CHECK LIST FOR COMMISSIONING OF FM200 SYSTEM
IR Ref. No.: Date:
Ref. Documents: Discipline:
Area/Location: Element:
SN DESCRIPTION Y N N/A Remarks
1 Check all materials installed are as per approved material submittal.
2 Check the drawings used for installation are approved.
3 Check for the continuity of Fire Cables before termination
4 Check for the power supply of FM 200 Control panel
5 Check the first stage activation of smoke detector
6 Check for second stage activatin of smoke detectors
7 Check for the signal in Fire Main Panel
8 Check for the functionality of Abort Switches
9 Check for the functionality of Manual release station
10 Check for theCylinder Solenoid functionality
11 Check for the interface with Building Main Fire Alarm Control Panel
Remarks (if any):
Sub-Contractor Representative Main Contractor Representative Consultant/Client Representative
Name:
Signature:
Date: