0% found this document useful (0 votes)
238 views2 pages

Data: Rate Analysis Unit 1 RMT A. Materials:: R.C.C Hume Pipes

The document provides a detailed rate analysis for supplying and laying 450 mm diameter R.C.C Hume Pipes, including material costs, labor, and contractor's profit. It outlines the costs associated with materials like cement and steel, as well as labor for laying the pipes. The total cost for laying 10 joints is calculated to be Rs. 4,454.66, with a rate per joint of Rs. 445.46.

Uploaded by

mahipal287
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
238 views2 pages

Data: Rate Analysis Unit 1 RMT A. Materials:: R.C.C Hume Pipes

The document provides a detailed rate analysis for supplying and laying 450 mm diameter R.C.C Hume Pipes, including material costs, labor, and contractor's profit. It outlines the costs associated with materials like cement and steel, as well as labor for laying the pipes. The total cost for laying 10 joints is calculated to be Rs. 4,454.66, with a rate per joint of Rs. 445.46.

Uploaded by

mahipal287
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

և₩֏₩և

R.C.C Hume Pipes:

a) Supplying Spigot Pipes 450 mm dia NP3 Class SSP


DATA: RATE ANALYSIS UNIT 1 Rmt
A. MATERIALS:
Sl. No Particulars Unit Quantity Rate Amount in Rs.

Cost of Pipes as per SSR in page 19 to 26 of [Link] Rmt 1 1,872.00 1,872.00


Deduct R1= Variation in cost due to change in cost of M.S. Rods ( S2- S1)/1000 X Ws
Where S1 = Basic Cost of M.S. Rods as per SSR in Page 19 to 1.00 MT 45000.00
26 of Public Health items
S2 = Cost of M.S. rods at the time of Estimate 1.00 MT 45000.00

Ws= Weight of M.S. Rods required per meter of pipe as 1.00 kg 5.48
per IS:458/2003 (kg)
INCREASE FOR MILD
Steel required per RMT as per IS 458/2003 STEEL
Longitudinal steel in kgs 0.780 0.780
Spiral steel in kgs 3.790 4.245
Total steel required including increase for mild steel 5.478
or say 5.48 kgs
Therefore R1= Variation in cost due to change in cost of M.S. Rods ( S2- S1)/1000 X Ws =
R1 = ( 45000 - 45000 )/ 1000 X 5.48 1.00 RM 0.00

Deduct R2= Variation in cost due to change in cost of Cement ( C2- C1)/1000 X Wc
Where C1 = Basic Cost of Cement as per SSR in Page 19 to 26 1.00 MT 4750.00
of Public Health items
C2 = Cost of Cement at the time of Estimate 1.00 MT 4750.00
Wc= Weight of Cement required per meter of pipe in kgs
Cement required per RMT as per IS 458/2003
Thickness of Pipe = 75 mm
inner area 0.1590431 sqm
outer area 0.2827433 sqm
area of pipe 0.1237002 sqm
Qty of cement per RMT with CC-M35 @kgs/cum 450 55.665096 kg or say 55.67

Therefore R1= Variation in cost due to change in cost of M.S. Rods ( S2- S1)/1000 X Ws =
R1 = ( 4750 - 4750 )/ 1000 X 55.67 1.00 RM 0.00
Revised cost = Initial cost +R1+R2 1872.00
Total cost 1,872.00
[Link] for contractor's profit and overheads @ 13.615% 254.87
Rate per Rmt including Contrators profit & overheads Total 2,126.87
IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.

DATA: Consider 10 joints for analysis.


Cement : 248kg Sand : 0.25 cum
Hemp yarn : 2.20 kg
2.5 Masons & 3 mazdoors considered for 10 joints.
1mazdoor for curing @ daily 1 hour for one week.

DATA: RATE ANALYSIS UNIT : 10.00 Joints


A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement kg 174.00 5.30 922.20
2 Sand (Screened) cum 0.22 760.00 167.20
3 Hemp yarn kg 1.27 72.00 91.44
Total cost of Materials Rs: 1180.84

B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00

C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.00 450.00 900.00
2 work inspector Day 1.00 565.00 565.00
3 mazdoor Day 3.00 425.00 1275.00
Total cost of Labour Rs: 2740.00
labour component/unit qty 274.00
Add contractor's profit and overhead charges 13.615% 37.30
labour component/unit qty (including contractor's profit) 311.30

ABSTRACT:
A. Cost of Materials Rs: 1180.84
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 2740.00
Total Rs: 3920.84
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 533.82
Total cost for 10.00 Joints Rs: 4454.66
Rate per joint (A+B+C+D)/10.0 Rs. 445.46

Note: (1) For NP3 Class - 10% extra over the rates of NP2 Class NP3 Class Rs. 490.01
(2) For NP4 Class - 20% extra over the rates of NP2 Class Joint

You might also like