include expert knowledge relative to the specific equipment
involved and a willingness to work with the Commissioning Authority. Contractor shall provide
adequate documentation and tools to start up and test the equipment, system, and/or sub-
system.
Corrective work shall be completed in a timely fashion to permit the completion of the
Commissioning Process. Experimentation to demonstrate system performance may be
permitted. If the Commissioning Authority deems the experimentation work to be ineffective or
untimely as it relates to the Commissioning Process, the Commissioning Authority shall notify
the Owner, indicating the nature of the problem, expected steps to be taken, and suggested
deadline(s) for completion of activities. If the deadline(s) pass without resolution of the problem,
the Owner reserves the right to obtain supplementary services and/or equipment to resolve the
problem. Costs incurred to solve the problems in an expeditious manner shall be the
contractor’s responsibility.
The Owner’s contract with the Commissioning Authority includes up to two Functional
Performance Tests of each piece of equipment or system included in the commissioning scope.
Commissioning Authority time and expenses required for retests beyond two, if required, due to
incomplete installation or otherwise, will be paid by the Owner and reimbursed by the
contractor.
Seasonal commissioning pertains to testing under full load conditions during peak heating and
peak cooling seasons, as well as part load conditions during off-peak periods. Initial
commissioning shall be done as soon as contract work is completed, regardless of season.
Subsequent commissioning may be undertaken at any time thereafter to ascertain adequate
performance during the different peak and off-peak conditions. Each contractor and
manufacturer shall be responsible to participate in the initial and the alternate peak and off-peak
tests of the systems as required to demonstrate performance.
1. The Commissioning Authority will conduct periodic observations during the Construction
Phase to monitor progress and compliance with the design intent and contract
documents. It is the responsibility of the contractor to address the issues noted on the
Issues Log and notify Commissioning Authority of completion.
2. Commissioning Authority observations will coincide with Design Team observations and
are not intended to take the place of this work.
Pre-Functional Checklists
1. The Commissioning Authority shall select, at random, 10 percent of the report data for
verification.
2. The TAB contractor shall be given sufficient advance notice of the date of field
verification. However, they shall not be informed in advance of the data points to be
verified.
3. Failure of an item is defined as:
a. For all readings other than sound, a deviation of more than 10 percent.
b. For sound pressure readings, a deviation of 3 decibels. (Note: variations in
background noise must be considered).
4. A failure of more than 10 percent of the selected items shall result in the rejection of the
final TAB report.
a. Participants in the Functional Performance Tests shall be the same as those listed
in the Pre-Functional Checklists.
1) Set the system equipment (i.e. chiller, boiler, pumps, fans, etc.) into the
operating mode to be tested (i.e. normal shut-down, normal auto position,
normal manual position, unoccupied cycle, emergency power, and alarm
conditions).
2) The Commissioning Authority shall inspect and verify the position of each
device and interlock identified in the test procedure. Each item shall be
signed off as acceptable (yes) or failed (no).
3) This test shall be repeated for each operating cycle that applies to the
mechanical system being tested.
4) Operating checks shall include all safety cutouts, alarms, and interlocks with
smoke control and life safety systems during all modes of operation of the
mechanical system.
5) If during a test an operating deficiency is observed, appropriate comments
will be added to the Test Procedure form and the Issues Log.
6) Confirmation of the TAB results shall be verified utilizing the Building
Automation System. This shall include, but not be limited to, the following:
a) Verify supply and return flow rates for VAV and constant volume
systems in all modes of operation of the HVAC system.
b) Verify operation of the terminal units in both heating and cooling cycles.
c) Verify minimum outdoor air intake in all modes of operation and at
minimum and maximum total airflow rates.
d) Verify building pressurization.
e) Verify total exhaust airflow, and total outdoor air intake.
a. All measured data, data sheets, and a comprehensive summary, describing the
operation of the HVAC system at the time of testing shall be submitted to the
Commissioning Authority.
b. A preliminary Functional Performance Test report shall be prepared by the
Commissioning Authority and submitted to the Design Team for review. Any
identified deficiencies need to be evaluated by the Design Team and General
Contractor to determine if they are part of the contractor’s or sub-contractor’s
contractual obligations. Construction deficiencies shall be corrected by the
responsible contractor(s), and the specific Functional Performance Test repeated.
c. If it is determined that the HVAC system is constructed in accordance with the
contract documents, and the performance deficiencies are not part of the contract
documents, the Owner must decide whether any required modifications needed to
bring the performance of the HVAC system up to the finalized design intent shall
be implemented, or if the test shall be accepted as submitted. If corrective work is
performed, the owner shall determine if a portion or all required Functional
Performance Tests should be repeated, and a revised report submitted.
The Systems Manual shall be submitted in paper AND/OR electronic format and shall contain the
following major sections:
1. System Descriptions:
2. Operating Instructions:
b. The instructions shall be suitable for posting adjacent to the equipment concerned.
c. The contractor shall provide instructions for (at minimum):
1) Weekly
2) Monthly
3) Quarterly
4) Semi Annual
5) Annual
6) Other
1. Operating Instructions:
a. Simplified one (1) line diagrams of the systems listed shall be developed using
AutoCAD and posted neatly under Plexiglas in the main or most appropriate
equipment room for easy reference by operating and maintenance personnel.
These drawings shall be done in a professional manner which is acceptable to the
Owner. The diagrams shall show each component including all valves installed in
the system, with name and identifying number. If space does not permit valve
numbers on the diagrams, valve charts shall be provided. Explanatory notes,
where needed, shall be provided.
b. These diagrams shall be suitable for reduction in size and use in the Systems
Manual system descriptions previously covered.
a. Design intent
b. Occupied vs. unoccupied or partial occupancy
c. Seasonal modes of operation
d. Emergency conditions and procedures
e. Comfort conditions
f. Indoor air quality
g. Energy efficiency
h. Other issues important to facility operation
3. System operations
4. Use of control system
a. Sequence of operation
b. Problem indicators
c. Diagnostics
d. Corrective actions
The contractor shall provide, at or before substantial completion, a proposed agenda and
schedule of the above training for approval by the Commissioning Authority and the Owner.
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes pipe and fitting materials, joining methods, special-duty valves, and
certain specialties for the following:
B. Related Section:
A. Hydronic piping components and installation shall be capable of withstanding the following
minimum working pressure and temperature:
1.3 SUBMITTALS
B. [LEED Submittal:
1. Product Data for Credit EQ 4.1: For solvent cements and adhesive primers,
including printed statement of VOC content.]
C. Shop Drawings: Detail the piping layout, fabrication of pipe anchors, hangers, supports for
multiple pipes, alignment guides, expansion joints and loops, and attachments of the same to
the building structure. Detail location of anchors, alignment guides, and expansion joints and
loops.
A. ASME Compliance: Comply with ASME B31.9, "Building Services Piping," for materials,
products, and installation.
B. To assure uniformity and compatibility of piping components in grooved end piping systems, all
grooved products utilized shall be supplied by the same manufacturer. Grooving tools shall be
supplied by the same manufacturer as the grooved components.
C. Piping materials shall bear label, stamp, or other markings of specified testing agency, and shall
conform to ASTM standards.
D. Comply with FM Global requirements for pressure vessels and piping and for pressure relief
devices.
PART 2 - PRODUCTS
1. Pipe: API-5L, Grade B, Type DSAW, 0.375” wall thickness, carbon steel.
2. Fittings: ASTM A234, Grade WPB/ASME B16.9, 0.375” wall thickness, seamless, carbon
steel weld.
3. Flanges: Class 150. Refer to Unions and Flanges in this Section.
1. Same as existing or as run by the site utility contractor, refer to their drawings and specs.
A. Non-electrical pipe installed below grade shall have 19 AWG Trace-Safe water blocking tracing
wire with Copperhead Snakepit access boxes, or approved equal. Tracer wire to be accessible
at each end in manholes.
E. Grooved-End Copper Fittings: ASTM B 75, copper tube or ASTM B 584, bronze casting.
A. Steel Pipe: ASTM A 53/A 53M, black steel with plain ends; type, grade, and wall thickness or
schedule as indicated in Part 3 "Piping Applications" Article.
B. Cast-Iron Threaded Fittings: ASME B16.4; Classes 125 and 250 as indicated in Part 3 "Piping
Applications" Article.
C. Malleable-Iron Threaded Fittings: ASME B16.3, Classes 150 and 300 as indicated in Part 3
"Piping Applications" Article.
D. Malleable-Iron Unions: ASME B16.39; Classes 150, 250, and 300 as indicated in Part 3 "Piping
Applications" Article.
E. Cast-Iron Pipe Flanges and Flanged Fittings: ASME B16.1, Classes 25, 125, and 250; raised
ground face, and bolt holes spot faced.
F. Wrought Cast- and Forged-Steel Flanges and Flanged Fittings: ASME B16.5, including bolts,
nuts, and gaskets of the following material group, end connections, and facings:
G. Steel Pipe Nipples: ASTM A 733, made of same materials and wall thicknesses as pipe in
which they are installed.
A. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system
contents.
1. ASME B16.21, nonmetallic, flat, asbestos free, 1/8-inch maximum thickness unless
thickness or specific material is indicated.
a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.
b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.
B. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.
C. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according to
ASTM B 813.
D. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for joining copper
with copper; or BAg-1, silver alloy for joining copper with bronze or steel.
E. Gasket Material: Thickness, material, and type suitable for fluid to be handled and working
temperatures and pressures.
A. Unions:
a. Forged steel, ASTM A105 Grade 2, ASME B16.11, socket weld, 3000 lb. WOG
with steel to steel seats.
B. Flanges:
a. ASTM A105, ANSI B16.5, hot forged steel flanges, welding neck pattern. Slip-on
pattern flanges are not allowed. Bore dimension of welding neck flange shall match
inside diameter of connected pipe. Use raised face flanges for mating with other
raised face flanges with self-centering flat ring gaskets. Use flat face flanges for
mating with other flat face flanges with full face gaskets.
2. Flange pressure class indicated in respective piping service is minimum required. Mating
flange pressure class shall match pressure class of device connected to such as valves
and piping specialties. Flanged connection will on be permitted at specialty connections
such as at a vessel or specialty valve.
C. Flange Gaskets:
1. Gasket material to be asbestos free and suitable for pressure temperatures and fluid of
piping system. Non-metallic gaskets shall be in accordance with ANSI/ASME B16.21 and
ASTM F104.
2. Gaskets shall be equal to Flexitallic Style CG, graphite filler, 304 SS winding, carbon
steel centering ring, 0.175” thickness.
D. Bolting:
A. General: Install valves as shown on plans, details, and according to the valve manufacturer’s
installation recommendations.
B. Provide chain operators for manually operated valves 4” and larger, located more than 8’-0”
above normal working surface.
C. Refer to Division 23 Section "General-Duty Valves for HVAC Piping" for additional
requirements for valves and, from that section, refer to this section!
A. Valves to conform to latest revision of AWWA C-504. Valves to be tight closing, rubber seated.
Valves to be zero-leakage at 200 psig, and shall be suitable for throttling service and operation
after long periods of inactivity. Valves shall be rated for 250-psi non-shock working pressure
minimum.
B. Cast iron body ASTM A-126B, Class B, restrained flanged (ANSI B16.1) ends. Valves shall be
furnished complete with joint accessories (bolts, nuts, and gaskets). Flanging shall be lugged
type permitting removal of downstream piping while using valve for system shutoff.
C. Resilient seat shall be Ethylene Propylene Diene Monomer (M-class) rubber (EPDM). EPDM
seats shall be peroxide cured.
D. Valves 20" and smaller shall have the seat bonded directly to the body. Valve 24" and larger
shall have seats that are mechanically retained in the valve body. Either seat shall be capable
of mechanical adjustment in the field and field replacement.
E. Valve discs shall be constructed of cast iron ASTM A-126, Class B or ductile iron ASTM A-536.
Disc shall have stainless steel seating edge to mate with valve seat.
F. Valve shaft to be 18-8, Type 304 stainless steel with "V" / "cup" PTF style self-adjusting
packing.
G. Valve assembly shall be furnished with a non-adjustable factory set thrust bearing designed to
center the valve disc at all times.
H. Shaft bearings shall be contained in the integral hubs of the valve body and shall be self-
lubricated sleeve type and shall be sealed in place with "V" / "cup" PTF style self-adjusting
packing.
I. Prior to shipment, valves to be hydrostatically and leak tested at the factory in accordance with
AWWA C-504. Factory hydrostatic test shall be performed at 200 psig for all valves.
1. NU and Architect / Engineer shall have option to be present to witness factory testing for
the first valves that are 20" and smaller and the first valves that are 24" and larger. Valve
manufacturer shall be responsible for providing transportation and accommodations for
two (2) NU representatives and one (1) representative of the Architect / Engineer.
J. Provide worm gear operators. Provide rotary hand wheels with adjustable position stop and
position indicators. Size hand wheel operators with no higher than 40 lb rim pull at full valve
pressure rating.
A. Valves to conform to latest revision of AWWA C-504. Valves to be tight closing, rubber seated.
Valves to be zero-leakage at 200 psig, and shall be suitable for throttling service and operation
after long periods of inactivity. Valves shall be rated for 250-psi non-shock working pressure
minimum. Valves to be designed for direct buried application.
B. Cast iron body ASTM A-126B, Class B, restrained mechanical joint (AWWA C-151/ANSI 21.11)
or flanged (ANSI B16.1) ends. Valves shall be furnished complete with joint accessories (bolts,
nuts, gaskets and glands).
C. Resilient seat shall be Ethylene Propylene Diene Monomer (M-class) rubber (EPDM). EPDM
seats shall be peroxide cured.
D. Valves 20" and smaller shall have the seat bonded directly to the body. Valves 24" and larger
shall have seats that are mechanically retained in the valve body. Either seat shall be capable
of mechanical adjustment in the field and field replacement.
E. Valve discs shall be constructed of ASTM A-126 cast iron, Class B or ductile iron ASTM A-536.
Disc shall have stainless steel seating edge to mate with valve seat.
F. Valve shaft to be 18-8, Type 304 stainless steel with "V" / "cup" PTF style self-adjusting
packing.
G. Valve assembly shall be furnished with a non-adjustable factory set thrust bearing designed to
center the valve disc at all times.
H. Shaft bearings shall be contained in the integral hubs of the valve body and shall be self-
lubricated sleeve type and shall be sealed in place with "V" / "cup" PTF style self-adjusting
packing.
I. Prior to shipment, valves to be hydrostatically and leak tested at the factory in accordance with
AWWA C-504. Factory hydrostatic test shall be performed at 200 psig for all valves.
1. NU and Architect / Engineer shall have option to be present to witness factory testing for
the first valves that are 20" and smaller and the first valves that are 24" and larger. Valve
manufacturer shall be responsible for providing transportation and accommodations for
two (2) NU representatives and one (1) representative of the Architect / Engineer.
J. Valves to be complete with grease packed buried service gear operator, shaft extensions with
centering disk located on shaft, to within one foot of finished grade and soil pipe.
A. 2" and Smaller: bronze body, threaded, stainless steel ball and stem, full port, teflon seat rings,
blowout-proof stem, three piece construction, 600 psi WOG, 150 psi SWP.
A. Ball valves as specified above with hose thread adapter and cap. Provide 2” minimum drain
valves provided with short threaded nipple and cap. All vent valves shall be minimum ¾” in size.
A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solder-
joint, plain, or weld-neck end connections that match piping system materials.
C. Dielectric Nipples: With like material unions, for 250-psig minimum working pressure at 180
deg F.
F. Dielectric Nipples: Electroplated steel nipple with inert and non-corrosive, thermoplastic lining;
plain, threaded, or grooved ends; and 300-psig minimum working pressure at 225 deg F.
PART 3 - EXECUTION
A. For chilled water piping in CUP, underground chilled water piping, chilled water piping in
tunnels, and pressurized waste water piping, install per normal University standards and
procedures.
B. Hot-water heating and chilled water piping, aboveground, NPS 4 and smaller, shall be Type L,
drawn-temper copper tubing, wrought-copper fittings, with soldered joints 2" and smaller, and
brazed joints larger than 2".
C. Hot-water heating and chilled water piping, aboveground, larger than NPS 4, shall be any of the
following:
1. Schedule 40 steel pipe; Class 125 cast-iron or 150 malleable-iron fittings; cast-iron
flanges and flange fittings; and threaded joints.
E. Condenser-water piping, aboveground, NPS 2-1/2 and larger, shall be any of the following:
1. Schedule 40 type E or S grade B black steel pipe, wrought-steel fittings and wrought-cast
or forged-steel flanges and flange fittings, and welded and flanged joints. Flanged joints
only at valves, etc.
H. Blowdown-Drain Piping: Same materials and joining methods as for piping specified for the
service in which blowdown drain is installed.
I. Air-Vent Piping:
1. Inlet: Same materials and joining methods as for piping specified for the service in which
air vent piping is installed.
2. Outlet: Type K, annealed-temper copper tubing with soldered or flared joints.
J. Safety-Valve-Inlet and -Outlet Piping for Hot Water and Chilled Water Piping: Same materials
and joining methods as for piping specified for the service in which safety valve is installed
3.2 VALVE APPLICATIONS AND INSTALLATION
A. Install shutoff-duty valves at each branch connection to supply mains, at supply connections to
each piece of equipment, and at other locations in systems for convenient system isolation.
B. Install calibrated-orifice, balancing valves in the return pipe of each heating or cooling terminal.
C. Install check valves at each pump discharge and elsewhere as required to control flow direction.
D. Install safety valves at hot-water generators and elsewhere as required by ASME Boiler and
Pressure Vessel Code. Pipe drain to nearest floor drain or as indicated on Drawings. Comply
with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1, for installation
requirements.
F. All valves with position indicators are to be installed so that the indicators are facing in a
direction that is visible from floor level. Ball valve handles, if located near ceilings, are to be
located on the 3 or 9 o'clock positions to allow for actuation. All butterfly isolation valves that
are higher than 5' above the floor are to have chains for actuation. All valves need to have free
and clear access, minimum of 24" from valves to adjacent work.
A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping
systems. Indicate piping locations and arrangements if such were used to size pipe and
calculate friction loss, expansion, pump sizing, and other design considerations. Install piping
as indicated unless deviations to layout are approved on Coordination Drawings.
B. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms
and service areas.
C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right
angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated
otherwise, and are allowed if necessary, at common lines of chilled water bridges.
D. Grooved Joints: Assemble joints with coupling and gasket, lubricant, and bolts. Cut or roll
grooves in ends of pipe based on pipe and coupling manufacturer's written instructions for pipe
wall thickness. Use grooved-end fittings and rigid or flexible, where required, grooved-end-pipe
couplings. The gasket style and elastomeric material (grade) shall be verified as suitable for the
intended service as specified. A factory trained field representative shall provide on-site training
for contractor's field personnel in the use of grooving tools, application of groove, and
installation of grooved piping products. Factory trained representative shall periodically review
the product installation. Contractor shall remove and replace any improperly installed products.
E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
K. Select system components with pressure rating equal to or greater than system operating
pressure.
L. Install groups of pipes parallel to each other, spaced to permit applying insulation and servicing
of valves.
M. Install drains, consisting of a tee fitting, NPS 3/4 ball valve, and short NPS 3/4 threaded hose
end with brass cap, at low points in piping system mains and elsewhere as required for
complete system drainage. Locate as shown on drawings, and as required based on actual
installed conditions.
N. Install piping at a uniform grade of 0.2 percent upward in direction of flow for supply and 0.2
percent downward in direction of flow for return.
O. Install branch connections to mains using tee fittings in main pipe, with the branch connected to
the side or 45 degrees from the bottom of the main pipe.
P. Install valves according to Division 23 Section "General-Duty Valves for HVAC Piping."
Q. Install unions in piping, NPS 2 and smaller at final connections of equipment, and elsewhere as
indicated.
R. Install flanges in piping, NPS 2-1/2 and larger, at final connections of equipment and elsewhere
as indicated.
S. Install strainers on inlet side of each coil, pressure-reducing valve, solenoid valve, in-line pump,
and elsewhere as indicated. Install NPS 3/4 nipple and ball valve in blowdown connection of
strainers NPS 2 and larger. Match size of strainer blow-off connection for strainers smaller than
NPS 2.
T. Install expansion loops, expansion joints, anchors, and pipe alignment guides as specified in
Division 23 Section "Expansion Fittings and Loops for HVAC Piping."
V. Install sleeves for piping penetrations of walls, ceilings, and floors. Comply with requirements
for sleeves specified in Division 23 Section "Sleeves and Sleeve Seals for HVAC Piping."
W. Install sleeve seals for piping penetrations of concrete walls and slabs. Comply with
requirements for sleeve seals specified in Division 23 Section "Sleeves and Sleeve Seals for
HVAC Piping."
X. Install escutcheons for piping penetrations of walls, ceilings, and floors. Comply with
requirements for escutcheons specified in Division 23 Section "Escutcheons for HVAC
Piping."
A. Tracer wire shall be installed on the piping as shown on the contract drawings.
B. Tracer wires shall terminate in each tunnel and manhole where new utilities penetrate. Tracer
wires shall be provided with labels noting what pipe the wire is affixed to (ie. Chilled Water
Supply, Pumped Condensate Return, etc).
C. Tracer wires shall be installed with a separate access point from and next to vault.
A. Hanger, support, and anchor devices are specified in Division 23 Section "Mechanical
Supporting Devices." Comply with the following requirements for maximum spacing of supports
and minimum rod diameters.
1. Adjustable steel clevis hangers for individual horizontal piping less than 20 feet long.
2. Adjustable roller hangers and spring hangers for individual horizontal piping 20 feet or
longer.
3. Pipe Roller: MSS SP-58, Type 44 for multiple horizontal piping 20 feet or longer,
supported on a trapeze.
4. Spring hangers to support vertical runs.
5. Provide copper-clad hangers and supports for hangers and supports in direct contact with
copper pipe.
C. Install hangers for steel piping with the following maximum spacing (with minimum rod sizes per
MSS):
D. Install hangers for drawn-temper copper piping with the following maximum spacing and
minimum rod sizes:
1. NPS 3/4: Maximum span, 5 feet; minimum rod size, 1/4 inch.
2. NPS 1: Maximum span, 6 feet; minimum rod size, 1/4 inch.
3. NPS 1-1/2: Maximum span, 8 feet; minimum rod size, 3/8 inch.
4. NPS 2: Maximum span, 8 feet; minimum rod size, 3/8 inch.
5. NPS 3 and larger: Maximum span, 10 feet; minimum rod size, 3/8 inch.
E. Support vertical runs at roof, at each floor, and at 10-foot intervals between floors.
A. Join pipe and fittings according to the following requirements and Division 23 Sections
specifying piping systems.
B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.
C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before
assembly.
D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube
end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-
free solder alloy complying with ASTM B 32.
E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube"
Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8.
F. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut
threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore
full ID. Join pipe fittings and valves as follows:
1. Apply appropriate tape or thread compound to external pipe threads unless dry seal
threading is specified.
2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or
damaged. Do not use pipe sections that have cracked or open welds.
G. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service
application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.
H. Grooved Joints If Used In Copper Systems: Assemble joints with coupling and gasket,
lubricant, and bolts. Create grooves in ends of pipe based on pipe and coupling manufacturer's
written instructions for pipe wall thickness. Use grooved-end fittings and HVAC Shop approved
grooved-end-pipe couplings.
A. Install manual air vents at high points in piping, at heat-transfer coils, and elsewhere as shown
and required for complete system air venting. Vents points to have isolation valves, pressure
gages, and drain valves with hose connections.
A. Sizes for supply and return piping connections shall be the same as or larger than equipment
connections.
C. Install ports for pressure gages and thermometers at coil inlet and outlet connections according
to Division 23 Section "Meters and Gages for HVAC Piping."
1. Leave joints, including welds, uninsulated and exposed for examination during test.
2. Provide temporary restraints for expansion joints that cannot sustain reactions due to test
pressure. If temporary restraints are impractical, isolate expansion joints from testing.
3. Flush hydronic piping systems with clean water; then remove and clean or replace
strainer screens.
4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure shall be
capable of sealing against test pressure without damage to valve. Install blinds in
flanged joints to isolate equipment.
5. Install safety valve, set at a pressure no more than one-third higher than test pressure, to
protect against damage by expanding liquid or other source of overpressure during test.
1. Use ambient temperature water as a testing medium unless there is risk of damage due
to freezing. Another liquid that is safe for workers and compatible with piping may be
used.
2. While filling system, use vents installed at high points of system to release air. Use
drains installed at low points for complete draining of test liquid.
3. Isolate expansion tanks and determine that hydronic system is full of water.
4. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the
system's working pressure. Test pressure shall not exceed maximum pressure for any
vessel, pump, valve, or other component in system under test. Verify that stress due to
pressure at bottom of vertical runs does not exceed 90 percent of specified minimum
yield strength or 1.7 times "SE" value in Appendix A in ASME B31.9, "Building Services
Piping."
5. After hydrostatic test pressure has been applied for at least 10 minutes, examine piping,
joints, and connections for leakage. Eliminate leaks by tightening, repairing, or replacing
components, and repeat hydrostatic test until there are no leaks.
6. Prepare written report of testing.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes certain special-duty valves and specialties for the following:
1. Valves: Include flow and pressure drop curves based on manufacturer's testing for
calibrated-orifice balancing valves and automatic flow-control valves.
2. Air-control devices.
3. Hydronic specialties.
A. Operation and Maintenance Data: For air-control devices, hydronic specialties, and special-duty
valves to include in emergency, operation, and maintenance manuals.
A. Differential Pressure Meter: For each type of balancing valve and automatic flow control valve,
include flowmeter, probes, hoses, flow charts, and carrying case.
A. Pipe Welding: Qualify procedures and operators according to ASME Boiler and Pressure Vessel
Code: Section IX.
1. Safety valves and pressure vessels shall bear the appropriate ASME label. Fabricate and
stamp air separators and expansion tanks to comply with ASME Boiler and Pressure
Vessel Code: Section VIII, Division 1.
B. Comply with FM Global requirements for pressure vessels and piping and for pressure relief
devices.
PART 2 - PRODUCTS
A. Hydronic piping components and installation shall be capable of withstanding the following
minimum working pressure and temperature unless otherwise indicated:
2.2 VALVES
A. Check, Ball, and Butterfly Valves: Comply with requirements specified in Section 23 0523
"General Duty Valves for HVAC."
2. Body: Cast-iron or steel body, ball, plug, or globe pattern with calibrated orifice or venturi.
3. Ball: Brass or stainless steel.
4. Stem Seals: EPDM O-rings.
5. Disc: Glass and carbon-filled PTFE.
6. Seat: PTFE.
7. End Connections: Flanged.
8. Pressure Gage Connections: Integral seals for portable differential pressure meter.
9. Handle Style: Lever, with memory stop to retain set position.
10. CWP Rating: Minimum 125 psig (860 kPa).
11. Maximum Operating Temperature: 250 deg F (121 deg C).
1. Not Allowed.
2.3 AIR CONTROL DEVICES, EXPANSION TANKS, AND AIR AND DIRT SEPARATORS
2. Body: Bronze.
3. Internal Parts: Nonferrous.
4. Operator: Screwdriver or thumbscrew.
5. Inlet Connection: NPS 1/2.
6. Discharge Connection: NPS 1/8.
7. CWP Rating: 150 psig.
8. Maximum Operating Temperature: 225 deg F.
B. Expansion Tanks:
2. Tank: Welded steel, rated for 125-psig working pressure and 375 deg F maximum
operating temperature, with taps in bottom of tank for tank fitting and taps in end of tank
for gage glass. Tanks shall be factory tested with taps fabricated and labeled according
to ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.
3. Pressurization system: Replaceable bladder-type expansion tank which will
accommodate the expanded water of the system generated within the normal operating
temperature range, limiting this pressure increase at those components in the system to
the maximum allowable pressure at those components. It shall maintain minimum
operating pressure necessary to eliminate all air. the only air in the system shall be the
permanent sealed-in air cushion contained in the replaceable bladder-type tank, with
dimensions as indicated on the drawings.
2. Body: ASME welded steel, with inlet and outlet connections, bottom valved blowdown
and top vent connections, brass vent head/valve, non-ferrous float, Viton seals and O-
rings, brass skim valve, copper coalescing medium, and other internal components that
effectively separate the air from solution and divert it to the vent for quick removal, and
that effectively remove dirt and divert it for removal.
3. Maximum Working Pressure: 150 psig.
4. Maximum Operating Temperature: 270 deg F.
E. Air Purgers:
2. Body: Cast iron with internal baffles that slow the water velocity to separate the air from
solution and divert it to the vent for quick removal.
3. Maximum Working Pressure: 150 psig (1035 kPa).
4. Maximum Operating Temperature: 250 deg F (121 deg C).
A. Y-Pattern Strainers:
1. Body: ASTM A 126, Class B, cast iron with bolted cover and bottom drain connection.
2. End Connections: Threaded ends for NPS 2 (DN 50) and smaller; flanged ends for
NPS 2-1/2 (DN 65) and larger.
3. Strainer Screen: Stainless-steel, [20] [40] [60]-mesh strainer, or perforated stainless-steel
basket.
4. CWP Rating: 125 psig (860 kPa).
B. Basket Strainers:
1. Body: ASTM A 126, Class B, high-tensile cast iron with bolted cover and bottom drain
connection.
2. End Connections: Threaded ends for NPS 2 (DN 50) and smaller; flanged ends for NPS
2-1/2 (DN 65) and larger.
3. Strainer Screen: [40] [60]-mesh startup strainer, and perforated stainless-steel basket
with 50 percent free area.
4. CWP Rating: 125 psig (860 kPa).
C. T-Pattern Strainers:
1. Body: Ductile or malleable iron with removable access coupling and end cap for strainer
maintenance.
2. End Connections: Flanged ends.
3. Strainer Screen: [40] [60]-mesh startup strainer, and perforated stainless-steel basket
with 57 percent free area.
4. CWP Rating: 750 psig (5170 kPa).
F. Expansion Fittings: Comply with requirements in Section 230516 "Expansion Fittings and Loops
for HVAC Piping."Section 15124 "Expansion Fittings and Loops for HVAC Piping."
PART 3 - EXECUTION
A. Install shutoff-duty valves at each branch connection to supply mains and at supply connection
to each piece of equipment.
C. Install calibrated-orifice, balancing valves in the return pipe of each heating or cooling terminal.
D. Install check valves at each pump discharge and elsewhere as required to control flow direction.
E. Install safety valves at hot-water generators and elsewhere as required by ASME Boiler and
Pressure Vessel Code. Install drip-pan elbow on safety-valve outlet and pipe without valves to
the outdoors; pipe drain to nearest floor drain or as indicated on Drawings. Comply with ASME
Boiler and Pressure Vessel Code: Section VIII, Division 1, for installation requirements.
A. Install manual air vents at high points in piping, at heat-transfer coils, and elsewhere as required
for system air venting.
B. Install automatic air vents at high points of system piping in mechanical equipment rooms only.
Install manual vents at heat-transfer coils and elsewhere as required for air venting.
C. Install piping from boiler air outlet, air separator, or air purger to expansion tank with a 2 percent
upward slope toward tank.
D. Install in-line air separators in pump suction. Install drain valve on air separators NPS 2 (DN 50)
and larger.
E. Install tangential air separator in pump suction. Install blowdown piping with gate or full-port ball
valve; extend full size to nearest floor drain.
F. Install air and dirt separators as shown on drawing and with blowdown piping with gate or full-
port ball valve; extend full size to nearest floor drain. These separators are required to be
installed for any new chilled water and heating hot water connections to a building, on closed
loop hydronic systems involved with renovations, and as otherwise shown on the drawings.
G. Install expansion tanks above the air separator. Install tank fitting in tank bottom and charge
tank. Use manual vent for initial fill to establish proper water level in tank.
H. Install expansion tanks on the floor. Vent and purge air from hydronic system, and ensure that
tank is properly charged with air to suit system Project requirements.
J. Install stainless steel bellows type and/or spherical rubber type flexible connectors as shown on
the drawings.
K. Install flexible stainless steel hose connectors at HVAC equipment utilizing hydronic piping and
as shown on drawings.
L. All valves with position indicators are to be installed so that the indicators are facing in a
direction that is visible from floor level. Ball valve handles, if located near ceilings, are to be
located on the 3 or 9 o'clock positions to allow for actuation. All butterfly isolation valves that
are higher than 5' above the floor are to have chains for actuation. All valves need to have free
and clear access, minimum of 24" from valves to adjacent work.
M. This contractor shall install pump differential pressure switches/devices provided by the Division
25 contractor.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 SUBMITTALS
A. Product Data: Include certified performance curves and rated capacities, operating
characteristics, furnished specialties, final impeller dimensions, and accessories for each type of
product indicated. Indicate pump's operating point on curves.
B. Shop Drawings: Show pump layout and connections. Include setting drawings with templates
for installing foundation and anchor bolts and other anchorages.
D. Grooved joint couplings and fittings specifically identified with the applicable style or series
number.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Source Limitations: Obtain hydronic pumps through one source from a single manufacturer.
PUMPS 23 2123 - 1
D. To assure uniformity and compatibility of piping components in grooved end piping systems, all
grooved products utilized shall be supplied by the same manufacturer. Grooving tools shall be
supplied by the same manufacturer as the grooved components.
A. Manufacturer's Preparation for Shipping: Clean flanges and exposed machined metal surfaces
and treat with anticorrosion compound after assembly and testing. Protect flanges, pipe
openings, and nozzles with wooden flange covers or with screwed-in plugs.
C. Retain protective covers for flanges and protective coatings during storage.
D. Protect bearings and couplings against damage from sand, grit, and other foreign matter.
1.6 COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete,
reinforcement, and formwork requirements are specified in Division 03.
PART 2 - PRODUCTS
A. Pump motors shall be 1750 rpm maximum unless otherwise scheduled on drawings and sized
for non-overloading service.
B. Pump impeller shall be shaved to a minimum of [110%] [120%] of design flow at the required
pump head after balancing.
C. Pumps motors operated by Variable Frequency Drives shall have pump impellor balanced for
variable speed operation.
D. All pumps to be provided with permanently affixed nameplates which include impeller diameter,
rated capacity in gpm, rated head in feet, rpm, and motor horsepower.
A. Pump Manufacturers: Subject to compliance with the requirements, provide products by one of
the following:
A. Pump Manufacturers: Subject to compliance with the requirements, provide products by one of
the following:
B. Pump Construction:
1. Casing: Radially split, cast iron, with replaceable bronze wear rings, threaded gage
tappings at inlet and outlet, and threaded companion-flange connections.
2. Impeller: ASTM B 584, cast bronze; statically and dynamically balanced, keyed to shaft,
and secured with a locking cap screw. Trim impeller to match specified performance.
