Installation Notes For Generac Air Cooled Generators
Installation Notes For Generac Air Cooled Generators
DISCLAIMER: Only Generac’s official documents for the correct model and serial number of the equipment
you are installing should be relied upon. These technical notes are intended to be helpful as a secondary
source when you are out in the field.
1
Table of Contents: Page Number
Permits & Applications 3
Generac Equipment and Accessories 4
Pick Up and Delivery 7
Site Selection and Preparation 8
Fuel Requirements & Pipe Sizing 20
Transfer Switches 32
Basics of How the System Works 34
How to Wire Switches 40
How to Wire the Genset 50
Activation 63
Initial System Tests 67
Loadshedding/SMM Smart Management Modules 73
Smart AC Modules 80
Load Shedding RTSY/T/W-R/P/C, RTSB, & I 81
Prolonged Outages 88
2
Do NOT modify any equipment.
Do NOT install anything that is not to code.
Any $$ you think you will save on your install by modifying equipment, NOT following the recommended
installation procedures, or going against local code, may be a safety issue for your customer, may void
warranties, and may not pass required inspections.
A Generator installation should be a very easy job. Just follow the manufacturer’s instructions, local
requirements, and you should have no problems.
Read ALL Manuals and Install Guides before attempting an install.
The Local Code Office has the final say on your install.
All Towns have different requirements. Check with the local code office before submitting a final quote
to your customer.
Brighton and Perinton are two of the more restrictive towns in our area.
Attached are examples of permit for the Town of Perinton and, if you have a NatGas installation
examples of the required RG&E Forms. NYSEG & Other Utilities may have different requirements.
Elevated Pressure Commitment Letter (RG&E) – Residential You probably will not need this
because Generac Evolution Series Air-cooled generators can run on 3.5” to 5” Water Column
Natural Gas Appliance Inventory (RG&E) – Residential Generator Installation This should be filled
out for all NatGas installations
RG&E is looking to see that the total BTU requirements for all appliances and the generator don’t exceed
350,000 BTU.
If exceeded, they may have to increase the pressure to the residence. There is a cost for that. It’s
usually between $150 - $350.
The Town may also ask for things like - Certificates of Liability & Worker’s Comp Site drawing showing
generator placement, nameplate and spec sheet information.
3
Equipment
Generators:
Generac Air-cooled, QT, Protector Gaseous, and Protector Series Diesels are designed to work with
Generac RTS Switches.
QT, Protector Gaseous, and Protector Diesel Gensets
4
Transfer Switches
The Whole-House Transfer Switch amperage must be equal to or greater than the generator output or
service amperage, whichever is greater.
Air-cooled Generators 6 to 22kW will put out 25 to 91.6 Amps.
GenReady Panel
Used in New Construction or Service upgrades.
It replaces the Main Panel in the house.
It's a 200 Amp service with a 125 Amp Transfer Switch.
There is a built-in transfer switch in the middle of the panel.
You have 10 non-protected circuits on the top of the panel and 18 to 30 protected circuits
(with tandem breakers) on the bottom of the panel.
5
RTSJ200A3 Switch
This switch is basically a combination of the RTSY200A3 and the RTG16EZA1 switches.
It's a 200-Amp Whole House Service Entrance Switch that load sheds to a 16-circuit
priority load center. This Switch will become obsolete in 2015.
ELECTRICAL ITEMS
Liquid Tite Conduit,
Approved Conduit for inside the building,
Appropriate-sized main AC Wire (Black, Red, White, Green),
Correct size control wire (2-Yellow, White, Red, Blue, Black),
(Generac has Installation cable and Control cable)
Wire Nuts, Fittings.
EZ Switch - 50A double Pole Breaker for the 8 and 11kws, or a 70A double-pole breaker for the 16kWs
15A single pole breaker for GenReady)
TOOLS NEEDED
General SAE and Metric hand tools,
Wrenches, Sockets, Screwdrivers,
Standard Electrician’s hand tools,
Drill and Bits (for routing and mounting conduit),
4mm Allen Wrench,
3/16" Allen Wrench,
Manometer
Meter capable of measuring AC/DC Voltage and Frequency.
Level
6
Optional Items You May Purchase from Better Power
Starting Battery,
Warning Stickers,
Cold Weather Kit,
Remote Monitors,
Brownout Kit,
PMM Kit and Modules, also SymCom Timers
SMM Smart Management Modules & Smart AC Modules
SoftStarts
Fascia Kit,
3" GenPad,
Generator Transport Cart.
250, 500, or 1000 roll of Generac Control Wire, or 100, 250, 500,or 1000’ Generac Install Cable (good
for installs up to 113')
Also a Ground/ Neutral Bar Kit.
Delivery
You can pick up for free at our Rochester C&M Forwarding Warehouse, or have your system delivered.
There is a delivery charge from our Rochester Warehouse, or if we direct ship from the factory there
is no charge for delivery. – If you are in the Rochester area we also have a cart to rent (if you are
local) -- try before you buy.
Safety Tip for the Generac Generator Cart - Use the long strap from a ratchet tie down. Hook the
end to the Generator Pad, when the unit is raised tie the other end off to the cart handle. This will
prevent the handle from flipping over accidently.
The PowerPact may be moved with a 2 wheeled cart. Leave it on the pallet & place cardboard
between the generator & cart. At the site the generator must be lifted off the pallet NOT dragged off.
7
Site Selection and Preparation
This section can be found on page 10 of the Installation Guidelines for Air-cooled Generators.
Location of Generator
•Air-cooled generators should be located as close as possible to the transfer switch and fuel supply.
•There must be 5 feet of clearance around the gas meter.
•Leave adequate room around the area for service access (check local code),
•Place high enough to keep rising water from reaching the generator.
•Install the generator, in its protective enclosure, outdoors, where adequate cooling and ventilating air is
always available.
Not only too close to a window but how about three windows! Maybe a few more plants and you won’t notice the windows.
Mounting
•The generator comes with a composite pad.
•You can place the generator with the composite pad on pea gravel or a concrete pad.
•Check local codes to see what type of base is required.
Note: Whatever mounting you choose, the generator must be level within ½”.
8
Generac doesn't recommend a wood box platform.
9
And the internet say’s - The shed that this generator is mounted in greatly reduces the noise level.
NO…..NO……NO!!!!!!!
That's better
10
Wood Deck- Not
recommended
Allow sufficient room on all sides of the generator for maintenance and servicing.
DO NOT install under wooden decks or structures unless there is at least four (4) feet of clearance
above the generator, three (3) feet of clearance on sides and front, and 18 inches of clearance at back
of unit.
