Safety Analysis for Derrick Operations

1. The document provides a job safety analysis for work at the monkey board on an oil rig. 2. It identifies potential hazards such as falls from heights and recommends safety measures to mitigate risks, including using fall protection equipment and maintaining good housekeeping. 3. Key responsibilities are outlined for the driller and derrickman to communicate clearly and follow safety procedures around raising and lowering pipe stands to prevent injuries or equipment damage.

Uploaded by

khurram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views2 pages

Safety Analysis for Derrick Operations

1. The document provides a job safety analysis for work at the monkey board on an oil rig. 2. It identifies potential hazards such as falls from heights and recommends safety measures to mitigate risks, including using fall protection equipment and maintaining good housekeeping. 3. Key responsibilities are outlined for the driller and derrickman to communicate clearly and follow safety procedures around raising and lowering pipe stands to prevent injuries or equipment damage.

Uploaded by

khurram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

Daqing Petroleum Iraq Branch HSE-MS/Doc. No.

22

JOB SAFETY ANALYSIS 工作安全分析

Rig: Well: Date:


Associated Permit No(IF required).:
工作许可号(如果需要)
Loacation/Area: Date Of Elaboration:
位置/区域
Work/Job/Project : Crew:
工作/工程名称 WORK AT MONKEY BOARD 人员:
Description For the job: Estimated Time Hours
工作描述: 预计时间: 小时
N0. Work Sequence Hazards or Potential Incidents Recommendations to Eliminate or
(Job Steps) Reduce Hazards
Derrickman informs
Driller prior to climbing
the derrick. Derrickman must be trained for the job he
Derrickman wears full is performing. Untrained crewmember
body safety harness, must never be used as a stopgap
attaches frontal D-ring Derrickman fails to use safety line / SRL – replacement. Derrickman and everyone
1.
to the climb assist Falls from the ladder. else climbing the derrick must safety lines
(Lad-Safe). Attaches attached to their full body harness front
SRL or counterweight and back. Prior to climbing the derrick the
safety line at back D- Driller must be informed.
ring (secondary
protection)
Derrickman uses safety Derrickman fails to use safety line when Prior to commencing work at the monkey
2. line at the monkey working at monkey board. - board the Derrickman must attach the
board. Derrickman fall from monkey board. safety line.
The Derrickman must maintain good
Ensures work area housekeeping:
Injury to Derrickman and or floorman. –
(monkey board) is clear Keep all walking surfaces clean and clear.
3. Derrickman slips or falls.
of tripping hazards and All loose equipment must have a securing
Floorman struck by falling equipment / object.
loose equipment. rope. Particularly tools, water bottles,
hard-hat.
Derrickman shifts
stands in and out of the
monkey board fingers.
Whilst tripping out,
once the stand is
lowered to the rig floor,
the Derrickman open Stand crashes across the derrick, possibly The Derrickman must open and release
the elevators then pulls smashing lights, which drop to the drill floor. the elevators before he has pulled the
4. the stand back to the Derrickman open elevators too late.- stand back too far. This will stop the
next open finger and Elevators and blocks swing across the derrick elevators and block swinging across the
secures the stand in it. and strike or catch on the derrick beams. derrick and hitting beams or equipment.
Tripping in, the
derrickman supplies
each stand out of the
fingers into the
elevators and closes
the elevators.
5 Communication Failure of communications- Good communications must exist. If the
between Driller and Driller or Derrickman moves pipe when other Derrickman has a problem, he must
Daqing Petroleum Iraq Branch HSE-MS/Doc. No.22

inform the Driller and give suitable


instructions.
Derrickman not expecting it, probably injuring floorman.
On long trips or hot conditions – the
Derrickman must have adequate relief
periods.
Executor Personnel 执行人员
Company/RIG Position Signature Company/RIG Position Signature
公司/队伍 岗位 签字 公司/队伍 岗位 签字

Elaborated By: HSE Supervisor.: Rig Manager:

Name: Name: Name:


Signature:_________________ Signature: ____________ Signature: ____________

Observations: Personnel Understood And Assumed Risk Associated With The Work To Be Done.