SAFE WORK METHOD STATEMENT
Slab Concreting
PURPOSE
The purpose of this Work Procedure is to provide a controlled system of operation within
project specifications and applicable codes/standards.
SCOPE
This Work Procedure shall cover the Process of Slab concreting Work and identify the
responsible personnel, sequence of operations and EHS Guidelines.
REFERENCES
(Drawing, IS codes & legal Specification)
IS:3696- Code of practice for Scaffolding and ladders
IS:11057- Code of practice for industrial safety net
IS:2925- Code of practice for Safety helmet
IS:11016- General of safety requirement machine tools & their operator
IS:5914- Safety code for safety shoes
IS:7524- Safety Goggles
IS:4082- Recommendation on stacking & storage of construction material at site
IS:3521- Industrial safety belt & Harness
RESPONSIBILITIES
Project Manager/ Site Engineer to ensure that site supervisor / Foreman are familiar
with work instruction, quality control and safety requirements for the activity and
ensure that these requirements are put into practice.
The Foreman would report to Site Engineer and the Site Engineer would report to the
Project Manager and he would report to the Regional Planning Manager and the
Regional Manager.
The foreman and site engineer shall be responsible for all the works being carried out.
Site Supervisor is responsible for the continuous supervision of the work.
Safety Engineer is responsible to monitor the work and ensure the safety in the
proposed work.
MATERIALS
Scaffolding materials
Ladder
Safety net
Rebar steel
Electrical connections
Cement
PPEs
Safety Helmet
Safety Shoes
Gum boot
High Visibility Vest
Safety goggle
Ear plug
Face shield
Hand gloves
Full body harness
EQUIPMENTS
Bar bending Machine
Bar cutting machine
Chop saw cutting machine
Circular saw wood cutting machine
Drilling machine
Concrete vibrator
Concreting pump
Concrete mixer (TM)
METHODOLOGY FOR HOT WORK:
Man power entry:
Document verification by HR
Pre Medical Checkup
Safety Induction & Gate pass
Work related training
MOS, RA, Permit to work
TBT
Material Shifting: Material will be shifted from material yard to working location.
Shuttering material and reinforcement material will be shifted manually.
Scaffolding: Scaffolding SWMS has been submitted with reference number
“RBIPL/ITC/AMLF-08”. Scaffold shall be made as per approved design calculation.
The design drawing is enclosed with this document for the reference.
Shuttering: Shuttering SWMS has been submitted with reference number
“RBIPL/ITC/AMLF-04”. Scaffold will be performed as per approved design
calculation. The design drawing is enclosed with this document for the reference.
RCC: RCC SWMS has been submitted with reference number “RBIPL/ITC/AMLF-
06”.
De shuttering: De Shuttering SWMS has been submitted with reference number
“RBIPL/ITC/AMLF-04”. All safety precautions will be followed as per the same.
Housekeeping: Proper material stacking and housekeeping will be maintained. All
loose materials and debris will be cleared periodically from the site.
Working at height: Proper platform, access, fall prevention and fall protection will be
provided for working at height. Material movement and men movement procedure
will be ensured with safety.
Night work: Proper illumination will be provided for night work. Proper access and
area lighting also will be provided.
SAFETY ASPECTS
All workers shall be inducted.
All workers shall be trained in work at height safety.
Work permit and TBT shall be maintained on daily basis.
Material storage at height is only according to load bearing capacity of the scaffold.
Area shall be clear from Obstructions.
Proper access and platform shall be provided for work at height.
Electrical connection shall be through ELCB and MCB.
All equipment, connections and tools shall be inspected and color coded.
Proper supervision and safety coverage shall be provided.
Guard rail system and fall arresting system shall be followed.
Full body harness with 100% fall protection required.
Prepared By Reviewed By Approved By
Rajesh Singh
Mahesh P S