Lift Installation Project in APU Block D
Lift Installation Project in APU Block D
I would like to thank everyone who had contributed to the successful completion of this
assignment. I would like to express my gratitude to my lecturer IR. DR. DHAKSHYANI
A/P RATNADURAI for her invaluable advices and guidance that helped me to complete
this assignment as well as his explanation and simplifying the concepts needed for
assignment. Her clarifying and explaining to me with some examples that related to the
topic of my assignment make the ideas simple and understandble .
2
Abstract
The main objective of this project to renovate the Cafeteria at the APU New
Campus building to fit more than 250 people. Included food counters, tables, chairs,
power supply points, hand wash area, trash removal area and high-quality lighting as well
as safety features. The objectives of this project set to be SMART and explained in terms
of specific, measurable, attainable, relevant, and time based. Furthermore, this project
start on 3th of April 2017 and by 30th June 2017 should be handover to APU property
Services Department. In this project, there are 23 activities and all of these activities
executed based on the timeline given to complete the project.
Moreover, by implement new chairs and tables, increasing the space between the
tables, positioning food counters and cashiers, breaking the walls and adding oval and bar
table, the Cafeteria renovated to accommodate around 238 people. Therefore, the total
costing including the Workforce costing list, items costing list, martial costing list,
equipment costing list and miscellaneous was about RM531, 424.40 for the renovation of
Cafeteria in new campus. Lastly, the risk management plan that might be occurred on this
project identified and explain in details based on the quantitative and qualitative analysis
forms.
Table of Contents
Title
Page No.
Acknowledgment.................................................................................................................2
Abstract................................................................................................................................3
List of Tables.......................................................................................................................3
List of Figures......................................................................................................................4
1.0 Introduction of the Project........................................................................................5
2.1 Project Scope Statement...........................................................................................6
2.2 SMART Criteria.......................................................................................................6
2.2.1 Specific 7
2.2.2 Measurable........................................................................................................7
2.2.3 Attainable 7
2.2.4 Relevant 8
2.2.5 Time Based.......................................................................................................8
2.3 Project Deliverables.................................................................................................8
2.4 Project Assumptions.................................................................................................9
2.5 Project Constraints..................................................................................................9
3.1 Work Breakdown Structure....................................................................................10
3.2 Preparatory stage....................................................................................................11
3.3 Interior Design stage..............................................................................................11
3.4 Construction stage..................................................................................................12
3.5 Installation stage.....................................................................................................12
3.6 Completion stage....................................................................................................12
4.0 Network Diagram...................................................................................................13
5.0 Project Schedule.....................................................................................................15
6.0 Floor plan design....................................................................................................17
7.0 Cost Estimates........................................................................................................21
1
8.1 Project Organisation...............................................................................................28
8.2 Scheduling Team....................................................................................................30
8.3 Design & Construction Team.................................................................................30
8.4 Quantity and Safety Team......................................................................................30
9.1 Risk Management Plan...........................................................................................31
9.2 Risk Identification..................................................................................................31
9.3 Qualitative and Quantitative Risk Analysis...........................................................31
9.4 Risk Response Planning.........................................................................................34
10 Communication Plan.................................................................................................35
Conclusion.........................................................................................................................36
References..........................................................................................................................37
2
List of Tables
It has been decided by the APU Property Services Department that they
need to build a new lift in Block D for students, staffs and visitors to reduce the
waiting time while waiting for a place inside the lift. It has been noted that the
peak time for lift usage in Blocks A, B and E of APU currently is during class time
in the morning and afternoon. The new lift is to be consolidated to accommodate
more people in one ride. The Lift should be comprised of high-quality lighting, the
safety features and be able to accommodate more people in one time and should
follow the modern standards of operation. Sustainability resources including time
management should be taken into consideration as well as the cost of repairs and
for the maintenance.
The conditions set by APU are that the project need to be complete by 31 st
December 2019 and there should be no disruption of service during the system
upgrade. The project manager is to submit the project plan to APU Property
Services Department, and the latter should be responsible for the smooth running
of the plan after the approval of the project. (EE0919-3.5-3-EPM-Assignment-
Question).