Install the unit where rain gutter down spouts, roof run-off, landscape irrigation, water sprinklers or
sump pump discharge does not flood the unit or spray the enclosure, including any air inlet or outlet
openings.
11
I guess Koehler's don't need air flow.
This one may be ok, but ugly … but then look at the Service
Entrance NEMA-3R Switch.
12
• Install the unit
where rain gutter down
spouts, roof run-off,
landscape irrigation, water
sprinklers or sump pump
discharge does not flood
the unit or spray the
enclosure, including any air
inlet or outlet openings.
Install the generator as close as possible to the fuel supply, to reduce the length of piping.
Install the generator as close as possible to the transfer switch.
If you have to choose between Fuel & Switch, install closer to the Fuel.
REMEMBER THAT LAWS OR CODES MAY REGULATE THE DISTANCE AND LOCATION.
13
The genset must be installed on a level surface. The base frame must be level within 1/2 inch all
around (Nexus manual says 2”).
The generator is typically placed on pea gravel or crushed stone.
Pea gravel - must be 4" (102mm) deep, compacted and level. You may build a frame around the area
that you want to install the generator. Also, use something to inhibit weed growth through the gravel.
Check local codes if a concrete slab is required. If a concrete base slab is required.
Concrete base slab which should exceed the length and width of the generator by a minimum of six
(6) inches (0.152 meters) on all sides.
There are four mounting holes in the base of the generator to secure it to the concrete.
3" GenPad - Level and compact the ground where the pad will be placed. Lay the GenPad on the
ground. Bolt the generator to the pad.
14
Looks nice but pavers eventually get out of level, and the
generator will walk if it’s not bolted down.
15
Very small concrete pad.
16
I hope this isn’t PVC ??? And NEMA-3R Switch?
Note: Southwest Research Institute testing approves 18-in. (457mm) installation minimum from
structure. Southwest Research is a nationally recognized third party testing and listing agency.
Southwest Research Institute Decal (located inside the generator, next to the generator's data decal)
[Link]
17
18
DO NOT Install Inside the House!
19
Gaseous Fuel Requirements and Installation
This section can be found in:
Page 16 thru 21 in the Installation Guidelines Air-cooled Generators
Page 7 thru 9 in the Generac Generator Sizing Guide
Most Generators using gaseous fuels have a higher kW rating on Propane vs Natural Gas.
Generac Guardian Series Air-Cooled (Evolution) generators require 3.5 to 7" of water column for
Natural Gas, and 10 - 12" Water column for Liquid Propane Vapor.
For NatGas, verify that the meter is capable of providing enough fuel flow to include all household
appliances and other loads.
Order New Gas Meter from the Utility if it needs to be upsized (Customer may have to place the
order)
LP Gas Requirements
With LP Gas, use only the vapor withdrawal system. This type of system uses the vapors formed
above the liquid fuel in the storage tank.
The minimum LP tank size is 250 gallons unless unit calculations dictate the use of a larger tank.
Vertical tanks which are measured in pounds will not usually meet the minimum requirements. A
1050LB vertical tank size is minimum required.
20
Fuel Consumption Chart from Sizing Guide
(Also see the Spec Sheet for the Generator)
21
Converting from NatGas to LP
•The Guardian Series Air-cooled Generators are configured at the factory for NatGas.
•To switch over to LP, turn the orange fuel conversion knob towards the marked fuel source arrow until it
stops (clockwise).
• If needed, push in and use pliers to break free in the correct direction of the arrow.
• The fuel knob will rotate 180deg and slide into the mixer body when converting to LP.
•The generators are run at the factory with NatGas; sometimes the O rings seat themselves when the
Generator heats up.
• If the orange knob breaks off when you turn it with pliers, call us and we can get a replacement. (Generac
says they have fixed the problem.)
The knob is located at the bottom of the fuel mixer for the single cylinder engines (as shown). It is
located on the top for the V-twin engines.
Turn the valve 180 degrees in the direction of the arrow until it stops. Use pliers only if needed.
22
PowerPact – Use pliers to squeeze clamp and remove hose from fuel inlet
Remove the NatGas Jet and insert the Propane Jet, reinstall the hose.
23
Gas Pipe Sizing
Gas pipe under-sizing is one of the most commonly made mistakes. A properly sized gas
pipe is critical to the proper operation of the generator.
Gas line connections should be made by a certified plumber familiar with local codes.
If you are not capable of doing NatGas or LP work, please partner up with a Certified NatGas/LP
installer.
OVERSIZE the pipe rather than undersize.
If you have the pipe oversized it creates a fuel reservoir at the generator and helps it start better.
The Generator inlet size and Flex Hose have no bearing on the proper gas pipe size.
Do not reduce the fuel pipe size exiting the secondary regulator, unless necessary to accommodate
the 1/2" or 3/4" flexible fuel line that is shipped with the generator. This may potentially cause
starting or performance issues.
See Charts from Sizing Guide & Manuals - Pipe Sizes given are for Black Iron Pipe ONLY. Other
types of pipe may require a different size pipe.
24
PowerPact NatGas 5-7" WC
25
PowerPact Propane
26
Gas Regulator Issues
The Primary Regulator for the propane supply is NOT INCLUDED with the generator.
Note: LP Pipe sizes given in the manual are using a second stage regulator.
When sizing a secondary regulator for LP or High Pressure NatGas, be sure to note the Maximum
individual load capabilities which will be lower than the total capacity. This could impact generator
starting performance issues.
Second stage regulators function to further decrease pressure to a usable level for appliance demand. These
regulators work with the lower pressures delivered by first stage regulators and in turn, lower the pressure
even more so that the propane will adequately and safely supply the demand of the appliances
27
The Demand regulator on the 8kW single cylinder generator only has one side. The twin cylinder 11 - 20kW
units have a two sided regulator.
A - Is a Full Flow Shutoff Valve. B - Is a Full Flow Shutoff Valve with a manometer port for making fuel
pressure checks without going into the generator enclosure.
28
Pipe elbows, tees, drip legs, etc. - ADD 2.5 feet (.76m) per EACH elbow, tee, etc. to the overall
calculated distance from the source to the generator. (Some local codes require you to add 5 feet.)
Do NOT install Street Elbows, they restrict the gas flow thru the pipe.
Remember the Perinton permit required you to add 5 feet for every elbow.
Most towns in our area also require the gas line to be painted.
29
Don't bend the flex hose!!
The flex hose is used for vibration and ground movement, NOT to go around corners or change
direction of the gas line. Flex hose must be horizontal NOT vertical.
