Environmental Protection Guidelines 2077
Environmental Protection Guidelines 2077
The Natural Environment
It encompasses all living and non-living things occurring naturally, meaning in this case
not artificial. The term is most often applied to the Earth or some parts of Earth. This
environment encompasses the interaction of all living species, climate, weather and natural
resources that affect human survival and economic activity.
Environmental Degradation
It is the deterioration of the environment through depletion of resources such
as air, water and soil; the destruction of ecosystems; habitat destruction;
the extinction of wildlife; and pollution.
Environmental Issues
They are harmful effects of human activity on the biophysical environment. Environmental
protection is a practice of protecting the natural environment on the individual, organizational or
governmental levels, for the benefit of both the environment and humans. Environmentalism,
a social and environmental movement, addresses environmental issues through advocacy,
education and activism
Major current environmental issues may include climate change, pollution, environmental
degradation, and resource depletion. The conservation movement lobbies for protection
of endangered species and protection of any ecologically valuable natural areas, genetically
modified foods and global warming.
Environmentalism or Environmental Rights
It is a broad philosophy, ideology, and social movement regarding concerns for environmental
protection and improvement of the health of the environment, particularly as the measure for this
health seeks to incorporate the impact of changes to the environment on humans, animals, plants
and non-living matter.
An environmentalist is a person who may speak out about our natural environment and the
sustainable management of its resources through changes in public policy or individual behavior.
Development
The process of economic and social transformation that is based on complex cultural and
environmental factors that their interactions.
Development Infrastructures vs. Environmental Considerations
Environmental consideration in and around development should be led by a local understanding
of ecological networks, and should seek to include
Habitat restoration, re-creation and expansion
Tools for the Environmental Inclusion in Development (Types of EA)
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 1
In order to achieve the objectives of environmental protection, environmental experts have
developed a number of tools to protected and manage the environment during development
projects. The tools are:
1. Initial Environmental Examination (IEE)
2. Environmental Impact Assessment (EIA)
3. Strategic Environmental Assessment (SEA)
4. Brief Environmental Assessment (BEA)
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 2
Topic
EA Steps
It is generally conduced in tiers. In most countries, EA processes fall into four tiers:
· Screening: decides whether the EA process is applicable at all to the development project.
Screening should basically "clear'' all those projects where there are no major negative impact
issues.
· Scoping: helps in understanding the extent of environmental impacts and identifies significant
environmental issues for further study. In the activity-component framework, this would mean
that scoping should assist in the identification of impacting activities and impacted
environmental components for all major negative impact issues.
· Initial environmental examination: assesses the severity of the significant issues and finds
ways to mitigate or enhance environmental impacts by considering the available information
from past experience or the standard operating practices.
Global commitment
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 3
Lower project cost in long term
Government policy
International obligation
1. Screening
3. Report Preparation
Preparation of draft Initial Environmental Examination Report based on approved ToR and
in the format, as appropriate
A 15-day public Notice on National level Newspaper .Deed of recognizance posting the
notice in the offices of concerned DDC, VDC/Municipality, health post, schools and other
organizations
Submission of Final Report to the concerned Ministry with proof of public notice and deed
of recognizance and recommendation letter(s)
Implementation of project
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 4
Report Format of IEE
Technical Differences
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 5
Topic EIA Process (Steps of EIA)
As a project management tools, EIA are used to organize, collect and analyses information on
the environmental effects of particular projects. The sequences of steps are:
Step2: Scoping: identification of all potentially significant impacts and basis for information of
TOR
Step 4: Prediction of Impacts: identifies and predicts impacts in terms of magnitude and, extent
and duration
Step6: Mitigation Measures: design systems and process to avoid, reduce and minimize
adverse impacts and enhance beneficial outcomes
Step 7: Stakeholder Involvement: ensure stakeholders views and issues are addressed in
decision making process
Step 8: Monitoring and Auditing Measures: identification of impacts that require monitoring
and auditing
Step 9 EIA Report Preparation: contain all the information obtained, analyzed, interpreted and
complied in a report form
Step 10: Review: assess whether or not all possible issues have been address properly or not to
facilitate decision making process
Step11: Decision Making: determine whether or not project should proceed based on conclusion
provided in EIA report and review.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 6
During this stage scoping and TOR document are prepared. Scoping identifies the
environmental issues to be considered. TOR is developed for stage of EIA based on the
result of scoping.
2. Feasibility Stage
4. Implementation of Project
EIA report acts as guide book for the implementation of mitigation measures and
monitoring schemes. EIA forms a basis for developing a management plan to assist in
project implementation and management practice. Recommendations in EIA report form
a part of contract tender documents
Topic Screening
Process of selecting the projects through the establishment of a proper mechanism is called
screening.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 7
It is the first step of EIA process. Under it decision is made for the requirement of EIA. So
unless it is carried, no further action can be done.
Screening is required to ensure that only those projects that might have significant impacts on
environment are addressed and project with few or no impacts are screened out. To carry out
screening decision, information about scale and location and the process to be involved is
required.
Screening is mandatory and it calls for the authorizing agency to screen the projects after
developers submit the details of proposed project.
Benefits of Screening
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 8
Topic Scoping
Scoping is 2nd stage of EIA process, carried in order to determine the coverage and scope of EIA
study for the project proposal with potentially significant environmental impacts.
