50 Dev Checklist
50 Dev Checklist
Capitalized text represents significant changes or additions from the 30% requirements. However, all requirements are
applicable.
GENERAL
COMMENTS FROM 30% REVIEW INCORPORATED – 30% PS&E COMMENT & RESPONSE TRACKING FORM SUBMITTED
REVIEW/CHECK ALL ELEMENTS OF DESIGN THAT HAVE AN INFLUENCE ON THE FINAL FOOTPRINT (HORIZONTAL AND VERTICAL
ALIGNMENTS, DRAINAGE STRUCTURES, RETAINING WALLS, SLOPES, EROSION CONTROL DEVICES, PARKING AREAS,
MISCELLANEOUS WIDENINGS, APPROACH ROADS, ETC.)
Documents are in compliance with established CFLHD format standards – Match agreed to format,
PDDM, CADD Standards Manuals, and Sample Plan Sheets.
ALL PHYSICAL IMPACTS TO THE WORK HAVE BEEN IDENTIFIED. FOOTPRINT IS WELL DESCRIBED (I.E. RETAINING WALL,
STRUCTURES, SLOPES)
COORDINATION OF ALL COMPETING DESIGN ELEMENTS HAVE BEEN REVISED AND OPTIMIZED.
Sheet numbers may be hand written
Insert design file path on all sheets (Place in lower left corner – outside of border)
TITLE SHEET
Use the Title Sheet Template at [Link]
Location Map shows:
BEGIN & END STATIONS OF PROJECT (ALL MAJOR ROADWAYS, NOT JUST MAINLINE)
Distances to Nearest Large Destinations
Design Designations included for all major roadways (not only mainline).
SITE PLAN
Section lines, property boundaries, ownership, land marks (significant planimetric features), horizontal
alignment, north arrow, and graphic scale
Previous CFLHD project boundaries and dates of construction, including projects under construction.
Include all projects constructed during the previous 10 years.
TYPICAL SECTION(S)
THE TYPICAL SECTIONS ARE FINALIZED
Use the Typical Section Sheet Template at [Link]
Typical Section shown for all roadways, including access and detour roads
SUMMARY OF QUANTITIES
Use the Summary of Quantities Template at [Link]
QUANTITIES FOR ALL BID ITEMS THAT AFFECT THE FOOTPRINT ARE COMPUTED (INCLUDES EARTHWORK, SURFACING
QUANTITIES, BRIDGES, DRAINAGE ITEMS, RETAINING WALLS, GUARDRAIL, CURBS, REVEGETATION, ETC.) MINOR ITEMS CAN
BE CALCULATED AT 70%. SHOW AN ESTIMATED QUANTITY IN BID COLUMN
CORRECT QUANTITIES BROUGHT FORWARD FROM MISCELLANEOUS QUANTITIES SHEETS
PLAN TOTALS MATCH SUPPORT DOCUMENTATION
SHOW MEASUREMENT INFORMATION AND DESCRIPTIVE REMARKS IN “REMARKS AND/OR DETERMINATION OF ESTIMATED
QUANTITIES” COLUMN.
SHEET NUMBERS AND SHEET DESCRIPTIONS ARE CORRECT
DRAINAGE SUMMARY
Use the Drainage Summary Template at [Link]
REVISE DRAINAGE SUMMARY TO INCORPORATE PREVIOUS COMMENTS AND FOR ADVANCEMENT OF DESIGN. LIST ALL
CULVERTS
ITEM NUMBER, DESCRIPTIONS, AND PAY UNITS MATCH ESTIMATE
CORRELATION WITH PLAN-PROFILE AND CULVERT CROSS-SECTIONS
STATIONING, LENGTH, DIAMETER, END TREATMENTS, SURVEY AND STAKING, PERMANENT EROSION CONTROL DEVICES, AND
GEOTEXTILE QUANTITIES SHOWN
SHOW SKEW ANGLES TO THE NEAREST 5 DEGREES (MEASURE SKEW FROM PERPENDICULAR TO CENTERLINE)
SHOW DESCRIPTOR OF DRAINAGE WORK, I.E. CULVERT STATIONING ALONG APPROACH ROAD CENTERLINE, INLET/OUTLET
DITCH LENGTHS, RIPRAP TYPES, ETC. IN REMARKS COLUMN
EARTHWORK SUMMARY
USE THE GRADING SUMMARY AND MASS HAUL DIAGRAM TEMPLATE
HTTP://[Link]/DESIGN/_DOCUMENTS/TECHNICAL_GUIDES/GRADING_SUMMARY.XLS
GRADING SUMMARY AND MASS HAUL DIAGRAM REVISED
GRADING SUMMARY IS BROKEN DOWN INTO STATION RANGES EQUAL TO APPROXIMATELY EVERY PLAN AND PROFILE SHEET
(350/700 METERS, 1000/2000 FEET)
MISCELLANEOUS SUMMARIES
TABULATION OF ALL BID ITEM QUANTITIES THAT AFFECT THE FOOTPRINT (INCLUDES EARTHWORK, SURFACING QUANTITIES,
BRIDGES, DRAINAGE ITEMS, RETAINING WALLS, GUARDRAIL, CURBS, REVEGETATION, TRAFFIC CONTROL, APPROACH ROADS,
ETC.) NOT REQUIRED FOR MINOR BID ITEMS (I.E. SIGNING, STRIPING, TEMPORARY EROSION CONTROL ITEMS, SEEDING, ETC.