2.1 Project Scope Statement
Currently the number of staffs, students and visitors taking the lifts from Blocks A,
B and E is increasing at an alarming rate. The waiting time is getting greater and no space
inside the lifts to accommodate them all to the 9 floors of APU. Also, among the current
lifts, only Block A and B lifts provide access to the 8th and 9th floor, and hence increasing
the lift traffic. Some classes in the morning have only a 15 to 30 mins break in between,
and the waiting time makes it impossible for students or staffs to have a snack break in
between their classes considering that the waiting time is around 5 to 10 mins depending on
the amount of people waiting.
There are always uncertainties in any projects and in order to manage those
uncertainties and risks, the project manager need to specify what is to be done, decide on
how to tackle with the project and making sure it is completed within the time frame set.
This is called managing uncertainties from the stage of ‘Conception’ to the final Support’
stage by following the Project Life Cycle (PLC) (Ward and Chapman, 2003). Uncertainty
means not being certain about certain aspects of the projects for example cost, duration, or
quality of project. It also includes being a team player and managing the team properly and
at the same time respecting the team’s opinions. The project scope statement is set to
explain the whole project using the following SMART criteria, deliverables and
assumptions.
2.2.2 Measurable
2.2.3 Attainable/Achievable
2.2.4 Relevant/Realistic
The deliverables set by APU to be completed by the end of this project are:
1. A new lift in APU New Campus Block D is to be built and able to accommodate up to 15
people at a time.
2. The lift speed is to be set at 1.75 m/s.
3. The new lifts are to include high quality lighting and all the safety features.
4. The new lifts are to be up to the modern standards and according the lift safety and comfort
norms set by the JKKP (Jabatan Keselamatan Dan Kesihatan Pekerjaan Malaysia).
5. The project needs to be time saving and completed within or before the time frame set in
the proposal.
6. Cost of repairs and the maintenance cost are to also be taken into consideration.
2.4 Project Assumptions
The overall Budget assumptions to conduct this project is given the below table.
The Workforce (labor cost), is estimated at RM23,120.00. The cost for Sitework, utilities
and construction material are estimated at RM63,904.00. The Elevator materials and
equipment’s cost is RM.167,900.00. and lastly, the Miscellaneous costs are rounded to
RM2400.00.
Therefore, the total estimated budget to be allocated for the construction of a new
lift in Block D of APU New Campus is RM257,324.00.
Another assumption made is that a few extra days will be allocated in case of any damaged
part within the foyer during construction of the lift.
All the heavy construction work will be done after 6:00 pm when classes are over and
weekends.
No construction work will be done on days that there are events in the foyer.
Like any other projects, this project is also prone to constraints. There are 2 types of
constraints, namely internal and external. The internal constraints for this project are the
policies and corporation limitations set by APU property Services department. They state
that there should be no disruption of service during the system upgrade and the project
must be completed within the time frame set. The external constraints on the other hand is
the environmental factors such as weather or the materials availability. Another factor can
be the time to deliver the materials from the stores to APU or any items missing in the
delivery or damaged during transportation.
11
3.1 Work Breakdown Structure
A Work Breakdown Structure, WBS, also forms part of the important deliverable of
the project life cycle. It is designed in order to breakdown the project into simpler and more
manageable tasks. Those smaller tasks are then easier to tackle with and helps the team
working on the project to meet its objectives within the timeframe set for the project to
complete. According to PMBOK (Project Management Body Of Knowledge), the WBS is
‘a deliverable oriented hierarchical decomposition of work’ that needs to be completed by
the assigned team to the project (workbreakdownstructure.com, 2018). The WBS can be
drafted in two ways: Graphically and tabularly as shown in the figures below. Both
methods consist of different levels that have been categorized according to their
importance, size, and type of the project. There are two approaches in making a WBS, Top-
Down Approach, whereby the deliverables are set from top-level and get decomposed into
sub-deliverables while the second approach, Bottom-Up, the low-level deliverables are set
first then followed by the main project deliverables.
1. The project can be broken down into simpler and more manageable tasks
2. The cost involved in fulfilling the project can be easily allocated and categorized
according to different tasks and hence easy to calculate.
4. Allows the project manager to divide the tasks among the team and formulate a
proper communication plan for the success of the project.
