0% found this document useful (0 votes)
102 views1 page

Electrical Works Specifications Guide

The document provides specifications for electrical works on a construction project. It lists 7 general notes that electrical works must be done according to the Philippine Electrical Code, rules of the local power company, and relevant government agencies. It specifies that wiring in concrete must be in rigid PVC conduit. Pull boxes and junction boxes should be installed as needed. Wall outlets must be installed at standardized heights above the finished floor level based on their type. All electrical works must be done by skilled labor supervised by a licensed electrical engineer using new, certified materials. The completed installation must be reviewed to ensure proper operation.

Uploaded by

Randy Donato
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views1 page

Electrical Works Specifications Guide

The document provides specifications for electrical works on a construction project. It lists 7 general notes that electrical works must be done according to the Philippine Electrical Code, rules of the local power company, and relevant government agencies. It specifies that wiring in concrete must be in rigid PVC conduit. Pull boxes and junction boxes should be installed as needed. Wall outlets must be installed at standardized heights above the finished floor level based on their type. All electrical works must be done by skilled labor supervised by a licensed electrical engineer using new, certified materials. The completed installation must be reviewed to ensure proper operation.

Uploaded by

Randy Donato
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

LEGENDS AND SYMBOLS GENERAL NOTES AND SPECIFICATIONS

ELECTRICAL WORKS SHALL BE DONE IN ACCORDANCE TO THE FOLLOWING SPECIFICATIONS:


PPB POWER PANEL BOARD
1. ALL ELECTRICAL WORKS SHALL BE DONE IN ACCORDANCE TO THE LATEST EDITION OF THE
PPB POWER PANEL BOARD PHILIPPINE ELECTRICAL CODE, THE RULES AND REGULATIONS OF THE LOCAL POWER
COMPANY, AND GOVERNMENT AGENCIES HAVING JURISDICTION OVER THE PROJECT.

CIRCUIT HOMERUN 2. ALL WIRINGS RUNNING THRU OR EMBEDDED IN CONCRETE SHALL BE "PHILFEX",
"DURATEX", OR EQUIVALENT IN RIGID PVC CONDUIT.
AIRCON. OUTLET
3. UNLESS OTHERWISE INDICATED IN THE PLANS, THE MINIMUM SIZES OF WIRE AND

POST LAMP
4. WHENEVER REQUIRED AND NECESSARY, PULL BOXES AND JUNCTION BOXES OF
RECESSED TYPE LIGHTING FIXTURE PROPER SIZES SHALL BE INSTALLED AT CONVENIENT AND INCONSPICUOUS
LOCATIONS ALTHOUGH SUCH BOXES ARE NOT SHOWN ON THE PLANS NOR
MENTIONED IN THE SPECIFICATIONS.
2-GANG FLUSH MOUNTED C.O
2
5. ALL WALL OUTLETS SHALL BE INSTALLED AT THE FOLLOWING HEIGHTS ABOVE THE
Sab 2-POLE FLUSH MOUNTED SWITCH FINISHED FLOOR LEVEL:

Sa 1-POLE FLUSH MOUNTED SWITCH A.) WALL SWITCHES - 1.2m


B.) CONVENIENCE OUTLETS - 0.3m
CIRCUIT BREAKER C.) ACU OUTLETS - 1.9m
D.) FIRE ALARM BELLS - 2.6m
M KILOWATT-HOUR METER
6. ALL ELECTRICAL WORKS SHALL BE DONE IN STANDARD WORKMANSHIP MANNER WITH
SKILLED MANPOWER DULY SUPERVISED BY A PROFESSIONAL ELECTRICAL ENGINEER.

7. ALL MATERIALS SHOULD BE NEW AND BEAR APPROPRIATE SEAL OF DTI-BUREAU


PRODUCT STANDARDS FOR SPECIFIC PURPOSE.

8. ALL WORKS BE EXECUTED IN REAL AND WORKMAN LIKE MANNER. UPON COMPLETION
OF THE ELECTRICAL WORK, THE CONDUCTOR/INSTALLER SHALL REVIEW AND CHECK
THE ENTIRE INSTALLATION AND ENSURE THAT THE DEVICES ARE OPERATING PROPERLY.