3. Pump Shaft: Steel, with copper-alloy shaft sleeve.
C. Motor: Single speed, with permanently lubricated ball bearings, unless otherwise indicated; and
rigidly mounted to pump casing. Comply with requirements in Division 23 Section "Motors."
B. Pump Construction:
1. Casing: Radially split, cast iron, with drain plug at bottom and air vent at top of volute,
threaded gage tappings at inlet and outlet.
2. Impeller: ASTM B 584, cast bronze; statically and dynamically balanced, keyed to shaft,
and secured with a locking cap screw. Trim impeller to match specified performance.
3. Pump Shaft: Stainless steel.
4. Mechanical Seal: Carbon rotating ring against a ceramic seat held by a stainless-steel
spring, and Buna-N bellows and gasket. Equal to John Crane Type 21.
5. Pump Bearings: Permanently lubricated ball bearings through 5 hp. Over 5 hp : grease-
lubricated ball bearings.
6. Motor: Single speed, with permanently lubricated ball bearings, unless otherwise
indicated; rigidly mounted to pump casing with integral pump support. Comply with
requirements in Division 23 Section "Motors."
B. Pump Construction:
1. Casing: Radially split, cast iron, with threaded gage tappings at inlet and outlet, and
threaded [companion-flange] [union end] connections.
2. Impeller: ASTM B 584, cast bronze; statically and dynamically balanced, and keyed to
shaft. Trim impeller to match specified performance.
3. Pump Shaft: [Steel, with copper-alloy shaft sleeve] [Stainless steel].
4. Mechanical Seal: Carbon rotating ring against a ceramic seat held by a stainless-steel
spring, and [Buna-N] [EPT] bellows and gasket. Include water slinger on shaft between
motor and seal.
5. Pump Bearings: Permanently lubricated ball bearings.
C. Shaft Coupling: [Molded rubber insert with interlocking spider] [Interlocking frame with
interconnecting springs] capable of absorbing vibration.
D. Motor: Single speed, with [permanently lubricated ball] [oil-lubricated sleeve] bearings,
unless otherwise indicated; and [resiliently] [rigidly] mounted to pump casing. Comply with
requirements in Division 23 Section "Motors."
B. Pump Construction:
1. Casing: Radially split, cast iron, with[ replaceable bronze wear rings,] threaded gage
tappings at inlet and outlet, and threaded [companion-flange] [union end] connections.
2. Impeller: ASTM B 584, cast bronze; statically and dynamically balanced, keyed to shaft,
and secured with a locking cap screw. Trim impeller to match specified performance.
3. Pump Shaft: [Steel, with copper-alloy shaft sleeve] [Stainless steel].
4. Mechanical Seal: Carbon rotating ring against a ceramic seat held by a stainless-steel
spring, and [Buna-N] [EPT] bellows and gasket. Include water slinger on shaft between
motor and seal.
5. Packing Seal: Stuffing box, with a minimum of four rings of graphite-impregnated braided
yarn with bronze lantern ring between center two graphite rings, and bronze packing
gland.
6. Pump Bearings: [Permanently lubricated ball bearings] [Oil lubricated; bronze-
journal or thrust type].
D. Motor: Single speed, with [permanently lubricated] [grease-lubricated] ball bearings, unless
otherwise indicated; rigidly mounted to pump casing with lifting eye and supporting lugs in motor
enclosure. Comply with requirements in Division 23 Section "Motors."
B. Pump Construction:
1. Casing: Radially split, cast iron, with drain plug at bottom and air vent at top of volute,
threaded gage tappings at inlet and outlet.
2. Impeller: ASTM B 584, cast bronze; statically and dynamically balanced, keyed to shaft,
and secured with a locking cap screw.
3. Pump Shaft: Stainless steel.
4. Mechanical Seal: Carbon rotating ring against a ceramic seat held by a stainless-steel
spring, and Buna-N bellows and gasket. Equal to John Crane Type 21.
5. Pump Bearings: Permanently lubricated ball bearings through 5 hp. Over 5 hp : grease-
lubricated ball bearings.
C. Shaft Coupling: Molded rubber insert and interlocking spider capable of absorbing vibration.
Couplings shall be drop-out type to allow disassembly and removal without removing pump
shaft or motor [EPDM coupling sleeve for variable-speed applications].
D. Coupling Guard: Dual rated; ANSI B15.1, Section 8; OSHA 1910.219 approved; steel;
removable; attached to mounting frame.
E. Mounting Frame: Welded-steel frame and cross members, factory fabricated from
ASTM A 36/A 36M channels and angles. Fabricate to mount pump casing, coupling guard, and
motor.
F. Motor: [Open Drip Proof] [TEFC] Single speed, with permanently lubricated ball bearings,
unless otherwise indicated; secured to mounting frame, with adjustable alignment. Comply with
requirements in Division 23 Section "Motors."
A. Suction Diffusers:
2. Angle pattern, 175-psig pressure rating at 250 degree F, cast ductile-iron body and end
cap, pump-inlet fitting; with removable strainer (bronze for startup and stainless-steel for
permanent); bronze or stainless-steel full length straightening vanes; drain plug; and
factory-fabricated support. Provide optional magnetic insert.
3. Angle pattern, grooved pump inlet with flanged outlet system connections, 300-psig
pressure rating at 250 degree F, ductile-iron body, coupling and cap, 304 stainless steel
frame and perforated sheet diffuser with 3/16” diameter holes. Integral flow
straightening device. Removable 16 mesh bronze start-up pre-filter, pressure port with
drain plug. Provide optional magnetic insert.
1. Not allowed.
PART 3 - EXECUTION
B. Install all pumps in strict accordance with manufacturer’s instructions. Provide service space
around pumps as recommended by the pump manufacturer.
C. Independently support pumps and piping so weight of piping is not supported by pumps and
weight of pumps is not supported by piping.
D. Install continuous-thread hanger rods and spring hangers of sufficient size to support pump
weight. Vibration isolation devices are specified in Division 23 Section "Vibration Isolation."
Fabricate brackets or supports as required. Hanger and support materials are specified in
Division 23 Section "Mechanical Supporting Devices."
E. Suspend vertically mounted, in-line centrifugal pumps independent of piping. Install pumps with
motor and pump shafts vertical. Use continuous-thread hanger rods and spring hangers of
sufficient size to support pump weight. Vibration isolation devices are specified in Division 23
Section "Vibration Isolation." Hanger and support materials are specified in Division 23 Section
"Mechanical Supporting Devices."
F. Set base-mounted pumps on concrete foundation. Disconnect coupling before setting. Do not
reconnect couplings until alignment procedure is complete.
1. Support pump baseplate on rectangular metal blocks and shims, or on metal wedges with
small taper, at points near foundation bolts to provide a gap of 3/4 to 1-1/2 inches
between pump base and foundation for grouting.
2. Adjust metal supports or wedges until pump and driver shafts are level. Check coupling
faces and suction and discharge flanges of pump to verify that they are level and plumb.
G. Do not mount pumps on walls that are common to critical areas such as offices, conference
rooms, classrooms, etc. In-line pumps shall be installed directly in the piping system, and
supported independently from the piping.
H. Install grooved piping products in accordance with the manufacturer's guidelines and
recommendations. Grooved end shall be clean and free from indentations, projections and roll
marks in the area from pipe end to groove.
I. Grooved Joints: Assemble joints with coupling and gasket, lubricant, and bolts. Cut or roll
grooves in ends of pipe based on pipe and coupling manufacturer's written instructions for pipe
wall thickness. The gasket style and elastomeric material (grade) shall be verified as suitable
for the intended service as specified. A field representative shall provide on-site training for
contractor's field personnel in the use of grooving tools, application of groove, and installation of
grooved piping products. Factory trained representative shall periodically review the product
installation. Contractor shall remove and replace any improperly installed products.
3.2 ALIGNMENT
A. Align pump and motor shafts and piping connections after setting on foundation, grout has been
set and foundation bolts have been tightened, and piping connections have been made.
C. Adjust pump and motor shafts for angular and offset alignment by methods specified in HI 1.1-
1.5, "Centrifugal Pumps for Nomenclature, Definitions, Application and Operation."
D. After alignment is correct, tighten foundation bolts evenly but not too firmly. Completely fill
baseplate with non-shrink, nonmetallic grout while metal blocks and shims or wedges are in
place. After grout has cured, fully tighten foundation bolts.
E. Grout pump mounting base full after piping is connected but before pump drive is aligned. After
grouting, align pump drive shaft to 5 mils, even if pump is factory aligned, and conduct vibration
test.
3.3 CONNECTIONS
A. Piping installation requirements are specified in other Division 23 Sections. Drawings indicate
general arrangement of piping, fittings, and specialties.
C. Connect piping to pumps. Install valves that are same size as piping connected to pumps.
D. Install suction and discharge pipe sizes equal to or greater than diameter of pump nozzles.
F. Install Y-type strainer and shutoff valve on suction side of pumps. Suction diffusers can be used
in lieu of in-line strainers, long radius elbow and spool piece.
G. Install flexible connectors or Victaulic flexible couplings on suction and discharge sides of base-
mounted pumps between pump casing and valves.
H. Install pressure gages on pump suction and discharge, at integral pressure-gage tapping, or
install single gage with multiple input selector valve.
I. Install check valve and ball valve on each condensate pump unit discharge.
J. Install electrical connections for power, controls, and devices.
a. Verify that pump is free to rotate by hand and that pump for handling hot liquid is
free to rotate with pump hot and cold. If pump is bound or drags, do not operate
until cause of trouble is determined and corrected.
b. Verify that pump is rotating in the correct direction.
3.5 DEMONSTRATION
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following for HP (High Pressure) and LP (Low Pressure) steam and
condensate piping:
B. Related Requirements:
C. For the Evanston campus, central steam is distributed at 150 psig (known as the "Campus
Line"), and at 230 psig. These are distinct piping systems but they both originate from the same
high pressure header in the CUP. Steam is and needs to be metered and reduced in pressure
after entrance of each building as required. On the condensate return side, there is high
pressure condensate return and pumped condensate return.
E. Both campus's utilize direct buried piping and piping run through tunnels.
A. Components and installation shall be capable of withstanding the following minimum working
pressures and temperatures:
1. HP Steam and Medium Pressure (MP) Piping: XXX psig and XXXF.
2. LP Steam Piping: 15 psig and 300F.
3. HP and MP Condensate Piping: XXX psig at XXX deg F.
4. LP Condensate Piping: 15 psig at 250 deg F.
5. Blowdown-Drain Piping: Equal to pressure of the piping system to which it is attached.
6. Air-Vent and Vacuum-Breaker Piping: Equal to pressure of the piping system to which it
is attached.
7. Safety-Valve-Inlet and -Outlet Piping: Equal to pressure of the piping system to which it
is attached.
1.5 SUBMITTALS
B. Shop Drawings (For Use Amongst the Contractors and For University Reference, Not for
Engineer Approval): Detail fabrication of pipe anchors, hangers, pipe, multiple pipes,
alignment guides, and expansion loops and their attachment to the building structure. Detail
locations of anchors, alignment guides, and expansion loops.
C. Coordination Drawings (For Use Amongst the Contractors and For University Reference,
Not for Engineer Approval): Piping layout, drawn to scale, on which the following items are
shown and coordinated with each other, using input from installers of the items involved:
F. Operation and Maintenance Data: For valves and expansion joints, to include in emergency,
operation, and maintenance manuals.
G. Delegated-Design Submittal (For Use Amongst the Contractors and For University
Reference, Not for Engineer Approval):
1. Design calculations and detailed fabrication and assembly of pipe anchors and alignment
guides, hangers and supports for multiple pipes, expansion loops, and attachments of the
same to the building structure.
2. Locations of pipe anchors and alignment guides and expansion joints and loops.
3. Locations of and details for penetration and fire-stopping for fire- and smoke-rated wall
and floor and ceiling assemblies.
1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."
2. Certify that each welder has passed AWS qualification tests for welding processes
involved and that certification is current.
Retain applicable codes in paragraph below: B31.1 for HP steam system and B31.9 for LP steam
system.
B. ASME Compliance: Comply with ASME B31.1, “Power Piping” and ASME B31.9,
"Building Services Piping," for materials, products, and installation. Safety valves and
pressure vessels shall bear the appropriate ASME label.
C. Steel Support Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M,
"Structural Welding Code, Steel."
D. Comply with FM Global requirements for pressure vessels and piping and for pressure relief
devices.
E. Piping materials shall bear label, stamp, or other markings of specified testing agency.
A. Product Delivery Requirements: Accept valves and accessories on site in shipping containers
with labeling in place.
B. Product Storage and Handling Requirements: Protect piping and fittings from soil and debris
with temporary and caps and closures. Maintain in place until installation. Provide temporary
protective coating on steel valves and specialties.
2.1 GENERAL
A. All non-electrical pipe installed below grade shall have a 19 AWG Trace-Safe water blocking
tracing wire with Copperhead Snakepit access boxes, or equal. Tracer wire to be accessible at
each end in manholes.
B. Tracer wire shall be installed on the pipe as shown on the contract drawings.
C. Tracer wires shall terminate in each tunnel and manhole where new utilities penetrate. Tracer
wires shall be provided with labels noting what pipe the wire is affixed to (i.e., HP Steam Supply,
Pumped Condensate Return, etc.)
2.3 HIGH PRESSURE STEAM IN CUP, IN INTERIOR MANHOLES (IF APPLICABLE), AND
SHORT SECTIONS JUST ENTERING BUILDING MECHANICAL ROOMS
A. 2½ and Smaller:
A. Same as existing, or same as new as installed by the site utility contractor, and work of this
section for this application only meant to cover new piping in from 5'-0" outside of building if the
site utility responsibility ends there, refer to their drawings and specs. Contractor fabricated
piping and fittings are not allowed. No metal components shall be exposed to earth. Refer to
Section 33 6313 for information and requirements on site HP steam and condensate piping
systems (including vaults) and also including (but not limited to) pipe support guides, expansion
loops, moment guided, elbows and tees, anchors, end seals and gland seals, and field joints.
B. If drainable/dryable type, all straight sections, fittings, anchors and other accessories shall be
factory prefabricated to job dimensions, and designed to minimize the number of field welds.
The design shall be computer analyzed by the piping system manufacturer to determine
stresses and movements of the service pipe and to ensure that the system design is in strict
conformance with ANSI B31.1 latest edition, and stamped by a registered professional engineer
licensed in the state of Illinois. The analysis shall include piping and structures inside the
manholes.
C. The piping manufacturer shall provide minimum of 2 days of on-site technical assistance during
installation of the piping. The factory representative shall be a factory trained technician to
witness requirements outlined in the installation portion of this specification.
D. Contractor shall perform a computerized pipe stress analysis for the piping systems in the
underground steam system. Submit stress analysis report including input data, system graphics,
output data including: system forces and moments, system deflections, system stresses,
hanger, support and anchor loading summary and other pertinent data. Analysis shall consider
actual materials of construction and a system pressure and temperature of 250 PSIG and
450°F, base temperature is 50°F. Analysis output data shall be utilized to select proper
supports, guides and anchors to resist actual loads calculated. Pipe stress analysis calculations
to be submitted to the Engineer for review along with the re-engineered piping system shop
drawings.
2.7 LP STEAM AND CONDENSATE PIPING
A. LP Steam: 2" and smaller: ASTM A53, Grade B, ERW, schedule 40 carbon steel, with screwed
joints. Fittings, unions, flanges, and couplings to be ANSI/ASTM B16.3. malleable iron, Class
150.
B. LP Steam: 2-1/2" and larger: ASTM A53, Grade B, ERW, schedule 40, carbon steel, with
ANSI/AWS D1.1 butt welded joints. Fittings to be ASTM A234, forged steel, Class 150.
Flanges to be Class 150 forged steel slip-on type, or weld-neck flanges for carbon steel.
C. LP Steam Condensate: 2" and smaller: ASTM A53, Grade B, ERW, schedule 80 carbon steel,
with screwed joints. Fittings, unions, flanges, and couplings to be ANSI/ASTM B16.3. malleable
iron, Class 150.
D. LP Steam Condensate: 2-1/2" and larger: ASTM A53, Grade B, ERW, schedule 80, carbon
steel, with ANSI/AWS D1.1 butt welded joints. Fittings to be ASTM A234, forged steel, Class
150. Flanges to be Class 150 forged steel slip-on type, or weld-neck flanges for carbon steel.
E. Pumped Condensate, 2" and smaller: ASTM A53, Grade B, ERW, schedule 80 carbon steel,
with screwed joints. Fittings, unions, flanges, and couplings to be ANSI/ASTM B16.3. malleable
iron, Class 150.
F. Pumped Condensate, 2-1/2" and larger: ASTM A53, Grade B, ERW, schedule 80, carbon steel,
with ANSI/AWS D1.1 butt welded joints. Fittings to be ASTM A234, forged steel, Class 150.
Flanges to be Class 150 forged steel slip-on type, or weld-neck flanges for carbon steel.
G. Steel Pipe Nipples: ASTM A733, made of ASTM A 53/A 53M, black steel, of same type, grade,
and schedule as pipe in which installed.
A. Unions:
a. Forged steel, ASTM A105 Grade 2, ASME B16.11, socket weld, 3000 lb. WOG
with steel to steel seats.
B. Flanges:
a. ASTM A105, ANSI B16.5, hot forged steel flanges, welding neck pattern. Slip-on
pattern flanges are not allowed. Bore dimension of welding neck flange shall match
inside diameter of connected pipe. Use raised face flanges for mating with other
raised face flanges with self-centering flat ring gaskets. Use flat face flanges for
mating with other flat face flanges with full face gaskets.
2. Flange pressure class indicated in respective piping service is minimum required. Mating
flange pressure class shall match pressure class of device connected to such as valves
and piping specialties. Flanged connection will on be permitted at specialty connections
such as at a vessel or specialty valve.
C. Flange Gaskets:
1. Gasket material to be asbestos free and suitable for pressure temperatures and fluid of
piping system. Non-metallic gaskets shall be in accordance with ANSI/ASME B16.21 and
ASTM F104.
2. Gaskets shall be equal to Flexitallic Style CG, graphite filler, 304 SS winding, carbon
steel centering ring, 0.175” thickness.
D. Bolting:
A. General: Install valves as shown on plans, details and according to the valve manufacturer’s
installation recommendations.
B. Provide chain operators for manually operated valves 4” and larger, located more than 8’-0”
above normal working surface.
2.10 HIGH PRESSURE STEAM, PUMPED CONDENSATE, AND STEAM TRAP CONDENSATE
SYSTEM VALVES (100 TO 230 PSIG/450°F):
A. Isolation Valves:
1. High pressure steam and condensate isolation valves shall be ANSI Class 300.
a. Up thru 2½ inches:
1) Description: Ball, full port, carbon steel body, 316 SS ball & stem, “Xtreme”
seats & PTFE seals or reinforced PTFE seats & seals, rated for 300 psi at
600°F, threaded end connections, 4” steam extension, Jamesbury: ASTM
A193 Grade B7 bolts with ASTM A194 Grade 2H nuts.
2) Manufacturer and Model No.:
a) Apollo 83-540-64-04.
b) Jamesbury 4BX-22236XT-1.
a) Zwick A1-YZA11AG.
2. Prior to shipment, valves to be hydrostatically and leak tested at the factory. Factory
hydrostatic test shall be performed at 300 psig for all valves.
1. 2” and Smaller: ASTM B62, cast steel body, threaded ends, regrinding, Y-pattern swing
type, renewable TFE seat disc, Class 300 (300 psi WOG), conforming to MSS SP-80.
C. Globe Valves:
1. 2” and Smaller: ANSI Class 600, steel body, stainless steel disc & seat ring, threaded
ends.
2. 2½” and Larger: ANSI Class 300, steel body, stainless steel disc & seat ring, butt weld
ends, constructed in accordance with ASME B16.34
1. Use 1-1/4” globe valve for use on valves 3” and 4" valves.
2. Use 1½” globe valve for use on valves 6” to 10”.
3. Use 2” globe valves for use on valves larger than 12”.
E. Drain Valves:
1. Gate valves as specified above with hose thread adapter and cap. Provide 1” minimum
drain valve except strainer blowdown valves to be blowdown connection size. Drain
valves shall be provided with short threaded nipple and cap.
2.11 VALVES AND SPECIALTIES FOR LP STEAM AND CONDENSATE PIPING
A. Gaskets:
B. Joint Sealers:
C. Flange Bolts and Nuts: Unless required otherwise, conform to ASTM A-354 Grade BD and SAE
J-429 Grade 8 for steam and condensate application.
D. Welding Filler Metals: Comply with AWS D10.12for welding materials appropriate for wall
thickness and chemical analysis of steel pipe being welded.
E. Welding Materials: Comply with Section II, Part C, of ASME Boiler and Pressure Vessel Code
for welding materials appropriate for wall thickness and for chemical analysis of pipe being
welded.
2.13 CHAINWHEELS
B. Description: Valve actuation assembly with sprocket rim, brackets, and chain.
1. Brackets: Type, number, size, and fasteners required to mount actuator on valve.
2. Attachment: For connection to valve stems.
3. Sprocket Rim with Chain Guides: Ductile iron, of type and size required for
valve. Include zinc coating.
4. Chain: Hot-dip, galvanized steel, of size required to fit sprocket rim and long enough to
reach from particular valve height to 3' from finished floor.
PART 3 - EXECUTION
A. Blowdown-Drain Piping: Same materials and joining methods as for piping specified for the
service in which blowdown drain is installed.
B. Air-Vent Piping:
D. Safety Valve Inlet and Outlet Piping: Same materials and joining methods as for piping
specified for the service in which safety valve is installed.
E. As detailed on drawings, install manual pressure relief assemblies to allow safer access to
system components for servicing. Assemblies to be made up of tees, nipples, ball valves, and
strainers with nipple and cap.
A. As shown and detailed, and as called out in conjunction with Section 23 2216.
B. First isolation valves off of mains to be high performance, triple offset butterfly valves.
Downstream from these points for isolation, non-high performance valves may be used.
A. Refer to Division 23 Section “Common Work Results for HVAC” for basic installation
requirements.
B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping
systems. Use indicated piping locations and arrangements if such were used to size pipe and
calculate friction loss, expansion, and other design considerations. Install piping as indicated
unless deviations to layout are approved on Coordination Drawings.
C. Install piping in concealed locations unless otherwise indicated and except in equipment rooms
and service areas.
D. Install piping indicated to be exposed and piping in mechanical rooms and service areas at right
angles or parallel to building walls. Diagonal runs are prohibited unless otherwise indicated.
E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
F. Install piping to permit valve and trap servicing (minimum 14" unobstructed area around traps).
G. Install piping free of bends and sags.
J. Select system components with pressure rating equal to or greater than system operating
pressure.
K. Install groups of pipes parallel to each other, spaced to permit applying insulation and servicing
of valves.
L. Install drains, consisting of a tee fitting, properly rated NPS 3/4 full port ball valve, and short
NPS 3/4 threaded nipple with cap, at low points in piping system mains an elsewhere as
required for system drainage.
M. Install piping, as well as expansion loops, guides and anchors, to allow controlled movement of
piping systems and components, and to minimize stresses from same.
N. Install steam supply piping at a minimum uniform grade of 0.2 percent downward in direction of
steam flow.
O. Install condensate return piping at a minimum uniform grade of 0.4 percent downward in
direction of condensate flow.
P. Reduce pipe sizes using eccentric reducer fitting installed with level side down.
Q. Install branch connections to mains using tee fittings in main pipe, with the branch connected to
top of main pipe, at a 45 degree angle.
R. Install properly rated unions in piping, NPS 2 and smaller, adjacent to valves, at final
connections of equipment, and elsewhere as indicated.
S. Install properly rated flanges in piping, NPS 2-1/2 and larger, at final connections of equipment
and elsewhere as indicated.
T. Install properly rated strainers on supply side of control valves, pressure-reducing valves, traps,
and elsewhere as indicated. Install NPS 3/4 nipple and full port ball valve in blowdown
connection of strainers NPS 2 and larger. Match size of strainer blow-off connection for
strainers smaller than NPS 2.
U. Strainers ahead of steam pressure regulating and control valves shall be mounted on the side
and have blow-off valves.
V. Install properly rated strainers installed ahead of traps on steam main drip legs.
Y. Install drip legs at low points and natural drainage points such as ends of mains, bottoms of
risers, and ahead of pressure regulators, and control valves.
1. On straight runs with no natural drainage points, install drip legs at intervals not
exceeding 150 feet.
2. Size drip legs same size as main. In steam mains NPS 6and larger, drip leg size can be
reduced, but to no less than NPS 4.
3. Install dirt pockets of the drip legs and strainer blow downs with gate valves to remove
dirt and scale.
Z. Comply with requirements in Section 23 0516 "Expansion Fittings and Loops for HVAC
Piping" for installation of expansion loops, expansion joints, anchors, and pipe alignment
guides.
AA. Comply with requirements of Section 23 0553 "Mechanical Systems Identification" for identifying
piping.
BB. Install sleeves for piping penetrations of walls, floors, and ceilings. Comply with requirements
for sleeves specified in Section 23 0517 "Sleeves and Sleeve Seals for HVAC Piping."
CC. Install sleeve seals for piping penetrations of concrete walls, floors, and slabs. Comply with
requirements for sleeves specified in Section 23 0517 "Sleeves and sleeve Seals for HVAC
Piping."
DD. Install escutcheons for piping penetrations of walls, ceilings and floors. Comply with
requirements for escutcheons specified in Section 23 0518 "Escutcheons for HVAC Piping."
A. Join pipe and fittings according to the following requirements and Division 23 Sections
specifying piping systems.
B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.
C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before
assembly.
D. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut
threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore
full ID. Join pipe fittings and valves as follows:
1. Apply appropriate tape or thread compound to external pipe threads unless dry seal
threading is specified.
2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or
damaged. Do not use pipe sections that have cracked or open welds.
E. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and
welding operators according to Part 1 "Quality Assurance" Article.
F. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service
application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.
1. All welding shall be done in accordance with the ANSI B-31.1 and the ASME welding
code.
2. Pipe ends on welded pipe lines shall be suitably beveled to permit butt-welding.
3. All welds shall be of sound metal thoroughly fused to the base metal and penetrating to
the bottom of the joints.
4. Use welding bends in changing pipe directions. Mitered joints will not be accepted.
5. Welders shall be experienced in the type of work to be done. Any welder, who, in the
opinion of the Architect/Engineer or Construction Representative, is not competent to
perform the work required, shall be dismissed from the job. At no time shall any welder
not approved by the Architect/Engineer be allowed to weld pipe on the project.
6. All welders shall be certified under the procedure of the ANSI B-31.1 and the ASME
Welding Code, Section 9, for the thickness and type of high pressure piping and
equipment they work on. Tests shall be conducted by Hartford Insurance Co., or
equivalent certifying agency. The Engineer shall be sent a copy of the certification of all
welders employed on the project.
A. Size for supply and return piping connections shall be the same as or larger than equipment
connections.
B. Install traps and control valves in accessible locations close to connected equipment.
C. Install vacuum breakers downstream from control valve, close to coil inlet connection.
D. Install bypass piping with globe valve around control valves. If parallel valves are installed, only
one bypass is required.
A. Prepare steam and condensate piping according to ASME B31.1, "Power Piping" and/or
ASME B31.9, "Building Services Piping," as applicable, and as follows:
1. Leave joints, including welds, uninsulated and exposed for examination during test.
2. Provide temporary restraints for expansion joints that cannot sustain reactions due to test
pressure. If temporary restraints are impractical, isolate expansion joints from testing.
3. Flush system with clean water. Clean strainers.
4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure shall be
capable of sealing against test pressure without damage to valve. Install blinds in
flanged joints to isolate equipment.
B. Test steam and condensate piping according to ASME B31.1, "Power Piping" and/or
ASME B31.9, "Building Services Piping," as applicable, and as follows:
1. Use ambient temperature water as a testing medium unless there is risk of damage due
to freezing. Another liquid that is safe for workers and compatible with piping may be
used.
2. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the
working pressure. Test pressure shall not exceed maximum pressure for any vessel,
pump, valve, or other component in system under test. Verify that stress due to pressure
at bottom of vertical runs does not exceed 90 percent of specified minimum yield
strength.
3. After hydrostatic test pressure has been applied for at least 10 minutes, examine piping,
joints, and connections for leakage. Eliminate leaks by tightening, repairing, or replacing
components, and repeat hydrostatic test until there are no leaks.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following for LP (Low Pressure) and HP (High Pressure) steam and
condensate piping:
1. Butterfly valves.
2. Check valves.
3. Chainwheels.
4. Strainers.
5. Safety valves.
6. Pressure regulating/reducing valves.
7. Sound attenuators.
8. Steam traps.
9. Thermostatic air vents and vacuum breakers.
10. Pressure gages and gage attachments.
11. Condensate receiver sets.
12. Drip pan elbows.
13. Steam and condensate meters.
C. For the Evanston campus, central steam is distributed at 150 psig (known as the "Campus
Line"), and at 230 psig. These are distinct piping systems but they both originate from the same
high pressure header in the CUP. Steam is and needs to be metered and reduced in pressure
after entrance of each building as required. On the condensate return side, there is high
pressure condensate return and pumped condensate return.
D. For the Chicago campus, central steam is distributed at 170 psig. Steam is and needs to be
metered and reduced in pressure after entrance of each building as required.
E. Both campus's utilize direct buried piping and piping run through tunnels.
A. Components and installation shall be capable of withstanding the following minimum working
pressures and temperatures:
1.5 SUBMITTALS
B. Shop Drawings: Detail condensate receiver set installations, steam pressure reducing valve
and station assemblies, and sound attenuator installations.
D. Operation and Maintenance Data: For all valves, steam traps, air vents, vacuum breakers,
strainers, condensate receiver sets, sound attenuators, and meters to include in emergency,
operation, and maintenance manuals.
E. Coordination Drawings (For Use Amongst the Contractors and For Owner Reference, Not for
Engineer Approval): Piping layout, drawn to scale, on which the following items are shown and
coordinated with each other, using input from installers of the items involved:
H. Delegated-Design Submittal (For Use Amongst the Contractors and For Owner Reference, Not
for Engineer Approval):
1. Design calculations and detailed fabrication and assembly of pipe anchors and alignment
guides, hangers and supports for multiple pipes, expansion joints and loops, and
attachments of the same to the building structure.
2. Locations of pipe anchors and alignment guides and expansion joints and loops.
3. Locations of and details for penetration and firestopping for fire- and smoke-rated wall
and floor and ceiling assemblies.
A. ASME Compliance: Comply with ASME B31.1, “Power Piping” and ASME B31.9, "Building
Services Piping," for materials, products, and installation. Safety valves and pressure vessels
shall bear the appropriate ASME label. Fabricate and stamp air separators and expansion
tanks to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 01.
1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."
2. Certify that each welder has passed AWS qualification tests for welding processes
involved and that certification is current.
C. Steel Support Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M,
"Structural Welding Code, Steel."
D. Piping materials shall bear label, stamp, or other markings of specified testing agency.
E. Comply with FM Global requirements for pressure vessels and piping and for pressure relief
devices.
PART 2 - PRODUCTS
a. Zwick.
2. Description:
1. Class 800:
a. Manufacturers:
1) Kitz (Preferred).
2) Aloyco.
3) Smith.
b. Description: ASME B16.34, Class 800, ASTM A105/A105M forged steel body,
conventional port, horizontal type, bolted bonnet, piston check, spiral wound
gasket, 13 percent chromium stainless steel hard faced seats, threaded or socket
weld ends to match adjacent piping.
B. Over 2 Inch:
1. Class 150:
a. Manufacturers:
b. Description: ASME B16.34, Class 150, ASTM A216/A216M Grade WCB cast steel
body, bolted bonnet, swing check, 13 percent chromium stainless steel hard faced
seats, flanged ends.
c. Accessories (Where Indicated):
2. Class 300:
a. Manufacturers:
b. Description: ASME B16.34, Class 300, ASTM A216/A216M Grade WCB cast steel
body, bolted bonnet, swing check, 13 percent chromium stainless steel hard faced
seats, flanged ends.
c. Accessories (Where Indicated):
B. Description: Valve actuation assembly with sprocket rim, brackets, and chain.
1. Brackets: Type, number, size, and fasteners required to mount actuator on valve.
2. Attachment: For connection to valve stems.
3. Sprocket Rim with Chain Guides: Ductile iron, of type and size required for
valve. Include zinc coating.
4. Chain: Hot-dip, galvanized steel, of size required to fit sprocket rim and long enough to
reach from particular valve height to 3' from finished floor.
2.4 STRAINERS
1. Keckley.
B. LP Y-Pattern Strainers:
1. Body: ASTM A 126, Class B cast iron, with bolted cover and bottom drain connection.
2. End Connections: Threaded ends for strainers NPS 2and smaller; flanged ends for
strainers NPS 2-1/2and larger.
3. Strainer Screen: Monel metal or stainless-steel, 0.033” dia. for steam and 0.045” for
condensate. Free area through the screen shall be at least 2-1/2 times the pipe area in
which it is installed.
4. CWP Rating: 250-psig working steam pressure.
C. LP Basket Strainers:
1. Body: ASTM A 126, Class B cast iron, with bolted cover and bottom drain connection.
2. End Connections: Threaded ends for strainers NPS 2and smaller; flanged ends for
strainers NPS 2-1/2and larger.
3. Strainer Screen: Stainless-steel, 20 mesh strainer, and perforated stainless-steel basket
with 50 percent free area.
4. CWP Rating: 250-psigworking steam pressure.
D. HP Y-Pattern Strainers:
1. ASME, Class 600, cast carbon or cast alloy steel or stainless steel models, properly
outfitted for the duty and with suitable end connections.
E. HP Basket Strainers:
1. ASME, Class 600, cast carbon steel or stainless steel with bolted bonnet, properly
outfitted for the duty and with suitable end connections. ValvSource/Spence 150V2 or
approved equal by Mueller or Sarco.
C. HP Safety Valves:
1. Fisher 92B
B. Description: Single seated, normally closed, pilot operated, packless type, with stainless steel
diaphragms, hardened seats and discs, and stainless steel stems.
D. Rated for specific project application as far as maximum working pressures and temperatures.
E. Limit inlet velocity to 10,000 FPM, and exit velocity to 30,000 FPM.
G. Pilot: Externally-mounted for valves 6" and larger, and top or externally-mounted for 5" and
smaller.
H. Body: Cast iron or ductile iron for LP, cast steel or ductile iron for HP.
I. End Connections: Threaded connections for valves NPS 2 and smaller and flanged
connections for valves NPS 2-1/2 and larger.