Do NOT attach directly to the Generator!
30
Test for Leaks and Pressure
Check the installation for leaks by spraying all connection points with a soap solution made of
dishwashing soap and water. You should not see the solution being blown away of form bubbles. (A
gas installer may have better leak test procedures)
Check the gas pressure at the test port with a Manometer to ensure the pressure is within specified
values. If not contact the local gas supplier.
31
Transfer Switches
GenReady Info:
This section can be found in the GenReady Load Center and Transfer Switch Owner’s Manual, Page 5 and 6.
RTG-EZ Switch Info:
This section can be found in the Installation Guide For Pre-wired Automatic Switch/Load Center Models, pages
4 and 5.
RTSY/T/W, RTSR/P/C info: (RTSW & RTSC will replace RTSY/T & RTSR/P Fall 2015)
This Section can be found in the Owner’s Manual, Automatic Transfer Switch, page 4.
Switch location is up to the contractor, homeowner, and Local Code Official. Generac recommends
that a licensed electrician or an individual with complete knowledge of electricity preform the
installation and wiring of the switch and connection to the generator.
32
RTG-EZ Switches
The RTG-EZ Switches are NEMA-1 and must be mounted inside next to the main Panel
The 50A 10 & 12 Circuit Switches can be flush mounted
The NEW RTG16EZA3 Switch is NEMA-3R and has No whips.
GenReady Advanced
The GenReady Advanced Panel is NEMA-1. It’s used for new construction and to upgrade a service to
200A. A NEMA-3R model is available also
33
RTSR/P /C Non-Service Switch
The RTSR/P/C Switches are NEMA-3R and can be used inside or outside
All of RTS and GenReady switches are compatible with any Generac Air-cooled permanent standby
generator (depending on sizing requirements) - except the for the RTG switches - the 7/8kW is
compatible with 10, 12, and 16 circuit switches, 10/11kW is compatible with 12, and 16 circuit switches,
16/16kW is compatible with the 16 circuit switch. The 18/20 and 19.5/22kWs are not rated for the RTG
switches, use a RTSR/P/C switch and sub panel instead.
The 10 and 12 circuit switches are 50A and the 16 circuit switches are 100A. The wiring harness power
wire gauge is different in each switch so the output amps in the larger generators may be more than the
harness on the smaller switches is rated for.
The 14 circuit switch has been discontinued for 2015.
The RTSB & RTSI switches have Fast Loadshed to work with the Synergy Generator.
Control Wires
All Generac Generators and Switches have the same color codes and wire numbers:
N1 and N2 (Yellow) Fused 240VAC Sensing for Utility Dropout and Pickup
T1 (Blue) Fused 120VAC for Battery Charger
0 (Black) DC (-) Common Ground Wire
15B or 194 (Red) Provides (+) 12VDC for Transfer Controls (15B older Models)
23 (White) Transfer Control Signal Wire (held open to ground by the controller)
Three 5A fuses - F1 and F2 on (N1 and N2), F3 on (T1) protect the sensing and battery charger
circuits from overload.
34
Generac Control Cable is 18AWG 7 conductor TFFN 600V
90degC dry, 75degC wet, UL Listed Type
TC-ER UL1277
Probably requires 300-600V rated wire. Thermostat wire will not meet code. N1, N2, & T12 are 120V. Must meet local
code.
Transfer Operation
Generac (RTS switch) Transfer Relays are controlled by the controller in the Generator set.
The transfer relay gets 12VDC from the Generator battery via wire 15B or 194 from the generator
control board.
The 12VDC circuit is completed through the transfer relay coil and back to the controller via wire 23.
The controller holds wire 23 circuit open to ground (normally open) and the relay is de-energized.
When de-energized, the relay contacts are in their normal condition (one set open and one set closed).
The normally closed relay contacts deliver utility source power to the utility closing circuit of the transfer
switch.
The normally open relay contacts will deliver standby source power to the transfer switch standby
closing circuit only when the transfer relay is energized by the control panel in the generator.
During automatic system operation, when the generator controller senses that the utility source voltage
has dropped out (via wires N1 and N2), the controller will initiate a ten-second Line Interrupt Delay
Timer. At the end of the ten-second delay, the controller will crank and start the engine.
35
Typical Transfer Switch diagrams – 120/240V 1ph
36
37
38
Three possible configurations with On Grid Solar/Wind Systems.
The Solar/Wind Inverter MUST be installed so it does NOT see the Generator when the
Generator in online.
39
How to wire Transfer Switches
All Generac Transfer Switches have the same basic wiring.
See the Manuals, Install Guides, and Handout for detailed instructions.
40
(RTSR/P/C, RTSI)
The RTG Switches customer load leads are prewired.
41
42
Control Wires
Control wires between the switch and the generator consist of:
Utility voltage sensing wires N1 and N2,
Operating control wires #23,and 15B or 194 and 0,
And don't forget T1 120VAC for the Battery charger.
GenReady
Connect N1 and N2 to the 15A 2 pole breaker provided in the top of the load center (switch).
Connect wires 23 to Transfer, 15B or 194 to 12VDC+ and 0 to 12VDC - on the green block on the side
of the transfer switch operator.
The transfer switch operator requires a 5A fuse (supplied) in the +12Vdc for operation.
It will be necessary to install the 5A fuse in the 12Vdc supply line before it leaves the generator.
Wire T1 (battery charger) from the generator will go to the bottom right 15A Duplex Breaker (Not
Supplied) to be installed on the Generator-fed load circuit breakers.
Control circuit wire must run in a separate conduit, unless the length is 30 feet or less.
All control wires must be a minimum 300Vac rating and #14 AWG size. (Generac Control & Install
Cables are #18 AWG 600Vac rated)
THHN wire is recommended. Do not use Thermostat wire.
RTG – Prewired
The Control Wires are prewired on the RTG Switches from the 30’ whip. Note: RTG switches do not
require a 0 wire.
Circuit Breakers RTG-EZ Switch & RTSR/I Sub-Panel
Note: Some local codes may require splices to be in a separate junction box not in the main panel box.
Turn off the main breaker on the distribution panel before running any wires into the panel box.
Balance must be maintained when moving circuit locations from the main panel box to the emergency
load center.
Circuit breaker positions alternate buss bars vertically.
Circuits sharing a neutral wire should be either moved together or NOT moved.
Circuits to be removed must be protected by the same size breaker. For example, 15A to 15A, 20A to
20A. (RTG is all #12 wire so you can swap out the breakers)
In the main panel box, remove the black wire (hot) from the circuit breaker of the circuit to be
protected in the event of a power failure.
