Study Plan

This document outlines a project plan for revising knowledge areas for an exam. It includes tasks for project integration management, scope management, schedule management, cost management, quality management, and resource management. Each task includes subtasks to be completed over several weeks, along with estimated durations and dependencies between tasks. Progress percentages are provided for completing online quizzes and questions associated with each task.

Uploaded by

Dinesh Shukla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views15 pages

Study Plan

This document outlines a project plan for revising knowledge areas for an exam. It includes tasks for project integration management, scope management, schedule management, cost management, quality management, and resource management. Each task includes subtasks to be completed over several weeks, along with estimated durations and dependencies between tasks. Progress percentages are provided for completing online quizzes and questions associated with each task.

Uploaded by

Dinesh Shukla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID Task Task Name Duration Start Finish % Complete Exam 20

Result
Jul '20 Predecessors
Mode T F S
1 1 Revision By Knowledge Area 33 days? Sat 25/07/20 Tue 08/09/20 76%
2 1.1 Project Integration Management 1 day? Sat 25/07/20 Sat 25/07/20 100%
3 1.1.1 Develop Project Charter 1 day? Sat 25/07/20 Sat 25/07/20 100%
4 1.1.2 Develop Project Management Plan 1 day? Sat 25/07/20 Sat 25/07/20 100%
5 1.1.3 Direct & Manage Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100%
6 1.1.4 Monitor & Control Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100%
7 1.1.5 Close Project or Phase 1 day? Sat 25/07/20 Sat 25/07/20 100%
8 1.1.6 Complete PrepCast 20 Q's 1 day? Sat 25/07/20 Sat 25/07/20 100% 85%
9 1.1.7 Complete Andy Crowe Quiz 1 day? Sat 25/07/20 Sat 25/07/20 100% 80%
10
11 1.2 Project Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100% 2
12 1.2.1 Plan Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100%
13 1.2.2 Collect Requirements 2 days Mon 27/07/20 Tue 28/07/20 100%
14 1.2.3 Define Scope 2 days Mon 27/07/20 Tue 28/07/20 100%
15 1.2.4 Create WBS 2 days Mon 27/07/20 Tue 28/07/20 100%
16 1.2.5 Validate Scope 2 days Mon 27/07/20 Tue 28/07/20 100%
17 1.2.6 Control Scope 2 days Mon 27/07/20 Tue 28/07/20 100%
18 1.2.7 Complete PrepCast 20 Q's 2 days Mon 27/07/20 Tue 28/07/20 100% 75%
19 1.2.8 Complete Andy Crowe Quiz 2 days Mon 27/07/20 Tue 28/07/20 100% 84%
20
21 1.3 Project Schedule Management 2 days Wed 29/07/20 Thu 30/07/20 100% 11

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 1
ID Task Task Name Duration Start Finish % Complete Exam 20
Result
Jul '20 Predecessors
Mode T F S
22 1.3.1 Plan Schedule Management 2 days Wed 29/07/20 Thu 30/07/20 100%
23 1.3.2 Define Activities 2 days Wed 29/07/20 Thu 30/07/20 100%
24 1.3.3 Sequence Activities 2 days Wed 29/07/20 Thu 30/07/20 100%
25 1.3.4 Estimate Activity Durations 2 days Wed 29/07/20 Thu 30/07/20 100%
26 1.3.5 Develop Schedule 2 days Wed 29/07/20 Thu 30/07/20 100%
27 1.3.6 Control Schedule 2 days Wed 29/07/20 Thu 30/07/20 100%
28 1.3.7 Complete PrepCast 20 Q's 2 days Wed 29/07/20 Thu 30/07/20 100% 75%
29 1.3.8 Complete Andy Crowe Quiz 2 days Wed 29/07/20 Thu 30/07/20 100% 85%
30
31 1.4 Project Cost Management 3 days? Fri 31/07/20 Tue 04/08/20 100% 21
32 1.4.1 Plan Cost Management 3 days? Fri 31/07/20 Tue 04/08/20 100%
33 1.4.2 Estimate Costs 3 days? Fri 31/07/20 Tue 04/08/20 100%
34 1.4.3 Determine Budget 3 days? Fri 31/07/20 Tue 04/08/20 100%
35 1.4.4 Control Costs 3 days? Fri 31/07/20 Tue 04/08/20 100%
36 1.4.5 Complete PrepCast 20 Q's 3 days? Fri 31/07/20 Tue 04/08/20 100% 73%
37 1.4.6 Complete Andy Crowe Quiz 3 days? Fri 31/07/20 Tue 04/08/20 100% 70%
38
39 1.5 Project Quality Management 2 days Wed 05/08/20 Thu 06/08/20 100% 31
40 1.5.1 Plan Quality Management 2 days Wed 05/08/20 Thu 06/08/20 100%
41 1.5.2 Manage Quality 2 days Wed 05/08/20 Thu 06/08/20 100%
42 1.5.3 Control Quality 2 days Wed 05/08/20 Thu 06/08/20 100%