K. Head and Seat: Replaceable, main head stem guide fitted with flushing and pressure-arresting
device cover over pilot diaphragm.
1. Fisher, Whisperdisc.
2. Spirax Sarco, Inc.
B. Description: Dissipative reactive type to provide maximum sound attenuation for each individual
application, with minimal pressure drop.
C. Noise suppressor: Consist of a welded steel expanded outlet shell suitable for up to 300 psig
steam maximum working pressure, containing a deflector assembly and acoustic packing of
stainless steel.
D. Muffling orifice(s): Consist of a steel plate with primary orifices to which is welded a stainless
steel plate with secondary orifices.
1. Armstrong.
1. Cast iron body and cover, non-asbestos gasket, screwed ends, stainless steel heads,
seats and thermostatic air vent.
2. Basis of Design: Armstrong – Models as commonly used on campus. Confirm with
EVENG shop.
1. Cast iron body and cover, threaded connections, stainless steel bucket, renewable
hardened stainless steel head and seat.
2. Basis of Design: Armstrong – Models as commonly used on campus. Confirm with
EVENG shop.
1. Cast steel body and cover, non-asbestos gasket, ends as needed, stainless steel heads,
seats and thermostatic air vent.
2. Basis of Design: Armstrong – Models as commonly used on campus. Confirm with
EVENG shop.
1. Cast steel or stainless steel, connections as required, stainless steel bucket, renewable
hardened stainless steel head and seat.
2. Basis of Design: Armstrong models as commonly used on Campus, confirm with HVAC
Shop.
1. ASTM A743 GR. CA40F 420F, stainless steel, 600 psig PMO, NPT connections.
2. Spirax Sarco TD-52.
C. Vacuum Breakers:
a. Trerice, H. O. Co.
b. Weiss Instruments, Inc.
c. Weksler.
A. Snubbers: ASME B40.100, brass; with NPS 1/4 or NPS 1/2 (DN 8 or DN 15), ASME B1.20.1
pipe threads and porous-metal-type surge-dampening device. Include extension for use on
insulated piping.
B. Siphons: Loop-shaped section of stainless-steel or steel pipe with NPS 1/4 or NPS 1/2 (DN 8 or
DN 15) pipe threads.
C. Valves: Brass ball, with NPS 1/4 or NPS 1/2 (DN 8 or DN 15), ASME B1.20.1 pipe threads.
2.12 STEAM CONDENSATE RECEIVER SET WITH DUPLEX CENTRIFUGAL PUMPS AND
FLOOR-MOUNTED RECEIVER (FOR NORMAL DUTY)
1. ITT Hoffman.
C. Configuration: Duplex floor-mounted pump with receiver and float switches; rated to pump 200
deg F steam condensate.
D. Receiver:
1. Floor mounted.
2. Primed and painted or coated steel.
3. Externally adjustable float switches.
4. Flanges for pump mounting.
5. Water-level gage and dial thermometer.
6. Pressure gage at pump discharge.
7. Bronze fitting isolation valve between pump and receiver.
8. Inlet vent and an overflow.
9. Cast-iron inlet strainer with self-cleaning bronze screen and large dirt pocket.
10. Inlet centerline no higher than 7" above mounting surface.
E. Pumps:
F. Motors:
1. Comply with NEMA designation, temperature rating, service factor, and efficiency
requirements for motors specified in Section 23 0513 "Motors."
2. Enclosure: TEFC.
3. Efficiency: Meet in force energy code.
4. NEMA Design: To suit installation location.
5. Service Factor: Manufacturer's standard.
6. RPM: 1800 maximum.
G. Control Panel:
1. Factory wired between pumps and float switches, for single external electrical
connection.
2. Provide fused, control-power transformer if voltage exceeds 230 V ac.
3. NEMA 250 enclosure (as properly suited for installation location) with hinged door and
grounding lug, mounted on pump.
4. Motor controller for each pump.
5. Electrical pump alternator to operate pumps in lead-lag sequence and allow both pumps
to operate on receiver high level.
6. Manual lead-lag control to override electrical pump alternator and manually select the
lead pump.
7. Momentary-contact "TEST" push button on cover for each pump.
8. Numbered terminal strip.
9. Disconnect switch.
A. ASTM A126 CL B cast iron, with female NPT connections up thru 4" and ANSI 125 flanges for
6" and 8" sizes. Pipe and support as shown on drawings.
A. Steam - All buildings that purchase steam from Northwestern University, or are research
facilities with a steam turndown ratio less than 15:1, shall have a direct measurement of steam.
Steam flow shall be measured using a differential pressure flow meter. Condensate meters shall
also be provided in these buildings.
1. All buildings where steam is not directly measured shall have condensate metered to
determine the steam usage.
2. Steam flow meters shall measure volumetric flow. The flow processor shall input the
volumetric flow rate, and utilize internal steam tables and a static steam pressure sensor
to determine the mass flow rate of the steam. The flow processor shall assume that the
steam is saturated.
B. Steam Condensate - Condensate shall be measured using a positive displacement type meter
for pipe sizes less than 1”, and a vortex shedding flow meter for pipe sizes 1” and greater. Flow
Switches shall be installed on all condensate receiver drain pipes. Provide a valved
(removable/lockable handle) meter bypass and a bleed-off drain pipes sizes greater than 1”.
C. Flow meters used to measure Energy Consumption or Mass Flow require a flow processor to
input the flow meter and pressure sensors (steam), calculate the Energy Consumption or Mass
Flow, and send a pulse output signal to the BAS that represents the results of this calculation.
Spare flow processor analog outputs shall be used to output real-time flow rate and steam
pressure. The Northwestern FMO Instrumentation Specialist shall define the ranges of these
output(s) for proper scaling of the 4-20mA signal.
E. Positive displacement impeller type condensate meters shall be Data Industrial BR-250 Tee
Flow Sensor with conduit adaptor, or approved equal. Features and performance data as
follows:
F. Vortex Shedding Flow Meter with Integral Pressure and Temperature Measurement:
a. Onicon.
b. Krohne.
2. Description:
a. Mass flow measurement corrected for density using vortex shedder body with
integral piezoelectric pressure sensors and 1000-ohm platinum RTD.
b. Meter NPS 1/2 through NPS 12.
c. Each meter shall be factory calibrated at five points from Zero to 250 fps and
tagged accordingly against the manufacturer's flow standards. The manufacturer
shall provide a certificate of calibration for meter.
d. Each meter shall be programmed using project-specific application data.
e. Meter shall include integral diagnostics to verify installation conditions and proper
operation.
3. Performance:
a. Volumetric Flow Accuracy for Liquid: Within 0.75 percent of reading for Reynolds
numbers 20000 and larger.
b. Volumetric Flow Accuracy for Steam and Gas: Within 1 percent of reading for
Reynolds numbers 20000 and larger.
c. Mass Flow Accuracy for Steam and Gas: Within 1.5 percent of reading for
Reynolds numbers 20000 and larger.
d. Repeatability: Within 0.1 percent.
e. Long-Term Stability: Within 0.1 percent per year.
f. Ambient Temperature: Minus 40 to plus 185 deg F.
g. Process Temperature: Minus 40 to plus 464 deg F.
h. Pressure: Equal to flange rating.
4. Output Signals:
1) Pulse output for flow totalization. Two wire, scaled pulse, 0.5 Hz, 100 mA at
30-V dc.
2) Protocol: compatible with project DDC/BAS, see Section 25 0000.
5. Operator Interface:
a. Keypad.
b. Digital Display: Two-line digital display of alphanumerical characters. The meter
shall display flow rate, flow totalization, pressure, temperature, and support field
programming of all parameters.
6. Construction:
A. Blowdown-Drain Piping: Same materials and joining methods as for piping specified for the
service in which blowdown drain is installed.
B. Air-Vent Piping:
D. Safety Valve Inlet and Outlet Piping: Same materials and joining methods as for piping
specified for the service in which safety valve is installed.
E. Drip Pan Elbows: Pipe per drip pan elbow and safety valve manufacturer's instructions,
coordinate with GC for roof penetrations.
F. As detailed on drawings, install manual pressure relief assemblies to allow safer access to
system components for servicing. Assemblies to be made up of tees, nipples, ball valves, and
strainers with nipple and cap.
A. Install shutoff duty valves at branch connections to steam supply mains, at steam supply
connections to equipment, at the outlet of steam traps, and as shown or noted on the drawings.
B. Install safety valves at pressure-reducing stations and elsewhere as required by ASME Boiler
and Pressure Vessel Code. Comply with ASME Boiler and Pressure Vessel Code: Section VIII,
Division 1, for installation requirements.
C. Install check valves at traps as detailed and as otherwise required to control flow direction.
D. For anything over 3” and 75 psi, the first isolation valves off of mains to be high performance,
triple offset butterfly valves. Downstream from these points for isolation, non-high performance
valves may be used.
E. Add chainwheels to valves 6" or larger and mounted 8 feet above the floor or higher. Provide
gear operators for valves 8" and larger.
B. Install drains, consisting of a tee fitting, NPS 3/4 full port-ball valve, and short NPS 3/4 threaded
nipple with cap, at low points in piping system mains and elsewhere as required for system
drainage.
C. Install valves according to Section 23 0523 "General Duty Valves for HVAC" and per this
section.
D. Install unions in piping, NPT 1-1/4 and smaller, adjacent to valves, at final connections of
equipment, and elsewhere as indicated.
E. Install flanges in piping, NPS 1-1/2 and larger, at final connections of equipment and elsewhere
as indicated.
G. Install strainers on supply side of control valves, pressure-reducing valves, traps, and elsewhere
as indicated. Install NPS 3/4 nipple and full port ball valve in blowdown connection of strainers
NPS 2 and larger. Match size of strainer blowoff connection for strainers smaller than NPS 2.
A. Install steam traps as shown and as required in accessible locations as close as possible to
connected equipment. Minimum of 14" unobstructed space around traps required.
B. Provide test port downstream of each steam trap assembly. The test port assembly is to consist
of a tee, nipple, ball valve, and nipple plug. The test port assembly is to be before the check.
C. Install full-port ball valve, strainer, and union upstream from trap; install union, check valve, and
full-port ball valve downstream from trap unless otherwise indicated. Install two full-port ball
valves, union, and strainer upstream of trap; and check valve, union, and two full-port ball
valves after trap.
D. All low points and drip legs in steam lines and the bottom of down feed risers shall have traps of
proper size.
E. Return ends of all equipment where steam is condensed, shall have traps of proper size and
type.
G. Install traps with isolation valves and unions on both sides. Ahead of each high pressure drip,
install a dirt pocket not less than 8 inches long and fitted with threaded reducer, 1” rising stem
valve, nipple and a threaded cap on the bottom for 2” and smaller; and with welded cap, 1”
thread-o-let, isolation valve, nipple and threaded cap for 2-1/2” and larger.
H. Steam trap of temperature-regulated equipment must not be located at less than 14" below the
bottom of the coil outlet, and condensate discharge from the trap must flow by gravity, without
any lifts in the piping, to the condensate receiver.
B. Install gate or butterfly valves on both sides of pressure-reducing valves. A warmup line shall be
provided around butterfly valves where used in this application.
C. Install unions or flanges on both sides of pressure-reducing valves having threaded or flanged
end connections respectively.
D. Install pressure gages on high and low-pressure sides of pressure-reducing valves (after the
bypass connections) according to Division 23 Section "Meters and Gages for HVAC Piping" and
this section.
E. Install strainers upstream for pressure-reducing valves. Install strainers with blow-off valves on
side.
H. Provide straight run of pipe on sides of the PRVs, at least 10 pipe diameters to the inlet and 20
pipe diameters of expanded line size from the outlet.
I. Install bypass piping around pressure regulating/reducing valves with globe valve equal in size
to the pressure regulating/reducing valve seat ring, unless indicated otherwise.
J. Avoid abrupt changes in pipe size. Use eccentric reducers upstream and concentric increasers
downstream of the PRVs.
A. Install meters with lengths of straight pipe upstream and downstream according to meter
manufacturer's instructions.
A. Install safety valves according to ASME B31.1, "Power Piping" and/or ASME B31.9, "Building
Services Piping."
C. Install drip-pan elbow fitting adjacent to safety valve and pipe drain connection to nearest floor
drain.
D. Install exhaust head with drain to waste, on vents equal to or larger than NPS 2-1/2.
A. Size for supply and return piping connections shall be the same as or larger than equipment
connections.
B. Install traps and control valves in accessible locations close to connected equipment.
C. Install vacuum breakers downstream from control valve, close to coil inlet connection.
A. Prepare steam and condensate piping according to ASME B31.1, "Power Piping" and/or
ASME B31.9, "Building Services Piping," and as follows:
1. Leave joints, including welds, uninsulated and exposed for examination during test.
2. Provide temporary restraints for expansion joints that cannot sustain reactions due to test
pressure. If temporary restraints are impractical, isolate expansion joints from testing.
3. Flush system with clean water. Clean strainers.
4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure shall be
capable of sealing against test pressure without damage to valve. Install blinds in
flanged joints to isolate equipment.
1. Use ambient temperature water as a testing medium unless there is risk of damage due
to freezing. Another liquid that is safe for workers and compatible with piping may be
used.
2. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the
working pressure. Test pressure shall not exceed maximum pressure for any vessel,
pump, valve, or other component in system under test. Verify that stress due to pressure
at bottom of vertical runs does not exceed 90 percent of specified minimum yield
strength.
3. After hydrostatic test pressure has been applied for at least 10 minutes, examine piping,
joints, and connections for leakage. Eliminate leaks by tightening, repairing, or replacing
components, and repeat hydrostatic test until there are no leaks.
PART 1 - GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
A. Product Data: For each type of valve and refrigerant piping specialty indicated. Include
pressure drop based on manufacturer's test data.
B. Shop Drawings: Show layout of refrigerant piping and specialties, including pipe, tube, and
fitting sizes, flow capacities, valve arrangements and locations, slopes of horizontal runs, oil
traps, double risers, wall and floor penetrations, and equipment connection details. Show
interface and spatial relationships between piping and equipment.
1. Refrigerant piping indicated on Drawings is schematic only. Size piping and design
actual piping layout, including oil traps, double risers, specialties, and pipe and tube sizes
to accommodate, as a minimum, equipment provided, elevation difference between
compressor and evaporator, and length of piping to ensure proper operation and
compliance with warranties of connected equipment.
A. Comply with ASHRAE 15 (latest edition), "Safety Code for Refrigeration Systems."
B. Comply with ASME B31.5 (latest edition), "Refrigeration Piping & Heat Transfer Components."
A. Store piping in a clean and protected area with end caps in place to ensure that piping interior
and exterior are clean when installed.
1.5 INSTALLATION
A. Provide filter/dryer assemblies, moisture indicators, thermal expansion valve and solenoid
valves for each refrigeration circuit.
C. Leak test piping and joints with an electronic or halide leak detector.
D. Evacuate entire system with an approved high vacuum pump system to 500 microns.
PART 2 - PRODUCTS
1. Moisture/Liquid Indicators:
2. Replaceable-Core Filter Dryers: Comply with ARI 730.
3. Permanent Filter Dryers: Comply with ARI 730.
4. Liquid Accumulators: Comply with ARI 495.
PART 3 - EXECUTION
A. Suction Lines, Hot Gas and Liquid Lines All Sizes to be Copper, Type ACR, annealed-temper
tubing and wrought-copper fittings with brazed joints.
B. Safety-Relief-Valve Discharge Piping: Copper, Type ACR, drawn-temper tubing and wrought-
copper fittings with brazed joints.
A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping
systems; indicated locations and arrangements were used to size pipe and calculate friction
loss, expansion, pump sizing, and other design considerations. Install piping as indicated
unless deviations to layout are approved on Shop Drawings.
B. Install refrigerant piping according to ASHRAE 15.
C. Install piping in concealed locations unless otherwise indicated and except in equipment rooms
and service areas.
D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right
angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated
otherwise.
E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
I. Select system components with pressure rating equal to or greater than system operating
pressure.
J. Refer to Division 23 Sections "Instrumentation and Control for HVAC" and "Sequence of
Operations for HVAC Controls" for solenoid valve controllers, control wiring, and sequence of
operation.
K. Install piping as short and direct as possible, with a minimum number of joints, elbows, and
fittings.
L. Arrange piping to allow inspection and service of refrigeration equipment. Install valves and
specialties in accessible locations to allow for service and inspection. Install access doors or
panels as specified in Division 08 Section "Access Doors and Frames" if valves or equipment
requiring maintenance is concealed behind finished surfaces.
M. Install refrigerant piping in rigid or flexible conduit in locations where exposed to mechanical
injury.
1. Install horizontal hot-gas discharge piping with a uniform slope downward away from
compressor.
2. Install horizontal suction lines with a uniform slope downward to compressor.
O. When brazing, remove solenoid-valve coils and sight glasses; also remove valve stems, seats,
and packing, and accessible internal parts of refrigerant specialties. Do not apply heat near
expansion-valve bulb.
P. Install piping with adequate clearance between pipe and adjacent walls and hangers or between
pipes for insulation installation. Insulate suction lines with 1.5" of flexible elastomeric insulation,
and weather-proof same outdoors with two coats of insulation manufacturer's weather-proofing
coating. Refer to Section 230719 for further general requirements pertaining to pipe insulation.
Q. Identify refrigerant piping and valves according to Division 23 Section "Identification for HVAC
Piping and Equipment."
R. Install sleeves for piping penetrations of walls, ceilings, and floors. Comply with requirements
for sleeves specified in applicable Division 23 Section. Install sleeve seals for piping
penetrations of concrete walls and slabs. Comply with requirements for sleeve seals specified
in applicable Division 23 Section. Install escutcheons for piping penetrations of walls, ceilings,
and floors. Comply with requirements for escutcheons specified in applicable Division 23
Section.
A. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," Chapter "Pipe and
Tube."
A. Hanger, support, and anchor products are specified in Division 23 Section "Hangers and
Supports for HVAC Piping and Equipment."
1. Adjustable steel clevis hangers for individual horizontal runs less than 20 feet long.
2. Roller hangers and spring hangers for individual horizontal runs 20 feet or longer.
3. Pipe Roller: MSS SP-58, Type 44 for multiple horizontal piping 20 feet or longer,
supported on a trapeze.
4. Spring hangers to support vertical runs.
5. Copper-clad hangers and supports for hangers and supports in direct contact with copper
pipe.
C. Install hangers for copper tubing with the following maximum spacing and minimum rod sizes:
1. NPS 1/2: Maximum span, 60 inches; minimum rod size, 1/4 inch.
2. NPS 5/8: Maximum span, 60 inches; minimum rod size, 1/4 inch.
3. NPS 1: Maximum span, 72 inches; minimum rod size, 1/4 inch.
4. NPS 1-1/4: Maximum span, 96 inches; minimum rod size, 3/8 inch.
5. NPS 1-1/2: Maximum span, 96 inches; minimum rod size, 3/8 inch.
6. NPS 2: Maximum span, 96 inches; minimum rod size, 3/8 inch.
B. Piping shall be evacuated, tested, adjusted, and charged in strict accordance with the
equipment manufacturer's instructions.
PART 1 - GENERAL
A. Conform to applicable EPA code for addition of non-potable chemicals to building mechanical
systems and for discharge to public sewage systems.
PART 2 - PRODUCTS
2.1 MATERIALS
A. All materials proposed must be compatible with existing treatment systems and chemicals.
B. System Cleaner:
1. Liquid alkaline compound with emulsifying agents and detergents to remove grease and
petroleum products.
2.2 EQUIPMENT
A. Water Meter: Displacement type cold water meter with sealed, tamper proof magnetic drive,
impulse contact register, single pole, double throw dry contact switch.
PART 3 - EXECUTION
3.1 PREPARATION
A. Systems shall be operational, filled, started and vented prior to cleaning. Use water meter to
record capacity in each system.
C. Chilled Water Systems: Circulate for 48 hours, then drain systems as quickly as possible. Refill
with clean water, circulate for 24 hours, then drain. Refill with clean water and repeat until
system cleaner is removed.
D. Steam Systems: Apply heat, slowly raising boiler temperature to 160°F and maintain for 12
hours minimum. Cool, then drain as quickly as possible. Refill with clean water, drain, refill and
check for sludge. Repeat until system is free of sludge. Apply heat to produce steam for piping
system and maintain for 8 hours minimum. Bypass traps and waste condensate.
E. Use neutralizer agents on recommendation of system cleaner supplier and approval of Owner.
F. Flush open systems with clean water for one hour minimum. Drain completely and refill.
H. Inspect, remove sludge and flush low points with clean water after cleaning process is
completed. Include disassembly of components as required.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
B. Related Sections:
A. Delegated Duct Design: Duct construction, including sheet metal thicknesses, seam and joint
construction, reinforcements, and hangers and supports, shall comply with SMACNA's "HVAC
Duct Construction Standards - Metal and Flexible" and performance requirements and design
criteria indicated in the "Duct Schedule" Article and on the drawings.
B. Structural Performance: Duct hangers and supports shall withstand the effects of gravity loads
and stresses within limits and under conditions described in SMACNA's "HVAC Duct
Construction Standards - Metal and Flexible."
C. Airstream Surfaces: Surfaces in contact with the airstream shall comply with requirements in
ASHRAE 62.1.
DUCTWORK 23 3114 - 1
D. SMACNA's 3rd Edition, 2005, "HVAC Duct Construction Standards - Metal and Flexible," as
referenced herein.
B. Delegated-Design Information (for Contractor Use and University Reference, Not For Engineer
Approval) :
1.5 INFORMATIONAL SUBMITTALS (For Use Amongst the Contractors and For Owner Reference,
Not For Engineer Approval)
A. Coordination Drawings: Plans, drawn to scale, on which the following items are shown and
coordinated with each other, using input from installers of the items involved:
B. Welding certificates.
1. AWS D1.1/D1.1M, "Structural Welding Code - Steel," for hangers and supports.
2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum," for aluminum supports.
3. AWS D9.1M/D9.1, "Sheet Metal Welding Code," for duct joint and seam welding.
PART 2 - PRODUCTS
A. Not allowed.
A. Not allowed.
A. Fabricate and install all duct fittings, branches, inlets, outlets, transitions, take-offs, laterals,
offsets, and elbows to minimize air turbulence and resistance and to ensure proper airflows.
C. Elbows, Transitions, Offsets, Branch Connections, and Other Duct Construction: Select types
and fabricate according to SMACNA's 2005 "HVAC Duct Construction Standards - Metal and
Flexible," Chapters 3 and 4, for static-pressure class, applicable sealing requirements, materials
involved, duct-support intervals, and other provisions in SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible." But:
1. Mitered elbows with turning vanes not permitted, use radius elbows.
2. Radius elbows shall have minimum centerline radius to width or diameter ratio of 1.5. If
1.5 ratio elbows do not fit, use 1.0 radius elbows. Where 1.0 radius elbows do not fit, use
square throat elbows with turning vanes.
3. Pleated or adjustable elbows not allowed.
4. No straight taps, branch or lateral take-offs, or connections, all to be expanded or conical,
and taken off at an angle < 90° if possible.
5. No bullhead tees for either diverging or converging flow.
6. For transitions, where the shape of the duct changes, ensure the angle of the side of the
transition piece does not exceed 15° from the straight run of duct connected thereto.
Where equipment is installed in the ductwork, ensure the angle of the side of the
transition piece from the straight run of duct connected thereto does not exceed 15° on
the upstream side of the equipment and 22.5° on the downstream side of the equipment.
7. Special duct branch requirements: Where a duct branch handles over 25% of the air
transported by the duct main, use a complete 90° increasing elbow, with an inside radius
of 0.75 times the duct branch width. Ensure the size of the trailing end of the increasing
elbow within the duct main is in the same ratio to the main duct size as the ratio of the
relative air quantities being handled. Where a duct branch is to handle 25% or less of the
air handled by the duct main, provide a branch connection with an inside radius of 0.75
times the branch duct width, a minimum arc length of 45°, and an outside radius of 1.75
times the duct branch width. Place arc tangent to the duct main.
8. Saddle taps are not allowed on new or existing ducts.
9. See more information and requirements in PART 3 herein.
A. General Fabrication Requirements: Comply with SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible" based on indicated static-pressure class unless otherwise
indicated. But, duct wall thickness to be minimum 22 gage except where any welding other
than longitudinal seams is performed, then the minimum thickness shall be 18 gage, and, no
crimp joints allowed.
B. Transverse Joints: Select joint types and fabricate according to SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible," Figure 2-1, "Rectangular Duct/Transverse Joints,"
for static-pressure class, applicable sealing requirements, materials involved, duct-support
intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and
Flexible." But, transverse (girth) joints T-4, 9, 17 through 20, and 23 not permitted.
C. Longitudinal Seams: Select seam types and fabricate according to SMACNA's 2005 "HVAC
Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Duct/Longitudinal
Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-
support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards -
Metal and Flexible." But, button punch snaplock seams are not permitted.
B. General Fabrication Requirements: Comply with SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible" based on indicated static-pressure class unless otherwise
indicated. Duct wall thickness to be minimum 22 gage except where any welding other than
longitudinal seams is performed, then the minimum thickness shall be 18 gage.
C. Contractor Fabricated Ductwork: Ductwork of this section (2.5) may be fabricated by the
contractor if it can be demonstrated that it meets or exceeds the performance of the
manufacturer's products listed directly above.
D. Rectangular Ducts: Fabricate ducts with indicated dimensions for the inner duct. But, duct wall
thicknesses to be minimum 22 gage except where any welding other than longitudinal seams is
performed, then the minimum thickness shall be 18 gage.
E. Outer Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal and
Flexible" based on indicated static-pressure class unless otherwise indicated.
F. Transverse Joints: Select joint types and fabricate according to SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible," Figure 2-1, "Rectangular Duct/Transverse Joints,"
for static-pressure class, applicable sealing requirements, materials involved, duct-support
intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and
Flexible." But, transverse (girth) joints T-4, 9, 17 through 20, and 23 not permitted.
G. Longitudinal Seams: Select seam types and fabricate according to SMACNA's 2005 "HVAC
Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Duct/Longitudinal
Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-
support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards -
Metal and Flexible." But, button punch snaplock seams are not permitted.
H. Interstitial Insulation: Fibrous-glass liner complying with ASTM C 1071, NFPA 90A, or
NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard."
1. Maximum Thermal Conductivity: 0.27 Btu x in./h x sq. ft. x deg F (0.039 W/m x K) at 75
deg F mean temperature.
2. Install spacers that position the inner duct at uniform distance from outer duct without
compressing insulation.
3. Coat insulation with antimicrobial coating.
4. Cover insulation with polyester film complying with UL 181, Class 1.
5. Insulation Thickness: See PART 3.
J. Formed-on Transverse Joints (Flanges): Select joint types and fabricate according to
SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-1, "Rectangular
Duct/Traverse Joints," for static-pressure class, applicable sealing requirements, materials
involved, duct-support intervals, and other provisions in SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible." But, transverse (girth) joints T-4, 9, 17 through
20, and 23 not permitted.
2.6 SINGLE-WALL ROUND AND FLAT-OVAL DUCTS AND FITTINGS
A. General Fabrication Requirements: Comply with SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible," Chapter 3, "Round, Oval, and Flexible Duct," based on
indicated static-pressure class unless otherwise indicated but, only spiral seam or fully welded
longitudinal seam duct is to be used. And, longitudinal seam ductwork not to be used if
exposed.
B. Contractor Fabricated Ductwork: Ductwork of this section (2.6) may be fabricated by the
contractor if it can be demonstrated that it meets or exceeds the performance of the
manufacturer's products listed directly above.
C. Flat-Oval Ducts: Indicated dimensions are the duct width (major dimension) and diameter of the
round sides connecting the flat portions of the duct (minor dimension). SMACNA Type 1
reinforcement (Figure 3-6 of SMACNA's Duct Construction Standards) is not allowed.
D. Transverse Joints: Select joint types and fabricate according to SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible," Figure 3-1, "Round Duct Transverse Joints," for
static-pressure class, applicable sealing requirements, materials involved, duct-support
intervals, and other provisions in SMACNA's 2005 "HVAC Duct Construction Standards - Metal
and Flexible." But, no crimp joints allowed.
E. Longitudinal Seams: Select seam types and fabricate according to SMACNA's 2005 "HVAC
Duct Construction Standards - Metal and Flexible," Figure 3-2, "Round Duct Longitudinal
Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-
support intervals, and other provisions in SMACNA's 2005 "HVAC Duct Construction Standards
- Metal and Flexible." But, snaplock seams not allowed.
1. Fabricate round ducts larger than 90 inches in diameter with butt-welded longitudinal
seams.
2. Fabricate flat-oval ducts larger than 72 inches in width (major dimension) with butt-
welded longitudinal seams.
B. Contractor Fabricated Ductwork: Ductwork of this section (2.7) may be fabricated by the
contractor if it can be demonstrated that it meets or exceeds the performance of the
manufacturer's products listed directly above.
C. Flat-Oval Ducts: Indicated dimensions are the duct width (major dimension) and diameter of the
round sides connecting the flat portions of the duct (minor dimension) of the inner duct.
SMACNA Type 1 reinforcement (Figure 3-6 of SMACNA's Duct Construction Standards) is not
allowed.
D. Outer Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal and
Flexible," Chapter 3, "Round, Oval, and Flexible Duct," based on static-pressure class unless
otherwise indicated.
E. Transverse Joints: Select joint types and fabricate according to SMACNA's 2005 "HVAC Duct
Construction Standards - Metal and Flexible," Figure 3-1, "Round Duct Transverse Joints," for
static-pressure class, applicable sealing requirements, materials involved, duct-support
intervals, and other provisions in SMACNA's 2005 "HVAC Duct Construction Standards - Metal
and Flexible." And, no crimp joints allowed.
F. Longitudinal Seams: Select seam types and fabricate according to SMACNA's 2005 "HVAC
Duct Construction Standards - Metal and Flexible," Figure 3-2, "Round Duct Longitudinal
Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-
support intervals, and other provisions in SMACNA's 2005 "HVAC Duct Construction Standards
- Metal and Flexible." But, no snaplock seams allowed.
1. Fabricate round ducts larger than 90 inches in diameter with butt-welded longitudinal
seams.
2. Fabricate flat-oval ducts larger than 72 inches in width (major dimension) with butt-
welded longitudinal seams.
G. Inner Duct: Minimum 0.028-inch thick solid sheet steel. Factory fabricated, insulated round
duct to be McGill Airflow, Acoustic K-27, or approved equal by SEMCO or Spiral Manufacturing
Co., Inc.
H. Interstitial Insulation: Fibrous-glass liner complying with ASTM C 1071, NFPA 90A, or
NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard."
1. Maximum Thermal Conductivity: 0.27 Btu x in./h x sq. ft. x deg F (0.039 W/m x K) at 75
deg F mean temperature.
2. Install spacers that position the inner duct at uniform distance from outer duct without
compressing insulation.
3. Thickness for ducts inside the building minimum 1.5", 3" thickness for ducts outside.
A. Ductwork and shall be all welded Type 316 stainless steel, minimum 18 gage.
2.9 SHEET METAL MATERIALS
A. General Material Requirements: Comply with SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible" for acceptable materials, material thicknesses, and duct
construction methods unless otherwise indicated. Duct wall thickness to be minimum 22 gage
except where any welding other than longitudinal seams is performed, then the minimum
thickness shall be 18 gage.
B. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains, discolorations,
and other imperfections.
D. Stainless-Steel Sheets: Comply with ASTM A 480/A 480M, Type 304 or 316 (Type 316 only for
Lab exhaust), as indicated in the "Duct Schedule" Article; cold rolled, annealed, sheet. Exposed
surface finish shall be No. 2B, No. 2D, No. 3, or No. 4 as indicated in the "Duct Schedule"
Article.
E. Aluminum Sheets: Comply with ASTM B 209 (ASTM B 209M) Alloy 3003, H14 temper; with mill
finish for concealed ducts, and standard, one-side bright finish for duct surfaces exposed to
view.
F. Reinforcement Shapes and Plates for Galvanized Ducts: ASTM A 36/A 36M, steel plates,
shapes, and bars; black and galvanized.
1. Where black and galvanized-steel shapes and plates are used to reinforce aluminum or
stainless steel ducts, isolate the different metals with butyl rubber, neoprene, or EPDM
gasket materials.
G. Tie Rods: Galvanized steel, 1/4-inch minimum diameter for lengths 36 inches or less; 3/8-inch
minimum diameter for lengths longer than 36 inches.
A. General Sealant and Gasket Requirements: Surface-burning characteristics for sealants and
gaskets shall be a maximum flame-spread index of 25 and a maximum smoke-developed index
of 50 when tested according to UL 723; certified by an NRTL.
D. Flanged Joint (SMACNA Joints T-24, T-25, and proprietary slip-on flanges) Sealant: Comply
with ASTM C 920.
E. Flange Gaskets: Butyl rubber, neoprene, or EPDM polymer with polyisobutylene plasticizer.
G. Duct Sealer Manufacturers/Products: United Airseal - United Duct Seal, Mon-Eco Industries
44/48, or Foster 32.
H. Lab Exhaust Duct/System Sealant: For any non-welded joints or connections, sealants shall be
custom selected for the duty, including proper chemical resistance against whatever is to be
transported in the duct system.
A. Shall be in accordance with SMACNA's 2005 "HVAC Duct Construction Standards - Metal and
Flexible" except non-engineered wire hangers are not permitted. Engineered cable support
systems may be used if they meet SMACNA, Ductmate or approved equal.
B. Hanger Rods for Noncorrosive Environments: Cadmium-plated steel rods and nuts.
C. Hanger Rods for Corrosive Environments: Electrogalvanized, all-thread rods or galvanized rods
with threads painted with zinc-chromate primer after installation.
D. Strap and Rod Sizes: Comply with SMACNA's 2005 "HVAC Duct Construction Standards -
Metal and Flexible," Table 5-1 (Table 5-1M), "Rectangular Duct Hangers Minimum Size," and
Table 5-2, "Minimum Hanger Sizes for Round Duct."
E. Steel Cables for Galvanized-Steel Ducts: Galvanized steel complying with ASTM A 603.
F. Steel Cables for Stainless-Steel Ducts: Stainless steel complying with ASTM A 492.
G. Steel Cable End Connections: Cadmium-plated steel assemblies with brackets, swivel, and
bolts designed for duct hanger service; with an automatic-locking and clamping device.
H. Duct Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws; compatible
with duct materials.
PART 3 - EXECUTION
A. Drawing plans, schematics, and diagrams indicate general location and arrangement of duct
system. Indicated duct locations, configurations, and arrangements were used to size ducts
and calculate friction loss for air-handling equipment sizing and for other design considerations.
Install duct systems as indicated unless deviations to layout are approved on Shop Drawings
and Coordination Drawings.