(SHOW ESTIMATED QUANTITY IN BID COLUMN ONLY).
CORRELATION WITH PLAN & PROFILE OR WORK IN INDIVIDUAL SECTION AS APPROPRIATE
TABLES INCLUDE THE FOLLOWING:
STATIONING, LOCATION (LEFT, RIGHT), ITEM NUMBER, DESCRIPTION, PAY UNITS, QUANTITIES WITH TOTALS, AND
REMARKS AS APPROPRIATE
GEOMETRY
Horizontal Alignment
REVIEW THE GEOMETRY DESIGN ELEMENTS LISTED IN THE 30% DEVELOPMENT CHECKLIST AND ENSURE THAT REVISIONS
MADE TO THE PLANS ALSO INCORPORATE REVISIONS TO THOSE ELEMENTS
HORIZONTAL ALIGNMENT IS OPTIMIZED PENDING 50% REVIEW
Vertical Alignment
REVIEW THE GEOMETRY DESIGN ELEMENTS LISTED IN THE 30% DEVELOPMENT CHECKLIST AND ENSURE THAT REVISIONS
MADE TO THE PLANS ALSO INCORPORATE REVISIONS TO THOSE ELEMENTS
VERTICAL ALIGNMENT IS OPTIMIZED PENDING 50% REVIEW COMMENTS.
Horizontal and Vertical Alignment Relationships
REVIEW THE GEOMETRY DESIGN ELEMENTS LISTED IN THE 30% DEVELOPMENT CHECKLIST AND ENSURE THAT REVISIONS
MADE TO THE PLANS ALSO INCORPORATE REVISIONS TO THOSE ELEMENTS
Superelevation
REVIEW THE GEOMETRY DESIGN ELEMENTS LISTED IN THE 30% DEVELOPMENT CHECKLIST AND ENSURE THAT REVISIONS
MADE TO THE PLANS ALSO INCORPORATE REVISIONS TO THOSE ELEMENTS
Profile
PROFILE UPDATED TO INCLUDE ALL COMMENTS AND OBSERVATIONS FROM THE 30% FIELD REVIEW
REVISED VERTICAL ALIGNMENT – RECHECK ALL ITEMS BELOW WHERE CHANGES OCCURRED
Existing ground line shown and labeled
Proposed profile grade shown and labeled – maximum gradient not exceeded.
Length of Vertical Curves, K-Values, and Stopping Sight Distance shown
Grid elevations
Profile grade agrees with Typical Section grade point location
VPI’s Stations and Elevations
BEGINNING AND END OF WORK, STATIONS AND ELEVATIONS SHOWN
Culvert locations agree with plan sheets and drainage summary
Culvert symbol(s) shown
TEXT SHOWS STATION, CULVERT DIAMETER AND LENGTH, NUMBER OF BARRELS, END TREATMENT, AND PERMANENT
EROSION CONTROL DEVICES
Correct culvert symbol and scale is used
Hydraulic Information for Large Culverts, 1200mm (48”) and above (design flow, drainage basin area,
etc.)
Show revised retaining wall face outline
Show revised structure layout shape
Show low water crossings
HYDRAULICS
Review and incorporate intermediate hydraulic recommendations (from H2 activity)
Revise standard, detail, and/or special drainage plan sheets
PAVEMENTS
REVIEW AND INCORPORATE RECOMMENDATIONS FROM THE DRAFT PAVEMENT REPORT.
GUARDRAIL
GUARDRAIL TYPICAL SECTION SHOWN. PROPER SHY LINE DISTANCE BEING USED. SHOULDER WIDENING INCLUDES REQUIRED
DISTANCES FROM BACK OF POSTS TO HINGE POINT. IF MAJORITY OF POSTS NEED TO BE LENGTHENED, POST DETAIL CHANGED
AND SPECIAL CONTRACT REQUIREMENTS AMENDED.
TERMINAL SECTION CHOSEN IS APPROVED BY THE MAINTAINING AGENCY
BARRIER SELECTION CONSIDERED DISTANCE TO FIXED OBJECTS AND BARRIER DEFLECTION
ENVIRONMENT
REVIEW ENVIRONMENTAL DOCUMENTS AND INCORPORATE THE MITIGATION MEASURES INTO THE DESIGN.
SUPPORT THE ENVIRONMENTAL PROCESS AS NECESSARY
PERMANENT SIGNING
INCLUDE DETAIL AND SPECIAL DRAWINGS
PRELIMINARY SIGNING LAYOUT PLAN
ROAD APPROACHES
FINAL HORIZONTAL AND VERTICAL ALIGNMENTS DEVELOPED FOR PUBLIC INTERSECTION APPROACH ROADS
FINALIZE LOCATION OF MINOR APPROACH ROADS. STANDARD ROADWAY CONNECTION SYMBOL WITH TYPE, CLASS, MAINLINE
STATIONING, AND DESIGN GRADE SHOWN FOR MINOR APPROACH ROADS
APPROACH ROAD PROFILES AND RADII DESIGNED ACCORDING TO THE APPROACH ROAD TYPICAL SECTION TEMPLATE
HTTP://[Link]/DESIGN/TEMPLATEFILES/
PARKING AREAS
LAYOUT DETAILS FOR PARKING AREA(S) DEVELOPED, INCLUDING SLOPES, STALLS, ETC. ALL ELEMENTS OF DESIGN
AFFECTING THE FINAL FOOTPRINT ARE DEVELOPED. NUMBER OF ACCESSIBLE SPACES APPROPRIATE FOR TOTAL NUMBER OF
PARKING AREA SPACES.
PARKING AREA PLANS CHECKED FOR SUFFICIENT TURNING AND BACK-UP MOVEMENT WIDTHS. SUFFICIENT STALL AND AISLE
WIDTHS.
MEETS AMERICANS WITH DISABILITIES ACT (ADA) REQUIREMENTS
EROSION CONTROL
PRELIMINARY EROSION CONTROL PLAN LAYOUT SHEETS DEVELOPED SHOWING TEMPORARY AND PERMANENT EROSION
CONTROL DEVICES. DEVELOP EROSION CONTROL DEVICES IN SUFFICIENT DETAIL TO IDENTIFY ALL IMPACTS TO THE FINAL
FOOTPRINT.
Incorporate CFLHD erosion control Details showing the typical materials, installation, and dimensions of
the erosion control devices proposed. Identify additional erosion control Specials and continue
development.
PRELIMINARY SEDIMENT BASINS DESIGNED, INCLUDING COMPUTATIONS ON THE SIZE REQUIREMENTS FOR THE BASINS.
MAJOR STRUCTURES
PRELIMINARY RETAINING WALL LAYOUT SHEETS DEVELOPED IN SUFFICIENT DETAIL TO IDENTIFY ALL IMPACT TO THE FINAL
FOOTPRINT.
LAYOUT SHEETS FOR LARGE CULVERTS (I.E. REQUIRE HEADWALL, SPECIAL DETAILS) ARE DEVELOPED IN DETAIL TO IDENTIFY
ALL IMPACT TO FINAL FOOTPRINT.