For this project, a Top-Down approach was used to derive the WBS as shown below:
12
13
3.1. Project Planning Stage (1.0):
Before starting the project, the project needs to be planned and any acquisition of
permit required needs to be completed beforehand. The project planning stage is broken
down into 3 categories, the designing (1.2, 1.3, 1.4), the cost estimations (1.5) and the
permits acquisition (1.6) from JKKP (Department of occupational safety and health
Malaysia).
For the design parts, the company, SLS (Smart Lifts Systems), needs to make the
hand sketches, 3D designs and electrical designs to present to the customer, in this case,
APU Property Services Department and only after their approvals, the documents will be
submitted to the JKKP Board for the permits issuance. The cost estimation needs to be
submitted to APU as well before gaining the approval to proceed with the construction of
the lifts in Block D.
The cost estimation plan will be based on all the costs involved such as labor cost,
materials costs, the transport of materials, the elevator system, etc. The company needs to
make sure that the cost estimation is within a proper budget and the designs made are
according to the correct dimensions and verified by a professional who will perform the
blueprints of the designs. Once the permits acquired and the designs are made and
approved, the company may proceed to the next task.
According to the WBS, the 2nd stag is the construction phase, whereby the materials
have been acquired already and all the stage 1 tasks have been completed. First the
Unnecessary materials and components (2.1) need to be removed from the site chosen for
the lift construction. For examples all the Block D rooms on level 8 and 9 need to be
emptied and the walls removed so that those floors can also be accessed through the lift.
Then platforms need to be made on level 6 to 7 for the lift to reach the wall under the
platform construction stage (2.2). the shafts supporting the wall construction (2.3) need to
be done as well and then the conduits (2.4) also need to be added. On all the 9 floors a
landing door need to be built and installed (2.5). Furthermore, a machine room need to be
built (2.6) for the engineers to work on the electrical wiring and the mechanics of traction
mechanism as well as counter-weight mechanism. Finally, the lift cabin is set up and the
interior of the lifts including the ceiling, flooring, handles are installed (2.7).
3.3. Installation stage (3.0):
The installation phase is broken down into 3 phases, namely the Electrical works
(3.1), the mechanical works (3.2) and lastly the safety and security (3.3) phase.
The electrical part comprises of firstly the Wiring of the lift system (3.1.1), whereby
the wiring is done for the lift cabin for the lighting and other components inside the cabin
and the for the lift controls until the machine room. Then the ventilation system is set up
(3.1.2) where the lift is fitted with a ventilation system to provide oxygen inside the lifts at
all time. Then the lift control system is set up (3.1.3) for the basic operations of the lifts.
The trunkings (3.1.4) are then installed over all the wires to secure the wiring and avoid any
electrical incidents. The last stage is the set up of lighting and speakers inside the lift (3.1.5)
for the comfort of the users and also for passing announcement in the lift in case of
emergency or in case of lift breakdown, to notify the users about the situation.
The mechanical part is the part where the lift mechanism is set up. The buffer spring
(3.2.1) is first adjusted to create smooth landing on floors and to no damage the lift system.
Then the control box is set up (3.2.2) for users to control the lift and set the floor number
they want to go to. Then the pully system is set up (3.2.3) in order to connect the lift to the
mechanism, allowing the lift to move up and down. The traction system and counterweight
are built (3.2.4), thus enabling the lift to functionate. The counterweight system works as a
counterbalance for when the lift goes down the counterweight goes up and vice versa.
Finally, the lift door controls are added (3.2.5) for the lift manipulation.
The Safety and security phase (3.3) are the phase where the security measures are
installed inside the lift cabin. The emergency alarm (3.3.1) is set up in case of any incidents.
A button inside the lift can be used to trigger the alarm in case of lift breakdown or in case
of any incidents outside the lift, the alarm will be let off to inform the users of the lifts that
there is an ongoing issue. CCTV cameras (3.3.2) are also set up in order to record live
actions inside the lift in case of any mishap in the lift. Fore extinguishers are added (3.3.3)
in order to prevent any fire related accidents and an intercom (3.3.4) is added to allow
communication between lift users and lift operating staffs outside in case of any lift
breakdown. Finally, a weight and measuring system (3.3.5) is also included in the lift to
estimate the number of people inside the lift and to send off an alarm whenever the weight
has been exceeded. This is to warn the users that the lift is overcrowded, and some people
need to get off the lift. The lift will not move unless the extra weight of taken off the lift
cabin.