B. Install ducts according to SMACNA's 2005 "HVAC Duct Construction Standards - Metal and
Flexible" unless otherwise indicated.
E. Install factory or shop fabricated fittings for changes in direction, size, and shape and for branch
connections.
F. Unless otherwise indicated, install ducts vertically and horizontally, and parallel and
perpendicular to building lines.
G. Install ducts close to walls, overhead construction, columns, and other structural and permanent
enclosure elements of building.
H. Install ducts with a clearance of 1 inch, plus allowance for insulation thickness.
I. Route ducts to avoid passing through transformer vaults and electrical equipment rooms and
enclosures.
J. Where ducts pass through non-fire-rated interior partitions and exterior walls and are exposed
to view, cover the opening between the partition and duct or duct insulation with sheet metal
flanges of same metal thickness as the duct. Overlap openings on four sides by at least 1-1/2
inches.
K. Where ducts pass through fire and/or smoke and/or fire/smoke rated surfaces, install
appropriate safety dampers. Comply with requirements in Section 23 3314 "Duct Specialties"
for safety dampers.
L. Protect duct interiors from moisture, construction debris and dust, and other foreign
materials. Comply with SMACNA's "IAQ Guidelines for Occupied Buildings Under
Construction," Appendix G, "Duct Cleanliness for New Construction Guidelines."
A. Protect ducts exposed in finished spaces from being dented, scratched, or damaged.
B. Trim duct sealants flush with metal. Create a smooth and uniform exposed bead. Do not use
two-part tape sealing system.
C. Grind welds to provide smooth surface free of burrs, sharp edges, and weld splatter. When
welding stainless steel with a No. 3 or 4 finish, grind the welds flush, polish the exposed welds,
and treat the welds to remove discoloration caused by welding.
D. Maintain consistency, symmetry, and uniformity in the arrangement and fabrication of fittings,
hangers and supports, duct accessories, and air outlets.
E. Repair or replace damaged sections and finished work that does not comply with these
requirements.
A. Install commercial kitchen hood exhaust ducts without dips and traps that may hold grease, and
sloped a minimum of 2 percent to drain grease back to the hood.
B. Install fire-rated access panel assemblies at each change in direction and at maximum intervals
of 10 feet in horizontal ducts, and at every floor for vertical ducts, or as indicated on Drawings.
C. Install access openings at each change in direction and at intervals defined by NFPA 96; locate
on sides of duct a minimum of 1-1/2 inches from bottom; and fit with grease-tight fire rated
covers of same material as duct.
D. Do not penetrate fire-rated assemblies except as allowed by applicable building codes and
authorities having jurisdiction.
B. Seal ducts for duct static-pressure, seal classes, and leakage classes specified in "Duct
Schedule" Article according to SMACNA's 2005 "HVAC Duct Construction Standards - Metal
and Flexible."
C. Seal all ducts to Seal Class A according to SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible."
A. Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal and Flexible,"
Chapter 5, "Hangers and Supports."
C. Hanger Spacing: Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal
and Flexible," Table 5-1 (Table 5-1M), "Rectangular Duct Hangers Minimum Size," and Table 5-
2, "Minimum Hanger Sizes for Round Duct," for maximum hanger spacing; install hangers and
supports within 24 inches of each elbow and within 48 inches of each branch intersection.
E. Support vertical ducts with steel angles or channel secured to the sides of the duct with welds,
bolts, sheet metal screws, or blind rivets; support at each floor and at a maximum intervals of 16
feet.
F. Install upper attachments to structures. Select and size upper attachments with pull-out,
tension, and shear capacities appropriate for supported loads and building materials where
used.
3.6 CONNECTIONS
A. Make connections to equipment with flexible connectors complying with Section 23 3314 "Duct
Specialties."
B. Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal and Flexible" for
branch, outlet and inlet, and terminal unit connections, and see drawings/details.
3.7 PAINTING
A. Prime and paint interior of metal ducts that are visible through registers and grilles and that do
not have duct liner. Apply one coat of flat, black, latex paint over a compatible galvanized-steel
primer.
1. Leakage tests shall be conducted in accordance with 1985, 1st Edition, of SMACNA's
"HVAC Air Duct Leakage Test Manual," Sections 3 and 5. Positive pressure ductwork to
be tested under positive pressure. Negative pressure ductwork to be tested under
positive and negative pressure. Submit a test report for each test.
2. Test the following systems:
a. Supply Ducts with a Pressure Class of 3-Inch wg (750 Pa) or Higher: Test
representative duct sections, selected by Engineer from sections installed, totaling
no less than 50 percent of total installed duct area for each designated pressure
class.
b. All Lab exhaust ductwork.
a.
Supply Ductwork: Ductwork downstream of VAV/CAV Terminals, Return Ductwork:
Ductwork upstream of VAV/CAV Terminals.
b.
Supply, Return, and Exhaust Ductwork
1. Visually inspect duct system to ensure that no visible contaminants are present.
2. Test sections of metal duct system, chosen randomly by Owner, for cleanliness
according to "Vacuum Test" in NADCA ACR, "Assessment, Cleaning and Restoration of
HVAC Systems."
a. Acceptable Cleanliness Level: Net weight of debris collected on the filter media
shall not exceed 0.75 mg/100 sq. cm.
D. Duct system will be considered defective if it does not pass tests and inspections.
E. Prepare test and inspection reports.
B. Clean existing ducts 10' each direction which become open due to equipment or duct removal,
and clean before testing, adjusting, and balancing.
1. Create new openings and install access panels appropriate for duct static-pressure class
if required for cleaning access. Provide insulated panels for insulated or lined duct.
Patch insulation and liner as recommended by duct liner manufacturer. Comply with
Section 23 3314 "Duct Specialties" for access panels and doors.
2. Disconnect and reconnect flexible ducts as needed for cleaning and inspection.
3. Remove and reinstall ceiling to gain access during the cleaning process.
1. When venting vacuuming system inside the building, use HEPA filtration with 99.97
percent collection efficiency for 0.3-micron-size (or larger) particles.
2. When venting vacuuming system to outdoors, use filter to collect debris removed from
HVAC system, and locate exhaust downwind and away from air intakes and other points
of entry into building.
1. Clean metal duct systems using mechanical cleaning methods that extract contaminants
from within duct systems and remove contaminants from building.
2. Use vacuum-collection devices that are operated continuously during cleaning. Connect
vacuum device to downstream end of duct sections so areas being cleaned are under
negative pressure.
3. Use mechanical agitation to dislodge debris adhered to interior duct surfaces without
damaging integrity of metal ducts, duct liner, or duct accessories.
4. Clean fibrous-glass duct liner with HEPA vacuuming equipment; do not permit duct liner
to get wet. Replace fibrous-glass duct liner that is damaged, deteriorated, or delaminated
or that has friable material, mold, or fungus growth.
5. Clean coils and coil drain pans according to NADCA 1992. Keep drain pan operational.
Rinse coils with clean water to remove latent residues and cleaning materials; comb and
straighten fins.
6. Provide drainage and cleanup for wash-down procedures.
7. Antimicrobial Agents and Coatings: Apply EPA-registered antimicrobial agents if fungus
is present. Apply antimicrobial agents according to manufacturer's written instructions
after removal of surface deposits and debris.
3.10 START UP
A. Fabricate ducts with galvanized sheet steel unless called for as another material on drawings,
or if Lab exhaust, dishwasher exhaust, and any other high humidity applications or areas,
ducting to be stainless steel, sloped, and drained.
B. For outdoor ducts exposed to wind forces, anchor and brace as required.
D. Fabricate underground ducts with galvanized sheet steel except as otherwise indicated and as
follows:
E. Supply Ducts:
1. Ducts Connected to Fan Coil Units, Furnaces, Heat Pumps, and Terminal Units:
F. Return Ducts:
1. Ducts Connected to Fan Coil Units, Furnaces, Heat Pumps, and Terminal Units <Insert
equipment>:
G. Exhaust Ducts:
1. Ducts Connected to Fan Coil Units, Furnaces, Heat Pumps, and Terminal Units
<Insert equipment>:
3. Stainless-Steel Ducts:
K. Elbow Configurations To Be Use, Unless More Stringent Requirements Are Required Per PART
2 of This Section:
1. Rectangular Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards -
Metal and Flexible," Figure 4-2, "Rectangular Elbows."
2. Rectangular Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards -
Metal and Flexible," Figure 4-2, "Rectangular Elbows."
3. Round Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards - Metal
and Flexible," Figure 3-4, "Round Duct Elbows."
1) Velocity 1000 fpm (5 m/s) or Lower: 1.5 radius-to-diameter ratio and three
segments for 90-degree elbow.
2) Velocity 1000 to 1500 fpm (5 to 7.6 m/s): 1.5 radius-to-diameter ratio and
four segments for 90-degree elbow.
3) Velocity 1500 fpm (7.6 m/s) or Higher: 1.5 radius-to-diameter ratio and five
segments for 90-degree elbow.
4) Radius-to Diameter Ratio: 1.5.
L. Branch Configurations To Be Use, Unless More Stringent Requirements Are Required Per
PART 2 of This Section:
1. Rectangular Duct: Comply with SMACNA's 2005 "HVAC Duct Construction Standards -
Metal and Flexible," Figure 4-6, "Branch Connection."
2. Round and Flat Oval: Comply with SMACNA's 2005 "HVAC Duct Construction
Standards - Metal and Flexible," Figure 3-5, "90 Degree Tees and Laterals," and Figure
3-6, "Conical Tees."
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product and Technical Data: For each type of product indicated, including (but not limited to)
installation requirements, dimensions, color charts and water penetration data for louvers, wiring
diagrams, dynamic insertion loss and self-noise data for attenuators, and air pressure drop
information.
B. [LEED Submittals:
1. Product Data for Prerequisite EQ 1: Documentation indicating that units comply with
ASHRAE 62.1-2007, Section 5 - "Systems and Equipment."
2. Any data that can be used for recycled content and regional materials credits.]
A. Comply with NFPA 90A, "Installation of Air Conditioning and Ventilating Systems," and with
NFPA 90B, "Installation of Warm Air Heating and Air Conditioning Systems."
B. Comply with AMCA 500-D testing for damper rating, and with AMCA 500-L for louver
performance.
C. For louver finishes, comply with applicable SSPC and AAMA requirements.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for
acceptable materials, material thicknesses, and duct construction methods unless otherwise
indicated. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains,
discolorations, and other imperfections.
C. Stainless-Steel Sheets: Comply with ASTM A 480/A 480M, Type 304 except for Lab exhaust,
which shall be Type 316.
D. Aluminum Sheets: Comply with ASTM B 209, Alloy 3003, Temper H14; with mill finish for
concealed ducts and standard, 1-side bright finish for exposed ducts.
E. Extruded Aluminum: Comply with ASTM B 221, Alloy 6063, Temper T6, except for louvers,
which are to be Temper T5.
G. Tie Rods: Galvanized steel, 1/4-inch minimum diameter for lengths 36 inches or less; 3/8-inch
minimum diameter for lengths longer than 36 inches.
1. Air Balance.
2. Cesco.
3. Greenheck Fan Corporation.
4. Nailor Industries Inc.
5. Prefco (Basis of Design)
6. Ruskin Company.
E. Blades: Multiple single-piece blades, maximum 6-inch width with sealed edges.
H. Bearings: Provide end bearings on all dampers. On multiple blade dampers bearing shall be oil-
impregnated nylon or sintered bronze.
I. Accessories:
6. Blades:
a. Rectangular dampers shall be single blade type in ducts up to 11" high and shall
be opposed blade type in ducts 12" high and above.
b. Round dampers shall be single blade type.
c. Stiffen damper blades for stability.
7. Provide end bearings on all dampers. On multiple blade dampers bearing shall be oil-
impregnated nylon or sintered bronze.
8. Provide locking indicating quadrant regulators on all dampers. Where rod lengths exceed
30-inches, provide a regulator at both ends.
9. On insulated ducts mount quadrant regulators on stand-off mounting brackets, bases, or
adapters.
10. Jackshaft:
a. Zinc-plated, die-cast core with dial and handle made of 3/32-inch- thick zinc-plated
steel, and a 3/4-inch hexagon locking nut.
b. Include center hole to suit damper operating-rod size.
c. Include elevated platform for insulated duct mounting.
A. Fire dampers shall be dynamic, multiple airfoil blade type (not curtain type) with integral wall
sleeve, constructed in accordance with UL Standard 555.
B. Closing rating in ducts up to 8-inch wg static pressure class and minimum 4000-fpm velocity.
C. Dampers shall be for horizontal or vertical mounting and shall be of sizes shown on the
drawings.
D. Dampers shall have 1-1/2 or 3 hour rating as shown on drawings, replaceable 212 degree F
fusible link, and access panels (with UL 181 rated viewports), for installation on both sides of
damper.
C. Frame: Multiple blade type (not curtain type); fabricated with roll-formed, 0.034-inch- thick
galvanized steel; with mitered and interlocking corners.
F. Rated pressure and velocity to exceed design airflow conditions, and dampers to be rated for
4,000 fpm and 8" pressure minimum.
G. Mounting Sleeve: Factory-installed, 0.052-inch- thick, galvanized sheet steel; length to suit wall
or floor application with factory-furnished silicone calking.
I. Comply with NEMA designation, temperature rating, service factor, enclosure type, and
efficiency requirements for motors specified in Division 23 Section "Motors."
1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load
will not require motor to operate in service factor range above 1.0.
2. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical
devices and connections specified in [Division 25 Section "Integrated Automation."]
[Division 26 Sections.]
3. Permanent-Split-Capacitor or Shaded-Pole Motors: With oil-immersed and sealed gear
trains.
4. Spring-Return Motors: Equip with an integral spiral-spring mechanism where indicated.
Enclose entire spring mechanism in a removable housing designed for service or
adjustments. Size for running torque rating of 150 in. x lbf and breakaway torque rating
of 150 in. x lbf.
5. Outdoor Motors and Motors in Outdoor-Air Intakes: Equip with O-ring gaskets designed to
make motors weatherproof. Equip motors with internal heaters to permit normal operation
at minus 40 deg F.
6. Nonspring-Return Motors: For dampers larger than 25 sq. ft., size motor for running
torque rating of 150 in. x lbf and breakaway torque rating of 300 in. x lbf.
7. Electrical Connection: 115 V, single phase, 60 Hz.
J. Dampers shall be supplied/installed with access panels (with UL 181 rated viewports), for
installation on both sides of damper.
K. Accessories:
A. Type: Dynamic; rated and labeled according to UL 555 and UL 555S by an NRTL, multiple
blade, not curtain type. Basis of Design Prefco Model 5010.
B. Closing rating in ducts up to 4-inch wg (1-kPa) static pressure class and minimum 4000-fpm
velocity.
D. Frame: Hat-shaped, 0.094-inch- (2.4-mm-) thick, galvanized sheet steel, with welded or
mechanically attached corners and mounting flange.
E. Heat-Responsive Device: Reusable electric "McCabe™" link, with an external manual reset
lever (see drawing details). The releasing device shall be 24Vdc in compliance with UL 873.
The resettable link shall be 280°F, and UL 33 listed.
H. Leakage: Class I
M. Comply with NEMA designation, temperature rating, service factor, enclosure type, and
efficiency requirements for motors specified in Section 23 0513 "Common Motor Requirements
for HVAC Equipment."
1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load
will not require motor to operate in service factor range above 1.0.
2. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical
devices and connections specified in Division 25.
3. Permanent-Split-Capacitor or Shaded-Pole Motors: With oil-immersed and sealed gear
trains.
4. Spring-Return Motors: Equip with an integral spiral-spring mechanism where indicated.
Enclose entire spring mechanism in a removable housing designed for service or
adjustments. Size for running torque rating of 150 in. x lbf (17 N x m) and breakaway
torque rating of 150 in. x lbf (17 N x m).
5. Outdoor Motors and Motors in Outdoor-Air Intakes: Equip with O-ring gaskets designed to
make motors weatherproof. Equip motors with internal heaters to permit normal operation
at minus 40 deg F (minus 40 deg C).
6. Non-spring-Return Motors: For dampers larger than 25 sq. ft. (2.3 sq. m), size motor for
running torque rating of 150 in. x lbf (17 N x m) and breakaway torque rating of 300 in. x
lbf (34 N x m).
7. Electrical Connection: 24 or 115 V as called for by control systems specifications,
sequences, or on drawings, and as required, single phase, 60 Hz, and as coordinated
with electrical contractor.
N. Accessories:
A. General Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal
and Flexible"; Figures 2-3, "Vanes and Vane Runners," and 2-4, "Vane Support in Elbows."
B. Vane Construction: Single wall for ducts up to 48 inches wide and double wall for larger
dimensions.
A. Duct-Mounted Access Doors: Fabricate access panels according to SMACNA's "HVAC Duct
Construction Standards - Metal and Flexible"; Figures 2-10, "Duct Access Doors and Panels,"
and 2-11, "Access Panels - Round Duct."
1. Door:
a. Double wall, rectangular, and 24" x 24" or as close to 24" x 24" as possible.
b. Galvanized sheet metal with insulation fill and thickness as indicated for duct
pressure class.
c. Hinges and Latches: 1-by-1-inch butt or piano hinge and cam latches.
d. Fabricate doors airtight and suitable for duct pressure class.
2. Frame: Galvanized sheet steel, with bend-over tabs and foam gaskets.
3. Number of Hinges and Locks:
a. Access Doors Less Than 12 Inches Square: No hinges and two sash locks.
b. Access Doors up to 18 Inches Square: Two hinges and two sash locks.
c. Access Doors up to 24 by 48 Inches: Three hinges and two compression latches
D. Fasteners: Stainless steel. Panel fasteners shall not penetrate duct wall.
E. Gasket: Comply with NFPA 96; grease-tight, high-temperature ceramic fiber, rated for minimum
2000 deg F.
D. Material shall be crimped into a metal edging strip and shall be approximately 3 inches wide.
E. Indoor System, Flexible Connector Fabric: Minimum 0.024 " thick glass fabric double coated
with neoprene.
F. Outdoor System, Flexible Connector Fabric: Minimum 0.024" thick glass fabric double coated
with weatherproof, synthetic rubber resistant to UV rays and ozone.
1. Casco.
2. Flexmaster U.S.A., Inc., Type 6.
3. Thermaflex, Model M-KE.
B. Non-insulated, Flexible Duct: UL 181, Class 1, 2-ply vinyl film supported by helically wound,
spring-steel wire.
C. Insulated, Flexible Duct: UL 181, Class 1, black polymer film supported by helically wound,
spring-steel wire; fibrous-glass insulation; fire resistive vapor-barrier film.
D. Insulated, Flexible Duct: UL 181, Class 1, multiple layers of aluminum laminate supported by
helically wound, spring-steel wire; fibrous-glass insulation; fire resistive vapor-barrier film.
A. Instrument Test Holes: Cast iron or cast aluminum to suit duct material, including screw cap
and gasket. Size to allow insertion of pitot tube and other testing instruments and of length to
suit duct-insulation thickness.
B. Adhesives: High strength, quick setting, neoprene based, waterproof, and resistant to gasoline
and grease.
2.15 LOUVERS
2. Louver Depth, Blade Angle, and Free Area: 6 inch depth, blades at 45° angle, and
minimum free area of 49.4%.
3. Frame and Blade Materials of Construction and Nominal Thickness: Not less than 0.081
inch, and constructed of ASTM B221 aluminum extrusions, Alloy 6063-T5.
4. Fabrication: Welded.
5. Frame Type: XXXXXXXXX
6. Sill Type: Extended.
7. Mullion Type: Exposed.
8. Sleeve: Minimum 16 gage galvanized steel, by contractor.
9. Size and performance data: See schedules/drawings.
10. Finish: 2-coat, oven cured Kynar 500, 2.0 mils dry film coating thickness per AAMA
2605.
11. Louver Performance Ratings:
a. Free Area: Not less than 7.9 sq. ft. for 48-inch wide by 48-inch high louver.
b. Point of Beginning Water Penetration: Not less than 1065 fpm.
c. Air Performance: Not more than 0.072-inch wg static pressure drop at 700-fpm
free-area intake velocity.
d. Air Performance: Not more than 0.17-inch wg static pressure drop at 1000-fpm
free-area exhaust velocity.
12. Wind Loads: Determine loads based on a uniform pressure of XX lbf/sq. ft. based upon
project structural wind values and other data, acting inward or outward.
13. AMCA Seal: Mark units with AMCA Certified Ratings Seal.
14. Screens: 1/2" aluminum birdscreen finished same as louver, located XXXXX.
15. Insulated Blank-off Panels: XXXXXXXXXXXXX.
2.16 DUCT SOUND ATTENUATORS
1. Aerocoustic.
2. Aerosonics.
3. Commercial Acoustics, Metalform Corp.
4. Industrial Acoustics.
5. McGill AirFlow LLC.
6. Pottorff/Dynasonics.
7. Ruskin Sound..
8. Semco.
9. Vibro-Acoustics.
B. General Requirements:
1. Factory fabricated.
2. Fire-Performance Characteristics: Adhesives, sealants, packing materials, and
accessory materials shall have flame-spread index not exceeding 25 and smoke-
developed index not exceeding 50 when tested according to ASTM E 84.
3. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1.
C. Shape:
D. Rectangular Silencer Outer Casing: ASTM A 653/A 653M, G90 (Z275) galvanized sheet steel
minimum 22 ga.
E. Round Silencer Outer Casing: ASTM A 653/A 653M, G90 (Z275) galvanized sheet steel.
1. Sheet Metal Thickness for Units up to 24 Inches (600 mm) in Diameter: 0.034 inch (0.85
mm) thick.
2. Sheet Metal Thickness for Units 26 through 40 Inches (660 through 1000 mm) in
Diameter: 0.040 inch (1.02 mm) thick.
3. Sheet Metal Thickness for Units 42 through 52 Inches (1060 through 1300 mm) in
Diameter: 0.05 inch (1.3 mm) thick.
4. Sheet Metal Thickness for Units 54 through 60 Inches (1370 through 1500 mm) in
Diameter: 0.064 inch (1.62 mm) thick.
F. Inner Casing and Baffles: ASTM A 653/A 653M, [G90 (Z275)] [G60 (Z180)] galvanized sheet
metal, 0.034 inch (0.85 mm) thick, and with 1/8-inch- (3-mm-) diameter perforations.
G. Special Construction:
a. Reactive type (No Media) Controlled impedance membranes and broadly tuned
resonators without absorptive media.
b. Dissipative Film-lined type with fill material for Hospital use.
J. Fabricate silencers to form rigid units that will not pulsate, vibrate, rattle, or otherwise react to
system pressure variations. Do not use mechanical fasteners for unit assemblies.
K. Accessories:
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install duct accessories according to applicable details in SMACNA's "HVAC Duct Construction
Standards - Metal and Flexible" for metal ducts, and according to manufacturer's
instructions/recommendations..
B. Install duct accessories of materials suited to duct materials; use galvanized-steel accessories
in galvanized-steel ducts, stainless-steel accessories in stainless-steel ducts, and aluminum
accessories in aluminum ducts.
C. Install backdraft dampers at inlet of exhaust fans or exhaust ducts as close as possible to
exhaust fan unless otherwise indicated.
D. Install volume dampers at points on supply, return, and exhaust systems where branches
extend from larger ducts. Where dampers are installed in ducts having duct liner, install
dampers with hat channels of same depth as liner, and terminate liner with nosing at hat
channel.
E. Set dampers to fully open position before testing, adjusting, and balancing.
F. All dampers to be accessible and labeled, and are to have at least 24" around them for
servicing, adding up to and including valves, actuators, and other devices that need service or
need to be accessed to provide service.
G. Install test holes at fan inlets and outlets and elsewhere as indicated.
J. Install duct access doors on sides of ducts to allow for inspecting, adjusting, and maintaining
accessories and equipment at the following locations:
M. Label access doors according to Division 23 Section "Identification for HVAC Piping and
Equipment" to indicate the purpose of access door.
N. Install flexible connectors to connect ducts to equipment.
O. For fans developing static pressures of 5-inch wg and more, cover flexible connectors with
loaded vinyl sheet held in place with metal straps.
P. Connect terminal units to supply ducts directly or with maximum 12-inch lengths of flexible duct.
Do not use flexible ducts to change directions.
Q. Flexible duct elbows at diffusers are not allowed, elbows at diffusers must be sheet metal, see
drawing detail(s).
S. Locate and place louvers level, plumb, and at indicated alignment with adjacent work.
T. For louvers, use concealed anchorages where possible. Provide brass or lead washers fitted to
screws where required to protect metal surfaces and to make a weather-tight connection. Form
closely fitted joints with exposed connections accurately located and secured. Provide
perimeter reveals and openings of uniform width for sealants and joint fillers, as indicated.
Protect unpainted galvanized and nonferrous-metal surfaces that are in contact with concrete,
masonry, or dissimilar metals from corrosion and galvanic action by applying a heavy coating of
bituminous paint or by separating surfaces with waterproof gaskets or nonmetallic flashing.
Install concealed gaskets, flashings, joint fillers, and insulation as louver installation progresses,
where weather-tight louver joints are required. Comply with Section 07 9200 "Joint Sealants" for
sealants applied during louver installation.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. For fans in air handling units, refer to project air handling unit section(s) for additional
requirements.
1.2 SUMMARY
1.3 REFERENCES
F. UL 705.
H. ANSI/AIHA Z9.5-2012.
A. Performance ratings: Conform to applicable ANSI/AMCA Standards 210, 260 and 300. Fans
must be tested in accordance with applicable AMCA Publications 211, 260 and 311 in an AMCA
accredited laboratory and certified for air and sound performance. Fans shall be licensed to
FANS 23 3400 - 1
bear the AMCA ratings seal for air performance (AMCA 210), sound performance (AMCA 300),
and induced flow fan for high plume dilution blowers (AMCA 260). Manufacturers that are not
licensed to bear the AMCA 210 and 260 ratings seal, must provide performance witness testing
(at the manufacturer's expense), per paragraph 1.4.D.
B. Classification for Spark Resistant Construction shall conform to ANSI/AMCA Standard 99.
C. Each fan shall be vibration tested before shipping, as an assembly, in accordance with
ANSI/AMCA Standard 204. Each assembled fan shall be test run at the factory at the specified
fan RPM and vibration signatures shall be taken on each bearing in three planes - horizontal,
vertical, and axial. The maximum allowable fan vibration shall be less than 0.08 in. /sec peak
velocity; filter-in reading as measured at the fan RPM. This report shall be provided at no
charge to the customer upon request.
D. Manufacturers that do not comply with paragraph 1.4.A must also provide, at the owner and
engineer's option and manufacturer's expense, witness testing of fan discharge and entrainment
airflow, performed in an AMCA accredited laboratory, in accordance with AMCA 210 and 260.
This test shall verify the critical and safety related dilution performance of high plume dilution
blowers, as stated by the manufacturer.
E. Comply with FM Global requirements for fans and blowers and for monitoring and diagnosis of
vibration in rotating machinery.
A. Product Data:
1. Include rated capacities, furnished specialties, and accessories for each fan.
2. Certified fan performance curves with system operating conditions indicated.
3. Certified fan sound-power ratings.
4. Motor ratings and electrical characteristics, plus motor and electrical accessories.
5. Material thickness and finishes, including color charts.
6. Dampers, including housings, linkages, and operators.
B. Shop Drawings:
A. Coordination Drawings: Show fan room layout and relationships between components and
adjacent structural and mechanical elements. Show support locations, type of support, and
weight on each support. Indicate and certify field measurements.
B. Field quality-control reports.
A. Operation and Maintenance Data: For centrifugal fans to include in emergency, operation, and
maintenance manuals.
A. Deliver materials to site in manufacturer’s original, unopened containers and packaging, with
labels clearly indicating manufacturer, material, products included, and location of installation.
B. Store materials in a dry area indoor, protected from damage, and in accordance with
manufacturer’s instructions. For long term storage, follow manufacturer’s Installation, Operation
and Maintenance manual.
C. Handle and lift fans in accordance with the manufacturer’s instructions. Protect materials and
finishes during handling and installation to prevent damage. Follow all safety warnings posted
by the manufacturer.
PART 2 - PRODUCTS
A. Fan arrays are the standard for the University air handlers, and other fan types for air handling
units are considered exceptions.
B. AMCA Compliance:
1. Comply with AMCA performance requirements and bear the AMCA-Certified Ratings
Seal.
2. Operating Limits: Classify according to AMCA 99.
1. Barry Blower.
2. Howden/Buffalo.
3. Chicago Blower.
4. Greenheck Fan Corporation.
5. Industrial Air.
6. Twin City
B. Description:
C. Housings:
D. Airfoil Wheels:
E. Shafts:
1. Statically and dynamically balanced and selected for continuous operation at maximum
rated fan speed and motor horsepower, with adjustable alignment and belt tensioning.
2. Turned, ground, and polished hot-rolled steel with keyway. Ship with protective coating
of lubricating oil.
3. Designed to operate at no more than 70 percent of first critical speed at top of fan's
speed range.
F. Grease-Lubricated Shaft Bearings:
1. Self-aligning, pillow-block-type, ball or roller bearings with adapter mount and two-piece,
cast-iron housing.
2. [Retain "Ball-Bearing Rating Life" or "Roller-Bearing Rating Life" Subparagraph below.]
3. Ball-Bearing Rating Life: ABMA 9, Ll0 at [50,000] [120,000] hours.
4. Roller-Bearing Rating Life: ABMA 11, Ll0 at [50,000] [120,000] hours.
H. Belt Drives:
I. Accessories:
B. Description:
C. Housings:
D. Backward-Inclined Wheels:
E. Shafts:
1. Statically and dynamically balanced and selected for continuous operation at maximum
rated fan speed and motor horsepower, with adjustable alignment and belt tensioning.
2. Turned, ground, and polished hot-rolled steel with keyway. Ship with protective coating
of lubricating oil.
3. Designed to operate at no more than 70 percent of first critical speed at top of fan's
speed range.
G. Belt Drives:
H. Accessories:
1. Barry Blower.
2. Howden/Buffalo.
3. Chicago Blower.
4. Greenheck Fan Corporation.
5. Industrial Air.
6. Twin City
B. Description:
C. Airfoil Wheels:
1. Statically and dynamically balanced and selected for continuous operation at maximum-
rated fan speed and motor horsepower, with adjustable alignment and belt tensioning.
2. Turned, ground, and polished hot-rolled steel with keyway. Ship with protective coating
of lubricating oil.
3. Designed to operate at no more than 70 percent of first critical speed at top of fan's
speed range.
G. Accessories:
1. Shaft Cooler: Metal disk between bearings and fan wheel, designed to dissipate
heat from shaft.
2. Spark-Resistant Construction: AMCA 99.
3. Shaft Seals: Airtight seals installed around shaft on drive side of single-width
fans.
B. General
1. All fan and system components (fan, nozzle, windband and plenum) shall be corrosion
resistant coated with a two part electrostatically applied and baked, sustainable,
corrosion resistant coating system, or equal. Standard finish color to be chosen by
University.
2. All parts shall be cleaned and chemically prepared for coating using a multi-stage wash
system which includes acid pickling that removes oxide, increases surface area, and
improves coating bond to the substrate.
3. The first powder coat applied over the prepared surface shall be a zinc rich epoxy primer
(no less than 70% zinc) and heated to a gelatinous consistency (partial cure) at which the
second powder coat of polyester resin shall be electrostatically applied and
simultaneously be cured at a uniform temperature of 400°F.
4. The coating system, a total thickness of up to 6 mils, is not affected by the UV component
of sunlight (does not chalk), and has superior corrosion resistance to acid, alkali, and
solvents. Coating system shall exceed 4000 hour ASTM B117 Salt Spray Resistance.
5. Note that 10-20 mil thick wet coating systems pollute the environment (air and water),
and that these manually applied coatings are not uniform over the impeller surface and
can cause fan imbalance and vibration.
1. Fan impeller shall be mixed flow design with non-stall characteristics. The impeller shall
be electronically balanced both statically and dynamically exceeding AMCA Standards.
2. Fan impeller shall be manufactured of welded and coated steel. Reference specification
section 2.5-C for corrosion resistant coating.
3. Fan impellers that are fabricated of polypropylene or fiberglass that have lower
mechanical properties than steel, and lower maximum tip speeds are not acceptable.
4. Vacuum Seal: Fan impeller shall include a secondary fan blade located on the impeller
back plate. This secondary impeller shall create a negative pressure at the shaft opening;
preventing hazardous or toxic exhaust fumes from escaping through the housing shaft
opening. Mechanical shaft seals that wear out and need to be replaced or seal systems
that use hoses or tubes that can leak, are not acceptable.
1. For constant volume systems, the fan / nozzle assembly shall be connected directly to
roof curb and exhaust duct without the need of the bypass air plenum. Fans mounted
directly to roof curb shall be provided with a damper tray located in the roof curb for
mounting of the gravity isolation damper.
2. For variable volume systems, a bypass air plenum shall be provided as shown on
drawings. The plenum shall be provided with bypass air damper(s) for introducing outside
air at roof level upstream of the fan, complete with bypass air weatherhood and bird
screen.
3. The plenum shall be constructed of welded and coated steel and meet specification
section 2.5-C for corrosion resistant coating. Plenums that are fabricated of plastics or
resins that are combustible and have mechanical properties less than steel shall not be
acceptable.
4. The bypass air plenum shall be mounted on factory fabricated roof curb provided by the
fan manufacturer, as shown on the project drawings.
5. Fan designs that use inlet flexible connectors that can leak causing loss of lab exhaust
shall not be permitted.
6. Bypass air damper(s) shall be opposed-blade design for airflow control, airfoil design,
fabricated of galvanized steel [316 stainless steel] for structural rigidity as standard.
Bypass damper(s) shall have plated steel damper rods, stainless steel sleeved bearings,
301 stainless steel jamb seals and the blades shall have polymer edge seals. Damper
model shall be equal to or exceed a heavy duty control damper, Greenheck HCD-130 or
equal. Damper blade drive linkage shall be set by manufacturer and welded to eliminate
linkage slippage. All damper access and service (drive actuators) shall be performed
outside of the contaminated airstream.
7. If stated in the schedule notes, an optional, integral bypass air packed acoustic
attenuator fabricated of galvanized steel [galvanneal or stainless steel construction]
shall be provided by the fan manufacturer (if shown on the drawings).