Update temporary shoring to accommodate traffic and facilitate construction
INCORPORATE FINAL BRIDGE TS&L, PENDING FINAL HORIZONTAL AND VERTICAL ALIGNMENT APPROVAL
UTILITIES
LOCATIONS OF ALL KNOWN EXISTING AND PROPOSED UTILITIES SHOWN ON PLAN VIEW AND DETAIL SHEETS
PLANS REFLECT ALL UTILITY CONFLICTS (EXISTING AND PROPOSED)
UNDERGROUND UTILITY SURVEY COMPLETED, IF NECESSARY. TEST BORINGS TAKEN
HEIGHT CLEARANCE FOR OVERHEAD UTILITIES FIELD CHECKED
DEVELOP A UTILITY ACCOMMODATION/RELOCATION PLAN. THIS ACTIVITY WILL CONTINUE THROUGH THE 95% DESIGN
DEVELOPMENT PHASE
STANDARD DRAWINGS
Applicable FLH Standard Drawings included, current version
Applicable CFLHD Detail Drawings included, current version
ROADWAY CROSS-SECTIONS
CUT AND FILL SLOPES REVISED IN ACCORDANCE WITH THE GEOTECHNICAL MEMORANDUM, ADJUSTED TO BEST FIT THE
TOPOGRAPHY, MINIMIZE ENVIRONMENTAL AND VISUAL IMPACTS, AND MINIMIZE OVERALL CONSTRUCTION COSTS.
Cross-sections match Typical Section
Final cross-section locations are included for intermediate stations at all changes in subgrade width (i.e.
guardrail terminal locations, culvert inlets, curve widening, pullouts, etc.). Locate changes in template
width on 10 or 20 meter (25’ or 50’) stations where possible. Provide cross-sections on 10 meter (25’)
intervals through retaining walls and on centerline curves with a radius of 75 meters (250’) or less. Cross-
sections reflect the stations to be reference hubbed. Delete all extraneous cross-sections.
DITCH WIDENING AT CULVERT INLETS INCORPORATED, INCLUDING WIDTH TRANSITIONS
WIDEN DITCHES AT END OF CUTS – TRANSITION FROM CUT TO FILL (I.E. FLARE DITCH AND FLATTEN CUTSLOPE)
INCORPORATED.
Existing ground
Proposed cross-section showing all structural section layers
Curve widening, paved ditches, curbs, retaining walls, guardrail, etc. is incorporated
Slope ratios for all slopes outside of subgrade shoulder
Superelevation rates (m/m or ft/ft) between subgrade shoulders
Station, design grade, subgrade, and original ground elevations
Centerline symbol
Horizontal location of existing and proposed Right-of-Way limits
Horizontal and vertical location of utilities
Guardrail symbol
Retaining wall shape
Grid elevations and offset distances
CULVERT CROSS-SECTIONS
Cross-sections match Typical Section
Cross-sections show end treatment, including riprap and inlet and outlet ditches
Culvert is located to match the natural stream gradient and proper cover is achieved
Culverts station and skew agree with plan and profile sheet
Text shows station. Culvert slope shown on culvert cross-section with an arrow indicating direction of
flow.
Culvert is drawn proportional to grid
Existing ground
Proposed cross-section (drawn along alignment of culvert)
Slope ratios shown for all slopes outside of subgrade shoulder
Superelevation rates (m/m or ft/ft) between subgrade shoulders
Horizontal location of existing and proposed Right-of-Way limits shown
Horizontal and vertical location of utilities shown
SPECIFICATIONS
DEVELOP DRAFT SPECIFICATIONS FOR ALL ITEMS OF WORK. INCLUDE ALL APPROPRIATE UP-TO-DATE SPECIFICATIONS FROM
THE LIBRARY OF SPECIFICATIONS.
INCLUDE SPECIFICATIONS FOR LIMITS ON CONSTRUCTION OPERATIONS, INCLUDING DATES AND ENVIRONMENTAL
COMMITMENTS
PROJECT SPECIFIC SCRS ARE HIGHLIGHTED OR REDLINED IN COPIES DISTRIBUTED FOR FHWA REVIEW. CLEAN COPIES (NO
REDLINE OR HIGHLIGHT) PROVIDED FOR EXTERNAL DISTRIBUTION
INCORPORATE RECOMMENDATIONS FROM GEOTECH, HYDRAULICS, BRIDGE, MATERIALS, SAFETY, AND PARTNER AGENCIES
INCORPORATE COMMENTS FROM PREVIOUS REVIEWS, COMMUNICATION, ETC.
