Buttu Batu HEPP Procurement Timeline

The document outlines the procurement schedule for the Buttu Batu HEPP 2 x 100 MW project from November 2018 to May 2019. Key activities include: - Invitation to bidders from December 3-7 - Tender document retrieval period from December 10-12 - Explanation to bidders from December 18-25 including an office explanation on December 18 and site visit from December 19-25 - Submission of bidder proposals from December 26 to April 16 - Opening of documents on April 16 - Evaluation of bidder proposals from April 17-23 - Clarification and negotiation period from April 24-26 - Award decision on April 26 - Contract discussion agreement from April

Uploaded by

anisya hamdan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
106 views1 page

Buttu Batu HEPP Procurement Timeline

The document outlines the procurement schedule for the Buttu Batu HEPP 2 x 100 MW project from November 2018 to May 2019. Key activities include: - Invitation to bidders from December 3-7 - Tender document retrieval period from December 10-12 - Explanation to bidders from December 18-25 including an office explanation on December 18 and site visit from December 19-25 - Submission of bidder proposals from December 26 to April 16 - Opening of documents on April 16 - Evaluation of bidder proposals from April 17-23 - Clarification and negotiation period from April 24-26 - Award decision on April 26 - Contract discussion agreement from April

Uploaded by

anisya hamdan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Procurement Schedule for Buttu Batu HEPP ( 2 X 100 MW )

ID Description November 2018 Duration December 2018 January 2019 February 2019 March 2019 April 2019 May 2019
11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27
1 1 Invitation to Bidder 5 days 12/3 12/7
Invitation to Bidder

2 2 Tender Document Retrieval 3 days 12/10 12/12


Tender Document Retrieval

3 3 Explanation To Bidder 6 days? 12/18 12/25

4 3.1 Explanation in Office 1 day? 12/18 12/18


Explanation in Office

5 3.2 Site Visit 5 days 12/19 12/25


Site Visit

6 4 Submission of Bidder Proposal 4 mons 12/26 4/16


Submission of Bidder Proposal

7 5 Openning Document 0 days 4/16


Openning Document

8 6 Evaluation Bidder Proposal 1 wk 4/17 4/23


Evaluation Bidder Proposal

9 7 Clarification and Negotiation 3 days 4/24 4/26


Clarification and Negotiation

10 8 Award 0 days 4/26


Award

11 9 Contract Discussion Agreement ( CDA ) 5 days 4/29 5/3


Contract Discussion Agreement ( CDA )

12 10 Sign Contract 1 day 5/6 Sign Contract

Page 1