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 2
ID Task Task Name Duration Start Finish % Complete Exam 20
Result
Jul '20 Predecessors
Mode T F S
43 1.5.4 Complete PrepCast 20 Q's 2 days Wed 05/08/20 Thu 06/08/20 100% 80%
44 1.5.5 Complete Andy Crowe Quiz 2 days Wed 05/08/20 Thu 06/08/20 100% 68%
45
46 1.6 Project Resource Management 2 days Fri 07/08/20 Mon 10/08/20 100% 39
47 1.6.1 Plan Resource Management 2 days Fri 07/08/20 Mon 10/08/20 100%
48 1.6.2 Estimate Activity Resources 2 days Fri 07/08/20 Mon 10/08/20 100%
49 1.6.3 Acquire Resources 2 days Fri 07/08/20 Mon 10/08/20 100%
50 1.6.4 Develop Team 2 days Fri 07/08/20 Mon 10/08/20 100%
51 1.6.5 Manage Team 2 days Fri 07/08/20 Mon 10/08/20 100%
52 1.6.6 Control Resources 2 days Fri 07/08/20 Mon 10/08/20 100%
53 1.6.7 Complete PrepCast 20 Q's 2 days Fri 07/08/20 Mon 10/08/20 100% 70%
54 1.6.8 Complete Andy Crowe Quiz 2 days Fri 07/08/20 Mon 10/08/20 100% 100%
55
56 1.7 Project Communications Management 1 day? Tue 11/08/20 Tue 11/08/20 100% 46
57 1.7.1 Plan Communications Management 1 day? Tue 11/08/20 Tue 11/08/20 100%
58 1.7.2 Manage Communications 1 day? Tue 11/08/20 Tue 11/08/20 100%
59 1.7.3 Monitor Communications 1 day? Tue 11/08/20 Tue 11/08/20 100%
60 1.7.4 Complete PrepCast 20 Q's 1 day Tue 11/08/20 Tue 11/08/20 100% 65%
61 1.7.5 Complete Andy Crowe Quiz 1 day Tue 11/08/20 Tue 11/08/20 100% 80%
62
63 1.8 Project Risk Management 2 days? Wed 12/08/20 Thu 13/08/20 100% 56

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 3
ID Task Task Name Duration Start Finish % Complete Exam 20
Result
Jul '20 Predecessors
Mode T F S
64 1.8.1 Plan Risk Management 2 days? Wed 12/08/20 Thu 13/08/20 100%
65 1.8.2 Identify Risks 2 days? Wed 12/08/20 Thu 13/08/20 100%
66 1.8.3 Perform Qualitative Risk Analysis 2 days? Wed 12/08/20 Thu 13/08/20 100%
67 1.8.4 Perform Quantative Risk Analysis 2 days? Wed 12/08/20 Thu 13/08/20 100%
68 1.8.5 Plan Risk Responses 2 days? Wed 12/08/20 Thu 13/08/20 100%
69 1.8.6 Implement Risk Responses 2 days? Wed 12/08/20 Thu 13/08/20 100%
70 1.8.7 Monitor Risks 2 days? Wed 12/08/20 Thu 13/08/20 100%
71 1.8.8 Complete PrepCast 20 Q's 2 days? Wed 12/08/20 Thu 13/08/20 100% 70%
72 1.8.9 Complete Andy Crowe Quiz 2 days? Wed 12/08/20 Thu 13/08/20 100% 76%
73
74 1.9 Project Procurement Management 1 day? Fri 14/08/20 Fri 14/08/20 0% 63
75 1.9.1 Plan Procurement Management 1 day? Fri 14/08/20 Fri 14/08/20 0%
76 1.9.2 Conduct Procurements 1 day? Fri 14/08/20 Fri 14/08/20 0%
77 1.9.3 Control Procurements 1 day? Fri 14/08/20 Fri 14/08/20 0%
78 1.9.4 Complete PrepCast 20 Q's 1 day Fri 14/08/20 Fri 14/08/20 0%
79 1.9.5 Complete Andy Crowe Quiz 1 day Fri 14/08/20 Fri 14/08/20 0%
80
81 1.10 Project Stakeholder Management 3 days Mon 17/08/20 Wed 19/08/20 0% 74
82 1.10.1 Identify Stakeholders 3 days Mon 17/08/20 Wed 19/08/20 0%
83 1.10.2 Plan Stakeholder Engagement 3 days Mon 17/08/20 Wed 19/08/20 0%
84 1.10.3 Manage Stakeholder Enagagement 3 days Mon 17/08/20 Wed 19/08/20 0%