ESTIMATE
50% COST ESTIMATE
ESTIMATE TO INCLUDE ALL PAY ITEMS, INCLUDING: EARTHWORK, SURFACING QUANTITIES, DRAINAGE ITEMS, RETAINING
WALLS, GUARDRAIL, CURBS, REVEGETATION, ETC. ALL BID ITEMS AFFECTING THE FOOTPRINT HAVE TABULATIONS AND
MINOR BID ITEMS ARE ESTIMATED.
UPDATE PRELIMINARY COST ESTIMATE FOR BRIDGE ON SQUARE AREA BASIS
CONTINGENCY IS INCLUDED IN BID ITEM ROUNDUPS
DISTINGUISH MATERIAL QUALITY AND SMOOTHNESS INCENTIVES (USE FP AND SCRS FOR COMPUTATION OF INCENTIVES,
ENGINEER’S ESTIMATE DOES NOT COMPUTE THEM CORRECTLY)
DISTINGUISH CONTRACT QUANTITY BID ITEMS
DBE/WBE INCENTIVE NOT INCLUDED IN ESTIMATE
UNIT PRICE ANALYSIS FOR ALL PAY ITEMS
Cost estimate may be provided in a spreadsheet format or Engineer’s Estimate program
Verify that the estimate is within the programmed amount
PERMITS
DRAFT PERMIT APPLICATION, DRAWINGS, FORMS, AND DATA DEVELOPED (I.E. 404 AND STATE 401 PERMIT APPLICATIONS)
IDENTIFY AND RESEARCH THE NEED FOR PERMITS
DELIVERABLES
50% PLANS
50% SPECIFICATIONS
50% COST ESTIMATE
REVISED UNIT PRICE ANALYSIS FOR ALL BID ITEMS
FIELD REVIEW
SC50 activity - Alignment Staking For 50% Field Review
Alignment staked on 100 foot (40 meter) stations for tangents and 50 foot (20 meters) for curves. As a
minimum stake the beginning, end, and center point on short curves. Limits of staked alignment are as
needed.
Topography is checked by visual observation, hand level, and cloth tape by designer at critical
locations to confirm aerial topography
Prepare agenda for field review
Prepare a list of discussion topics for the field review
REVIEW THE DESIGN AT ALL PROPOSED NATURAL DRAINAGES AND DITCH RELIEF CULVERT LOCATIONS
REVIEW ALL IMPACTS TO THE FINAL FOOTPRINT
Review intersections, mailbox areas, wall areas, etc.
Produce a master redlined plan set with field review comments for inclusion in the 70% design
Prepare trip report
POST 50% ACTIVITIES
Activities to be conducted between the 50 and 70 percent reviews so data can be incorporated into the
70% PS&E package.
REVISE THE HORIZONTAL AND VERTICAL ALIGNMENTS AND ALL OTHER ELEMENTS OF THE WORK THAT AFFECT THE FINAL
FOOTPRINT; UPDATE THE FOOTPRINT IMPACT; AND SUBMIT THE PLAN & PROFILE SHEETS AND CROSS-SECTIONS FOR REVIEW
AND APPROVAL PRIOR TO FINALIZING THE RIGHT-OF-WAY PLANS
REVEGETATION NEEDS
DETERMINE SEED, PLANT, AND FERTILIZER TYPES FOR WORK AREAS DISTURBED BY THE PROJECT, INCLUDING WASTE,
BORROW, AND ROADWAY OBLITERATION AREAS.
DRAFT SEED MIXTURES DETERMINED
SEED PRODUCERS CONTACTED TO DETERMINE AVAILABILITY.
SEEDING SEASONS, FERTILIZER REQUIREMENTS, METHOD OF SEEDING, APPLICATION RATES, MULCH TYPE, ETC.
DETERMINED BASED ON DISCUSSIONS WITH CLIENT OR MAINTAINING AGENCY AND PRODUCT SUPPLIERS.
DRAFT PLANTING STOCK DETERMINED
NURSERIES CONTACTED TO DETERMINE AVAILABILITY.
PLANTING SEASONS, FERTILIZER REQUIREMENTS, METHOD OF PLANTING, WATER REQUIREMENTS, STAKING, BACKFILL,
AND ETC. DETERMINED BASED ON DISCUSSIONS WITH CLIENT OR MAINTAINING AGENCY AND PRODUCT SUPPLIERS.
TREES (EXISTING OR PROPOSED) NOT ENCROACHING INTO CLEAR ZONE.