Connect it to the matching lead from the circuit breaker in the load center of the transfer switch.
All circuit wires in the transfer switch load center are color-coded and labeled for easy identification.
Trace each black (hot) wire connected and remove the corresponding white wire from the neutral
block in the main panel (from the same Romex cable).
Connect the white wire to the matching circuit number on the white (neutral) wire from the
emergency load center.
Repeat this process for the remaining circuits to be transferred to the transfer switch load center.
Use the same procedure for the RTSR/P/C Sub-Panel except it will not be prewired in the Sub-Panel.
43
44
45
46
Multiple RTS Switches
You may run into a situation where you need to switch two panels from a single generator. You can
run two RTSY/T/W/R/P/C switches together with no additional equipment. On rare occasions you may
need more than two switches.
If two RTSY/T/W or RTSR/P/C switches are required: The 1st switch is wired normally. This will be the
switch that sends N1, N1 and T1 120VAC to the generator. The second switch will have only 23,
194/15B, and 0 wires.
If more than 2 switches are required, you'll need to add a relay to the first switch. There are several
different versions of how to do this; call us for help if you need more than two switches.
Failure to add the Relay Circuit for 3 or more switches, will result in permanent damage to the Generator
Controller.
Important Note: A maximum of Ten (10) Transfers Switches can be used in this configuration.
This added Relay Circuit will work with all single and 3 phase RTS Style Switches.
47
Two RTS Transfer Switch - Wiring
48
Three to Ten RTS Transfer Switch Wiring
49
Wiring the Generator
This section can be found in the Installation Guidelines for Air-cooled Generators, page 21 thru 23.
•Do Not Install the Battery until the Switch and Generator installation is complete.
•The Generator Control board requires 12VDC to operate when the Generator is off.
•If you don’t have T1 (120V) from the switch (live) to the Generator Control board.
•The battery will be dead in 2 – 3 days.
•Remove the 7.5A fuse from the control panel and set aside.
50
RTSY/T/W, RTSR/P/C, RTSB, RTSI, RTSJ, and GenReady Switches
Run the A/C main wires (E1, E2, Neutral, and Ground as well as the control wires N1, N2, T1, 23, 0,
and 15B or 194) through the proper conduit to the generator.
All Switches
Route the conduit With Power and Control Wires into the appropriate knockout hole in the back of the
generator.
There are two knockouts on the Guardian Series in case you need to run the control wire in a separate
conduit.
51
Your wiring will come into the unit just above the gas
manifold.
52
The main A/C Standby Source wires go into the Breaker panel on the side of the generator.
E1 and E2, remove the two cap plugs behind the breaker door to the right of the main breaker.
Insert into the bottom lugs and torque to spec.
There are three screws inside the top of the breaker panel (behind the breaker door).
Removing these screws will allow the entire breaker box to be CAREFULLY pulled out.
When reinstalling be certain that the tabs on the bottom lock into place.
Use caution when working around the door, it can break or crack if stressed.
Connect the Neutral wire to the Neutral lug and torque to spec.
Connect the Ground wire to the Ground lug and torque to spec.
Torque all wiring lugs to the proper torque specs.
Torque specs for the Main Line Breaker can be found on a decal located on the inside of the Main Line
Circuit Breaker door.
53
Neutral Bonding
For installations that require the neutral to be bonded to the ground, this is to be done on the
customer connections terminals inside the generator.
Connect a suitably sized wire from the neutral bar to the ground bar.
This is normally required when the generator is the source in a separately-derived system.
It is NOT required when the generator is a backup source in a utility-supplied electrical
system with a 2-pole transfer switch. The grounding electrode for a ground rod is not to
be used either. See Ground [Link] Ground Lug will not be included on Newer Air-
cooled Units
Control Wiring
To access the terminal strips for the control wires, remove the three 5/32” Allan head screws from the
control cover.
Under the cover there is a plastic box on the backside of the controller.
Squeeze the tab (facing the back of the generator) and the cover will lift off to give you access to the
control terminal blocks.
54
55
56
57
58
59
60
Common Alarm Relay
On the low voltage side of the terminal block there is a common alarm relay connection.
This can be used to connect to a home security system to send a signal that the generator has failed
and needs service.
When the controller is powered up and there are No Alarms, the relay contacts will be OPEN.
Any Alarm (Not warning) will trigger the common alarm relay to close the contacts.
The connections are made at Common Alarm 1 (209) and common alarm 2 (210).
61
Installing the Battery
• The Required Battery for Generac Air-cooled generators is a Group 26R 525CCA or greater. Use of a
smaller battery may void the warranty. (PowerPact Group U1 300CCA or greater)
• Before installing the battery, complete the following steps:
1. - Verify that the generator has been turned off.
2. - Turn off Utility to the Transfer Switch.
3. - Remove the 7.5A fuse from the control panel.
• Battery cables are factory connected at the generator.
1. - Connect the Red Battery Cable to the positive (+) post (1st).
2. - Connect the Black Cable to the Negative (-) post (last).
3. - Install the Red Post Cover.
• DO NOT ATTEMPT to START the GENERATOR MANUALLY AT THIS TIME.
• If in an area where temperatures REGULARLY fall below 32 F, it is recommended that a Cold Weather Kit
be installed to aid in cold-climate starting.
• Synergy Note: The Automatic Voltage Regulator (AVR) has two cooling fans to cool the AVR electronics.
• The Primary fan is powered by 120V & the secondary fan is 12VDC through the controller.
• The secondary fan continues to run up to one hour after the generator has shut down.
• Proper cooling must occur before removing either the 7.5A fuse or the battery connections for
maintenance or other activities.
• If a failure occurs an alarm will be displayed.
62
Control Panel/Activation-Registration
This section can be found in the Installation Guidelines, Air-cooled Generators, page 24 through 27.
Off Button - This button shuts down the Engine and prevents Automatic Operation.
Manual Button - This button cranks and starts the engine. Transfer to standby power will not occur
unless there has been a utility failure.
Auto Button - This button activates fully automatic system operation. It also allows the unit to
automatically start and exercise the engine every seven days.
Enter Button - This button is used to make a selection from the on screen menu.
Up Arrow or Down Arrow Buttons - (Above and below the enter button) these are used to navigate
through the on screen menu.
Escape Button - This button takes you back to the previous menu item
63
Control Panel LCD Display
The Home page is the default page that will be displayed if no keys are pressed for five minutes.
This page normally shows the “current status” message and date and time.
The highest priority alarm and/or warning will also be posted on this page.
The backlight will flash when an event (Alarm) is detected. If there are multiple alarms, only the first
message will be displayed.