The commissioning stage is split into 2 stages: Pilot testing (4.1) and review (4.2).
The pilot testing is the testing of the lift before the handover of the project and the review is
the handover.
The testing phase is divided into parts, first the site needs to be cleaned (4.1.1), that
is, all the construction materials removed from the site, the lift cabin cleared from all the
cement or any other construction residue left and the site is painted and polished. The next
stage is to test the lift (4.1.2) whereby the lift is tested by the technicians and engineers
working on the project. The lift is also tested by a set of people who will in turn give a
feedback (3.1.3) about the lift’s functionality. Finally, a pilot run is made where the lift is
left for public usage over 2 days and tested if no breakdown occurs during that time.
The Project review is lastly made whereby the company conducts a final meeting
(4.2.1) with the APU Property Services Department and feedback will be given on the finish
work. The project is finally completed once APU signs the completion project file. (4.2.2).
4.0. Network Diagram
Table ## Activity List
A Network Diagram is a visual representation of a project’s schedule. Well known
complements to network diagrams include the PERT and Gantt charts. A network diagram in project
management is useful for planning and tracking the project from beginning to finish. It represents a
project’s critical path as well as the scope for the project (Brighthubpm, 2019). It will serve as a
planning tool in project management, using the Critical Path Method in the process to determine
timing effects, Precedence Diagramming Method and other tools.
The Project Network Diagram expresses the interdependence of the activities from the
decomposition of a complex project in the form of network diagram patterns, weighted
graphs including process and duration in the project. Project network diagram includes
Activity to be covered (task), the predecessors and duration of the tasks. Its derived from the
workflow diagram (work breakdown structure) of the project and it is represented in the
project documentation as flow chart pattern with shapes of blocks and arrows representations.
(Kehe et al., 2015).
The duration of each task has been looked into by the WBS group members and then
HR of the project. Initially the whole project was schedule for 87 days which is nearly 3
months while doesn’t seem efficient to build a single elevator. Hence, after thorough
discussion the whole project was scheduled for 60 days. The minimum duration possible with
a professional work for each task to complete this project is chosen. To finish the project with
minimum time but in the most efficient scheme.
Table ## shows the activity list that has been listed from the WBS (Work Breakdown
Structure) indicating the preceding task and the time taken to complete a specific task. The total
number of task 34 task named form A-Z-AH and denoted with the number of days a specific task
should be finished, if not the it will affect whole timing of the project. Some of the tasks can be
started even when the other has not begun, similarly some tasks cannot be started if a certain task has
not been completed. In our scenario, task Q (Trunking Installations) can be started only when the task
M (Lift Interior) and N (Wiring) has been completed. Since trunking is part where after the wires and
the interior has been placed the workers can cover up the wires making the elevator neat which is
known as trunking. In the other case, task R (Lighting and Speakers) can be installed when the P (Lift
Control Systems) and Q (Trunking Installation) are not completed. So, in these types of scenarios, it
does not affect the entire project schedule provided the float is kept in mind.
0 A 1 1 B 4 4 C 5 5 D 7 7 E 9 9 F 10 10 G 15
START 1
0 1 1 1 3 4 4 1 5 5 2 7 7 2 9 9 1 10 10 5 15
F=0 F=0 F=0 F=0 F=0 F=0 F=0
15 H 17 17 I 20 20 J 23 23 K 26 26 L 28 28 M 30 30 N 32
1 2
15 2 17 17 3 20 20 3 23 23 3 26 26 2 28 28 2 30 30 2 32
F=0 F=0 F=0 F=0 F=0 F=0 F=0
30 Q 31
34 1 35
F=4
32 O 34 34 P 35 35 R 36 36 S 38 38 T 39 39 U 41 41 V 43
2 3
32 2 34 34 1 35 35 1 36 36 2 38 38 1 39 39 2 41 41 2 43
