Competence skills : T I T L SCALAR WIRING Time : 4 x 45 '
Subjects :PDIL INSTALLATION SYSTEM Date :
Class : X TITIL IN PIPE Name :
PURPOSE : skilled students pewatan install a single switch installation.
INSTRUCTIONS : 1. Cables used NYA 1.5 mm
2. Semua cables installed in pipes.
3. Pengupasan wires must be really - really clean in order to get In
Contact good
TOOLS / MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 2. Screwdrivers –
3. Wood rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Clamp / Sengkang 6. Knife
7. Fitting seat
8. Single switch
9. Knie
10. Light bulb
SAFETY act of
1. Smoothed with a reamer end of the pipe so as not to injure the cable and hand.
2. Equipment and material placed in a safe place so as not to fall.
STEP WORK
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Put the box number, pipe in the image.
4. Put HER in the pipe box.
5. Peel and NYA wire connection in the connection box and the component.
6. Check your work with or AVO Megger meters.
7. Check the instructor
8. Done in check / assess, installations must be dismantled.
FIGURE WORK:
STATEMENT:
1. Why is it that for the filler wire in the cable the greater use of wire used for each
component of other users.
2. What is the key to something big fuse installation.
3. Write down the requirements for connection to sihasilkan good contacts on.
a. Linkage between the two conductive wires.
b. Junction between the wire Conductor and components (switches, fittings)
c. Between the two flexible wire.
4. Create reports of your work.
Competence skills : T I T L WIRING SWITCHES TO Time : 4 x 45 '
Subjects :PDIL SERVE TWO SINGLE Date :
Class : X TITIL LAMP Name :
GOAL : Students are skilled to install a single switch wiring installation.
INSTRUCTIONS :1. The cable that they use the NYA 1.5 mm
2. All cables installed in pipes
3. Stripping the cable must be really - really clean in order to get good
contact.
4. To understand the General Requirements for the installation of
electrical installations.
TOOLS / MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 2. Screwdrivers –
3. Wood rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Clamp / Sengkang 6. Knife
7. Fitting seat
8. Single switch
9. Knie
10. Light bulb
SAFETY MEASURES
1. Take care not to rupture component
2. Do not give stress prior to review instructor.
STEP WORK
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Put the box number, pipe in the image.
4. Put HER in the pipe box.
5. Peel and NYA wire connection in the connection box and the component.
6. Check your work with or AVO Megger meters.
7. Check the instructor
8. When finished unloading the installation back to the place originally.
FIGURE WORK:
QUESTION:
1. What utility box number.
2. How do I make a connection pigs / pig tail
3. Explain what is the meaning NYA
4. Create reports that you have the work completed.
Competence skills : T I T L WIRING SWITCHES TO Time : 4 x 45 '
Subjects :PDIL SERVE TWO SINGLE Date :
Class : X TITIL LAMP Name :
GOAL : Students are skilled to install a single switch wiring installation.
INSTRUCTIONS :1. The cable that they use the NYA 1.5 mm
2. All cables installed in pipes
3. Stripping the cable must be really - really clean in order to get good
contact.
4. To understand the General Requirements for the installation of
electrical installations.
TOOLS / MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 2. Screwdrivers –
3. Wood rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Clamp / Sengkang 6. Knife
7. Fitting seat
8. Single switch
9. Knie
10. Light bulb
SAFETY:
1. Equipment that is damaged should be replaced immediately or in repair
2. Wear work clothes and footwear that are insulators
3. Heart - heart with voltage 220 volts
4. Do not bersendagurau during practice
WORK STEPS:
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Install the dial box / pipe in the image.
4. NYA wire pairs in the pipe.
5. Peel and connect the wire connection box and NYA in the component.
6. Check your work with megger or AVO meters.
7. Report on the instructor / teacher
FIGURE WORK:
QUESTION:
1. What a difference a single switch and switch series. Explain.
2. Write the specifications of the switch that you use.
3. State the phase wire insulation that you wear.
4. How do you do the installation work
Competence skills : T I T L WIRING SCALAR SERVE Time : 4 x 45 '
Subjects :PDIL TWO LAMP SERIES Date :
Class : X TITIL Name :
PURPOSE : skilled students to install wiring installation series switch.
INSTRUCTIONS :
1. Cables used NYA 1.5 mm and 2.5 m
2. All cables installed in pipes.
3. Stripping the cable must be really - really clean in order to get good
contact.
4. To install the installation pemahami General Requirements for
Electrical Installation.
TOOLS / MATERIALS:
1. NYA 1.5 mm, 2.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 " 2. Screwdrivers –
3. Rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Clamp / Sengkang 6. Knife
7. Fitting seat
8. Knie
9. Light bulb
10. Switch series
SAFETY MEASURES:
1. Take care not to rupture component
2. Do not give prior review current instructor.
WORK STEPS:
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Install the dial box / pipe in the image.