To clear the alarm or warning:
Nexus - press the Off button then the Enter button
Evolution – Esc-Up-Up-Esc-Down-Up-Esc-Up-Up-Enter
The display backlight is normally off.
If any key is pressed, the backlight will come on and remain on for 30 seconds after the last key is
pressed.
You do not have to wait until you are at the job site to get your activation code.
You can get it at any time after you have serial numbers for the equipment.
If you get the code before you go out to the jobsite, you can print out the report and keep it in your
customer’s file.
Since you are probably doing this online - if you are registered on Powerhouse Pro as one of
Better Power’s Contractor/Customers, go to the Powerhouse Pro site and register the generator,
switch, and any other serialized item there to add to your purchase history for the Rewards Program.
Next, you should repeat the process for any switches or other items with serial numbers that were
purchased with the generator.
You will NOT receive any more activation codes for the non-generator items. Entering these items ties
them to the generator and starts the warranty period for the generator and associated items.
64
Entering the Activation Code
Use the arrow keys and scroll to the first number of your
activation code. Press enter to select. Repeat this for the
rest of the numbers. (Use Escape to correct previous
numbers)
65
Activation is complete when all the numbers are entered
and the display shows - Select Hour (0-23)
Installation Wizard
The maintenance intervals will be initialized when the exercise time is entered.
The Factory set exercise time is Wednesday at 1:00pm. The exercise time can be changed at any time
via the edit menu.
Note: If the battery is disconnected or the fuse removed, the installation wizard will operate upon
power restoration.
The only difference is, the display will only ask for the current time and date.
PowerPact
Control Panel
Note: Damage caused by mis-wiring of the interconnect wires is Not warrant-able.
Loss of Utility power will cause either the Auto or Off or Manual buttons to flash. Whichever mode the
generator is in at the time of Utility loss.
PowerPact - Activation
Note: If the Auto button is pressed prior to activation the Auto, Off, and Manual LEDs will flash three
times indicating activation is required.
When you call or go online for your activation code you will be given a sequence of six (6) button
presses using the Auto, Off, and Set Exercise buttons.
Begin by holding the Off button for 3 seconds. All the LEDs will flash twice indicating that the
activation mode has begun.
You have 20 seconds to enter the six key sequence activation code. The Yellow Maintenance button
will flash every time you press a button.
If you take longer than 20 seconds it will time out and you must begin the activation sequence again.
If you enter the wrong code the Auto, Off, and Manual buttons will flash 3 time and you have to start
over again.
66
When the sequence is entered correctly all the LEDs will scroll from bottom to top 5 times. The Off
button will light. The Generator is ready to operate.
Setting the Exercise Timer - PowerPact
Note: Do not attempt this until the Generator is ready to be started.
The Exerciser only works in the Auto Mode.
Place the generator in Auto.
Hold the Set Exercise button for 3 seconds.
The generator will start & run an exercise cycle and confirm the setting.
The exercise time must be established at the time will want the exercise to take place.
To change the exercise time, hold the Set Exercise button for 3 seconds at the time you want the new
exercise time to take place.
67
Check Manual Transfer Switch Operation
DANGER - DO NOT attempt manual transfer switch operation until ALL power voltage supplies to
the transfer switch have been TURNED OFF!
Failure to turn off all power voltage supplies to the transfer switch will result in extremely hazardous
and possibly fatal electrical shock.
If the automatic function of the switch fails at any time, you probably do NOT want the homeowner to
operate the switch manually.
If it needs to be switched manually, that means something is broken and they should call for service!
4. NOTE THE POSITION OF THE TRANSFER MECHANISM MAIN CONTACTS BY OBSERIVING THE
MOVEABLE CONTACT CARRIER ARM.
Manual operation handle towards the top of the switch mechanism - LOAD terminals (T1 and T2) are
connected to utility terminals (N1 and N2).
Manual operation handle towards the bottom of the switch - LOAD terminals (T1 andT2) are
connected to emergency terminals (E1 and E2).
CAUTION: DO NOT use excessive force when operating the transfer switch manually, or damage
could be done to the manual handle.
Be sure to hold the handle as it will move quickly after the center of travel.
If all switch positions are correct, return the handle to the Up position and return the handle to the
storage bracket.
RTG-EZ Switch
68
RTSY/T/W, RTSR/P/C, RTSB, & RTSI Switches
RTSJ Switch
3. NOTE THE POSITION OF THE TWO SWITCHES BELOW THE TRANSFER SWITCH OPERATOR.
If the utility supply switch (left side) is ON, move the Generator supply switch (left side) to ON. The
Utility Switch should move to the OFF position.
Return the Utility switch to the ON position and the generator supply switch should move to the OFF
position.
69
Do Not send power to the house before Electrical checks/tests have been performed!
Voltage Checks
Turn ON the Utility power supply to the transfer switch using the Mainline circuit breaker (Utility
Service Disconnect Breaker).
The RTG EZ switch may require the 2-pole transfer switch breaker in the main panel to be turned on
also.
DANGER - Proceed with Caution, the transfer switch is now electrically HOT. Contact with live
terminals results in extremely dangerous and possibly fatal electrical shock.
RTG, RTSR/P/C, RTSY/T/W,RTSB, RTSI, and RTSJ switches
With an accurate AC voltmeter, check for correct voltage. Measure across ATS terminal lugs N1 and
N2. Also check N1 to Neutral and N2 to Neutral.
GenReady
Measure across the terminals of the Utility voltage sensing circuit breaker. Also check Utility voltage
sensing terminals to Neutral.
All Switches
When certain that Utility voltage is correct and compatible with the transfer switch ratings, turn OFF
the Utility supply to the transfer switch.
Set the generator to manual mode. The generator should crank and start.
Let the generator stabilize and warm up for at least five minutes.
Set the generator's main circuit breaker (CB1) to its ON or Closed position.
DANGER - Proceed with Caution, Generator Output Voltage is now being delivered to the transfer
switch terminals; the transfer switch is now electrically HOT.
Contact with live terminals results in extremely dangerous and possibly fatal electrical shock.
With an accurate AC voltmeter and Frequency meter, check the no-load voltage and frequency.
70
RTG, RTSR/P/C, RTSY/T/W, & RTSJ
Measure across ATS terminal lugs E1 and E2. Also check E1 to Neutral and E2 to Neutral.
GenReady
Measure across Generator Supply Switch terminals.