8. Fan isolation damper(s), shall be parallel-blade design, airfoil design, fabricated of steel
[304 stainless steel construction] for structural rigidity as standard. Damper(s) shall be
coated up to 4 mils of chemically resistant Hi-Pro Polyester resin (or equal),
electrostatically applied and baked. Isolation damper(s) shall have plated steel damper
rods (if specified as 304 stainless steel damper, stainless steel damper rods will be
provided), stainless steel sleeved bearings, 301 stainless steel jamb seals and the blades
shall have polymer edge seals. Damper model shall be equal to or exceed a heavy duty
control damper, Greenheck HCD-130 or equal. Damper blade drive linkage shall be set
by manufacturer and welded to eliminate linkage slippage. All damper access and service
(drive actuators) shall be performed outside of the contaminated airstream.
9. Isolation damper actuator(s), if scheduled shall be factory mounted and shall be wired to
a step-down transformer. Actuator and transformer are located in a weatherproof
enclosure.
10. Blower / Plenum vibration isolation shall be limited to neoprene / cork vibration pads.
1. Exhaust system manufacturer shall supply a structural support curb for the plenum of
specified height as shown on the drawings.
2. Curb shall be fabricated of a minimum of 12 gauge corrosion-resistant coated steel and
structurally reinforced.
3. Curb shall be insulated.
4. When properly anchored to the roof structure, the standard curb / plenum / blower
assembly shall withstand project required wind loadswithout additional structural support.
1. Motors shall be premium efficiency, standard NEMA frame, 1800 or 3600 RPM, TEFC
with a 1.15 service factor. A factory-mounted NEMA 3R [NEMA 4X] disconnect switch
shall be provided for each fan.
2. Motor maintenance shall be accomplished without fan or fan impeller removal, or
requiring maintenance personnel to access the contaminated exhaust components.
3. Motor mounting shall be “C-face” and / or foot mount.
4. Drive arrangement shall be AMCA arrangement 2, utilizing a direct mount coupling
connecting the motor shaft and fan impeller shaft. Belt drive arrangement 9 or 10, or
direct drive arrangement 4 requiring access and handling of hazardous and contaminated
fan components are not acceptable.
5. Fan shaft to be turned and polished of 1040 steel material [316 stainless steel] as
standard, coated with corrosion resistant coating.
6. Fan shaft bearing shall be Air Handling Quality, ball or roller pillow block type, and sized
for an
L-10 life of no less than 200,000 hours.
7. All shaft bearings and non-permanently lubricated motors shall have nylon [stainless
steel braided] extended lube lines with zerk fittings.
8. Motor, coupling, and bearing shall all be outside the contaminated exhaust, and be
capable of replacement without disassembling fan and accessing hazardous and
contaminated fan components.
1. Fan Array
a. Fan array system shall consist of multiple, direct driven, arrangement 4 plenum
fans constructed per AMCA requirements for duty specified. Fans shall be selected
to deliver scheduled airflow quantity at scheduled operating total static pressure
and scheduled fan/motor speed. Fan array shall be selected to operate at system
total static pressure that does not exceed 90% of scheduled fan’s peak static
pressure producing capability at scheduled fan/motor speed.
b. Fan intake wall, inlet funnel, and motor support structure shall be powder coated
for superior corrosion resistance. Motors shall be standard pedestal mounted type,
T-frame motors selected at specified operating voltage, rpm, and efficiency as
needed to meet performance requirements. Motors shall include isolated bearings
or shaft grounding. Each fan/motor cartridge shall be dynamically balanced to
meet AMCA standard 204-96, category BV-5, to meet or exceed Grade 2.5
residual unbalance.
1) Fan array shall provide uniform air flow and velocity profile across entire air
way tunnel cross section. Airflow and velocity shall not exceed scheduled
cooling coil and/or filter bank face velocity when measured at a point 12
inches from intake side of fan wall array intake plenum wall, and distance of
48 inches from discharge side of fan wall intake plenum wall.
2) Provide partition between fans to minimize system effect.
3) Provide structural frame to support upper fans with solid floor panel partition
between fans as shown on drawings to minimize system effect.
4) Each fan in array shall be provided with back flow prevention means that
produces less than 0.10 inches wc of static pressure drop and/or system
effect when that fan is enabled. Any such system effects and/or pressure
drops shall be submitted and included as component in determining fan
system total static pressure as submitted. Manufacturer’s pressure drop
ratings of any such equipment, developed from straight run test conditions
will not be accepted.
5) Provide 2 separate variable frequency drives for fan array. Each VFD shall
control half of fans in array. Provide one backup VFD for air handling unit.
6) Fan array shall be sized such that upon single fan failure, remaining fans
could ramp up and provide same 100% design capacity.
7) Technology with multiple fans having individual VFDs may be considered.
8) Provide local electrical disconnect for each fan.
9) Contractor shall provide all wiring to air handling unit components that
require power.
2.7 MOTORS
A. Comply with NEMA designation, temperature rating, service factor, and efficiency requirements
for motors specified in Section 23 0513 "Motors."
A. Sound-Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan Sound
Ratings from Laboratory Test Data." Factory test fans according to AMCA 300, "Reverberant
Room Method for Sound Testing of Fans." Label fans with the AMCA-Certified Ratings Seal.
B. Fan Performance Ratings: Establish flow rate, pressure, power, air density, speed of rotation,
and efficiency by factory tests and ratings according to AMCA 210/ASHRAE 51, "Laboratory
Methods of Testing Fans for Certified Aerodynamic Performance Rating."
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas to receive fans. Notify the Engineer of conditions that would adversely affect
installation or subsequent utilization and maintenance of fans. Do not proceed with installation
until unsatisfactory conditions are corrected.
3.2 INSTALLATION AND ACCESS
A. Install fans level and plumb and according to fan manufacturer's instructions..
B. Disassemble and reassemble units, as required for moving to the final location, according to
manufacturer's written instructions.
C. Lift and support units with manufacturer's designated lifting or supporting points.
D. Equipment Mounting: Install centrifugal fans on cast-in-place concrete equipment base(s) using
[elastomeric pads] [elastomeric mounts] [restrained spring isolators]. Comply with
requirements for equipment bases specified in [Section 03 3000 "Cast-in-Place Concrete."]
[Section 03 3053 "Miscellaneous Cast-in-Place Concrete."] Comply with requirements for
vibration isolation devices specified in Section 23 0550 "Vibration Isolation."
E. Equipment Mounting: Install centrifugal fans using [elastomeric pads] [elastomeric mounts]
[restrained spring isolators]. Comply with requirements for vibration isolation devices
specified in Section 23 0550 "Vibration Isolation."
F. Equipment Mounting: Install centrifugal fans on vibration isolation equipment base. Comply
with requirements specified in Section 23 0550 "Vibration Isolation."
H. Curb Support: Install roof curb on roof structure, level and secure, according to "The NRCA
Roofing and Waterproofing Manual," Low-Slope Membrane Roofing Construction Details
Section, Illustration "Raised Curb Detail for Rooftop Air Handling Units and Ducts." Install and
secure centrifugal fans on curbs, and coordinate roof penetrations and flashing with roof
construction.[ Secure units to curb support with anchor bolts.]
I. Unit Support: Install centrifugal fans level on structural [curbs] [pilings]. Coordinate wall
penetrations and flashing with wall construction.[ Secure units to structural support with
anchor bolts.]
J. Isolation Curb Support: Install centrifugal fans on isolation curbs, and install[ flexible duct
connectors] and vibration isolation devices.
1. Comply with requirements in Section 23 3314 "Ductwork Specialties" for flexible duct
connectors.
2. Comply with requirements in Section 23 0550 "Vibration Isolation" for vibration isolation
devices.
N. Provide/build OSHA approved engineered platforms for preventative maintenance for items not
accessible from a normal area standing position.
3.3 CONNECTIONS
A. Drawings indicate general arrangement of ducts and duct accessories. Make final duct
connections with flexible connectors. Flexible connectors are specified in Section 23 3314
"Ductwork Specialties."
C. Install piping from scroll drain connection, with trap with seal equal to 1.5 times specified static
pressure, to nearest floor drain with pipe sizes matching the drain connection.
A. Testing Agency: University will engage a qualified testing agency to perform tests and
inspections.
C. Perform the following tests and inspections with the assistance of a factory-authorized service
representative:
D. Test and adjust controls and safeties. Controls and equipment will be considered defective if
they do not pass tests and inspections.
3.5 DEMONSTRATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
B. [LEED Submittal:
C. Shop Drawings: For air terminal units. Include plans, elevations, sections, details, and
attachments to other work.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
2.1 MANUFACTURERS
A. Subject to compliance with requirements, provide products by one of the following (see
schedules for Basis of Design):
1. Nailor
2. Price
3. Titus
4. Tuttle and Bailey
2.2 TERMINAL UNIT WALL CONSTRUCTION FOR CRITICAL AREAS/AIR AND NON-CRITICAL
AREAS/AIR
A. For critical areas/air, all units to be double wall. For high humidity areas/air (which are also
considered critical, units to be stainless steel (and this requirement for stainless steel for critical
areas/air overrides any conflicting material requirements that may exist below). For non-critical
areas/air, units can be double wall or single wall fiber free lined.
A. Configuration: Volume-damper assembly and fan in series arrangement inside unit casing with
control components inside a protective metal shroud for installation above a ceiling and in areas
without a ceiling.
B. Casing: minimum 22 gauge steel, single wall or double wall for non-critical areas/air, double
wall for critical areas/air.
1. Casing Lining:
2. Air Inlets: Round stub connections or S-slip and drive connections for duct attachment.
3. Air Outlet: S-slip and drive connections.
4. Access: Removable top and bottom panels for access to parts requiring service,
adjustment, or maintenance; with airtight gasket and quarter-turn latches.
5. Fan: Forward-curved centrifugal.
6. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1-2007.
C. Volume Damper: Minimum 22 gauge steel with shaft rotating in self-lubricating bearings. Shaft
shall be clearly marked on the end to indicate damper position.
D. Velocity Sensors: Single axis sensor shall not be acceptable for duct diameters 6" or larger.
Multiple pressure sensing points shall be utilized. The total pressure inputs shall be averaged
using a pressure chamber located at the center of the sensor. Sensor shall have an error of
plus or minus 5% or better.
E. Motor:
1. Comply with NEMA designation, temperature rating, service factor, enclosure type, and
efficiency requirements for motors specified in Division 23 Section "Common Motor
Requirements for HVAC Equipment."
2. Type: Electronically commutated motor.
3. Fan-Motor Assembly Isolation: Rubber isolators.
4. Efficiency: Premium efficient.
5. Motor Speed: Variable, SCR controlled.
6. Electrical Characteristics: as scheduled on drawings.
F. Filters: Terminals shall include a 1" thick disposable MERV 7 polyester filter (spun fiberglass is
not acceptable). Filter shall be secured with quick release clips, allowing removal without
horizontal sliding.
G. Hydronic Coils: Copper tube, with mechanically bonded aluminum fins spaced no closer
than 0.1 inch, and rated for a minimum working pressure of 300 psig and a maximum
entering-water temperature of 200 deg F. Include manual air vent and drain valve.
H. Control Panel Enclosure: Electrical components mounted in control box with removable cover
and mounted on side of unit. Incorporate single-point electrical connection to power source.
1. Control Transformer: Factory mounted for control voltage on electric and electronic
control units with terminal strip in control box for field wiring of thermostat and power
source.
2. Wiring Terminations: Fan and controls to terminal strip. Terminal lugs to match
quantities, sizes, and materials of branch-circuit conductors. Enclose terminal lugs in
terminal box that is sized according to NFPA 70.
3. Disconnect Switch: Factory-mounted, fuse type.
I. Direct Digital Controls : Single phase unitary controller and actuator as specified in Division 25.
J. All boxes shall have a maximum NC (Rad.) as scheduled on drawings. If required provide
attenuation to meet the NC level as scheduled.
A. Configuration: Volume-damper assembly and fan in parallel arrangement inside unit casing
with control components inside a protective metal shroud.
2. Air Inlets: Round stub connections or S-slip and drive connections for duct attachment.
3. Air Outlet: S-slip and drive connections.
4. Access: Removable panels for access to parts requiring service, adjustment, or
maintenance; with airtight gasket and quarter-turn latches.
5. Fan: Forward-curved centrifugal, located at plenum air inlet.
6. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1-2004.
C. Volume Damper: Galvanized steel with flow-sensing ring and peripheral gasket and self-
lubricating bearings.
1. Maximum Damper Leakage: ARI 880 rated, [2] [3] percent of nominal airflow at [3-inch
wg (750-Pa)] [6-inch wg (1500-Pa)] inlet static pressure.
2. Damper Position: Normally [open] [closed].
D. Velocity Sensors: Multipoint array with velocity sensors in cold- and hot-deck air inlets and air
outlets.
E. Motor:
1. Comply with NEMA designation, temperature rating, service factor, enclosure type, and
efficiency requirements for motors specified in Division 23 Section "Common Motor
Requirements for HVAC Equipment."
2. Type: [Permanent-split capacitor with SCR for speed adjustment] [Electronically
commutated motor].
3. Fan-Motor Assembly Isolation: Rubber isolators.
4. Enclosure: [Open dripproof] [Totally enclosed, fan cooled] [Totally enclosed, air
over] [Open, externally ventilated] [Totally enclosed, nonventilated] [Severe duty]
[Explosion proof] [Dust-ignition-proof machine].
5. Enclosure Materials: [Cast iron] [Cast aluminum] [Rolled steel].
6. Motor Bearings: <Insert special requirements>.
7. Unusual Service Conditions:
H. Hydronic Coils: Copper tube, with mechanically bonded aluminum fins spaced no closer
than 0.1 inch (2.5 mm), and rated for a minimum working pressure of 200 psig (1380 kPa)
and a maximum entering-water temperature of 220 deg F (104 deg C). Include manual air
vent and drain valve.
K. Control Panel Enclosure: NEMA 250, Type 1, with access panel sealed from airflow and
mounted on side of unit.
L. Electric Controls: 24-V damper actuator with wall-mounted electric thermostat and
appropriate mounting hardware.
A. Configuration: Volume-damper assembly inside unit casing with control components inside a
protective metal shroud.
B. Casing: minimum 22 gauge steel, single wall or double wall for non-critical areas/air, double
wall for critical areas/air.
1. Casing Lining:
2. Air Inlet: Round stub connection or S-slip and drive connections for duct attachment.
3. Air Outlet: S-slip and drive connections.
4. Access: Removable panels for access to parts requiring service, adjustment, or
maintenance; with airtight gasket.
5. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1-2007.
C. Velocity Sensors: Single axis sensor shall not be acceptable for duct diameters 6" or larger.
Multiple pressure sensing points shall be utilized. The total pressure inputs shall be averaged
using a pressure chamber located at the center of the sensor. Sensor shall have an error of
plus or minus 5% or better.
D. Volume Damper: Minimum 22 gauge steel with shaft rotating in self-lubricating bearings. Shaft
shall be clearly marked on the end to indicate damper position.
F. Hydronic Coils: Copper tube, with mechanically bonded aluminum fins spaced no closer
than 0.1 inch, and rated for a minimum working pressure of 300 psig and a maximum
entering-water temperature of 200 deg F. Include manual air vent and drain valve.
A. Configuration: [Mixing] [and] [non-mixing] with two volume dampers inside unit casing with
mixing attenuator section and control components inside a protective metal shroud[ with a third
primary air inlet with volume damper].
1. Casing Liner: Comply with requirements in "Casing Liner" Article for [fibrous-
glass] [flexible elastomeric] duct liner.
2. Air Inlets: Round stub connections or S-slip and drive connections for duct attachment.
3. Air Outlet: S-slip and drive connections.
4. Access: Removable panels for access to parts requiring service, adjustment, or
maintenance; with airtight gasket.
5. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1.
C. Volume Damper: Galvanized steel with peripheral gasket and self-lubricating bearings.
1. Maximum Damper Leakage: AHRI 880 rated, 3 percent of nominal airflow at [3-inch wg
(750-Pa)] [6-inch wg (1500-Pa)] inlet static pressure.
2. Damper Position: Normally [open] [closed].
D. Velocity Sensors: Multipoint array with velocity sensors in air inlets and air outlets.
1. Attenuator Section Liner: Comply with requirements in "Casing Liner" Article for [fibrous-
glass] [flexible elastomeric] duct liner.
2. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1.
F. Multioutlet Attenuator Section: With [two] [three] [four] <Insert number> [6-inch- (150-mm-)]
[8-inch- (200-mm-)] [10-inch- (250-mm-)] [12-inch- (300-mm-)] diameter collars, each with
locking butterfly balancing damper.
1. Attenuator Section Liner: Comply with requirements in "Casing Liner" Article for [fibrous-
glass] [flexible elastomeric] duct liner.
H. Control Sequence:
1. [System] [Room thermostat] modulates VAV damper and dual-duct damper.[ Room
sensor reports temperature.]
2. When Space Temperature Is below Set Point: Close VAV damper, open hot-deck
dampers and close cold-deck dampers, then open VAV damper.
3. When Space Temperature Is above Set Point: Close VAV damper, close hot-deck
dampers and open cold-deck dampers, then open VAV damper.
4. Occupancy sensor reports occupancy and enables occupied temperature set
point.
5. Occupancy sensor switches set point from occupied setting to unoccupied setting.
C. Steel Cable End Connections: Steel assemblies with brackets, swivel, and bolts designed for
duct hanger service; with an automatic-locking and clamping device.
D. Air Terminal Unit Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws;
compatible with duct materials.
E. Trapeze and Riser Supports: Steel shapes and plates for units with steel casings; aluminum for
units with aluminum casings.
A. Factory Tests: Test assembled air terminal units according to ARI 880.
1. Label each air terminal unit with plan number, nominal airflow, maximum and minimum
factory-set airflows, and ARI certification seal.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install air terminal units according to NFPA 90A, "Standard for the Installation of Air
Conditioning and Ventilating Systems."
B. Install air terminal units level and plumb. Maintain sufficient clearance for normal service and
maintenance.
C. If boxes have coils, install duct access doors downstream of same per Section 23 3314.
A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Chapter 4,
"Hangers and Supports."
D. Install upper attachments to structures. Select and size upper attachments with pull-out,
tension, and shear capacities appropriate for supported loads and building materials where
used.
3.3 CONNECTIONS
A. Install piping adjacent to air terminal unit to allow service and maintenance.
C. Make connections to inlets of air terminal units with flexible connectors complying with
requirements in Division 23 Section "Ductwork Specialties."
3.4 IDENTIFICATION
A. Label each air terminal unit with plan number, nominal airflow, and maximum and minimum
factory-set airflows. Comply with requirements in Division 23 Section "Mechanical Systems
Identification" for equipment labels and warning signs and labels.
1. After installing air terminal units and after electrical circuitry has been energized, test for
compliance with requirements.
2. Leak Test: After installation, fill water coils and test for leaks. Repair leaks and
retest until no leaks exist.
3. Operational Test: After electrical circuitry has been energized, start units to confirm
proper motor rotation and unit operation.
4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
B. Air terminal unit will be considered defective if it does not pass tests and inspections.
3.7 DEMONSTRATION
A. Train Owner's maintenance personnel to adjust, operate, and maintain air terminal units.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
A. Product Data: For each type of product indicated. Include dimensions; operating characteristics;
required clearances and access; rated flow capacity, including initial and final pressure drop at
rated airflow; efficiency and test method; fire classification; furnished specialties; and
accessories for each model indicated.
B. [LEED Submittals:
1. Product Data for Prerequisite IEQ 1: Documentation indicating that units comply
with ASHRAE 62.1, Section 5 - "Systems and Equipment."
2. Product Data for Credit IEQ 4.1: For adhesives and sealants, documentation
including printed statement of VOC content.
3. Laboratory Test Reports for Credit IEQ 4: For adhesives and sealants,
documentation indicating that products comply with the testing and product
requirements of the California Department of Public Health's "Standard Method for
the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor
Sources Using Environmental Chambers."]
C. Shop Drawings: For air filters. Include plans, elevations, sections, details, and attachments to
other work.
FILTERS 23 4114 - 1
1.4 INFORMATIONAL SUBMITTALS
A. Operation and Maintenance Data: For each type of filter and rack to include in emergency,
operation, and maintenance manuals.
A. Furnish extra materials that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents.
1. Provide three complete set(s) of pre-filters for each pre-filter bank, one set for use during
construction, one set for building turnover to University, and one spare set.
2. Provide two complete set(s) of after and final filters for each after and final filter bank, one
set for building turnover to University, and one spare set.
PART 2 - PRODUCTS
A. ASHRAE Compliance:
1. Comply with applicable requirements in ASHRAE 62.1, Section 4 - "Outdoor Air Quality";
Section 5 - "Systems and Equipment"; and Section 7 - "Construction and Startup."
2. Comply with ASHRAE 52.2 for MERV for methods of testing and rating air-filter units.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
a. AAF International.
b. Camfil Farr.
c. Flanders Corporation.
D. Filter-Media Frame: Cardboard frame with perforated metal retainer sealed or bonded to the
media.
E. Mounting Frames: Welded galvanized steel, with gaskets and fasteners; suitable for bolting
together into built-up filter banks.
a. AAF International.
b. Camfil Farr.
c. Flanders Corporation.
E. Mounting Frames: Welded galvanized steel, with gaskets and fasteners; suitable for bolting
together into built-up filter banks.
A. Framing System: Galvanized-steel (minimum 16 gage) framing members with access for either
upstream (front) or downstream (rear) filter servicing, cut to size and pre-punched for assembly
into modules. Vertically support filters to prevent deflection of horizontal members without
interfering with either filter installation or operation.
B. Pre-filters: Incorporate a separate track with spring clips, removable from front [or back].
C. Access Doors: Hinged, with continuous gaskets on perimeter and positive-locking cam or lever
type devices, and arranged so filter cartridges can be loaded from either side and access door.
D. Sealing: Factory-installed, positive-sealing device for each row of filters, to ensure seal between
gasketed filter elements and to prevent bypass of unfiltered air.
1. Ionizing Section: Alternately spaced grounded struts and charged ionizing wires.
2. Collecting Section: Alternately grounded and charged plates, with insulators located out
of airstream.
C. Power Pack: Self-contained, prewired rectifying unit to convert 24-V ac, single-phase, 60-Hz
power to approximately 9,500-V dc; include overload protection, on-off switch, pilot light
showing operating status, and access door interlock.
D. Safety Accessories: Manual-reset safety switches and warning lights for filter plenum access
doors, signal lights and safety switching upstream and downstream from unit within duct, and
enameled high-voltage warning signs.
E. Controls: Programmable logic controller in remotely mounted NEMA 250, Type 12 enclosure;
with integral time clock and manual override.
F. Finish of Interior Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1.
C. Access Doors: Hinged, with continuous gaskets on perimeter and positive-locking cam or lever
type devices, and arranged so filter cartridges can be loaded from either side and access door.
D. Sealing: Incorporate positive-sealing gasket material on channels to seal top and bottom of filter
cartridge frames and to prevent bypass of unfiltered air.
A. Diaphragm-type gage with dial and pointer in metal case, vent valves, black figures on white
background, and front recalibration adjustment.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Equipment Mounting:
B. Position each filter unit with clearance for normal service and maintenance. Anchor filter holding
frames to substrate.
C. Install filters in position to prevent passage of unfiltered air.
E. Do not operate fan system until filters (temporary or permanent) are in place. Replace
temporary filters used during construction and testing with new, clean filters.
F. Install filter-gage, static-pressure taps upstream and downstream from filters. Install filter gages
on filter banks with separate static-pressure taps upstream and downstream from filters. Mount
filter gages on outside of filter housing or filter plenum in an accessible position. Adjust and level
inclined gages.
A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.
D. Air filter will be considered defective if it does not pass tests and inspections.
3.3 CLEANING
A. After completing system installation and testing, adjusting, and balancing of air-handling and air-
distribution systems, clean filter housings and install new filter media.
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 DEFINITIONS
B. Shop Drawings: Signed and sealed by a qualified professional engineer. Detail equipment
assemblies and indicate dimensions, weights, loads, required clearances, method of field
assembly, components, and location and size of each field connection.
1. Design Calculations: Calculate requirements for selecting seismic restraints and for
designing bases.
2. Base Details: Detail fabrication including anchorages and attachments to structure and
to supported equipment.
A. Coordination Drawings: Equipment room, drawn to scale, on which the following items are
shown and coordinated with each other, using input from installers of the items involved:
1. Tube-removal space.
2. Structural members to which heat exchangers will be attached.
B. Product Certificates: For each type of shell-and-tube heat exchanger. Documentation that shell-
and-tube heat exchangers comply with "TEMA Standards."
A. Operation and Maintenance Data: For heat exchangers to include in emergency, operation,
and maintenance manuals.
B. Comply with FM Global requirements for pressure vessels and piping and for pressure relief
devices.
PART 2 - PRODUCTS
C. Construction:
1. Fabricate and label heat exchangers to comply with ASME Boiler and Pressure Vessel
Code, Section VIII, "Pressure Vessels," Division 1, National Board registered, and
registered with pressure vessel inspector.
2. Fabricate and label shell-and-tube heat exchangers to comply with "TEMA Standards."
F. Head:
G. Tubes:
1. Copper.
2. Tube diameter is determined by manufacturer based on service.
H. Tubesheet Material: Steel.
I. Baffles: Steel.
1. NPS 2 (DN 50) and Smaller: Threaded ends according to ASME B1.20.1.
2. NPS 2-1/2 (DN 65) and Larger: Flanged ends according to ASME B16.5 for steel and
stainless-steel flanges and according to ASME B16.24 for copper and copper-alloy
flanges.
K. Support Saddles:
1. Shell Side:
a. Fluid: Steam.
b. Working Pressure: 150 psig.
c. Test Pressure: 195 psig.
2. Tube Side:
2.2 ACCESSORIES
1. Custom, steel [supports] [cradles] for mounting on [floor] [wall] [structural steel].
A. Factory Tests: Test and inspect heat exchangers according to ASME Boiler and Pressure
Vessel Code, Section VIII, "Pressure Vessels," Division 1. Affix ASME label.
B. Hydrostatically test heat exchangers to minimum of one and one-half times pressure rating
before shipment.
C. Heat exchangers will be considered defective if they do not pass tests and inspections.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas for compliance with requirements for installation tolerances and for structural
rigidity, strength, anchors, and other conditions affecting performance of heat exchangers.
B. Examine roughing-in for heat-exchanger piping to verify actual locations of piping connections
before equipment installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
1. Coordinate sizes and locations of concrete bases with actual equipment provided.
2. Construct bases to withstand, without damage to equipment, seismic force required by
code.
3. Construct concrete bases [4 inches (100 mm)] high and extend base not less than 6
inches (150 mm) in all directions beyond the maximum dimensions of heat exchangers
unless otherwise indicated or unless required for seismic anchor support.
4. Minimum Compressive Strength: [5000 psi (34.5 MPa)] [4500 psi (31 MPa)] [4000 psi
(27.6 MPa)] [3500 psi (24.1 MPa)] [3000 psi (20.7 MPa)] at 28 days.
5. Install dowel rods to connect concrete base to concrete floor. Unless otherwise
indicated, install dowel rods on 18-inch (450-mm) centers around the full perimeter of
concrete base.
6. For supported equipment, install epoxy-coated anchor bolts that extend through concrete
base, and anchor into structural concrete floor.
7. Place and secure anchorage devices. Use setting drawings, templates, diagrams,
instructions, and directions furnished with items to be embedded.
8. Install anchor bolts to elevations required for proper attachment to supported equipment.
B. Equipment Mounting: Install heat exchangers with continuous-thread hanger rods and
[elastomeric hangers] [spring hangers] [spring hangers with vertical-limit stop] of size
required to support weight of heat exchangers filled with water.
1. Comply with requirements for vibration isolation devices specified in Section 23 0550
"Vibration Isolation."
2. Comply with requirements for hangers and supports specified in Section 23 0529
"Mechanical Supporting Devices."
C. Install heat exchangers on saddle supports.
3.3 CONNECTIONS
A. Comply with requirements for piping specified in other Section 23 2113 "Hydronic Piping."
Drawings indicate general arrangement of piping, fittings, and specialties.
B. Comply with requirements for steam and condensate piping specified in Section 23 2213
"Steam Piping."
C. Maintain manufacturer's recommended clearances for tube removal, service, and maintenance.
D. Install piping adjacent to heat exchangers to allow space for service and maintenance of heat
exchangers. Arrange piping for easy removal of heat exchangers.
F. Install relief valves on heat-exchanger heated-fluid connection and install pipe relief valves, full
size of valve connection, to floor drain.
I. Install thermometer on heat-exchanger and inlet and outlet piping, and install thermometer on
heating-fluid inlet and outlet piping. Comply with requirements for thermometers specified in
Section 23 0519 "Meters and Gages for HVAC Piping."
J. Install pressure gages on heat-exchanger and heating-fluid piping. Comply with requirements
for pressure gages specified in Section 23 0519 "Meters and Gages for HVAC Piping."
A. Perform the following tests and inspections with the assistance of a factory-authorized service
representative:
1. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest
until no leaks exist.
2. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
B. Heat exchanger will be considered defective if it does not pass tests and inspections.
3.5 CLEANING
A. After completing system installation, including outlet fitting and devices, inspect exposed finish.
Remove burrs, dirt, and construction debris and repair damaged finishes.
3.6 DEMONSTRATION
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1.3 DEFINITIONS
A. COP: Coefficient of performance. The ratio of the rate of heat removal to the rate of energy
input using consistent units for any given set of rating conditions.
C. EER: Energy-efficiency ratio. The ratio of the cooling capacity given in terms of Btu/h to the total
power input given in terms of watts at any given set of rating conditions.
D. IPLV: Integrated part-load value. A single number part-load efficiency figure of merit calculated
per the method defined by ARI 506/110 and referenced to ARI standard rating conditions.
E. kW/Ton: The ratio of total power input of the chiller in kilowatts to the net refrigerating capacity
in tons at any given set of rating conditions.
F. NPLV: Nonstandard part-load value. A single number part-load efficiency figure of merit
calculated per the method defined by ARI 506/110 and intended for operating conditions other
than the ARI standard rating conditions.
B. Shop Drawings: Complete set of manufacturer's prints of water chiller assemblies, control
panels, sections and elevations, and unit isolation. Include the following:
A. Coordination Drawings: Floor plans, drawn to scale, on which the following items are shown and
coordinated with each other, using input from installers of the items involved:
1. Structural supports.
2. Piping roughing-in requirements.
3. Wiring roughing-in requirements, including spaces reserved for electrical equipment.
4. Access requirements, including working clearances for mechanical controls and electrical
equipment, and tube pull and service clearances.
A. Operation and Maintenance Data: For each water chiller to include in emergency, operation,
and maintenance manuals.
B. If a manufacturer proposes a liquid chiller using HCFC-123 refrigerant, which has a planned
phase out date, then the manufacturer shall include in the chiller price:
1. A vapor activated alarm system consisting of all alarms, sensors, safeties, and ventilation
equipment as required by ANSI/ASHRAE (American National Standards
Institute/American Society of Heating, Refrigerating and Air-Conditioning Engineers)
Standard 15 Safety Code for Mechanical Refrigeration (latest edition) with the quotation.
System shall be capable of responding to HCFC-123 levels of 10 ppm Allowable
Exposure Limit (AEL).
2. A free-standing refrigerant storage tank and pumpout unit shall be provided. The storage
vessels shall be designed per ASME (American Society of Mechanical Engineers)
Section VIII Division 1 code with 300 psig (2068 kPa) design pressure. Double relief
valves per ANSI/ ASHRAE 15, latest edition, shall be provided. The tank shall include a
liquid level gage and pressure gage. The pumpout unit shall use a semi-hermetic
reciprocating compressor with water-cooled condenser. Condenser water piping, 3-phase
motor power, and 115-volt control power shall be installed at the jobsite by the installing
contractor.
3. Zero emission purge unit capable of operating even when the chiller is not operating.
4. Back-up relief valve to rupture disk.
5. Factory-installed chiller pressurizing system to prevent leakage of noncondensables into
the chiller during shutdown periods.
6. Plant room ventilation.
7. Removal and disposal of refrigerant at the end of the phase out period.
8. Chillers utilizing a purge unit shall include in the machine price the costs to perform the
following regular maintenance procedures:
A. Chiller performance shall be rated in accordance with AHRI (Air-Conditioning, Heating and
Refrigeration Institute) Standard 550/590, latest edition.
C. Cooler and condenser refrigerant side shall include ASME “U” stamp and nameplate certifying
compliance with ASME Section VIII, Division 1 code for unfired pressure vessels.
E. Chiller shall be designed and constructed to meet UL and UL of Canada requirements and have
labels appropriately affixed.
G. Each compressor assembly shall undergo a mechanical run-in test to verify vibration levels, oil
pressures, and temperatures are within acceptable limits. Each compressor assembly shall be
proof tested at a minimum 204 psig (1407 kPa) and leak tested at 185 psig (1276 kPa) with a
tracer gas mixture.
H. Entire chiller assembly shall be proof tested at 204 psig (1407 kPa) and leak tested at 185 psig
(1276 kPa) with a tracer gas mixture on the refrigerant side. The leak test shall not allow any
leaks greater than 0.5 oz per year of refrigerant. The water side of each heat exchanger shall be
hydrostatically tested at 1.3 times rated working pressure.
I. Prior to shipment, the chiller automated controls test shall be executed to check for proper
wiring and ensure correct controls operation.
B. Unit shall be shipped with all refrigerant piping and control wiring factory-installed.
C. Unit shall be shipped charged with oil and full charge of refrigerant HFC-134a or a nitrogen
holding charge as specified on the equipment schedule.
D. Unit shall be shipped with firmly attached labels that indicate name of manufacturer, chiller
model number, chiller serial number, and refrigerant used.
E. If the unit is to be exported, the manufacturer shall provide sufficient protection against sea
water corrosion, making the unit suitable for shipment in a standard open top ocean shipping
container.
F. Chiller and starter shall be stored indoors, protected from construction dirt and moisture. Chiller
shall be inspected under shipping tarps, bags, or crates to be sure water has not collected
during transit. Protective shipping covers shall be kept in place until machine is ready for
installation. The inside of the protective cover shall meet the following criteria:
1.10 WARRANTY
A. Warranty shall include parts and labor for one year after start-up or 18 months from shipment,
whichever occurs first. A refrigerant warranty shall be provided for a period of 5 years (North
America only).
2.1 MANUFACTURERS
2.3 GENERAL
A. General:
1. Factory-assembled, single piece, liquid chiller shall consist of compressor, motor, VFD,
lubrication system, cooler, condenser, initial oil and refrigerant operating charges,
microprocessor control system, and documentation required prior to start-up.
B. Compressor:
7. Compressor shall be fully field serviceable. Compressors that must be removed and
returned to the factory for service shall be unacceptable.
8. Acoustical attenuation shall be provided as required, to achieve a maximum (full load)
sound level, measured per AHRI Standard 575 (latest edition).