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 4
ID Task Task Name Duration Start Finish % Complete Exam 20
Result
Jul '20 Predecessors
Mode T F S
85 1.10.4 Monitor Stakeholder Enagagement 3 days Mon 17/08/20 Wed 19/08/20 0%
86 1.10.5 Complete PrepCast 20 Q's 3 days Mon 17/08/20 Wed 19/08/20 0%
87 1.10.6 Complete Andy Crowe Quiz 3 days Mon 17/08/20 Wed 19/08/20 0%
88
89 1.11 Exams 14 days Thu 20/08/20 Tue 08/09/20 0% 81
90 1.11.1 Exam 1 1 day Thu 20/08/20 Thu 20/08/20 0%
91 1.11.2 Revise Weaknesses 1 day Fri 21/08/20 Fri 21/08/20 0% 90
92 1.11.3 Exam 2 1 day Tue 25/08/20 Tue 25/08/20 0% 91FS+1 day
93 1.11.4 Revise Weaknesses 1 day Wed 26/08/20 Wed 26/08/20 0% 92
94 1.11.5 Exam 3 1 day Fri 28/08/20 Fri 28/08/20 0% 93FS+1 day
95 1.11.6 Revise Weaknesses 1 day Mon 31/08/20 Mon 31/08/20 0% 94
96 1.11.7 Exam 4 1 day Wed 02/09/20 Wed 02/09/20 0% 95FS+1 day
97 1.11.8 Revise Weaknesses 1 day Thu 03/09/20 Thu 03/09/20 0% 96
98 1.11.9 Exam 5 1 day Mon 07/09/20 Mon 07/09/20 0% 97FS+1 day
99 1.11.10 Revise Weaknesses 1 day Tue 08/09/20 Tue 08/09/20 0% 98
100
101 1.12 Exam Ready 0 days Tue 08/09/20 Tue 08/09/20 0% 89

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 5
27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20
S S M T W T F S S M T W T F S S M T W T F S S M T

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 6
27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20
S S M T W T F S S M T W T F S S M T W T F S S M T

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 7
27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20
S S M T W T F S S M T W T F S S M T W T F S S M T

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 8
27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20
S S M T W T F S S M T W T F S S M T W T F S S M T

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 9
27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20
S S M T W T F S S M T W T F S S M T W T F S S M T

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 10
17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20
T W T F S S M T W T F S S M T W T F S S M T W T F

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 11
17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20
T W T F S S M T W T F S S M T W T F S S M T W T F

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 12
17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20
T W T F S S M T W T F S S M T W T F S S M T W T F

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 13
17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20
T W T F S S M T W T F S S M T W T F S S M T W T F

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 14
17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20
T W T F S S M T W T F S S M T W T F S S M T W T F

08/09

Task Manual Task Deadline

Split Duration-only Late

Milestone Manual Summary Rollup Baseline

Project: Revision-Project-Plan Summary Manual Summary Baseline Milestone


Date: Fri 14/08/20 Project Summary Start-only Baseline Summary

Inactive Task Finish-only Progress

Inactive Milestone External Tasks Manual Progress

Inactive Summary External Milestone Slippage

Page 15