Also check each switch terminal to Neutral.
a - Frequency - 60-62Hz
b - Terminals E1 to E2 - 240-246VAC
c - Terminals E1 to Neutral - 120-123VAC
d - Terminals E2 to Neutral - 120-123VAC
Set the generator's main circuit breaker (CB1) to its OFF or Open position.
Set the generator to the OFF mode to shut down the Generator.
All Switches
Do NOT proceed until generator AC output voltage and frequency are correct and within the stated
limits.
If the no-load voltage is correct but the no-load frequency is incorrect, the engine-governed speed
may require adjustment.
If no-load frequency is correct but voltage is not, the voltage regulator may require adjustment.
71
DANGER - Proceed with Caution, Generator Output Voltage is now being delivered to the transfer
switch terminals. The transfer switch is now electrically HOT. Contact with live terminals results in
extremely dangerous and possibly fatal electrical shock.
Turn on electrical loads to the full rated wattage/amperage of the generator.
DO NOT OVERLOAD.
With the maximum rated load applied, check voltage and frequency across transfer switch terminals
E1 and E2.
Voltage should be greater than 230VAC and frequency should be greater than 59Hz.
Also verify the gas pressure remains within acceptable parameters.
Let the generator run the rated load at least 30 minutes.
With unit running, listen for unusual noises, vibration, overheating, etc.., that might indicate a
problem.
When checkout under load is complete, turn the generator’s main circuit breaker to its OFF position.
Let the generator run at no load for several minutes to cool down. Then shut it down by putting it in
the OFF mode.
72
Loadshedding
73
SMM Smart Management Modules
• SMM Modules are designed to prevent an overload on the generator when it is supplying the
customer loads.
• Up to eight loads can be managed by using SMM Modules.
• The SMM Modules manage the loads by shedding the connected loads in the event of a drop in
generator frequency (overload).
• Loads to be shed are grouped in 8 priority levels thru a setting on each SMM Module .
• Generator overload condition is determined by generator frequency.
• Loads are shed when the frequency is less than 58Hz for 3 seconds or less than 52Hz for 1/2
second (for 60Hz).
74
75
76
77
78
79
80
Load Shed Info and Wiring RTSY,RTSR, RTSB/RTSI
There is NO Load Shedding in the RTST & RTSP Switches (there is a set of Aux. Contacts to lock out a load)
RTSW & RTSC have the Smart AC Module to Loadshed up to four AC units. They install just like the OPCB Air
1 & Air 2. They will be priority 1, 2, 3, & 4. For 120/240v loads use the SMM Modules.
This Section can be found in the Owner’s Manual for Automatic Transfer Switch, pages 4 thru 6.
Also in Owner’s/Installation Manual Power Management Module (PMM) and Starter Kit.
81
Priorities 1-2, 3-4
Priority 1 and 2 have connections for both 1 air conditioner and 1 contactor (PMM).
Both an air conditioner and contactor (PMM) can be used at the same time if desired.
To control an air conditioner, no additional equipment is required. Internal relays interrupt the
thermostat 24VDC control signal to disable the air conditioner load.
Priorities 3 and 4 have connections for one contactor (PMM) only.
4 LEDs located on the OPCB will indicate when a load priority is enabled. When loads are connected,
the LEDs will be illuminated.
Any loads including central air conditioners can be controlled via a contactor (PMM) that must be
purchased separately.
Up to 4 contactors (PMMs) can be controlled by the OPCB (24VDC or 120VAC is supplied through the
OPCB to energize each contactor coil).
Generator Overload Condition
Generator overload condition is determined by generator frequency.
Loads are shed when the frequency is less than 58Hz for 3 seconds or less than 50Hz for 1/2 second
(for 60Hz).
The OPCB has a test button that forces the unit to act as if an overload has occurred.
This button operates even when the transfer signal is inactive.
Power Management Module and Kit
The Power Management Module (PMM) is not supplied with the transfer switch. You will also need a
PMM Kit consisting of a 24VAC supply class-2 power supply transformer and your 1st PMM Module.
The 24VAC Transformer mounts inside the transfer switch and connects to the OPCB :
Blue wire - OPCB Load Supply 1 terminal
Black wire - OPCB T1 terminal
White wire - OPCB Neutral terminal
Yellow wire - OPCB Load Supply 2 terminal
You may also still use the old DLM modules by using a jumper from OPCB Load Supply 1 to OPCB T1,
and OPCB Load Supply 2 to OPCB)Neutral. (This will supply the DLM modules with 120VAC)
**** CAUTION! *** The Load Supply Voltage on the OPCB terminals MUST MATCH the PMM/DLM coil voltage
or the equipment will be damaged.
82
Up to 4 contactors (PMMs) can be controlled by the OPCB (24VDC or 120VAC is supplied through the
OPCB to energize each contactor coil).
83
Generator Overload Condition
Generator overload condition is determined by generator frequency.
Loads are shed when the frequency is less than 58Hz for 3 seconds or less than 50Hz for 1/2 second
(for 60Hz).
The OPCB has a test button that forces the unit to act as if an overload has occurred.
This button operates even when the transfer signal is inactive.
Power Management Module and Kit
The Power Management Module (PMM) is not supplied with the transfer switch. You will also need a
PMM Kit consisting of a 24VAC supply class-2 power supply transformer and your 1st PMM Module.
The 24VAC Transformer mounts inside the transfer switch and connects to the OPCB :
Blue wire - OPCB Load Supply 1 terminal
Black wire - OPCB T1 terminal
White wire - OPCB Neutral terminal
Yellow wire - OPCB Load Supply 2 terminal
You may also still use the old DLM modules by using a jumper from OPCB Load Supply 1 to OPCB T1,
and OPCB Load Supply 2 to OPCB)Neutral. (This will supply the DLM modules with 120VAC)
**** CAUTION! *** The Load Supply Voltage on the OPCB terminals MUST MATCH the PMM/DLM coil voltage
or the equipment will be damaged.
84
Air 1 and Air 2 OPCB terminals (A/C1, A/C2, A/C3, A/C4 on the Smart AC Module)
Route the thermostat cable (from the furnace to the outside air conditioner unit) to the transfer
switch.
Route the cable away from High voltage wires.
Connect the wire to the upper terminal Air 1 on the OPCB. These are normally closed contacts which
open upon load shed conditions.
From the lower terminal Air 1 route the wire back to the air conditioner unit.
If you are shedding two air conditioners do the same procedure using OPCB Air 2 for the second air
conditioner.
Contact ratings for Air 1 and 2 - 24VAC, 5.0Amps Max
Note: These instructions are for typical air conditioner installation. Control of a heat pump and 2-stage
air conditioners will require special conditions or the use of a PMM/DLM module to control the loads.