C. Motor:
1. Compressor motor shall be of the semi-hermetic, liquid refrigerant cooled, squirrel cage,
induction type suitable for voltage shown on the equipment schedule.
2. If an open (air-cooled) motor is provided, a compressor shaft seal leakage containment
system shall be provided:
a. An oil reservoir shall collect oil and refrigerant that leaks past the seal.
b. A float device shall be provided to open when the reservoir is full, directing the
refrigerant/oil mixture back into the compressor housing.
c. A refrigerant sensor shall be located next to the open drive seal to detect leaks.
3. Motors shall be suitable for operation in a refrigerant atmosphere and shall be cooled by
atomized refrigerant in contact with the motor windings.
4. Motor stator shall be arranged for service or removal with only minor compressor
disassembly and without removing main refrigerant piping connections.
5. Full load operation of the motor shall not exceed nameplate rating.
6. One motor winding temperature sensor (and one spare) shall be provided.
7. Should mechanical contractor choose to provide a chiller with an air-cooled motor instead
of the specified semi-hermetic motor, the contractor shall install additional cooling
equipment to dissipate the motor heat.
8. Also, if an open motor is provided, a mechanical room thermostat shall be provided and
set at 104 F (40 C). If this temperature is exceeded, the chillers shall shut down and an
alarm signal shall be generated to the central Energy Management System (EMS)
display module, prompting the service personnel to diagnose and repair the cause of the
overtemperature condition. The mechanical contractor shall be responsible for all
changes to the design, including coordination with temperature control, electrical and
other trades. In addition, the electrical power consumption of any auxiliary ventilation
and/or mechanical cooling required to maintain the mechanical room conditions stated
above shall be considered in the determination of conformance to the scheduled chiller
energy efficiency requirement.
1. Evaporator and condenser shall be of shell and tube type construction, each in separate
shells. Units shall be fabricated with high-performance tubing, steel shell and tube sheets
with waterboxes. Waterboxes shall be nozzle-in-head type with stub out nozzles having
Victaulic grooves to allow for use of Victaulic couplings.
2. Tubing shall be copper, high-efficiency type, with integral internal and external
enhancement unless otherwise noted. Tubes shall be nominal 3/4-in. OD with nominal
wall thickness of 0.025 in. measured at the root of the fin unless otherwise noted. Tubes
shall be rolled into tube sheets and shall be individually replaceable. Tube sheet holes
shall be double grooved for joint structural integrity. Intermediate support sheet spacing
shall not exceed 36 in. (914 mm).
3. Waterboxes and nozzle connections shall be designed for 150 psig (1034 kPa) minimum
working pressure unless otherwise noted. Nozzles should have grooves to allow use of
Victaulic couplings.
4. The tube sheets of the cooler and condenser shall be bolted together to allow for field
disassembly and reassembly.
5. The vessel shall display an ASME nameplate that shows the pressure and temperature
data and the “U” stamp for ASME Section VIII, Division 1. A re-seating pressure relief
valve(s) shall be installed on each heat exchanger. If a non-reseating type is used, a
backup reseating type shall be installed in series.
6. Waterboxes shall have vents, drains, and covers to permit tube cleaning within the space
shown on the drawings. A thermistor type temperature sensor with quick connects shall
be factory-installed in each water nozzle.
7. Cooler shall be designed to prevent liquid refrigerant from entering the compressor.
Devices that introduce pressure losses (such as mist eliminators) shall not be acceptable
because they are subject to structural failures that can result in extensive compressor
damage.
8. Tubes shall be individually replaceable from either end of the heat exchanger without
affecting the strength and durability of the tube sheet and without causing leakage in
adjacent tubes.
9. The subcooler, located in the bottom of the condenser, shall increase the refrigeration
effect by cooling the condensed liquid refrigerant to a lower temperature, thereby
reducing compressor power consumption.
1. The variable flow control system regulates refrigerant flow according to load conditions,
providing a liquid seal at all operating conditions, eliminating unintentional hot gas
bypass.
1. Controls:
f. In addition to the default screen, status screens shall be accessible to view the
status of every point monitored by the control center including:
1) Evaporator pressure
2) Condenser pressure
3) Compressor speed
4) Bearing oil supply temperature
5) Compressor discharge temperature
6) Motor winding temperature
7) Number of compressor starts
8) Control point settings
9) Discrete output status of various devices
10) Variable frequency drive status
11) Optional spare input channels
12) Line current and voltage for each phase
13) Frequency, kW, kWhr, demand kW
g. Schedule Function:
h. Service Function:
1) Each chiller control panel shall be capable of viewing multiple point values
and statuses from other like controls connected on a common network,
including controller maintenance data. The operator shall be able to alter the
remote controller’s set points or time schedule and to force point values or
statuses for those points that are operator forcible. The control panel shall
also have access to the alarm history file of all like controllers connected on
the network.
j. Pump Control:
1) Upon request to start the compressor, the control system shall start the
chilled and condenser water pumps and shall verify that flows have been
established.
k. Ramp Loading:
1) The control center shall allow reset of the chilled water temperature set point
based on any one of the following criteria:
m. Demand Limit:
1) The control center shall limit amp draw of the compressor to the rated load
amps or to a lower value based on one of the following criteria:
2. Safeties:
a. Unit shall automatically shut down when any of the following conditions occur
(each of these protective limits shall require manual reset and cause an alarm
message to be displayed on the control panel screen, informing the operator of the
shutdown cause):
1) Motor overcurrent
2) Over voltage*
3) Under voltage*
4) Single cycle dropout* (LF-2 VFDs only)
5) Low oil sump temperature
6) Low evaporator refrigerant temperature
7) High condenser pressure
8) High motor temperature
9) High compressor discharge temperature
10) Low oil pressure
11) Prolonged stall
12) Loss of cooler water flow
13) Loss of condenser water flow
14) Variable frequency drive fault
15) High variable frequency drive temperature
b. The control system shall detect conditions that approach protective limits and take
self-corrective action prior to an alarm occurring. The system shall automatically
reduce chiller capacity when any of the following parameters are outside their
normal operating range:
c. During the capacity override period, a pre-alarm (alert) message shall be displayed
informing the operator which condition is causing the capacity override. Once the
condition is again within acceptable limits, the override condition shall be
terminated and the chiller shall revert to normal chilled water control. If during
either condition the protective limit is reached, the chiller shall shut down and a
message shall be displayed informing the operator which condition caused the
shutdown and alarm.
d. Internal built-in safeties shall protect the chiller from loss of water flow. Differential
pressure switches shall not be allowed to be the only form of freeze protection.
G. Electrical Requirements:
1. Electrical contractor shall supply and install main electrical power line, disconnect
switches, circuit breakers, and electrical protection devices per local code requirements
and as indicated necessary by the chiller manufacturer.
2. Electrical contractor shall wire the chilled water pump and flow, condenser water pump
and flow, and tower fan control circuit to the chiller control circuit.
3. Electrical contractor shall supply and install electrical wiring and devices required to
interface the chiller controls with the building control system if applicable.
4. Electrical power shall be supplied to the unit at the voltage, phase, and frequency listed in
the equipment schedule.
1. Mechanical contractor shall supply and install pressure gages in readily accessible
locations in piping adjacent to the chiller such that they can be easily read from a
standing position on the floor. Scale range shall be such that design values shall be
indicated at approximately midscale.
2. Gages shall be installed in the entering and leaving water lines of the cooler and
condenser.
I. Vibration Isolation:
1. Chiller manufacturer shall furnish neoprene isolator pads for mounting equipment on a
level concrete surface.
J. Start-Up:
K. Special Features:
1. Soleplate Package:
2. Spring Isolators:
a. Spring isolators shall be field furnished and selected for the desired degree of
isolation.
a. A free-standing pumpout unit shall be provided. The pumpout unit shall use a
semi-hermetic reciprocating compressor with liquid-cooled condenser. Condenser
liquid piping and 3-phase motor power shall be installed at the jobsite by the
installing contractor.
a. A free-standing refrigerant storage tank and pumpout unit shall be provided. The
storage vessels shall be designed per ASME Section VIII Division 1 code with 150
psig (1034 kPa) design pressure. Double relief valves per ANSI/ ASHRAE 15,
latest edition, shall be provided. The tank shall include a liquid level gage and
pressure gage. The pumpout shall use a hermetic reciprocating compressor with
water-cooled condenser. Condenser water piping and 3-phase motor power shall
be installed at the jobsite by the installing contractor.
a. The chiller control system shall have the ability to interface and communicate
directly to the building control using a LON based system. The LonWorks Carrier
Translator shall output data in standard LON profiles.
8. Refrigerant Charge:
a. The chiller shall ship from the factory fully charged with R-134a refrigerant and oil.
9. 9. Thermal Insulation:
a. Unit manufacturer shall insulate the cooler shell, economizer, suction elbow, motor
shell and motor cooling lines. Insulation shall be 1 in. (25.4 mm) thick with a
thermal conductivity not exceeding and shall conform to UL standard 94,
classification 94 HF-1.
)
(Btu · in.) W
0.28 hr. Ft2 F ( 0.0404 mC
a. Unit manufacturer shall provide the cooler and/ or condenser with 1, 2 or 3 pass
configuration on the water side.
a. Unit manufacturer shall furnish standard flanged piping connections on the cooler
and/ or condenser.
17. Hinges:
18. Optional Compressor Discharge Isolation Valve and Liquid Line Ball Valve:
a. Package shall meet International Building Code and ASCE 7 seismic qualification
requirements in concurrence with ICC ES AC156 Acceptance Criteria for Seismic
Qualification by Shake-Table Testing of Nonstructural Components and Systems.
Manufacturer shall provide seismic certificate from OSHPD (California only).
21. Unit-Mounted Variable Frequency Drive (VFD) with Built-In Harmonic LiquiFlo™ II Filter
(Q and R compressor only):
a. Design:
b. Enclosure:
c. Heat Sink:
1) The heat sink (frame sizes 3, 4, 5 heat exchangers only) shall be refrigerant
cooled. Heat sink and mating flanges shall be suitable for ASME design
working pressure of 185 psig (1276 kPa).
2) Refrigerant cooling shall be metered to maintain heat sink temperature
within acceptable limits for ambient temperature.
d. VFD Rating:
e. User Interface:
1) A single display shall provide interface for programming and display of VFD
and chiller parameters. Viewable parameters include:
f. VFD Performance:
1) The VFD Voltage Total Harmonic Distortion (THD) and Harmonic Current
Total Demand Distortion (TDD) shall not exceed IEEE-519 requirements
using the VFD circuit breaker input terminals as the point of common
coupling (PCC).
2) The VFD full load efficiency shall meet or exceed 97% at 100% VFD rated
ampacity.
3) Active rectifier shall regulate unity displacement power factor to 0.99 or
higher.
4) Voltage boost capability to provide full motor voltage at reduced line voltage
conditions.
5) The VFD shall feature soft start, linear acceleration, and coast to stop
capabilities.
6) Base motor frequency shall permit motor to be utilized at nameplate voltage.
Adjustable frequency range shall permit capacity control down to 15%.
7) The VFD shall have 150% instantaneous torque generation.
1) The VFD shall have input circuit breaker with minimum 65,000 amp interrupt
capacity.
2) The VFD shall have standard branch oil pump circuit breaker to provide
power for chiller oil pump.
3) The VFD shall have standard 3 KVA control power transformer with circuit
breaker to provide power for oil heater, VFD controls and chiller controls.
4) The branch oil pump circuit breaker and control power transformer shall be
factory- wired.
5) Input power shall be 380/460 vac, ±10%, 3 Phase, 50/60 Hz, ±2% Hz.
h. Discrete Outputs:
i. Analog Output:
1) Under-voltage
2) Over voltage
3) Phase loss
4) Phase reversal
5) Ground fault
6) Phase unbalance protection
7) Single cycle voltage loss protection (LF-2 VFD only)
8) Programmable auto re-start after loss of power
9) Motor overload protection (NEMA Class 10)
10) Motor over temperature protection
k. VFD Testing:
22. Unit-Mounted Variable Frequency Drive (VFD) without Built-In Harmonic Filter:
a. Design:
b. Enclosure:
c. Heat Sink:
1) The heat sink (frame sizes 3, 4, 5 heat exchangers only) shall be refrigerant
cooled. Heat sink and mating flanges shall be suitable for ASME design
working pressure of 185 psig (1276 kPa).
2) Refrigerant cooling shall be metered by integrated standard controls to
maintain heat sink temperature within acceptable limits for ambient
temperature.
d. VFD Rating:
1) Drive shall be suitable for nameplate voltage ±10%.
2) Drive shall be suitable for continuous operation at 100% of nameplate amps
and 150% of nameplate amps for 3 seconds.
3) Drive shall comply with applicable UL, CE, and NEMA standards.
4) Drive shall be suitable for operation in ambient temperatures between 40
and 104 F (4.4 and 40 C), 95% humidity (non-condensing) for altitudes up to
3300 feet (1006 m) above sea level. Specific drive performance at jobsite
ambient temperature and elevation shall be provided by the manufacturer in
the bid.
e. User Interface:
1) Displays shall provide interface for programming and display of VFD and
chiller parameters. Viewable parameters include:
f. VFD Performance:
1) VFD full load efficiency shall meet or exceed 97% at 100% VFD Rated
Ampacity.
2) Base motor frequency shall be either 50 or 60 hertz.
1) VFD shall have input circuit breaker with minimum 65,000 amp interrupt
capacity.
2) VFD shall have standard 15 amp branch oil pump circuit breaker to provide
power for chiller oil pump.
3) VFD shall have standard 3 kva control power transformer with circuit
breaker provides power for oil heater, VFD controls and chiller controls.
4) The branch oil pump circuit breaker and control power transformer shall be
factory wired.
5) Input power shall be 380/480 vac, ±10 percent, 3 phase, 50/60 Hz, ±3 Hz.
h. Discrete Outputs:
i. Analog Output:
k. VFD Testing:
1) The VFD shall be factory mounted, wire and tested on the chiller prior to
shipment.
23. Unit-Mounted Variable Frequency Drive (575-v VFD) without Built-In Harmonic Filter (Q
and R compressor only):
a. Design:
b. Enclosure:
c. Heat Sink:
1) The heat sink shall be refrigerant cooled. Heat sink and mating flanges shall
be suitable for ASME design working pressure of 185 psig (1276 kPa).
2) Refrigerant cooling shall be metered by integrated standard controls to
maintain heat sink temperature within acceptable limits for ambient
temperature.
d. VFD Rating:
e. User Interface:
1) Displays shall provide interface for programming and display of VFD and
chiller parameters. Viewable parameters include:
f. VFD Performance:
1) VFD full load efficiency shall meet or exceed 97% at 100% VFD Rated
Ampacity.
2) Base motor frequency shall be 60 hertz.
1) VFD shall have input circuit breaker with minimum 35,000 amp interrupt
capacity.
2) VFD shall have standard 15 amp branch oil pump circuit breaker to provide
power for chiller oil pump.
3) VFD shall have standard 3 kva control power transformer with circuit
breaker provides power for oil heater, VFD controls and chiller controls.
4) The branch oil pump circuit breaker and control power transformer shall be
factory wired.
5) Input power shall be 575 vac, ±10 percent, 3 phase, 60 Hz, ±3 Hz.
h. Discrete Outputs:
i. Analog Output:
1) Under-voltage
2) Over voltage
3) Phase loss
4) Phase unbalance protection
5) Programmable auto re-start after loss of power
6) Motor overload protection (NEMA Class 10)
7) Motor over temperature protection
k. VFD Testing:
1) The VFD shall be factory mounted, wire and tested on the chiller prior to
shipment.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Before water chiller installation, examine roughing-in for equipment support, anchor-bolt sizes
and locations, piping, and electrical connections to verify actual locations, sizes, and other
conditions affecting water chiller performance, maintenance, and operations.
1. Water chiller locations indicated on Drawings are approximate. Determine exact locations
before roughing-in for piping and electrical connections.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
B. Equipment Mounting:
D. Charge water chiller with refrigerant if not factory charged and fill with oil if not factory installed.
3.3 CONNECTIONS
A. Comply with requirements in Section 232113 "Hydronic Piping" and Section 232116 Hydronic
Piping Specialties." Drawings indicate general arrangement of piping, fittings, and specialties.
C. Evaporator Fluid Connections: Connect to evaporator inlet with shutoff valve, strainer, flexible
connector, thermometer, and plugged tee with pressure gage. Connect to evaporator outlet with
shutoff valve, balancing valve, flexible connector, flow switch, thermometer, plugged tee with
pressure gage, flow meter, and drain connection with valve. Make connections to water chiller
with a flange.
D. Refrigerant Pressure Relief Valve Connections: For water chillers installed indoors, extend vent
piping to the outside without valves or restrictions. Comply with ASHRAE 15.
E. Connect each drain connection with a union and drain pipe and extend pipe, full size of
connection, to floor drain. Provide a shutoff valve at each connection if required.
C. Complete installation and startup checks according to manufacturer's written instructions and
perform the following:
1. Verify that refrigerant charge is sufficient and water chiller has been leak tested.
2. Verify that pumps are installed and functional.
3. Verify that thermometers and gages are installed.
4. Operate water chiller for run-in period.
5. Check bearing lubrication and oil levels.
6. Verify that refrigerant pressure relief device for chillers installed indoors is vented outside.
7. Verify proper motor rotation.
8. Verify static deflection of vibration isolators, including deflection during water chiller
startup and shutdown.
9. Verify and record performance of chilled water flow and low-temperature interlocks.
10. Verify and record performance of water chiller protection devices.
11. Test and adjust controls and safeties. Replace damaged or malfunctioning controls and
equipment.
D. Prepare a written startup report that records results of tests and inspections.
3.5 DEMONSTRATION
GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 DEFINITIONS
1. Include rated capacities, pressure drop, fan performance data, rating at selected points
indicated, and furnished specialties and accessories.
2. Maximum flow rate.
3. Minimum flow rate.
4. Pressure required at cooling tower supply piping connections.
a. Sound pressure levels for operation with fan off, fan at minimum speed, and design
speed. If sound requirements are indicated at a specific distance, submit
performance using same distance for comparative analysis.
b. Sound power levels in eight octave bands for operation with fans off, fans at
minimum speed, and design speed.
11. Fan airflow at design conditions, brake horsepower, and drive losses (indicated in
horsepower and percent of brake horsepower).
12. Fan motor electrical characteristics including, but not limited to, speed, voltage, phase,
hertz, amperage, efficiency, and power factor at 100, 75, 50, and 25 percent of
nameplate horsepower.
13. Electrical power requirements for each cooling tower component requiring power.
Shop Drawings:
Delegated-Design Submittal: For cooling tower support structure indicated to comply with
performance requirements and design criteria, including analysis data signed and sealed by the
qualified professional engineer responsible for their preparation.
Coordination Drawings:
1. Drawings on which the following items are shown and coordinated with each other, using
input from installers of the items involved:
a. Structural supports.
b. Piping roughing-in requirements.
c. Conduit and wiring roughing-in requirements for controls and electrical power,
including spaces reserved for controls and electrical equipment.
d. Access requirements, including working clearances for controls and electrical
equipment, and service clearances. Mark and label clearances on drawings.
2. Drawings showing plans, sections, and elevation views, drawn to scale of at least 1/4” =
1’-0”.
3. Each view to show screened background with the following:
a. Structural grids.
b. Adjacent walls, floors, and roofs.
c. Equipment and products of other trades that are located in vicinity of cooling
towers and are part of final installation, such as, controls, power, lighting, fire-
suppression systems, and plumbing systems.
Seismic Qualification Data: Certificates, for cooling towers, accessories, and components, from
manufacturer.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
Operation and Maintenance Data: For each cooling tower to include in emergency, operation,
and maintenance manuals.
Instructional Videos: Including those that are prerecorded and those that are recorded during
training.
Belts:
1. Furnish one set of matching belts for each unique belt configuration and size furnished.
Tool Kit:
1. A tool kit specially designed by cooling tower manufacturer for use in servicing cooling
tower(s) furnished.
2. Special tools required to service components not readily available to Owner service
personnel in performing routine maintenance.
3. Lockable case with hinged cover, marked with large and permanent text to indicate the
special purpose of tool kit, such as "Cooling Tower Tool Kit." Text size shall be at least
1 inch (25 mm) high.
4. A list of each tool furnished. Permanently attach the list to underside of case cover. Text
size shall be at least 1/2 inch (13 mm) high.
Touchup Coating: 32-oz. (1-L) container of paint coating used. Label outside of container with
detailed description of coating to allow for procurement of a matching coating in the future.
CTI Certification: Cooling tower thermal performance according to CTI STD 201RS.
FM Global: Approval and listing in the latest edition of FM Global's "Approval Guide."
Coordinate requirements for multi-piece assembly for shipment. Limit the number of separate
pieces for field installation to as few as possible.
If factory assembly of multiple pieces is required for testing or other reasons, disassemble cooling
tower into major assemblies as required by installation before packaging for shipment.
1. Clearly label each separate package with a unique designation and include assembly
instructions for complete cooling tower.
Install seals on gear-drive assemblies to eliminate oil leakage during shipment if shipped with oil.
1.10 WARRANTY
The entire tower, including structure, casing, basins, decking, fan(s), motor(s), and all
mechanical drive components (including belts, if used) shall be warranted against failure due to
defects in materials and workmanship for a period of five (5) years from the date of shipment to
the job. Towers not covered by a warranty of this scope will not be accepted.
PRODUCTS
2.1 MANUFACTURERS
The tower structure, anchorage and all its components shall be designed by licensed
professional engineers, employed by the manufacturer, per the International Building Code to
withstand a wind load of 30 psf, as well as a .3g seismic load. The fan deck, hot-water basin
covers and, where specified, maintenance platforms shall be designed for 60 psf live load or a
200 lb concentrated load. Guardrails, where specified, shall be capable of withstanding a 200 lb
concentrated live load in any direction, and shall be designed in accordance with OSHA
guidelines.
The tower shall be structurally capable of being supported at the four outer corners of the tower
cell. Alternatively, the tower manufacturer shall provide supporting steel to adapt tower to be
supported at four outer corners. NC8401-NC8414 only.
Seismic Performance: Cooling towers shall withstand the effects of earthquake motions
determined according to ASCE/SEI 7.
1. The term "withstand" means "the unit will remain in place without separation of any parts
from the device when subjected to the seismic forces specified and the unit will be fully
operational after the seismic event."
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by
a qualified testing agency, and marked for intended location and application.
Vibration:
2.3 BASE
Provide an induced draft, crossflow type, factory assembled, film fill, industrial duty, galvanized
steel cooling tower situated as shown on the plans. The limiting overall dimensions of the tower
shall be wide, _ long, and high. Total operating horsepower of all fans shall
not exceed _ hp, consisting of @_ _ hp motor(s). Tower shall be similar and equal in
all respects to Marley Model _ .
Provide alternate pricing to provide an induced draft, crossflow type, factory assembled, film fill,
industrial duty, stainless steel cooling tower situated as shown on the plans. The limiting overall
dimensions of the tower shall be _ _ wide, _ long, and high. Total operating
horsepower of all fans shall not exceed hp, consisting of _@ hp motor(s). Tower
shall be similar and equal in all respects to Marley Model _.
The cooling tower shall be designed for quiet operation, and shall produce an overall level of
sound not higher than _ _ dB(A) measured at _ ft from the locations in the following
table. Sound levels shall be independently verified by a CTI-licensed sound test agency to
ensure validity and reliability of the manufacturer’s published values. Measurement and analysis
of the sound levels shall be conducted by a certified Professional Engineer in Acoustical
Engineering. Sound pressure levels shall be measured and recorded in the acoustic near-field
and far-field locations using ANSI S1.4 Type 1 precision instrumentation and in full conformance
with CTI ATC-128 test code published by the Cooling Technology Institute (CTI). All low sound
options shall be CTI certified for thermal performance.
The tower shall be capable of a minimum gpm/hp efficiency per ASHRAE Standard 90.1.
CTI and Eurovent certification notwithstanding, the cooling tower manufacturer shall guarantee
that the tower supplied will meet the specified performance conditions when the tower is
installed according to plan. If, because of a suspected thermal performance deficiency, the
owner chooses to conduct an on-site thermal performance test under the supervision of a
qualified, disinterested third party in accordance with CTI, Eurovent or ASME standards during
the first year of operation; and if the tower fails to perform within the limits of test tolerance; then
the cooling tower manufacturer will pay for the cost of the test and will make such corrections as
are appropriate and agreeable to the owner to compensate for the performance deficiency.
2.5 CONSTRUCTION
Except where otherwise specified, all components of the cooling tower shall be fabricated of
steel, protected against corrosion by G-235 galvanizing. The tower shall be capable of
withstanding water having a pH of 6.5 to 8.0; a chloride content (NaCl) up to 300 ppm; a sulfate
content (SO4) up to 250 ppm; a calcium content (CaCO 3) up to 500 ppm; and silica (SiO 2) up to
150 ppm. The circulating water shall contain no oil, grease, fatty acids or organic solvents.
Provide alternate pricing to provide except where otherwise specified, all components of the
cooling tower shall be fabricated of 301L stainless steel. The tower shall be capable of
withstanding water having a chloride content (NaCl) up to 750 ppm; a sulfate content (SO4) up
to 1200 ppm; a calcium content (CaCO3) up to 800 ppm; and silica (SiO2) up to 150 ppm. The
circulating water shall contain no oil, grease, fatty acids, or organic solvents.
Fiberglass casing, polyurethane barriers, and thermosetting hybrids and the components they are
adhered to shall be considered non-recyclable and not allowed.
The specifications, as written, are intended to indicate those materials that will be capable of
withstanding the above water quality in continuing service, as well as the loads described in
paragraph 4.1. They are to be regarded as minimum requirements. Where component materials
peculiar to individual tower designs are not specified, the manufacturers shall take the above
water quality and load carrying capabilities into account in the selection of their materials of
manufacture.
The tower shall be listed in the current FM Approval Guide (approvalguide.com) and conform to
the FM Approval Standard for Cooling Towers, Class Number 4930 that is approved for use
without sprinkler systems. The tower shall have successfully passed full scale fire testing, static
and cyclic wind pressure testing, large missile impact testing (for Zone HM), and structural
design
evaluation as administered by FM Approvals. The tower shall be capable of +70/-140 psf for
Zone H as defined by FM Global. A copy of the FM Approval Certificate of Compliance dated
November 2013 or later shall be available upon request.
Fan(s) shall be propeller-type, incorporating wide-chord acoustic geometry, corrosion and fire
resistant marine grade aluminum blades and aluminum hubs. Blades shall be resiliently
mounted to fan hub and individually adjustable. Fan blades shall be open cavity with suitable
drainage to avoid accumulation of moisture. Foam filled blades are not allowed due to potential
moisture contamination of the foam core causing an imbalance of the fan leading to vibration
issues. Maximum fan tip speed shall be 10,000 ft/min. Fan(s) shall be driven through a right
angle, industrial duty, oil lubricated, geared speed reducer that requires no oil changes for the
first five
(5) years of operation. The gearbox bearings shall be rated at an L10A service life of 100,000
hours or greater. The gear sets to have AGMA Quality Class of 9 or greater.
Two-speed motor(s) shall be hp maximum, TEFC, 1.15 service factor, variable torque, and
specially insulated for cooling tower duty (Class F). Speed and electrical characteristics shall be
RPM, 3 phase, __ hertz, volts. Motor shall operate in the shaft-horizontal position
for geardrive towers and the shaft-down position for belt drive towers. Nameplate horsepower
shall not be exceeded at design operation.
The motor to gearbox close coupling shall be a tire-type, single piece, flexible element design to
accommodate frequent speed changes that are inherent with VFD applications.
The complete mechanical equipment assembly for each cell shall be supported by two
horizontal steel beams that resist misalignment between the motor and the gear reducer/belt
drive system. The mechanical equipment assembly shall be warranted against any failure
caused by defects in materials and workmanship for no less than five (5) years following the
date of tower shipment. This warranty shall cover the fan, speed reducer, drive shaft and
couplings, and the mechanical equipment support. The electric motor shall carry a
manufacturer's warranty of at least one year.
A factory installed terminal box shall be furnished and mounted to the outside of the tower
where applicable. The fan motor and optional components—including the vibration switch and
water level probes—shall be factory wired to terminal points inside the terminal box. Optional
tower components which ship loose, including the oil level switch and immersion heaters shall
be field wired to the terminal box. Enclosure shall be NEMA 3R or NEMA 4X with hinged and
lockable door meeting UL and CSA standards. Terminal box shall include lockable stainless
steel snap- latch door fasteners, terminal blocks marked with wire numbers, sub-pan and a
wiring diagram. Complete assembly shall be built to UL 508A standards. Conduit entry and exit
points shall be the bottom of the enclosure preventing water collection in the enclosure.
A vibration limit switch in a NEMA 4X housing shall be installed on the mechanical equipment
support and wired to the shutdown circuit of the fan motor starter or VFD. The purpose of this
switch will be to interrupt control power voltage to a safety circuit in the event of excessive
vibration causing the starter or VFD equipment to de-energize the motor. It shall be adjustable
for sensitivity and include a means to reset the switch.
For fan control a complete UL listed variable speed drive system in a NEMA 1 indoor, NEMA 12
indoor or NEMA 3R outdoor enclosure shall be provided. The VFD shall use PWM technology
with IGBT switching. VFD output switching signal shall be programmed to not cause mechanical
vibration issues with backlash in gearbox teeth or vibration issues associated with long
driveshafts. The VFD shall be programmed for variable torque applications and shall catch a fan
spinning in the forward or reverse direction without tripping. VFD panel construction shall
include a main disconnect with short circuit and thermal overload protection with external
operating handle, lockable in the off position for lock-out tag-out safety procedures. A service
switch directly ahead of the VFD shall be provided for voltage isolation during VFD
maintenance. An integrated full voltage non-reversing bypass starter shall be furnished allowing
fan motor operation if VFD has failed. The VFD system shall receive a speed reference signal
from the building management system monitoring the cooling tower cold-water temperature. As
an option to receiving the speed reference signal from a building management system, the drive
must have the capability to receive a 4-20 mA temperature signal from an RTD transmitter.
When using an RTD for temperature monitoring and speed control the VFD shall have an
internal PI regulator to modulate fan speed maintaining set point temperature. The drive’s panel
shall display the set-point temperature and cold-water temperature on two separate lines. The
bypass shall include a complete electromechanical magnetic bypass circuit with the capability to
isolate the VFD when in the bypass mode. Transfer to the bypass mode shall be manual in the
event of VFD failure. Once the motor is transferred to the bypass circuit the fan motor will run at
constant full speed. Operator controls shall be mounted on the front of the enclosure and shall
consist of Start and Stop control, Bypass/VFD selection, Auto/Manual selections and manual
speed control. To prevent heating problems in the fan motor the VFD system shall de-energize
the motor once 25% motor speed is reached and cooling is no longer required. The cooling
tower manufacturer shall offer VFD start-up assistance to assure proper VFD programming for
cooling tower operation.
Each cell of the cooling tower shall be equipped with a UL/CUL 508 listed SPPC (Single Point
Power Connection) control panel in a NEMA 3R or 4X outdoor enclosure. The SPPC panel shall
include a main circuit breaker with an external operating handle, lockable in the off position for
safety. The SPPC main circuit breaker will feed various control circuits integrated into the SPPC
panel including but not limited to: fan motor starter, basin heater controls and water level
controls. In the event a VFD is furnished for the cooling tower fan, a feeder breaker in the SPPC
panel shall be provided to feed power to a remotely mounted VFD. Operational status contacts
wired to user terminal points shall be provided.
A portable davit crane shall be mounted on the fan deck of the tower and shall be capable of
lifting, extending, and lowering the heaviest mechanical component up to 1000 lb over the fan
deck and down the air inlet face of the tower. The davit crane system shall include a winch,
cable, and load hook. NC8401-NC8414 only.
An external oil level dipstick shall be located adjacent to the motor at the fan deck surface and
shall be accessible from a portable maintenance ladder.
Fill shall be film type, thermoformed PVC, with louvers and eliminators formed as part of each fill
sheet. Fill shall be suspended from hot dip galvanized structural tubing supported from the tower
NORTHWESTERN UNIVERSITY
PROJECT NAME FOR:
JOB # ISSUED: 03/29/2017
structure, and shall be elevated above the floor of the cold-water basin to facilitate cleaning. Air
inlet faces of the tower shall be free of water splash out.
Drift eliminators shall be PVC, triple-pass, and shall limit drift losses to 0.005% or less of the
design water flow rate.
Two open 301L stainless steel basins (one above each bank of fill) shall receive hot water piped
to each cell of the tower. These basin components shall be installed and sealed at the factory
and assembled with bolted connections. Tap screws shall not be acceptable due to their
potential to develop leaks. The basins shall be equipped with removable, stainless steel covers
capable of withstanding the loads described in paragraph 4.1. The water distribution system
shall be accessible and maintainable during tower fan and water operation.
Each basin shall include an inlet hole and bolt circle to accept a 125# flange connection per
ANSI B16.1. Removable, interchangeable polypropylene nozzles installed in the floor of these
basins shall provide full coverage of the fill by gravity flow.
The water distribution system shall be accessible and maintainable while tower is operating.
The casing and fan deck shall be galvanized steel, and shall be capable of withstanding the
loads described in paragraph 4.1. The top of the fan opening shall be equipped with a conical,
non- sagging, removable fan guard, fabricated of welded 5⁄16" and 7 gauge rods, and hot dip
galvanized after fabrication. Fan cylinders 5'-0" in height and over shall not be required to have
a fan guard.
Provide alternate pricing to provide the casing and fan deck shall be 301L stainless steel, and
shall be capable of withstanding the loads described in paragraph 4.1. The top of the fan shall
be equipped with a conical, non-sagging, removable fan guard, fabricated of welded 5/16" and 7
gauge rods, and hot dip galvanized after fabrication. Fan cylinders 5'-0" in height and over shall
not be required to have a fan guard.
The air inlet faces of the tower shall be covered by 1" mesh hot-dipped galvanized welded wire
screens. Screens shall be secured to removable galvanized U-edge frames. Screens shall be
designed to permit full access to the cold-water basin by removal of one panel on each air inlet.
2.10 ACCESS:
A large galvanized, rectangular access door shall be located on both cased faces for entry into
the cold-water basin. Doors shall provide convenient access to the fan plenum area to facilitate
inspection and allow maintenance to the fan drive system. The access doors shall be " wide
by " high.
Provide alternate pricing to provide a large 301L stainless steel, rectangular access door shall
be located on both cased faces for entry into the cold-water basin. Doors shall provide
convenient access to the fan plenum area to facilitate inspection and allow maintenance to the
fan drive system. The access doors shall be " wide by " high.