4. NYA wire pairs in the pipe.
5. Peel and connect the wire connection box and NYA in the component.
6. Check your work with megger or AVO meters.
7. Report on the instructor
8. After re-assessment of your installation bongkat
9. Create a report of the work that you accomplish.
FIGURE WORK:
QUESTION:
1. How do you do the installation work.
2. What about a combination of usefulness in tNYA work.
3. Write down the requirements to get a good connection.
Competence skills : T I T L SCALAR WIRING SINGLE Time : 4 x 45 '
Subjects :PDIL SAFETY EQUIPPED WITH Date :
Class : X TITIL CONTACT BOX Name :
GOAL : Students skilled install wiring with a series switch socket
INSTRUCTIONS :
1. Cables used NYA 1.5 mm
2. To install the installation pemahami General Requirements for
Electrical Installation.
3. Heart - heart when conducting connection, note the image schema
TOOLS / MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 " 2. Screwdrivers –
3. Rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Clamp / Sengkang 6. Knife
7. Fitting seat
8. Knie
9. Light bulb
10. Single switch
11. Socket
12. MCB
SAFETY MEASURES:
1. Take care not to rupture component.
2. Do not give prior review current instructor.
WORK STEPS:
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Attach PVC pipe according to plan
4. Learn drawing installation connection scheme
5. Connect each component.
6. Check your work with megger or AVO meters.
7. Report on the instructor
8. After review instructor, installations must be dismantled.
IMAGE WORK
QUESTION:
1. What is the function of MCB in the installation.
2. How high is the installation of the switch in an installation.
3. Why use a cable to the charger cable is larger than the cable at each kompoenen
4. According PUIL phase in the contact box located on the right. Explain why.
5. Create your report the work already completed.
Competence skills : T I T L INSTALLATION OF TWO Time : 4 x 45 '
Subjects :PDIL SINGLE LIGHT Date :
Class : X TITIL SWITCHES SERVED Name :
WITH CONTACT BOX
GOAL : Students skilled install wiring with a series switch socket
INSTRUCTIONS : any electrical installation a technician should consider PUIL 2000
(general requirements for electrical installations). For students in the
design, and Pemasngan, pemgujian, according PUIL care.
TOOLS / MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 " 2. Screwdrivers –
3. Single switch 3. Combination pliers
4. MCB 4. Cutting pliers
5. Fitting lamp 5. Freet drill / auger
6. Rosette 6. Knife
7. Knie
8. Wood Screws 5 / 8 ", 1 / 2", 3 / 4 "
9. Socket
10. Kelm / cross bar
11. Grid connection / T. Dos
SAFETY:
1. Equipment that is damaged must be replaced and repaired
2. Part of voltage to be closed
3. Do not put the contacts box stacked - stacked.
WORK STEPS:
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Attach PVC pipe according to plan
4. Learn drawing installation connection scheme
5. Connect each component
6. Check your work with megger or AVO meters.
7. Report on the instructor
8. After review instructor, installations must be dismantled.
FIGURE WORK:
QUESTION:
1. How many wires needed for the conducting phase and neutral conductor.
2. How is the working principle of the switch and socket.
3. How much MCB to be installed.
4. Explain how the installation of light fittings.
5. Create reports pekarjaan you are doing.
Competence skills : T I T L FITTING SERIES Time : 4 x 45 '
Subjects :PDIL SWITCHES WITH Date :
Class : X TITIL CONTACT BOX WITH Name :
SAFETY
GOAL : Students are skilled to install the wiring switch and socket series with
Safety
INSTRUCTIONS :
1. The power cord used NYA 1.5 mm
2. To understand the General Requirements for the installation of
electrical installations.
3. Heart - heart when conducting connection, consider the scheme
drawing plan.
EQUIPMENT AND MATERIALS:
1. NYA 1.5 mm 1. Screwdrivers +
2. PVC Pipe 5 / 8 2. Screwdrivers –
3. Wood rosette 3. Cutting pliers
4. Wood Screws Nails 5 / 8 ", 1 / 2", 3 / 4 " 4. Combination pliers
5. Grid Connect / T. Dos 5. Freet drill / auger
6. Single switch 6. Knife
7. Knie
8. Light bulb
WORK STEPS:
1. Prepare tools and materials as needed
2. Determine the locus of the components on the board work.
3. Attach PVC pipe according to plan
4. Learn drawing installation connection scheme
5. Connect each component.
6. Check your work with megger or AVO meters.
7. Report on the instructor
8. After review instructor, installations must be dismantled.
IMAGE WORK
a
.
QUESTION:
1. In the open state of the switch terminal which is connected to the phase wire?
2. How many wires at the point a. ?
3. Explain the function of MCB in the series tNYA installation.
4. Create reports of practices that already you are doing.