Order of Load Shedding
Load 1 - 4 OPCB terminals
Determine the order of shedding for the loads to be connected to Load 1 thru 4 on the OPCB.
Load 1 is the highest priority and Load 4 is the lowest priority.
If connecting an existing (Hot) load, make sure the circuit breaker for the load is in the off position.
PMM/DLM Installation
Handle the PMM/DLM carefully. Do not drop or damage, protect against impact, construction grit and
metal chips.
Install the PMM/DLM Module as close as possible to the load that is to be connected to it.
The PMM/DLM Module must be mounted on the back surface.
Indoor installation - The PMM/DLM Module can be mounted in any orientation that is convenient.
Outdoor installation - The PMM/DLM Module MUST be mounted with the drain hole on the bottom.
To prevent switch distortion, level all mounting points.
To maintain NEMA-3R rating, a suitable UL-listed-for wet-locations box connector must be used.
Connect the PMM/DLM
The PMM/DLM Module is NOT intended for use with rigid metal conduit.
Make sure to turn OFF both UTILITY (Normal) and EMERGENCY STANDBY power supplies before
trying to connect power source and load lines to the transfer switch and PMM/DLM Modules.
Use a torque wrench to tighten the lugs, being sure not to over- or under-tighten the lugs. (See decal
on top of contactor.)
Connect LINE power source wires to PMM/DLM contactor terminals L1 and L2.
Connect LOAD power wires to PMM/DLM contactor terminals T1 and T2.
Connect the Ground wires to the ground stud inside the PMM/DLM Module.
Connect the PMM/DLM contactor (coil) to the contactor (LOAD) terminal on the OPCB in the transfer
switch.
The selection of the contactor (Load) terminal used will determine the priority of the load being
controlled.
If using a PMM Module, it is a 24VAC circuit and wiring methods for class 2 should be used.
A grommet is provided to route Class 2 wire through the PMM Module.
The grommet can be used for any knockout for NEMA-1 installations.
For NEMA-3R it can only be used in the bottom knockouts.
If using an older DLM Module, it's a 120V circuit, 18-26AWG copper wires should be used as control
wires.
ONLY 1 PMM/DLM Module can be connected to each Load connection (1-4) on the OPCB. Up to a
total of 4 PMM/DLM Modules can be connected to the OPCB.
85
Testing the Overload Prevention Control Board (OPCB)
A test push button is provided on the bottom of the OPCB to test the operation of the tested functions.
The test button will work when the ATS is in the Utility or Generator position.
Turn the Utility supply on to the ATS.
Press the test push button on the OPCB and verify that all the connected loads to be shed become
disabled.
After 5 minutes verify AC1 and Load 1 are energized.
Status LED on AC1 and Load1 is on.
After another 15 seconds AC2 and Load 2 come on.
After another 15 seconds Load 3 comes on.
After another 15 seconds Load 4 comes on.
Testing is complete. Educate the End User on the proper operation, maintenance, and service
call procedures.
86
Synergy Loadshedding
The 20kW Synergy must use the RTSB200A3 or RTSI200A3 switch with fast Loadshed.
The Synergy Loadshed installs and works exactly like the RTSY/RTSR switch, except when there are
any loads greater than 10kW / 2hp motors on LP or 9kW on NatGas
Examples of these large loads are a 3 Ton A/C, 3hp Well Pump, 3hp Sump Pump, etc.
These Loads MUST be connected to the OPCB.
When the generator is running at low speed and it senses a large load coming on line it sheds the load
instantly (within milliseconds) and the engine revs up to 3600RPMs
This prevents stalling of the engine. The loads are then reapplied when the engine is back up to
speed.
The normal loads come back on in about six seconds. The large loads come back on in about five
minutes (to protect their motors)
When configuring the OPCB Fast Loadshed Mode, connect the loads in different priorities than Normal
Loadshed.
Fast Loadshed - 6 seconds Load 3 is reapplied, 15 seconds later Load 4 is reapplied, 5 minutes later
Load 1 is reapplied, 15 seconds later Load 2 is reapplied.
87
RTSJ Switch Only
Test Load Shed Function - Press the Load Shed Reset/Test pushbutton for more than 6 seconds on
the outside of the ATS door.
Release the pushbutton when the Load shed switch actuates disconnecting the non-essential loads.
The Load Shed LED will light up.
The next step will depend on how the LSC is set up: Manual or Automatic Operation
Manual Operation - Press the door mounted LOAD SHED/RESET/TEST button for greater than 2 seconds.
Release the button when the LSS actuates, reconnecting the non-essential loads.
AUTOMATIC Operation - the LSS will reconnect non-essential loads after the delay setup on the DIP
switches of the LSC
With the generator running and loads powered by the generator AC output, turn ON the Utility power
supply to the transfer switch.
After approximately 15 seconds the switch should transfer loads back to the Utility power source.
Approximately one minute after re-transfer, the engine should shut down.
The system is now set for fully automatic operation.
Install Accessories
This section can be found in :
Install the oil filter/battery heaters 0J6113 Rev D
Owner and Installation Manual Mobile Link
Instruction Manual Wireless Local Remote Monitor Model 006664-0
Service Information Bulletin SIB12-07-W-RTS (Brown-Out Kit)
88
6212 Cold Weather Kit
Do Not install until unit has completely cooled.
Set the generator to OFF. Remove 7.5A fuse and disconnect at the transfer switch any utility inputs to
the unit.
Remove front panel, remove fasteners securing control panel cover and remover cover.
Disconnect the battery (Negative cable first) and remove battery.
Using a clean cloth clean the bottom of the battery and battery compartment to remove any dirt or oil.
Place the battery heater underneath the battery, long side towards the right end of the unit with the
plug facing in.
Drain the oil and remove the oil filter.
Install new filter and fill engine with 5W30 Synthetic oil. Clean up any spilled oil and wipe oil filter to
remove any dirt or oil.
Slide oil filter heater over oil filter with lead wires facing away from the engine.
Some units may be prewired with accessory connectors for the heaters.
If your unit is not prewired, run on harness to the battery heater and plug in.
Run the other harness extension plug through the engine divider panel with the main harness.
Tie wrap to the main harness.
Run the plug under the engine and tie wrap.
Note: leave enough slack to be able to remove the heater for oil changes.
Plug in to the heater.
Route the bare ends of the harnesses up to N1 and N2 on the Control wire block.
It doesn't matter which wire goes into N1 or N2, you are supplying 240VAC to the heaters.
Check the harness to make sure no wires are pinched and tie wrap as necessary.
Reconnect the battery (Red Pos Cable first).