The top of the tower shall be equipped with a guardrail complete with kneerail and toeboard,
A heavy gauge aluminum safety cage, welded into subassemblies for ease of field installation,
shall surround the ladder, extending from a point approximately 7'-0" above the foot of the
ladder to the top of the guardrail. Maximum weight of welded subassemblies shall not exceed
20 lb for ease of installation.
There shall be an access platform at the base of the tower extending from the vertical ladder to
the access door. The platform shall be surrounded by an OSHA compliant guardrail system
welded into subassemblies for ease of installation. The walking surface of the platform shall be
perforated to provide a non-slip surface for personnel safety.
Provide a factory-installed walkway extending from one cased-face access door to the other
cased face. A steel framework shall support the walkway and the top of the walkway shall be at
or above the cold-water basin overflow level. The walkway and framework to be equivalent
material as the tower basin and have a minimum width of 36".
Interior Mechanical Equipment Access Platform: NC8410 thru NC8422: An internal ladder shall
extend upward from the plenum walkway to an elevated fiberglass bar grating platform
convenient for the care and maintenance of the tower's mechanical equipment. The platform
shall be surrounded by an OSHA compliant guardrail system welded into subassemblies for
ease of installation.
The collection basin shall be welded 301L stainless steel construction. Only low-carbon
stainless steel alloys will be accepted in order to minimize the risk of intergranular corrosion in
the weld zones. The basin shall include the number and type of suction connections required to
accommodate the outflow piping system shown on the plans. Suction connections shall be
equipped with stainless steel debris screens. A factory-installed, float-operated, mechanical
make-up valve shall be included. An overflow and drain connection shall be provided in each
cell of the cooling tower. The basin floor shall slope toward the drain to allow complete flush out
of debris and silt that may accumulate. Towers of more than one cell shall include a method for
flow and equalization between cells. The basin shall be accessible and maintainable while water
is circulating.
Provide a system of electric immersion heaters and controls for each cell of the tower to prevent
freezing of water in the collection basin during periods of shutdown. The system shall consist of
one or more stainless steel electric immersion heaters installed in threaded couplings provided
in the side of the basin. A NEMA 4 control panel and associated temperature probe shall
include
Provide a water level control system including a NEMA 4X control panel, water level probes and
probe stilling chamber. The control system shall monitor the water level in the cold-water basin
to determine level events used for cold-water make-up, high and low alarms or pump shut
down. The control panel shall use electromechanical relays providing power for the make-up
solenoid and electrical contacts for alarm and pump shutdown control circuits. Probes shall be
contained in a vertical stilling chamber to stabilize the water in the cold-water basin. Probes
shall have replaceable stainless steel tips and level height shall be field adjustable. The water
distribution system shall be equipped with a method to operate under variable flow conditions
while maintaining a uniform air-side pressure drop through the fill to maximize cooling efficiency
and minimize the risk of ice and scale formation in the fill. System must accommodate flow
rates down to % of design flow.
A hole and bolt circle shall be provided in the depressed section of the basin for equalizer piping
between cells. A full-face, .25" thick, 50 durometer gasket shall be provided at each equalizer
location.
The cold water basin shall be equipped with PVC sweeper piping with plastic nozzles. The
piping shall be factory installed under the fill and designed to force all dirt and debris to the
depressed section of the collection basin. NC8401-NC8414 only.
The cold-water basin shall be equipped with basin inlet covers to help shield basin from debris
and sunlight exposure.
EXECUTION
3.1 EXAMINATION
Examine cooling towers before installation. Reject cooling towers that are damaged.
Before cooling tower installation, examine roughing-in for tower support, anchor-bolt sizes and
locations, piping, controls, and electrical connections to verify actual locations, sizes, and other
conditions affecting cooling tower performance, maintenance, and operation.
Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
Install anchor bolts to elevations required for proper attachment to supported equipment.
Piping installation requirements are specified in other Sections. Drawings indicate general
arrangement of piping, fittings, and specialties.
Where installing piping adjacent to cooling towers, allow space for service and maintenance.
Install flexible pipe connectors at pipe connections of cooling towers mounted on vibration
isolators.
Install drain piping with valve at cooling tower drain connections and at low points in piping.
Connect cooling tower overflows and drains, and piping drains, to sanitary sewage system.
Makeup-Water Piping:
1. Comply with applicable requirements in Section 232213 "Steam and Condensate Heating
Piping" and Section 232216 "Steam and Condensate Piping Specialties."
2. Connect steam supply connection with shutoff valve, strainer, control valve, pressure
gage, and flow meter.
3. Connect to condensate connection with shutoff valve, strainer, and an appropriate steam
trap assembly.
4. Make connections with a flange or union.
Connect field electrical power source to each separate electrical device requiring field electrical
power. Coordinate termination point and connection type with Installer.
Comply with requirements in Section 260519 "Low-Voltage Electrical Power Conductors and
Cables" for wiring connections.
Comply with requirements in Section 260526 "Grounding and Bonding for Electrical Systems" for
grounding connections.
Install nameplate for each electrical connection indicating electrical equipment designation and
circuit number feeding connection. Nameplate shall be laminated phenolic layers of black with
engraved white letters at least 1/2 inch (13 mm) high. Locate nameplate where easily visible.
3.5 CONTROLS CONNECTIONS
Connect control wiring between cooling towers and other equipment to interlock operation as
required to achieve a complete and functioning system.
Connect control wiring between cooling tower control interface and control system for HVAC for
remote monitoring and control of cooling towers. Comply with requirements in Section 25 0000
"Integrated Automation."
Install label at each termination indicating control equipment designation serving cooling tower
and the I/O point designation for each control connection. Comply with requirements in
Section 260553 "Identification for Electrical Systems" for labeling and identifying products and
installations.
Include provisions for cooling tower future field-performance testing complying with
ASME PTC 23 and CTI ATC 105.
Include provisions in field piping for future field-performance testing complying with
ASME PTC 23 and CTI ATC 105.
Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.
Testing Agency: Engage a qualified testing agency to perform tests and inspections.
Perform tests and inspections with the assistance of a factory-authorized service representative.
Tests and Inspections: Comply with ASME PTC 23 and CTI ATC 105.
Cooling towers will be considered defective if they do not pass tests and inspections.
Inspect field-assembled components, equipment installation, and piping; controls; and electrical
connections for proper assemblies, installations, and connections.
Start cooling tower and associated water pumps. Follow manufacturer's written starting
procedures.
Prepare a written startup report that records the results of tests and inspections.
3.9 ADJUSTING
3.10 DEMONSTRATION
PART 1 - GENERAL
A. Outdoor and/or indoor modular air handling units and components as scheduled and shown on
drawings.
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Sections, apply to this section.
1.3 REFERENCES
G. AHRI 260 – Sound Rating of Ducted Air Moving and Conditioning Equipment
J. ASHRAE 52.1/52.2 – Method of Testing General Ventilation Air Cleaning Devices for
Removal Efficiency by Particle Size
L. ASHRAE 90.1 – Energy Standard for Buildings Except Low-Rise Residential Buildings
M. ASTM-C 1338 – Standard Test Method for Determining Fungi Resistance of Insulation
Material and Facings.
B. The design indicated on the schedules and shown on the drawings is based upon the products
of the named manufacturer. Alternate equipment manufacturers are acceptable if equipment
meets scheduled performance requirements and dimensional requirements.
C. ARI Compliance:
1. Comply with ARI 203/110 and ARI 303/110 for testing and rating energy efficiencies for
RTUs.
2. Comply with ARI 270 for testing and rating sound performance for RTUs.
D. ASHRAE Compliance:
H. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
I. Comply with FM Global requirements for fans and blowers, motors and VFD's, and for
monitoring and diagnosis of vibration in rotating machinery.
1.5 COORDINATION
A. If equipment is supplied by a manufacturer other than the one named, coordinate with the
General Contractor and affected subcontractors to ensure the specified performance is
met. This coordination shall include (but is not limited to) the following:
B. The Mechanical Contractor shall be responsible for costs incurred by the General
Contractor, Subcontractors, and Consulting Engineers to accommodate units furnished by a
manufacturer other than manufacturer named as basis of design.
A. Delegated Design: Design outdoor units/supports to comply with project wind performance
requirements, including comprehensive engineering analysis by a qualified professional
engineer, using performance requirements and design criteria indicated.
1. Wind-Restraint Performance:
A. [LEED Submittals:
C. Coordination Drawings: Plans and other details, drawn to scale, on which the following items
are shown and coordinated with each other, using input from installers of the items involved:
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculations.
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of wind force and
locate and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
E. Furnish fan performance ratings and fan curves with specified operating point clearly plotted.
F. Furnish drawings indicating unit dimensions, required clearances, field connection locations,
wiring diagrams, shipping drawings, and curb drawings.
G. Furnish performance report showing unit level performance data including: fan(s), motor(s),
coil(s) and other functional components. Performance report shall also include unit casing
performance.
H. Furnish operation and maintenance data, including instructions for lubrication, filter
replacement, motor and drive replacement, and condensate pan cleaning; spare parts lists,
and wiring diagrams.
I. Adjust and report performance ratings for the proper altitude of operation.
L. Report coil ratings in accordance with AHRI-410 (capacities and pressure drops).
M. Report unweighted octave band AHU sound power for inlets and outlets rated in
accordance with AHRI Standard 260. Provide eight data points, the first for the octave
centered at 63 Hz, and the eighth centered at 8,000 Hz. Manufacturer shall not use sound
estimates based on bare fan data (AMCA ratings), nor use calculations like the substitution
method based on AHRI 260 tests of other AHU products. Provide data for inlets and outlets
as scheduled. Report unweighted casing radiated sound power over the same 8 octave
bands in accordance with ISO 9614 Parts 1&2 and ANSI S12.12.
N. Airflow measuring device performance shall be certified and rated in accordance with AMCA-
611. Report data in accordance with AMCA-611. Provide AMCA Certified Rating Seal for
Airflow Measurement Performance.
O. Report panel deflection at +/-8 w.g., stated in terms of ‘L/X’ where ‘L’ is the casing panel
length and ‘X’ is a constant provided by the AHU manufacturer.
P. Report casing leakage rate at +/-8” w .g., specified in terms of percentage of design
airflow.
R. Report product data for filter media, filter performance data, filter assembly, and filter frames.
S. Report electrical requirements for power supply wiring including wiring diagrams for interlock
and control wiring, clearly indicating factory-installed and field-installed wiring.
U. Operation and Maintenance Data: For units to include in emergency, operation, and
maintenance manuals.
A. Comply with ASHRAE 62, Section 5 (mold and corrosion resistant casings, filters upstream of
wetted surfaces, and drain pan design).
B. Comply with ASHRAE 62, Section 7 (practices to be followed during construction and startup).
Protect equipment from moisture by appropriate in-transit and on-site procedures.
D. Protect, pack, and secure loose-shipped items within the air-handling units. Include detailed
packing list of loose-shipped items, including illustrations and instructions for application.
E. Protect, pack and secure controls devices, motor control devices and other electronic
equipment. Do not store electronic equipment in wet or damp areas even when they are sealed
and secured.
F. Enclose and protect control panels, electronic, and variable frequency drives. Do not store
equipment in wet or damp areas even when they are sealed and secured.
G. Seal openings to protect against damage during shipping, handling and storage.
H. Wrap indoor units with a tight sealing membrane. Wrapping membrane shall cover entire AHU
during shipping and storage. Cover equipment, regardless of size or shape. Alternatively AHU
must be tarped for shipment and storage.
I. Wrap equipment, including electrical components, for protection against rain, snow, wind, dirt,
sun fading, road salt/chemicals, rust and corrosion. Keep equipment clean and dry.
J. Tarp outdoor units to protect against rain and road debris during shipping.
K. Clearly mark AHU sections with unit tag number, segment sequence number, and direction of
airflow. Securely affix safety-warning labels.
A. Provide one set of filters for balancing, and one additional set for final turnover to owner.
B. Provide one extra set of fan belts, in addition to the factory-installed set.
A. Do not operate units for any purpose, temporary or permanent, until ductwork is clean, filters
are in place, bearings lubricated, and fan has been test run under observation.
B. Comply with manufacturer’s start-up requirements to ensure safe and correct operation
and integrity of warranty.
PART 2 - PRODUCTS
A. Air-handling units are to be designed and built to meet the performance detailed in this submittal
and as called for on the drawings.
B. Units will be complete with fans, motors, motor controls, coils, dampers, access doors
and other components/options, as shown on product drawings, wiring diagrams, and as
described in performance specifications.
B. Unit casing will consist of a structural frame with insulated roof, wall, and floor panels, with
panels fabricated from minimum 16 gauge, G-90, galvanized steel. Construction shall be bolted
standing seam type.
D. Unit casing will be insulated with spray injected foam to achieve thermal resistance of minimum
of R13 hr-ft2-°F/BTU. Insulation application will meet the requirements of NFPA 90A.
E. Unit base shall be minimum 2.5" welded structural steel channel construction with full walk-on
G-90 galvanized steel floors in all sections. No paint is permitted.
F. Unit will conform to ASHRAE Standard 111 Class 6 for casing leakage no more than 1% of
design airflow at 1.25 times design static pressure up to a maximum of +8 inches w.g. in
positive pressure sections and -8 inches w.g. in negative pressure sections.
G. Wall panels and access doors will deflect no more than L/240 when subjected to 1.5 times
design static pressure up to a maximum of +8 inches w.g. in positive pressure sections and -8
inches w.g. in negative pressure sections. ‘L’ is the panel-span length and ‘L/240’ is the
deflection at panel midpoint.
H. Access sections shall be 24" minimum and shall have access doors on both sides.
I. Unit will have double wall, 2” insulated panels for walls, roof, and floor. Exterior skin will be
galvanized sheet steel as described above. Individual segments will have galvanized solid
sheet steel interior liner except for fan sections, which shall be perforated.
1. Panels with perforated liners will have 1” of minimum 3 lb/ft.3 fiberglass board insulation,
faced to prevent fiber erosion, and 1” of foam insulation. Exterior skin will be galvanized
sheet steel. Interior liner will be perforated galvanized. Minimum perforated panel
thermal resistance will be R11 hr-ft2-°F/BTU.
J. For outdoor units, roofs will be double-sloped with a longitudinal peak and a minimum pitch of
1/4” per foot.
K. Floor panels will be double wall construction, designed to provide at most L/240 deflection when
subjected to a 300 lb. load at mid-span.
L. Double wall access doors will be provided on sections as shown on product drawings.
1. Stainless steel hinges permit a 180 door swing.
2. Access door will be of the same material type as exterior/interior casing.
3. Access door latches will use a roller cam latching mechanism.
N. Drain pans will comply with the guidelines of ASHRAE 62, and are to be minimum 16 gauge,
Type 304 stainless steel.
1. Drain pans will be double sloped at least 1/8” per foot, and have no horizontal surfaces.
2. Drain connection material will be the same as drain pan.
3. Drain pans will drain to one point and to be insulated double bottom type.
4. Drain connections will be welded to drain pans
5. Drain pans will have at least 1” clearance between pan and coil supports.
2.4 FANS
1. Blank off Panels — Each Multiple Fan section to be provided with one fan blank-off panel
to enable manual isolation of fan for servicing.
2. Fan Options — The following options will be available for multiple fans:
a. Piezometer Ring: Airflow station will be factory installed in each fan inlet. Tubing
will be manifolded so that the measurement is representative of all fans in the
array. The device will have a measurement accuracy of ± 5%.
b. Backdraft Damper: Backdraft dampers will be available for automatic isolation of
individual fans.
A. Fan motor disconnects will be provided with unit, as shown in performance specifications.
B. Disconnect will be housed in a NEMA 3R enclosure, and will be mounted on the primary access
side of segment.
C. Disconnect will be suitable for use as an OSHA lockout/tagout disconnect when applied in
accordance with part IV, Department of Labor OSHA 29 CFR Part 1910, Control of Hazardous
Energy Source (lockout/tagout): Final Rule.
D. Disconnect handles can be padlocked in the “off” position with up to three padlocks. Switch
mechanism can be directly padlocked in the “off” position when door is open.
E. Disconnects will be provided with an integral ground lug.
1. 16A to 100A disconnects will have two (2) #14 ground wires.
2. 200A to 400A disconnects will have one (1) #6-250 ground wire.
A. Constant speed motor starters will be furnished (shipped loose) or provided (factory mounted
and wired to motor) with units, as shown in submittal documents.
B. For outdoor units, motor starters will be housed in a dedicated, weather resistant compartment.
1. Shipped loose starters and starters provided on units without single point power will be
housed in a NEMA 3R enclosure.
2. Weatherproof compartments will be provided on units with single point power.
B. Variable frequency drives will be furnished (shipped loose) or provided (factory mounted and
wired to motor) with units, as shown in submittal documents.
C. For outdoor units, VFDs will be housed in a dedicated, weather resistant compartment.
1. Shipped loose VFDs and VFDs provided on units without single point power will be
housed in a NEMA 3R enclosure.
2. Weatherproof compartments will be provided on units with single point power.
D. VFDs furnished or provided with units will be programmed and started by a drive factory
authorized and trained technician.
B. Cooling coil segments will have a full-width IAQ drain pan that extends at least 6” downstream
of the last coil in the section.
C. Coils will be removable from the side of unit, via removable AHU panels. No more than one
panel must be removed to remove a coil.
D. Coils will have frames constructed of galvanized steel. Casing channels will be free-draining and
do not block fin area.
E. Cooling coils with finned height greater than 48” will have an intermediate drain pan with
downspout to drain condensate to main drain pan. Intermediate drain pan material will match
coil frame material.
F. Coil segment door clearances will allow for at least 2-inches of field installed piping insulation.
G. Coil bulkheads and blank-offs will prevent air from bypassing coils.
H. Coil segment casing to accommodate full-face or reduced-face coils will be provided. Provide
face and bypass coil segments with factory installed bypass damper
J. Water and glycol coils will have a 1/4" FPT plugged vent or drain tap on each connection that is
accessible from outside the unit.
K. Spool shaped coil grommets will be provided to insulate and seal coil penetrations.
2.10 FILTERS
B. Filter segments will be provided, as shown on product drawings. Filter tracks/frames will be an
integral part of the unit.
C. Filter types, nominal sizes, efficiencies, and performance characteristics will be as shown in
drawing schedules.
D. Filter access will be provided via access doors on filter segments or adjacent segments as
required by filter loading scheme. See product drawings for details.
E. Performance of installed HEPA filtration systems is certified via a DOP test and classified as UL
Class 1 when tested in accordance with UL Standard 586.
F. Flush mounted, factory installed differential pressure gauge on the drive side of unit to measure
pressure drop across filters will be provided
2.11 DAMPERS
A. Refer to Section 23 3314 if smoke dampers are required, Section 23 3314 if isolation
dampers are required, or Division 25 if control dampers are required.
C. Dampers will have airfoil blades with extruded vinyl edge seals and flexible metal compressible
jamb seals.
D. Dampers will have a maximum leakage rate of 4 CFM/square foot at 1" w.g. and comply with
ASHRAE 90.1.
E. Maximum damper torque requirement will be 7 in. lbs./ft2.
B. Airflow monitoring stations will bear the AMCA Certified Ratings Seal for Airflow
Measurement Performance.
C. Airflow monitoring station dampers will comply with leakage rates per ASHRAE 90.1.
D. Airflow monitoring stations will be accurate within 5% of actual airflow between 350 FPM
and 4000 FPM free area velocity.
E. Outdoor air intake openings with air flow monitoring stations will have rain louver.
2.13 DIFFUSERS
B. Perforated steel diffuser plates will be installed between fans and downstream
components when required to ensure proper velocity profiles across downstream
components.
A. Roof curbs for roof mounted units will be furnished, as shown on product drawings.
B. Roof curbs will be galvanized steel and support the perimeter of units, including pipe chases.
D. Roof curbs will be shipped loose for installation prior to unit installation.
2.15 APPURTENANCES
A. Safety grates capable of supporting a 300 lb. center load will be provided over bottom openings,
as scheduled.
B. Formed [Welded structural] steel base rails suitable for rigging and lifting will be provided, as
shown on product drawings.
2.16 FINISHES
B. Unpainted air-handling units constructed of galvanized steel will pass the ASTM B-117 test for
220-hour salt spray solution (5%) without any sign of red rust.
2.17 HUMIDIFIERS
B. Unit wiring with voltage greater than 30VAC will be hipot tested prior to shipping.
A. Provide all required framing, safing, supports, etc., for all components to be installed in
the unit, including (but not limited to): Fans, dampers. coils, piping, humidifier grids,
attenuators, heat exchangers, etc.
B. Stainless steel coil raising structures inside unit if required for proper cooling coil drain
trapping and/or steam condensate trapping/drainage.
C. Humidifier control valves, strainers and valves shall be outside the airstream.
D. Do not locate humidifiers upstream of fan sections. The preferred location for humidifier
sections are downstream of the fans.
E. Humidifiers shall be located 18" downstream of heating coils and a minimum of 3'
upstream of cooling coils.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install equipment per industry standards, applicable codes, and manufacturer’s instructions.
B. Do not use AHU's for temporary heating, cooling or ventilation prior to complete inspection and
startup performed per this specification.
C. Install AHU's on a concrete pad, roof curb, or structural steel base, as shown on drawings.
D. Install AHU's with manufacturer’s recommended clearances for access, coil pull, and fan
removal.
E. Provide one complete set of filters for testing, balancing, and commissioning. Provide second
complete set of filters at time of transfer to owner.
F. Install AHU's plumb and level. Connect piping and ductwork according to manufacturer’s
instructions.
I. Install insulation on all staggered coil piping connections, both internal and external to the unit.
A. Store per AHU manufacturer’s written recommendations. Store AHUs indoors in a warm, clean,
dry place where units will be protected from weather, construction traffic, dirt, dust, water and
moisture. If units will be stored for more than 6 months, follow manufacturer’s instruction for
long-term storage.
C. Training shall include startup and shutdown procedures as well as regular operation and
maintenance requirements.
D. If AHU is provided with a factory-mounted variable frequency drive (VFD), hire the VFD
manufacturer’s factory-trained and factory-employed service technician to inspect, test, adjust,
program and start the VFD. Ensure that critical resonant frequencies are programmed as ‘skip
frequencies’ in the VFD controller.
E. Submit a startup report summarizing any problems found and remedies performed.
A. Leakage: Pressurize casing to maximum operating static pressure (up to +/-8” w.g.) and
measure leakage. If leakage exceeds 1% of design airflow, seal leakage points with a
permanent solution. Repeat test. If the AHU still does not pass, contact the manufacturer to
seal unit.
B. Submit a field test report with testing data recorded. Include description of corrective actions
taken.
3.7 CLEANING
A. Clean unit interior prior to operating. Remove tools, debris, dust and dirt.
3.8 DOCUMENTATION
A. Provide Installation Instruction Manual, & Startup checklist in the supply fan section of each
unit.
B. Provide six copies of Spare Parts Manual for owner’s project system manual.
PART 1 - GENERAL
A. Indoor and outdoor air handling units and components as scheduled and shown on drawings.
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Sections, apply to this section.
1.3 REFERENCES
G. AHRI 260 – Sound Rating of Ducted Air Moving and Conditioning Equipment
J. ASHRAE 52.1/52.2 – Method of Testing General Ventilation Air Cleaning Devices for
Removal Efficiency by Particle Size
L. ASHRAE 90.1 – Energy Standard for Buildings Except Low-Rise Residential Buildings
M. ASTM-C 1338 – Standard Test Method for Determining Fungi Resistance of Insulation
Material and Facings.
B. The design indicated on the schedules and shown on the drawings is based upon the products
of the named manufacturer. Alternate equipment manufacturers are acceptable if equipment
meets scheduled performance requirements and dimensional requirements.
C. ARI Compliance:
1. Comply with ARI 203/110 and ARI 303/110 for testing and rating energy efficiencies for
RTUs.
2. Comply with ARI 270 for testing and rating sound performance for RTUs.
D. ASHRAE Compliance:
H. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
I. Comply with FM Global requirements for fans and blowers, motors and VFD's, and for
monitoring and diagnosis of vibration in rotating machinery.
1.5 COORDINATION
A. If equipment is supplied by a manufacturer other than the one named, coordinate with the
General Contractor and affected subcontractors to ensure the specified performance is
met. This coordination shall include (but is not limited to) the following:
B. The Mechanical Contractor shall be responsible for costs incurred by the General
Contractor, Subcontractors, and Consulting Engineers to accommodate units furnished by a
manufacturer other than manufacturer named as basis of design.
A. Delegated Design: Design RTU supports to comply with project wind performance
requirements, including comprehensive engineering analysis by a qualified professional
engineer, using performance requirements and design criteria indicated.
1. Wind-Restraint Performance:
A. [LEED Submittals:
1. Design Calculations: Calculate requirements for selecting vibration isolators and for
designing vibration isolation bases.
2. Detail mounting, securing, and flashing of roof curb to roof structure. Indicate
coordinating requirements with roof membrane system.
3. Wind-Restraint Details: Detail fabrication and attachment of wind restraints and snubbers.
Show anchorage details and indicate quantity, diameter, and depth of penetration of
anchors.
C. Coordination Drawings: Plans and other details, drawn to scale, on which the following items
are shown and coordinated with each other, using input from installers of the items involved:
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculations.
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of wind force and
locate and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
E. Furnish fan performance ratings and fan curves with specified operating point clearly plotted.
F. Furnish drawings indicating unit dimensions, required clearances, field connection locations,
wiring diagrams, shipping drawings, and curb drawings.
G. Furnish performance report showing unit level performance data including: fan(s), motor(s),
coil(s) and other functional components. Performance report shall also include unit casing
performance.
H. Furnish operation and maintenance data, including instructions for lubrication, filter
replacement, motor and drive replacement, and condensate pan cleaning; spare parts lists,
and wiring diagrams.
I. Adjust and report performance ratings for the proper altitude of operation.
L. Report coil ratings in accordance with AHRI-410 (capacities and pressure drops).
M. Report unweighted octave band AHU sound power for inlets and outlets rated in
accordance with AHRI Standard 260. Provide eight data points, the first for the octave
centered at 63 Hz, and the eighth centered at 8,000 Hz. Manufacturer shall not use sound
estimates based on bare fan data (AMCA ratings), nor use calculations like the substitution
method based on AHRI 260 tests of other AHU products. Provide data for inlets and outlets
as scheduled. Report unweighted casing radiated sound power over the same 8 octave
bands in accordance with ISO 9614 Parts 1&2 and ANSI S12.12.
N. Airflow measuring device performance shall be certified and rated in accordance with AMCA-
611. Report data in accordance with AMCA-611. Provide AMCA Certified Rating Seal for
Airflow Measurement Performance.
O. Report panel deflection at +/-10” [12”] w.g., stated in terms of ‘L/X’ where ‘L’ is the casing
panel length and ‘X’ is a constant provided by the AHU manufacturer.
P. Report casing leakage rate at +/-10” [12”] w.g., specified in terms of percentage of
design airflow.
R. Report product data for filter media, filter performance data, filter assembly, and filter frames.
S. Report electrical requirements for power supply wiring including wiring diagrams for interlock
and control wiring, clearly indicating factory-installed and field-installed wiring.
U. Operation and Maintenance Data: For RTUs to include in emergency, operation, and
maintenance manuals.
V. List of items for project turnover to the University, when they received same, and University
sign-off.
A. Comply with ASHRAE 62, Section 5 (mold and corrosion resistant casings, filters upstream of
wetted surfaces, and drain pan design).
B. Comply with ASHRAE 62, Section 7 (practices to be followed during construction and startup).
Protect equipment from moisture by appropriate in-transit and on-site procedures.
D. Protect, pack, and secure loose-shipped items within the air-handling units. Include detailed
packing list of loose-shipped items, including illustrations and instructions for application.
E. Protect, pack and secure controls devices, motor control devices and other electronic
equipment. Do not store electronic equipment in wet or damp areas even when they are sealed
and secured.
F. Enclose and protect control panels, electronic or pneumatic devices, and variable
frequency drives. Do not store equipment in wet or damp areas even when they are sealed
and secured.
G. Seal openings to protect against damage during shipping, handling and storage.
H. Wrap indoor units with a tight sealing membrane. Wrapping membrane shall cover entire AHU
during shipping and storage. Cover equipment, regardless of size or shape. Alternatively AHU
must be tarped for shipment and storage.
I. Wrap equipment, including electrical components, for protection against rain, snow, wind, dirt,
sun fading, road salt/chemicals, rust and corrosion. Keep equipment clean and dry.
J. Tarp outdoor units to protect against rain and road debris during shipping.
K. Clearly mark AHU sections with unit tag number, segment sequence number, and direction of
airflow. Securely affix safety-warning labels.
A. Provide one set of filters for balancing, and one additional set for final turnover to owner.
1.11 WARRANTY
A. Provide warranty for 5 ye a r s from date of turnover to the Owner at substantial completion,
see Division 01. Warranty shall cover manufacturer defects. Warranty work shall be
performed by manufacturer’s factory-trained and factory- employed technician.
C. Parts associated with routine maintenance, such as belts and air filters shall be excluded.
A. Do not operate units for any purpose, temporary or permanent, until ductwork is clean, filters
are in place, bearings lubricated, and fan has been test run under observation.
B. Comply with manufacturer’s start-up requirements to ensure safe and correct operation
and integrity of warranty.
PART 2 - PRODUCTS
A. Coils shall be arranged so that space between the coils is a minimum of 24".
B. Fan compartments shall be arranged such that the space between the fan inlets and the
housing is a minimum of one fan diameter.
C. Arrangement of components shall be such that coil face velocity distribution shall not vary by
more than 20% from the average coil velocity.
D. Coil assemblies shall have provisions to facilitate total or partial removal from coil bank.
Removal panels shall be provided on both sides of the unit.
F. Outdoor and return air mixing sections shall be arranged to minimize stratification.
1. Leakage shall be no more than 1/2% of rated unit CFM at +/- 10” static pressure.
Manufacturer shall perform a factory leakage test on at least one unit. Customer shall
select which unit to test. Perform test at 10” static pressure. If unit fails at the factory,
manufacturer shall seal and retest unit until it meets specified performance.
2. Deflection shall be no more than L/240 of panel length at +/- 10” static pressure.
Manufacturer shall perform a factory deflection test on at least one unit. Customer shall
select which unit to test. Measure deflection on the largest wall panel. Perform test at
10” static pressure. If unit fails, manufacturer shall add structural support required to
achieve specified performance.
3. Thermal performance:
a. Unit wall shall not sweat with interior air temperature of XX°F and exterior
air at XX/XX db/wb
b. R-value of wall shall be R-13[R19] [R25] at the center of panel.
B. 4” foam injected thermal break (thermal breaks in cooling coil sections and downstream
from same) in walls: Construct walls with interior and exterior sheet metal surfaces, welded
internal post structure, and 4’ of injected foam insulation. Foam board or fiberglass insulation is
not acceptable.
1. Interior Liner:
a. Exterior Fasteners
1) For outdoor units, units with stainless steel or aluminum exterior walls use
self-tapping series 400 stainless steel sheet metal screws to fasten exterior
sheet metal walls to post frame structure on 18” centers
2) For indoor units use self-tapping rust inhibited sheet metal screws to fasten
exterior sheet metal walls to post frame structure on 18” centers.
b. Interior Fasteners
1) For Galvanized interior liner: use self-tapping rust inhibited sheet metal
screws to fasten interior and exterior sheet metal walls to post frame
structure on 27” centers.
2) For Stainless steel or aluminum interior liner: use self-tapping series 400
stainless steel sheet metal screws to fasten exterior sheet metal walls to
post frame structure on 27” centers
6. Casing Joints: Joints shall be mechanically fastened. Fasteners shall not extend from the
outside to the inside of the unit. Use angle to fasten and seal walls at corners, floors, and
roofs.
7. Sealing: Seal joints with polyurethane water resistant sealant, no additional coating.
8. Mill finish for galvanized steel casings: Immediately after cleaning and pre-
treating, apply manufacturer's standard two-coat, baked-on enamel finish,
consisting of polyurethane prime coat and polyester thermosetting topcoat.
Coating shall pass ASTM B-117 1,000 hour salt spray test. Color shall be
manufacturer’s standard champagne.
9. Factory applied high build (3 to 5 mils) alkyd enamel. Coating shall pass ASTM B-
117 500 hour salt spray test. Color shall be manufacturer’s standard champagne,
or Architect shall specify color.
10. Factory applied single coat industrial 2-part epoxy shall be 3 – 4 mils and pass
ASTM B- 117 3,500 hours salt spray test. Color shall be manufacturer’s
standard champagne, or Architect shall specify color.
11. Factory applied double coat industrial 2-part epoxy shall be 6 – 8 mils and pass
ASTM B- 117 3,500 hours salt spray test. Color shall be manufacturer’s
standard champagne, or Architect shall specify color.
12. Airstream Surfaces: Surfaces in contact with the airstream shall comply with
requirements in ASHRAE 62.1-2013.
C. Roofs
1. Construction of the roof shall be identical to the wall construction specified.
2. Unit roof for outdoor units are to be sloped a minimum pitch of ¼” per foot.
3. The roof shall overhang all side and end panels to prevent precipitation drainage
from streaming down the unit wall panels. Gutter systems are not acceptable.
4. Roofs less than 12’ wide shall be sloped to the non-door side of the unit; roofs 12’ wide
and wider shall be peaked in the center and sloped to both sides of the unit.
5. Roof construction shall accommodate a minimum snow-load of 30 lb/ft2.
6. Roof shall be designed to hold a 300lb load for service and maintenance.
7. The roofing system shall consist of a white (or custom color) 100% acrylic elastomeric
coating with "Mildewcide". Coating shall be a minimum 20 mils thick. Coating shall meet
the following requirements:
8. Outdoor roofs supplied with non-sloped roofs or standing seam roof systems are
not acceptable.
9. For all outdoor roof duct connections provide a minimum 1.5” duct flange.
1. Panel and Door Fabrication: Formed and reinforced, double-wall, 4-inch insulated
panels of same material type and thickness as unit casing.
2. Inspection and Access Panels:
a. Fasteners: Attached to unit casing with tek screws with EPDM washers on
maximum 9-inch centers.
b. Gasket: 3/4” wide x 1/8” thick PVC gasket applied around entire perimeters of
panel frames [and the access opening].
c. Construction: Factory shall provide double sided tape where liner is attached to
internal supports.
