Compressor Autonomous Checklist

This document provides a monthly checklist for an air compressor system at Daikin Electronic Devices Malaysia Sdn. Bhd. It lists 16 items to check including: 1) Ensuring the main power supply board is free from dust; 2) Checking for blackening on MCB/DB cables; and 3) Verifying the compressor surface is free from dirt, dust, and rust. Daily checks include oil level and temperature readings, while weekly checks involve floor cleaning and monthly running hour verification.

Uploaded by

sambasivamme
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
434 views1 page

Compressor Autonomous Checklist

This document provides a monthly checklist for an air compressor system at Daikin Electronic Devices Malaysia Sdn. Bhd. It lists 16 items to check including: 1) Ensuring the main power supply board is free from dust; 2) Checking for blackening on MCB/DB cables; and 3) Verifying the compressor surface is free from dirt, dust, and rust. Daily checks include oil level and temperature readings, while weekly checks involve floor cleaning and monthly running hour verification.

Uploaded by

sambasivamme
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

DAIKIN ELECTRONIC DEVICES MALAYSIA SDN. BHD.

MONTH :

MONTHLY CHECKLIST
AIR COMPRESSOR SYSTEM Department : Facility

1 Main Power Supply board (DB) free from dust. D

2 Check MCB /DB cable - should not blackened. D

3 Compressor surface to be free from dirt, dust and rust. D

Check all valve in open condition for a system prior


4 D
operation.

5 Main compressor display panel to be free from dust. D

6 No water leaking around compressor area. D

7 Air filter - romove / clean trapped dust before operation. D

Oil level checking.


8 (be sure that oil level is kept between 2 red lines during D
operation)

9 Oil leaking check around oil tank, piping and fittings. D

Discharge air Temperature during operation.


10 D
(must be between 65 to 100°C and reading must take)

Ambient Temperature during operation.


11 D
(must be < 45°C and reading must take)

Check final load pressure after "AUTOSTOP".


13 D
(shall be min.0.71 MPa and Reading must take)

14 Check all Pressure Gauge and reading must show 7 bar. D

12 Air relief valve to be checked. D

13 Motor abnormal noise check. D

14 Floor Cleaning W

15 5S D

16 Running hour D

Checked By Technician

Verified By Supervisor / Engineer


(R) Repair
(X) Not Good (√) Good /Checked (D) Daily (W) Weekly
(S) Service

(signature)