Replace all covers, install the 7.5A fuse and reconnect utility inputs at the transfer switch. Set unit to
Auto.
If one of the wires are pinched or shorted. The N1 & N2 fuses could blow and the generator will start
and transfer to power the house when utility power is present.
89
6463 Mobile Link
Verify that there is Cell Phone Texting service available at the generator site. (usually Verizon and
AT&T)
Do NOT throw out the Box or any packing materials at this time. (You will need some numbers from
the box when you activate the unit)
Open the generator, press the OFF button. Remove the 7.5A fuse, turn the main utility disconnect to
the transfer switch to OFF or Open position. Remove T1 fuse from the transfer switch.
Disconnect the Black (-) battery cable, then disconnect the Red (+) battery cable
Remove the controller cover
Attach the provided template to position the mounting hole location.
Hole location is critical for proper operation, the antenna must be 1" above the top of the generator
roof when completed.
Note: 2013 and newer models have a prepositioned dimple to mark the center of the hole.
Inspect the area behind the external breaker box to make sure all wires are moved out of the way
before drilling.
Using the template and/or the prepositioned dimple, drill a 1 1/8" hole just behind the breaker box.
Route the six pin connector through the plastic fitting and one green gasket.
Insert the fitting from the inside of the unit through the hole. Position the threaded end out.
Install the 2nd green gasket over the threads on the outside of the enclosure.
Thread the antenna onto the Mobile Link unit. Turn clockwise until secure, position up.
Insert the six pin plug into the Mobile Link unit (connector will only fit one way - Do Not force)
With the plug installed, from the inside of the generator thread the Mobile Link onto the plastic fitting
and tighten to draw the MobileLink to the Generators wall.
Do Not over tighten. The antenna should be facing upwards.
Route the harness along the shelf. Tie wrap as necessary.
90
Evolution controllers the accessory port is located underneath the controller covered with a decal
labeled Accessory Port 1.
Remove the decal and plug in the harness.
The plug will only fit one way. Do Not force.
The power wires of the harness go directly to the battery.
Reconnect the battery Red (+) and Yellow fused (+) wires, then the two Black (-) wires.
Replace the positive terminal Cover.
Reinstall all covers, check to see that the unit is set to Off mode, reinstall the 7.5A fuse.
Reinstall the T1 fuse and turn on the utility power supply to the transfer switch.
Follow the install wizard instructions to reset the generator date and time.
Place the generator in the AUTO mode, turn off the utility disconnect to simulate an outage.
The generator should crank and start. Let it run approximately 30 seconds, then turn the utility
disconnect back on.
The transfer switch should transfer back to utility and the generator will cool down and turn off.
Verify that the Mobile Link unit’s middle LED is illuminated and the bottom LED is illuminated or
flashing at this time.
The top LED will not illuminate until enrollment/activation is complete.
91
Mobile Link Enrollment/Activation
You will need the following information to activate the unit:
One to Four E-mail addresses
One to Four Cell phone numbers (with texting capabilities)
Model Directory Number (MDN) located on the bottom of the Mobile Link of the box it came in.
Mobile Equipment Identification Number (MEID) located on the Mobile Link box.
The generator’s serial number.
Owner’s mailing address.
Valid credit card for the owner.
Address of the generator (if different from the owner).
You may also want to think of a name for the generator ex: Joe Smith Generator #1. This is in case
you have multiple generators or if one of the notifications is going out to your service technician he
can identify whose generator just sent him a message.
Go online to [Link] to complete the registration process.
Enter the required information and choose your renewal plan (the first year of service is free).
Once the enrollment is complete, the Mobile Link’s top LED will illuminate.
92
Display unit installation
Install two AAA non-rechargeable alkaline batteries in the display unit. (The expected life of the
batteries is six months.)
There is no power switch; the monitor will power up when the batteries are inserted.
Low Battery Indicator
The battery status indicator will flash every 5 seconds and the buzzer will sound every 15 minutes
when a low battery is detected.
The buzzer may be silenced by briefly pressing and releasing the test button (after the buzzer has
sounded).
The buzzer will pulse twice to indicate it has been silenced and will not reactivate until a new alarm is
detected.
Note: Batteries should be changed when the battery low indicator warning is activated.
93
The generator will not start or will be shut down if already running.
The Red light will flash every 5 seconds.
The internal buzzer will sound once every 5 seconds.
The buzzer may be silenced by briefly pressing and releasing the test button (after the buzzer has
sounded).
The buzzer will pulse twice to indicate it has been silenced and will not reactivate until a new alarm is
detected.
94
95
Bundle the newly added wires along the existing harness and tie to the harness as needed.
Plug the timer relay into the socket.
Set up the controls as follows:
Post-Installation Test
Close the circuit breaker on the generator, and place the generator in the AUTO mode.
The generator should start and run, the switch will transfer to the emergency position.
The LED on the timer relay should be off.
Energize the utility power to the transfer switch.
The transfer switch should switch back to the utility position, and the generator should cool down and
stop.
The LED on the timer should become a steady RED, but may go through steady or flashing Green
before getting to the Red state.
Installation is complete.
Warning Stickers
Reflective Decal Kit - Complete As Required By the latest edition of NFPA Part 70 The National Electrical
Code. Approved by Electrical and Building Inspectors. Complete kit ensures that your generator installation
meets current codes.
Reflective Generator Warning Decal - As required by NFPA Part 70 The National Electric Code. Protect
the lives of Service Personnel and alert Emergency Responders that a Backup Generator is installed. Includes
(2) 3M Reflective Warning Decals for the identification that a generator is installed on site. (one decal at the
meter, and one decal at the service panel)
Reflective Grounding Warning Decal - 3M Reflective Grounding Decals meet the requirements of Articles
700 and 702 for the identification of potential shock hazard. Where to use: This decal should be used
specifically on generator installations. The decal should be placed at the service equipment on
installations that are non-separately derived (a solid, un-switched neutral in the transfer
equipment)(RTSY, RTSB, RTSJ, or SE Switch on a RTSR or RTSI). The majority of residential
single-phase, and most light commercial applications fall into this category.
96
Some more Bad Installs
97
Service Entrance cable to the
Generator
98
99
We hope this information will help make your installs safe, easy, and your
customers Happy.
QT/RG Series - Liquid-cooled GenSets 22kW - 150kW Single & Three Phase
RD Protector Series - Diesel GenSets 15kW - 50kW Single & Three Phase
Generac iX, iQ, GP, LP, XG, & XP Series, DeWalt, & Powermate - Portable Gasoline,
Propane, & Diesel Generators
100