3. Access Doors:
a. Frames: Type 6063-T6 aluminum extrusion, [with thermal break for "no
through metal" construction], welded at the corners and attached to the
unit casing with [plated, stainless steel] hardware.
b. Hinges: A full height stainless-steel piano hinge with minimum two roller cam
latches per door, operable from inside and outside. Rotating knife-edge or “paw”
latches are not acceptable. [Provide galvanized, Z-type safety latch for all
outward opening access doors opening with unit pressure.]
c. Handles: Glass fiber reinforced, UV rated, padlockable, nylon polyamide as
manufactured by Allegis Corporation.
d. Gasket: EPDM-sponge, applied around entire perimeters of panel frames. [Provide
one set of spare door gaskets for each access door.]
e. Viewports: Provide [8”x8”, 12”x12”], [single pane, thermal pane] viewing
window centered in each access door with wire-reinforced safety glass.
f. Test Ports: Ventlok No. 699 instrument test holes installed in door locations as
required to measure pressure drops across unit.
g. Rain Lip: Provide rain lip of same material type as unit casing attached with tek
screws above all access doors.
h. Interlock Switch: Provide Nema 3R, plunger type interlock switch mounted on
doors as noted on submittal drawing.
F. Service Vestibule (recommended on outdoor units with at least six (6) ft. of interior clearance):
Air handling unit(s) shall be provided with a service vestibule equivalent to the unit casing,
having a minimum thermal conductivity R of 12 /hr-ft2-°F/BTU.
1. Service vestibule shall be a minimum six (6) ft. wide by full height and length of the unit.
2. Service vestibule floor construction shall be the same as the unit floor.
3. Selected access doors are provided as indicated in door section of this specification.
4. Selected lighting and outlets provided as indicated in the electrical section of this
specification (if selected). Lights shall provide a minimum of 10 foot-candles of
illumination per OSHA 1926.56(a) standards for mechanical equipment rooms.
5. Vestibule shall be provided with [208/240V 1-3Phase, 5KW or 480V 3Phase, 5KW]
electric heater with integral thermostat set to maintain a minimum of 50 deg F. (if
selected).
6. Vestibule shall be provided with hot water unit heater with wall mounted
thermostat set to maintain a minimum of 50 deg F. (if selected).
7. Provide ventilation for removing heat of motor starters or other devices located within the
vestibule.
G. Pipe-Chase:
1. Air handling unit(s) shall be provided with an external pipe-chase consisting of casing
equivalent to the unit casing, having a minimum thermal conductivity R of 12 hr-ft2-
°F/BTU.
H. Floors:
1. Floor shall be 10 ga. hot rolled steel [stitch welded, caulked and sealed] [full seam
welded] to the base.
2. Floor shall be thermally isolated from welded base frame members (perimeter and
internal supports). Construction without thermally isolated floor and walls shall not be
acceptable.
1) Floor shall have upturned lip with fully welded seams, and be capable of
holding 2-inch of water. Penetrations through the floor shall not exist.
Construction allowing screws or bolts to penetrate floor shall not be
allowed. All floor openings shall have a fully welded 2” upturned lip.
2) Each section shall be equipped with drain connection to facilitate
washdown and maintenance. Drain connection shall be extended through
the base and have a removable cap installed.
3) All internal equipment shall be provided with a minimum 2-inch high base to
raise equipment and components off the unit floor for housekeeping.
b. Floor Paint:
c. Subfloors:
d. Floor Drains:
e. Floor Openings:
I. Baserails:
1. [Type ASTM A36 welded structural steel c-channel, [6-inch, 8-inch, 10-inch, 12-
inch] height, with cross supports spaced at regular intervals and removable
lifting lugs. Factory shall provide curb angle welded to the base for outdoor curb
mounted units.] [Type 6061 T6 welded structural aluminum, [6-inch, 8-inch, 10-
inch, 12-inch] height, with cross supports spaced at regular intervals and
removable lifting lugs.]
2. [Factory applied high build (3 to 5 mils) alkyd enamel. Coating shall pass ASTM B-
117 500 hour salt spray test. Color shall be manufacturer’s standard champagne or
as specified by Architect.]
3. [Factory applied single coat industrial 2-part epoxy shall be 3 – 4 mils and pass
ASTM B- 117 3,500 hours salt spray test. Color shall be manufacturer’s standard
champagne.] [Factory applied double coat industrial 2-part epoxy shall be 6 – 8
mils and pass ASTM B-117 3,500 hours salt spray test. Color shall be
manufacturer’s standard champagne.]
J. Fan Removal Beams: For any units with fans 4'-0" or higher, fan removal beams/devices shall
be included in unit.
A. Fan Arrays: Fan arrays shall consist of multiple direct-drive, arrangement 4, modular plenum
fans selected to provide the scheduled airflow at the scheduled total static pressure. Fans
shall be statically and dynamically balanced and designed for continuous operation at
maximum- rated fan speed and motor horsepower. Fans shall have a sharply rising pressure
characteristic extending through the operating range and continuing to rise beyond the peak
efficiency to ensure quiet and stable operation. Fans shall have a non-overloading design with
self-limiting horsepower characteristics and shall reach a peak in the normal selection area. All
fans shall be capable of operating over the minimum pressure class limits as specified in
AMCA’s Standard 2408-69.
C. Fan Options
1. Back-Draft Dampers: Each fan shall have an individual industrial grade low leak back-
draft damper. Frame shall be minimum 9" deep x 2" (229 x 51) flanged 12 (2.8)
gage galvanized steel channel. The blades shall be maximum 7" (178) wide, minimum
.080 (2) thick, 6063T5 extruded aluminum airfoil shaped with integral structural
reinforcing tube running full length of each blade. Damper blades shall be equipped
with silicone rubber seals mechanically locked into extruded blade slots. Adhesive
type seals are not acceptable. Adhesive type seals are not acceptable. Dampers shall
be equipped with vinyl jamb seals for low leakage application. Wind stop type seals
are not acceptable. Axles shall be minimum 3/4" (19) diameter with machined edge
to provide positive locking connection to blades. Full round axles are not
acceptable. Bearings shall be ball style pressed into frame. Linkage shall be
minimum 3/16" thick 3/4" (5 x 19) bar located on face of blade in airstream. Submittal
must include leakage, pressure drop, and maximum pressure data based on AMCA
Publication 500 testing.
2. Airflow Measuring: Each fan shall include an Airflow Measuring System (AFMS)
consisting of a piezometer ring mounted in the throat and a static pressure tap
mounted on the face of the inlet cone. [A differential pressure transducer [and an
analog display] shall be provided. Transducer shall have a field configurable 0-5
VDC or 0-10 VDC output, as well as a 4-20 mA output. Transducer shall have a
standard accuracy of ±1% FS.] AFMS shall not obstruct the airflow in any way and
shall have no effect on fan airflow performance, static pressure, or sound power levels.
2.5 MOTORS
A. All fan motors shall comply with NEMA and IEEE for temperature rating, service factor,
enclosure type, and efficiency requirements for motors specified in S ec t i on 23 0 513
"Motors."
A. For coils, refer to Section 23 8216 "Coils" and meet requirements below
1. Cooling coil maximum face velocities at maximum design airflow to be 350 fpm.
2. Provide cooling coil drain pans that are sufficient to contain coil condensate. Drain pan
shall be 16 ga. 304 Stainless steel [16 ga. G-90 Steel][316L Stainless Steel]
construction and ex- tend a minimum of 6 [12] [18] inches downstream of leaving face of
the coil to allow for condensate pan access and maintenance and meet requirements for
ASHRAE 62-2007. IAQ drain pan must slope in 3 directions and have single 304
Stainless steel 1.5 [2] inch connection for trapping at jobsite. Pans to be insulated double
wall.
3. Provide a minimum of 24 inches clearance between preheat and cooling coil banks and
pro- vide access door as shown on drawings.
4. Locate access doors near coils connections to provide minimum clearance of 2 inches for
field installed external piping insulation. Space shall allow a minimum of 90 degrees of
door swing.
5. Provide coil segment casing that meets or exceeds casing thermal performance of the
unit. Provide coil pull panel that are easily removable with no special tools. Coils shall be
re- movable from the side of the AHU. [For units with multiple stacked coils, provide
a G-90 steel [304 stainless steel] [316L Stainless Steel] stacking rack to allow
individual coils to be removed from side of AHU without disturbing any other
coils].
1. Provide filter segments with filters and frames as scheduled, and per Section 23 4114
"Filters."
C. Filter Gages:
2.8 DAMPERS
2.9 HUMIDIFIERS
A. If the required sound attenuation can be provided with integral fan housing attenuators, that is
acceptable, but if not, see below.
D. Interior partitions for rectangular silencers shall be not less than 26 gauge type #G-90
galvanized lock-former-quality perforated steel [304 stainless steel].
E. Filler material shall be inorganic glass fiber of a proper density to obtain the specified acoustic
performance and be packed under not less than 5% compression to eliminate voids due
to vibration and settling. Material shall be inert, vermin- and moisture-proof. [Filler material
shall be totally encapsulated and sealed with polymeric film of an appropriate
thickness. The encapsulated fill material shall be separated from the interior perforated
baffles by means of a noncombustible, erosion resistant, factory-installed, acoustic
stand-off. It shall not be acceptable to omit the acoustic stand-off and try to
compensate for its absence by means of corrugated baffles. (Hospital grade)]
F. Combustion ratings for the silencer acoustic fill shall be not greater than the following when
tested to ASTM E 84, NFPA Standard 255, or UL No. 723:
1. Flamespread Classification 20
2. Smoke Development Rating 20
B. Air blenders shall be of the rotary turbulating design consisting of radially extending blades.
Units shall be completely fixed devices, with no moving parts.
C. Static air mixers material shall be .080” or .125” thick aluminum [.095” 304 Stainless Steel].
Static air mixers shall be welded.
D. When multiple air blenders are used, they shall impart a counter rotational mixing of the
airstreams relative to each other. Simple mixing devices that do not produce expanding
discharge with counter rotational mixing will not be acceptable.
E. The air blenders shall be installed such that the blender shall be capable of providing a
minimum mixing effectiveness of 75% and ± 6 °F standard deviation when mixing 50% OA
with 50% RAS at 50 °F inlet temperature differential, and minimum mixing effectiveness of
80% and ± 5 °F standard deviation when mixing 30% OA with 70% RAS at 50 °F inlet
temperature differential.
A. Unit shall include a discharge air sound attenuation barrier. The passive sound attenuator
barrier shall be mounted on the downstream side of the supply fan and shall block line of sight
between the fan and the unit discharge opening. End panel sound attenuator shall be used
with top, bottom and side discharge openings
2.13 TESTING
A. [Perform factory test on a fully assembled unit with sections joined per manufacturer’s
installation instructions. Use of additional material (tape, sealant, caulk) shall be
minimized to only that required to simulate permanent jobsite conditions not
otherwise duplicable in the factory.]
C. [Factory Panel Deflection Test: The unit manufacturer shall provide a factory deflection
test on one unit. Casing panel deflection shall not exceed L/240 at +/- 10” w.g. (or as
required by AHRI 1350.) ‘L” is defined as the panel span length and ‘L/X’ is the
deflection at panel midpoint. Measurements shall be taken along the vertical seam of
the largest panel on the side.]
D. [Factory Leak Testing: The unit manufacturer shall provide a factory leak test on one
unit across the cabinet exterior walls. Casing leakage shall not exceed 0.5% of design
CFM at +/-10” w.g. (or as required by AHRI 1350.)] Sections that will be negative pressure
shall be tested under negative pressure and sections that will be positive pressure shall be
tested under positive pressure.
E. [Factory Sound Pressure Testing: The unit manufacturer shall test one unit for sound power
of AHU discharge and/or return openings using sound pressure measurements. All sound
pressure level measurements shall be made with a Type 1, Precision Sound Level Meter
that complies with both ANSI S1.4 & ANSI S1.4A. Sound meter’s octave band filters
shall conform to ANSI1.11 and be calibrated with handheld acoustical calibrator immediately
before each measurement session. Sound pressure readings shall be reviewed and converted
to sound power level by a professional engineer (acoustical engineer) using established ANSI
S12.34 and ISO 3744 methods. Testing per AHRI 260 or AMCA 300 will be considered
acceptable alternative methods. All other test methods must be approved by Engineer prior to
bid.]
F. [Factory Sound Power Testing: The unit manufacturer shall test one unit for sound
power of AHU discharge and/or return openings using sound intensity measurements.
All sound intensity level measurements shall be made with a Type 1-D analyzer meeting
the requirements of ANSI S1.11 for octave and 1/3 octave band filters. Analyzer shall
be periodically calibrated with reference sound source as specified in Section 5.8 of
ANSI S12.12. Sound Intensity measurements shall be performed by professional
engineer (acoustical engineer) using methods based on AHRI Standard 230. Testing
per AHRI 260 or AMCA 300 will be considered acceptable alternative methods. All
other test methods must be approved by Engineer prior to bid.]
G. Should a unit fail a test, the unit shall be treated with a permanent remedy at manufacturer’s
expense until test is successfully passed.
H. Unit(s) shall be tested at the extreme winter and summer ambient and airway conditions stated
in the design and performance data sheets.
A. Lights
1. Vapor Resistant Pendant: Factory shall provide vapor resistant pendant, marine type
light fixture with clear globe, metal guard, and [100W incandescent, 23W compact
fluorescent] bulb in segments and quantity as noted on drawings.
2. Fluorescent Twin Tube: Factory shall provide 48” fluorescent light fixture with
corrosion resistant housing, acrylic diffuser and twin 32W, T8 lamps and rated for
installation in damp environment.
3. Provide low temperature ballasts for fixtures in low temperature locations. Ballasts to be
electronic.
4. Factory shall wire all light fixtures to a common 120v switch located on the supply fan
segment.
5. Factory shall wire each light fixture to a separate 120v switch located near the
access door of the segment with the light fixture.
B. Outlets
1. Factory shall provide a 15A GFI duplex outlet mounted in a weatherproof enclosure in
segments and quantity as indicated on the drawings.
A. Louvers
1. Provide 16 ga., galvanized steel, stationary type, drainable blade louver with
downspouts in the jamb and mullions and 1/4” sq. galvanized mesh birdscreen.
Blades shall be housed inside a 16 ga. galvanized steel frame flush mounted to the
unit exterior. Louver to be pre-painted with baked enamel finish in a manufacturer’s
standard color as selected by the Architect.
B. Weather Hood
1. Provide weather hood of same material type and thickness as unit exterior skin with 1/4”
[1/2"] sq. galvanized mesh birdscreen.
A. Provide galvanized steel safety step assemblies with railing(s) from roof up to service
corridor entry door(s).
B. Provide gutters over unit exterior doors with downspouts extending to below doors.
C. For all exterior and interior doors, provide sleeves and seals.
D. Provide gasketed and capped test ports for all sections of the unit.
E. Provide all required framing, safing, supports, etc., for all components to be installed in
the unit, including (but not limited to): Fans, dampers. coils, piping, humidifier grids,
attenuators, heat exchangers, etc.
G. Moisture eliminators.
J. Humidifier control valves, strainers and valves shall be outside the airstream.
K. Do not locate humidifiers upstream of fan sections. The preferred location for humidifier
sections are downstream of the fans.
L. Humidifiers shall be located 18" downstream of heating coils and a minimum of 3'
upstream of cooling coils.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install equipment per industry standards, applicable codes, and manufacturer’s instructions.
B. Do not use AHUs for temporary heating, cooling or ventilation prior to complete inspection and
startup performed per this specification.
C. Install AHUs on a concrete pad, roof curb, or structural steel base, as shown on drawings.
D. Install AHUs with manufacturer’s recommended clearances for access, coil pull, and fan
removal.
E. Provide one complete set of filters for testing, balancing, and commissioning. Provide second
complete set of filters at time of transfer to owner.
F. Install AHU plumb and level. Connect piping and ductwork according to manufacturer’s
instructions.
I. Install insulation on all staggered coil piping connections, both internal and external to the unit.
A. Store per AHU manufacturer’s written recommendations. Store AHUs indoors in a warm, clean,
dry place where units will be protected from weather, construction traffic, dirt, dust, water and
moisture. If units will be stored for more than 6 months, follow manufacturer’s instruction for
long-term storage.
B. Provide a minimum of 16 hours (but more if required based on actual project conditions and
complexity, coordinate with University and HVAC Shop) of training for owner’s personnel by
manufacturer’s factory- trained and factory-employed service technician. Training shall
include AHU controls, motor starters, VFD's, and AHU's. Training shall be videoed and DVD's
of same given to the University.
C. Training shall include startup and shutdown procedures as well as regular operation and
maintenance requirements.
D. If AHU is provided with a factory-mounted variable frequency drive (VFD), hire the VFD
manufacturer’s factory-trained and factory-employed service technician to inspect, test, adjust,
program and start the VFD. Ensure that critical resonant frequencies are programmed as ‘skip
frequencies’ in the VFD controller.
E. Submit a startup report summarizing any problems found and remedies performed.
A. Leakage: Pressurize casing to maximum operating static pressure and measure leakage. If
leakage exceeds 1% of design airflow, seal leakage points with a permanent solution. Repeat
test. If the AHU still does not pass, contact the manufacturer to seal unit.
B. Submit a field test report with testing data recorded. Include description of corrective actions
taken.
3.7 CLEANING
A. Clean unit interior prior to operating. Remove tools, debris, dust and dirt.
3.8 DOCUMENTATION
A. Provide Installation Instruction Manual, & Startup checklist in the supply fan section of each
unit.
B. Provide six copies of Spare Parts Manual for owner’s project system manual.
PART 1 - GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
C. Warranty
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
B. ASHRAE Compliance:
1. Fabricate and label refrigeration system to comply with ASHRAE 15, "Safety Standard for
Refrigeration Systems."
2. Applicable requirements in ASHRAE 62.1-2010, Section 4 - "Outdoor Air Quality,"
Section 5 - "Systems and Equipment," Section 6 - " Procedures," and Section 7 -
"Construction and System Start-Up."
1.4 WARRANTY
A. One (1) year manufacturer's warranty, provide an additional four (4) year warranty on all
compressors (5 years total).
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Carrier
2.2 GENERAL
A. Description:
B. Refrigeration Components:
1. Refrigeration circuit components will include liquid--line front--seating shutoff valve with
sweat connections, vapor--line front--seating shutoff valve with sweat connections,
system charge of R--410A refrigerant, and compressor oil. Unit will be equipped with
high--pressure switch, low pressure switch and filter drier for R-410A refrigerant.
A. Unit Cabinet
1. Cabinet discharge and inlet grilles shall be attractively styled, high--impact polystyrene.
Cabinet shall be fully insulated for improved thermal and acoustic performance.
B. Fans
1. Fan shall be tangential direct--drive blower type with air intake at the top of the unit and
discharge at the bottom front. Automatic, motor--driven vertical air sweep shall be
provided standard.
2. Air sweep operation shall be user selectable. The vertical sweep may be adjusted (using
the remote control) and the horizontal air direction may be set manually.
C. Coil
1. Coil shall be copper tube with aluminum fins and galvanized steel tube sheets. Fins shall
be bonded to the tubes by mechanical expansion.
2. A drip pan under the coil shall have two drain connections for hose attachment, on either
the left or right--hand side, to remove condensate. Condensate pan shall have internal
trap.
D. Motors
1. Motors shall be open drip--proof, permanently lubricated ball bearing with inherent
overload protection. Fan motors shall be 3--speed.
E. Filters
F. Operating Characteristics
1. SAHU-1 when matched with the appropriate outdoor section, shall have a minimum listed
SEER (seasonal energy efficiency ratio) of 13 at ARI conditions.
2. All other operating characteristics as scheduled on the drawings.
A. Unit Cabinet
1. Unit cabinet shall be will be constructed of galvanized steel, bonderized, and coated with
a powder coat paint.
B. Fans
C. Compressor
2.5 CONTROLS
A. Controls shall consist of a microprocessor-based control system which shall control space
temperature, determine optimum speed, and run self diagnostics.
1. User interface with the unit shall be accomplished through a wired controller.
1. An automatic restart after power failure at the same operating conditions as at failure.
2. A timer function to provide a minimum 24--hour timer cycle for system Auto Start/Stop.
3. Temperature--sensing controls shall sense return air temperature.
4. Indoor coil freeze protection.
5. Automatic vertical air sweep control to provide on or off activation of air sweep louvers.
6. Dehumidification mode shall provide increased latent removal capability by modulating
system operation and set point temperature.
7. Fan--only operation to provide room air circulation when no cooling is required.
8. Diagnostics shall provide continuous checks of unit operation and warn of possible
malfunctions. Error messages shall be displayed at the unit.
9. Fan speed control shall be user--selectable: high, medium, low, or microprocessor
controlled automatic operation during all operating modes.
A. Provide Low Ambient Kit: Control shall regulate fan--motor cycles in response to saturated
condensing temperature of the unit. The control shall be capable of maintaining a condensing
temperature of 100 F ± 10 F with outdoor temperatures to –20 F
B. Only control wiring shall run between the indoor and outdoor units.
C. Indoor and Outdoor unit electrical power shall be single point connection.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Condenser shall be installed in strict accordance with the manufacturer's printed instructions.
E. Test, dehydrate, and charge the refrigeration system in strict accordance with the
manufacturer's instructions.
3.2 CONNECTIONS
1. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest
until no leaks exist.
2. Operational Test: After electrical circuitry has been energized, start units to confirm
proper motor rotation and unit operation.
3. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
3.4 DEMONSTRATION
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Specification Book Division 01 Specification Sections, apply to this Section.
B. Refer to project air handling unit specification section(s) for additional requirements and
conditions affecting coil selections for AHU's.
1.2 SUMMARY
A. Coordination Drawings for Duct Mounted Coils: Reflected ceiling plans, drawn to scale, on
which coil location and ceiling-mounted access panels are shown and coordinated with each
other.
A. Operation and Maintenance Data: For air coils to include in operation and maintenance
manuals.
COILS 23 8216 - 1
PART 2 - PRODUCTS
2.1 DESCRIPTION
A. Performance Ratings: Tested and rated according to AHRI 410 and ASHRAE 33.
D. Coils for air handling units shall be slide-out style, not face bolted, so they can be removed
without affecting the structural integrity of the unit. Coil connections to be Schedule 40 red
brass. Vent and drain connections shall be stainless steel pipe and extend to the exteriors of
the units.
G. Headers: Cast iron with cleaning plugs and drain and air vent tappings, seamless copper tube
with brazed joints, prime coated, or steel with brazed joints, prime coated.
H. Frames: Galvanized-steel channel frame, minimum 0.052 inch thick for slip-in or flanged
mounting, as best suited to actual field conditions (verify in field).
I. Maximum face velocity for cooling coils to be [Determined by AE for the project and listed
here and/or shown on drawing schedules.]
J. Maximum face velocity for heating and other non-cooling coils to be [Determined by AE for the
project and listed here and/or shown on drawing schedules.]
A. Tubes: ASTM B 743 seamless copper, minimum 0.024 inch thick, 5/8" O.D..
B. Fins: Aluminum, minimum 0.006 inch thick. Maximum allowable fin spacing shall be 10 fins per
inch.
D. Casings: Minimum 16 gage, Type 304 stainless steel, with stainless steel end supports top and
bottom.
2.4 COILS - HOT WATER PREHEAT AND REHEAT
A. Tubes: ASTM B 743 seamless copper, minimum 0.024 inch thick, 5/8" O.D..
B. Fins: Aluminum, minimum 0.006 inch thick. Maximum allowable fin spacing shall be 10 fins per
inch.
D. Casings: Minimum 16 gage, galvanized steel, with galvanized steel end supports top and
bottom.
A. Tubes: ASTM B 743 seamless copper, minimum 0.035 inch thick, 5/8" O.D..
B. Fins: Aluminum, continuous plate type, minimum 0.006 inch thick. Maximum allowable fin
spacing shall be 10 fins per inch.
D. Casings: Minimum 16 gage, Type 304 stainless steel, with stainless steel end supports top and
bottom.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine units, ducts, plenums, and casings to receive air coils for compliance with
requirements for installation tolerances and other conditions affecting coil performance.
B. Examine roughing-in for piping systems to verify actual locations of piping connections before
coil installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
B. Install coils in metal ducts and casings constructed according to SMACNA's "HVAC Duct
Construction Standards, Metal and Flexible." Provide new adjacent ductwork/transitions as
required, and re-insulate.
D. Clean coils using materials and methods recommended in writing by manufacturers, and clean
inside of casings and enclosures to remove dust and debris.
3.3 CONNECTIONS
A. Piping installation requirements are specified in other Sections. Drawings indicate general
arrangement of piping, fittings, and specialties.
C. Connect water piping with unions and shutoff valves to allow coils to be disconnected without
draining piping. Control valves are specified in Section 25 0000 "Integrated Automation" and
other piping specialties are specified in Section 23 2113 "Hydronic Piping" and Section 23 2116
"Hydronic Piping Specialties."
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 DEFINITION
A. Low Voltage: As defined in NFPA 70 for circuits and equipment operating at less than 50 V or
for remote-control, signaling power-limited circuits.
A. Product Data: Include rated capacities, operating characteristics, furnished specialties, and
accessories.
B. Shop Drawings: Detail fabrication and installation of humidifiers, grids, and coolers. Include
piping details, plans, elevations, sections, details of components, manifolds, and attachments to
other work.
A. Coordination Drawings: Detail humidifiers, grids, and drain coolers and adjacent equipment.
Show support locations, type of support, weight on each support, required clearances, and
other details, drawn to scale, on which the following items are shown and coordinated with each
other, based on input from installers of the items involved:
HUMIDIFIERS 23 8413 - 1
1.6 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For humidifiers, grids and coolers to include in operation and
maintenance manuals.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Comply with FM Global requirements for and pressure vessels, piping, and pressure relief
devices.
1.8 COORDINATION
A. Coordinate location and installation of humidifiers with manifolds in ducts and air-handling units
or occupied space. Revise locations and elevations to suit field conditions and to ensure proper
humidifier operation.
PART 2 - PRODUCTS
B. Fabricate and label steam generator to comply with ASME Boiler and Pressure Vessel Code:
Section VIII, Division 1.
C. For campus "Clean Steam" applications, generator, Clean Steam and condensate piping,
dispersion grids/manifolds, and condensate drain cooler all to be rated for use with provided RO
or DI water. Type 304 stainless steel is acceptable.
D. Fabrication requirements:
1. Tank and cover: Minimum 14-gauge, 304-stainless steel with Heli-arc welded seams.
2. Removable cover with ¼" screws (M6).
3. Easily accessible cleanout plate.
4. Steam outlet on top of tank configured to connect to hose, pipe, or flange connection.
5. Tubular copper heat exchanger and header with nickel coating.
E. Mounting:
F. Water requirements: The humidifier shall be capable of generating steam from tap, softened, or
DI/RO water.
G. Drain: An electric operated drain valve shall be mounted on the humidifier assembly to allow
tank to drain automatically at the end of a humidification season.
H. Steam trap and strainer: Humidifier shall include a float/thermostatic steam trap and steam
supply line strainer.
I. Humidifier Options
1. Fabrication options:
a. Tank and cover shall be 316 stainless steel with Heli-arc welded seams.
b. Factory insulation: Humidifier shall be covered with 1" thick (25 mm) rigid,
foil-faced fiberglass insulation. All surfaces except front face panel shall
have insulation.
c. Humidifier shall have a tubular 316 stainless steel heat exchanger and
header with no coating.
2. Mounting options:
a. Four support legs shall provide a minimum of 24" (610 mm) between
underside of humidifier and floor.
b. Two welded and painted steel wall brackets shall support humidifier on a
vertical surface (for smaller units).
a. Humidifier shall have a stainless steel manually operated drain valve and a
stainless steel float operated fill valve (standard on DI/RO models).
b. Humidifier shall have a stainless steel electric operated drain valve and a
stainless steel float operated fill valve with an electric solenoid to prevent
tank from filling when the tank drains automatically at the end of a
humidification season (requires Vapor-logic controller, which allows user to
define the number of hours of humidifier inactivity that must occur before
automatic end-of-season draining begins).
c. Low water float switch. Humidifier shall have a field-wired float switch to
provide water level indication for building management systems.
J. Humidifier Controls
1. Steam valve: Valve shall be a normally closed modulating type with modified linear
flow characteristics, stainless steel trim, and electric actuator.
2. Control cabinet: Control cabinet shall be shipped loose and shall be a UL/CSA
listed JIC enclosure. Control devices shall be mounted on a subpanel within the
cabinet. A wiring diagram shall be included in the control cabinet.
3. Vapor-logic®4 (or approved equal by alternate listed manufacturer) microprocessor
controller with the following features or functions:
g. USB port on the control board for software updates, data backups, and data
restoration
h. Up-time optimizer function to keep humidifier(s) operating through
conditions such as fill, drain, or run-time faults, as long as safety conditions
are met, minimizing production down-time
i. Real-time clock to allow time-stamped alarm/message tracking, and
scheduled events
j. Factory commissioning of humidifier and control board, including system
configuration as-ordered
k. Keypad/display operable within a temperature range of 32 to 158 F (0 to
70 C), and that provides backlighting for viewing in low light
l. Alarms, unit configuration, and usage timer values shall remain in
nonvolatile memory indefinitely during a power outage.
m. The capability to monitor, control, and/or adjust the following parameters:
1) Relative humidity (RH) set point, actual conditions in the space (from
humidity transmitter), RH offset
2) Dew point set point, actual conditions in the space (from dew point
transmitter), dew point offset
3) Relative humidity (RH) duct high limit set point (switch) and actual
conditions
4) Relative humidity (RH) duct high limit set point, actual conditions
(from transmitter), high limit span, and high limit offset
5) Total system demand in % of humidifier capacity
6) Total system output in lbs/hour (kg/h)
7) Drain/flush duration
8) End-of-season drain status (on standard water systems and if ordered
as a DI water option) and hours humidifier is idle before end of season
draining occurs
9) Window glass surface temperature (in % RH offset application using
sensor ordered as an option) with programmable offset
10) Air temperature or other auxiliary temperature monitoring with
programmable offset (using sensor ordered as an option)
11) System alarms and system messages, current and previous
12) Adjustable water skim duration
13) Programmable outputs for remote signaling of alarms and/or
messages, device activation (such as a fan), or for signaling tank
heating and/or steam production
14) System diagnostics that include:
6. Valve options:
7. Remote keypad: Provide a keypad with cable for remote mounting. Available cable
lengths: 10' (3 m), 25' (7.6 m), 50' (15 m), 100' (30 m) or 500' (152 m)
8. Keypad mounted on cabinet: The keypad shall be factory-mounted on the side of
the control cabinet.
9. Cabinet door interlock switch: The control cabinet shall have an interlock control
switch with manual override to remove control voltage when door is opened
10. Control cabinet door lock: Control cabinet shall have a lock with keys provided.
11. Freeze protection: A factory-mounted aquastat shall be mounted on the front of
humidifier to sense and maintain the evaporating chamber water temperature
above freezing. Set point adjustable from 40 to 180 F (4 to 82 C).
12. Control input accessory options:
C. The generators and all components subject to steam side shall be 316-L grade stainless steel,
they shall have submerged coils of 18 BWG (316) (304) stainless steel tubes expanded into a
(316) (304) stainless steel tube sheet with cast iron heads, they shall be insulated with not less
than 3" of fiberglass insulation, protected by not less than 20 ga. thick enameled steel jacket,
and they shall be mounted on a suitable I-Beam support skid, which shall be permanently
welded to the shell.
D. Steam Control Valve(s): Generators shall be furnished with an electric operated control valve to
modulate the in-coming steam to maintain the desired output of steam pressure +2 psi. Control
valves shall be suitable for 150 psi and control valve pilot shall monitor output steam pressure
and modulate the steam to maintain constant output pressure.
E. Steam Traps, Strainers, Relief Valves, Gages, and Other Specialties: Generators shall be
factory supplied with dual float and thermostatic traps, one for the coil and one for the drip
before the control valve, and the generators shall have incoming strainers. The generators shall
be furnished with ASME Code Section I pressure relief valve or valves with a capacity to relieve
the total BTU of output of the generators. Generators shall be furnished with a vessel steam
gauges, electronic level controllers, water columns with gauge glasses, and tandem blow off
valves.
F. All components for the generators shall be factory mounted, piped, and tested and the unit shall
be shipped from the factory as a complete unit ready for installation, and they be furnished with
steam separators.
G. Unfired steam generators shall be supplied with solid-state control module with LED backlit LCD
display and LED pilot lights to indicate on off, high pressure, low pressure, low water, and water
feed. Solid-state control module shall allow the owner to set pressure limits on display screen.
Solid-state control module shall have flashing red alarm light and alarm horn with built in alarm
silence relay. Solid-state control module shall be supplied with dry contact closure outputs to
indicate to building automation controls (BAC) the occurrence of power on, high pressure, low
pressure, low water, and water feed. The control module shall allow the BAC to turn the unfired
steam generator on or off through a remote relay suitable for 24 VAC, 1 amp. The control
module shall allow the BAC to remotely monitor the operating pressure. Control module shall
be supplied with an on-off switch and shall be mounted in a NEMA 1 panel. All solenoids and
limits shall be 24 VAC.
H. Furnish a factory installed stainless steel feed water slow opening solenoid valve sized to feed
the capacity of the boiler with a maximum pressure drop of 5 psi. Slow opening solenoid valve
shall be factory wired to the level controller. Furnish a factory installed check valve between the
solenoid valve and Unfired Steam Generator.
I. Other features:
a. Furnish and install a feed water pump with flexible connector, shut off valve,
and check valve. Feed water pump shall be factory wired to level controller
and furnished with fused starter in NEMA 1 enclosure.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine ducts, air-handling units, and conditions for compliance with requirements for
installation tolerances and other conditions affecting performance.
B. Examine roughing-in for piping systems to verify actual locations of piping connections before
humidifier installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install humidifiers, generators, and dispersion with required clearance for service and
maintenance.[ Maintain path, downstream from humidifiers, clear of obstructions as
required by ASHRAE 62.1.]
C. Install humidifier manifolds in metal ducts and casings constructed according to SMACNA's
"HVAC Duct Construction Standards, Metal and Flexible."
1. Construct drain pans with connection for drain; insulated and complying with
ASHRAE 62.1.
2. Connect to condensate trap and drainage piping.
3. Extend drain pan upstream and downstream from manifold a minimum distance
recommended by manufacturer but not less than required by ASHRAE 62.1.
F. Install drip leg upstream from steam trap a minimum of [12 inches (300 mm)] <Insert height>
tall for proper operation of trap.
G. Equipment Mounting:
3.3 CONNECTIONS
A. Piping installation requirements are specified in other Sections. Drawings indicate general
arrangement of piping, fittings, and specialties.
B. Install electrical devices and piping specialties furnished by manufacturer but not factory
mounted.
D. Ground equipment according to Section 26 0526 "Grounding and Bonding for Electrical
Systems."
1. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest
until no leaks exist.
2. Operational Test: After electrical circuitry has been energized, start units to confirm
proper motor rotation and unit operation.
3. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.