F=0 F=0 F=0 F=0 F=0 F=0 F=0
43 W 44 44 X 45 45 Y 46 46 Z 47 47 AA 48 48 AB 50 50 AC 52
3 4
43 1 44 44 1 45 45 1 46 46 1 47 47 1 48 48 2 50 50 2 52
F=0 F=0 F=0 F=0 F=0 F=0 F=0
52 AD 54 54 AE 55 55 AF 57 57 AG 58 58 AH 59
4 END
52 2 54 54 1 55 55 2 57 57 1 58 58 1 59
F=0 F=0 F=0 F=0 F=0
Path 1:
=A+B+C+D+E+F+G+H+I+J+K+L+M+N+O+P+R+S+T+U+V+W+X+Y+Z+AA+AB+AC+AD+AE+AF+
AG+AH
=1+3+1+2+2+1+5+2+3+3+3+2+2+2+2+1+1+2+1+2+2+1+1+1+1+2+2+2+1+2+1+1
= 59 Days
Path 2:
=A+B+C+D+E+F+G+H+I+J+K+L+M+N+Q+R+S+T+U+V+W+X+Y+Z+AA+AB+AC+AD+AE+AF+A
G+AH
=1+3+1+2+2+1+5+2+3+3+3+2+2+2+1+1+1+2+2+2+1+2+1+1
= 46 Days
The longest path which has the float as 0 is considered as the critical path. So, in this scenario the
critical path is Path 1. Following the critical path, the project can be completed given duration. The project
can also be completed in 46 days but if Path 2 is taken then the task like the O (Ventilation) and P (Lift
Control System) is not completed. Hence in order to determine the critical path, the most easiest and
precise way is to mention the float and follow the path where the float is 0. Thereby, the whole project shall
be on schedule and there wouldn’t be any mistakes in finding the critical path for a PDM Network
Diagram.
5.0 Project Schedule
Figure 3 Holes were made on floor 8,9 and fences were cut for the lift entrance
As shown in figure 1, lift was installed near the APU new campus cafeteria area, the lift
consists of 10 floors including the bottom part. The lift system was designed to connect the third
floor until the ninth floor. From floor number 5,6, and 7, an additional platforms support was
installed in order to bridge the way between the lift and the floor, the illustration was described in
figure 2 above. Moreover, the fence which already there, will be trimmed to make a way clear for
the lift entrance. At floor number 8 and 9, wall of the building will be breached to make an
entrance for the lift, as shown in figure 3 above. No additional platform needed in these floors. An
elevator guide rail was installed from the basement floor until it reaches the ninth floor. The guide
rail was connected between the floor and the additional platform. The design of the elevator car
has a dimension 2400 x 2440 mm. The lift car has a door in it, and the other door which placed at
each floor at the entrance of the elevator. A counter weight frame was also installed at the elevator
rail, to counter the weight of the loaded elevator car, as shown in figure 4 above. Machine drive
and the overspeed governor was placed at the top of the elevator frame, to pull the elevator car and
the elevator counter weight. In figure 5 above, car buffer was placed at the bottom of the elevator
guide frame, to stop a descending car or counter weight beyond its limit
AutoCAD Designs
COST ESTIMATION
1.1 Overview
Cost estimation is an essential part of the planning stage as it is requiring estimating the projects
total worth for both the client and the company. As it helps the company to know what is requires
for purchases and the feasibility of the project as well as enabling effective communication with
the client. On the client is it crucial to know the required prices and cost of the whole project
before agreeing upon any work to be done. Hence this is a very essential stage for the project
undertaking and conceptualization.
Cost estimation is an essential element in the project management because it helps keeping the
project financially applicable and feasible. Many of the failures of construction project and
difficulties have been due to bad cost estimation and cost overruns. There are many examples of a
failed projects or projects that have been taken more than expected time to accomplished as for
example Sydney opera house was completed ten years late and more than fourteen times over
budget another example was Scottish parliament building which was originally expected to take
two years and cost 40 million pounds but took five years and cost 400 million pounds. Therefore,
it is very important to derive a very prices and organized plan. In this project, the report will
display the cost estimation as of the following:
1. Cost for Sitework, Utilities and Construction Material.
2. Elevator Materials and Equipment’s Cost.
3. Labour Cost (Installation Cost).
4. Miscellaneous Cost.
5. Total Estimated Cost
The above table shows the cost of the material required for construction the multipurpose of the
walls and beams for elevator which is the box of the elevator. As it can be seen from the table the
construction is going to use the ready mixed concrete with grade 25 and 30. The ready mixed
concrete is a concrete with sand and aggregate already mixed into it with proper ratios. The reason
that this concrete is used is the fact that this concrete is easier to calculate for price for a project, all
that is needed is to calculate the required volume of the project which in this case it was obtained
through the height of the campus and the length of the desired walls and it breath to be 89 m3 as
can be seen in table above, as well as being already mixed into appropriate grades making the
work very efficient and durable. Although, it is quite costly to use already mixed cement than
buying normal cement, aggregate and sand and mixing it in the work site by hand. The normal
Aggregate 30 41 RM / 1,230 RM 1 Tonne of
Ton
Aggregate
Sand 1 850 RM / 850 RM 1 Tonne of
Ton Sand
Mild Steel Bar R 5 2,230 11,150 RM 1 Tonne of
RM /
10mm - 12mm Steel Bars
Ton
10mm -
12mm
Mild Steel Bar R 3 2,080 6,240 RM 1 Tonne of
RM
16mm - 20mm Steel Bars
/Ton
16mm -
20mm
Others 7,000 RM Assuming
Cement
Adhesives
and other
materials as
well as
margin error
Total - - 44,081 RM -
cement, sand and aggregate will be used in case there is shortage in the other mixed cements as
well as used in the other processes of the project like framing, exterior and interior finishing, and
the major system installation. Therefore, for the steel bars with all the diameters given in table
above its wasn’t as costly as other materials. The total cost of materials for construction was found
to be 44081 rm, which in like the other multipurpose construction sites. Therefore, it is considered
appropriate estimate. [ CITATION Qua19 \l 2057 ]
Total - 10143.95 RM - -
Drilling and site work are part of building the project, even though in most of the cost estimation it
is always put into a separate cost estimation. So, there won’t be a calculation for the cost of the
foundation because by adding the results of the construction material to the site work with the
labor cost estimation that will include all the prices of the construction of the project. In every
construction project there must be site clearance which is cleaning the site and preparing it for the
project initiation. The project is going to take place at Block D of APU new campus. Therefore,
for drilling the walls for the space of the elevator car box and as well as rebuilding the walls and
railing at level 4 to level 8, the price of the site clearance was selected to be moderate to around
10143.95 rm. The reason for the price to be quite high because drilling is usually an expensive
process which is the case it cost around the amount. Summarizing the price of the drilling and site
clearance work is very moderate for a task that is essential and important. As it can be seen in the
above table. [ CITATION cos19 \l 2057 ]
The utilities for construction work unlike the common thought is very important to be included in
the calculation and estimation plan. As most of the time it falls into hidden costs of the project
which most of the time if not include in the cost estimation it drains the project client of his
financial capabilities leading in worst case scenarios to project termination or some aspect of the
project left unfinished. Hence the utilities were included which totals up to 5381.55 rm. It is not a
large sum considering the other costs involved in the project, however it differs from other cost in
the project in the fact these costs are hidden and only appear when the project start to consume
money and when it is not included it could add up drastically in ultimate cases might lead to
project termination so it is a good practice to write it down to keep an eye on it. Like there has
been scenarios where the electric bill of a construction site reaches a level where it becomes more
expensive than many other costs. The scaffolding price was added in this section as the aluminium
steel rod is not safe to keep it open due the project is going to be ongoing for more than 10 days
for safety purpose it is being used and as well as it could also prove useful.
Total RM 23,120
- Counterweight
- Suspension Cables
- Cabin door
- Landing door
- Pit Buffers
Stage 3 – Lift Driving Machine
This stage includes the costs of building a machine room and the cost of the driving machine
which consists of the following:
- Electrical Motor
- Drive Sheave
- Deflector Sheave
- Brake
This stage includes the costs of the installing of several components to raise the level of safety
of the lift, which include:
- Hoist way Door Interlock
The stage includes the installation of a control system cost, which consist of 3 main parts which is
stated below:
The cost in of miscellaneous is not included in the previous estimation on the materials and
equipment’s cost section and it is important to take into consideration while doing the cost
estimation.
The below table shows the total estimated cost need for the projects to finish, which includes Cost
for Sitework, Utilities and Construction Material, Elevator Materials and Equipment’s Cost,
Labour Cost (Installation Cost), Miscellaneous Cost
29
8.2 Scheduling Team
8.3 Design & Construction Team
8.4 Quantity and Safety Team
9.1 Risk Management Plan
4 Implementation PIC- Staff PIC should order the material at least one
delays (quantity) month before.
Avoidance
possibility of incidents.