Procurement Schedule for Buttu Batu HEPP ( 2 X 100 MW )
ID Description November 2018 Duration December 2018 January 2019 February 2019 March 2019 April 2019 May 2019
11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27
1 1 Invitation to Bidder 5 days 12/3 12/7
Invitation to Bidder
2 2 Tender Document Retrieval 3 days 12/10 12/12
Tender Document Retrieval
3 3 Explanation To Bidder 6 days? 12/18 12/25
4 3.1 Explanation in Office 1 day? 12/18 12/18
Explanation in Office
5 3.2 Site Visit 5 days 12/19 12/25
Site Visit
6 4 Submission of Bidder Proposal 4 mons 12/26 4/16
Submission of Bidder Proposal
7 5 Openning Document 0 days 4/16
Openning Document
8 6 Evaluation Bidder Proposal 1 wk 4/17 4/23
Evaluation Bidder Proposal
9 7 Clarification and Negotiation 3 days 4/24 4/26
Clarification and Negotiation
10 8 Award 0 days 4/26
Award
11 9 Contract Discussion Agreement ( CDA ) 5 days 4/29 5/3
Contract Discussion Agreement ( CDA )
12 10 Sign Contract 1 day 5/6 Sign Contract