It helps to develop and select alternatives to the proposed action and to identify the issues to be
considered in an EIA. It is used to establish TOR for an EIA.
To identify all the concerns and issues that needs to be considered in EIA
To evaluate and address the concerns expressed about possible impact on environment
Infrastructure requirements
Land Use
Hydrology
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 9
Ecology
Atmospheric Condition
Method of Scoping
Issues are identified, evaluated and organized to be presented to decision makers. The steps of
scoping are:
5. Evaluating the significance of the identified issues on the basis of available information
If screening indicates needs of EIA, the TOR is prepared to provide specific guidance or guide
lines for conducting a full scale EIA. TOR assists the EIA in following ways:
Fitting the EIA study in the context of existing polices, rules and procedures
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 10
Giving importance to the most essential elements for study
Format of TOR varies from countries to countries. TOR often serves as legal document against
which final outcomes of an EIA are compared. In some countries authoring agencies prepares
TOR whereas in some coutries project proponent is responsible for TOR development.
Barry Sadler in 1997 suggested the following outlines of TOR in EIA effective study:
Introduction
Purpose of TOR
EIA Guidelines
Background Information
Location and specific background and reports related to project are listed and described
Listing of varies environmental components which need detail study along the indicates
TOR required to measure those components.
Cost benefit analysis of project regarding its environmental implication should be done
Monitoring schedules needed for assessing the actual impacts of the project afterwards
should be given
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 11
Work task: description of each specific task to be done
Study team: experts and specifications needed for proposed projects should be described.
Conclusion
Budget
Topic Scoping Document (SD) and TOR Review & Approval Process in Nepal
1. Publication of a 15- day notice in a national daily by the proponent, informing the concerned
local organizations and individuals about the proposal in brief and defining the
VDC’s/municipalities (new local bodies) to be affected by the proposal implementation and
soliciting their concerns and suggestions on the proposal
2. Preparation of SD after field study and consultations/interactions with stakeholders and ToR
based on the SD by the proponent/consultants
6. Send a letter to the proponent for revision of SD and TOR reports as per suggestions of RSC
and EIA section of Ministry,
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 12
Topic Baseline Data Collection for EIA
Project area is defined as the area where environmental effects and impacts are felt during
construction or operational stages of a project.
A. Physical Environment:
It include varies conditions and parameters. They are: Topography, geology, soil types,
surface and ground water condition, watershed condition, pollution levels, noise level
B. Biological Environment:
It includes terrestrial and aquatic ecosystems, types of flora and fauna, environmentally
sensitive wetlands, prime agricultural land etc
C. Socio‐economic environment:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 13
Demography, development needs and potential, infrastructure facilities, economic activities etc.
D. Cultural:
Location and state of archeological, historical, religious sites
Primary Sources:
Result of the field and laboratory data collected and analyzed directly
Secondary sources:
Data collected indirectly from published records or documents such as project documents,
village profile, maps, photos, internet sources etc
2. For study of location, topography and area: topographical map and aerial
photographs interpretation
3. Field study and laboratory testing for drainage pattern, erosion and stability
Biological Environment
1. Sampling methods
a. Quadrate method
b. Transect method
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 14
c. Point frame method
4. Vegetation Analysis
a. basal area
d. dominance
e. abundance
structured interview
public meeting
Data Processing
Raw data is converted into knowledge and information that is more easily comprehensible. Tools
such as tables, graphs, maps can be used for presentation.
1. For physical data: graphs, tables, enumeration
2. For biological data: species numbers, volume, density, biomass can be calculated.
3. Species diversity (No. of species/Area sampled) can also be used for processing
biological data calculated through species richness of an area.
4. Socioeconomic data: Data such as male/female, skilled/semi skilled labor force
for construction and operational activities can be presented through, graphs, tables, and
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 15
population pyramids etc. which can be collected through sampling (random, stratified or
mixed).
Baseline studies in EIA may take a long time; hence EIA is blamed for higher costs and delays in
project implementation.
Therefore, the studies should be focused on those aspects that are likely to be affected.
Four critical points exist for project implementation
Topic
The concept of alternative can be defined as a possible course of action, in place of another, that
would meet the same purpose and need.
The role of alternatives is to find the most effective way of meeting the need and purpose of the
proposal, either through enhancing the environmental benefits of the proposed activity, and or
through reducing or avoiding potentially significant negative impacts.
1. Activity alternatives
These are sometimes referred to as project alternatives, although the term activity can be used in
a broad sense to embrace policies, plans and programs as well as projects. Consideration of such
alternatives requires a change in the nature of the proposed activity.
An example is incineration of waste rather than disposal in a landfill, or the provision of public
transport rather than increasing the capacity of roads.
2. Location alternatives
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 16
Location alternatives could be considered for the entire proposal or for a component of a
proposal, for example the location of a processing plant. The latter is sometimes considered
under site layout alternatives
3. Process alternatives
Various terms are used for this category, including technological alternative and equipment
alternative.
The purpose of considering such alternatives is to include the option of achieving the same goal
by using a different method or process. An industrial process could be changed or an alternative
technology could be used.
For example, 1000 megawatt of energy could be generated using a coal-fired power station or an
array of wind turbines.
4. Demand alternatives
Demand alternatives arise when a demand for a certain product or service can be met by some
alternative means. Thus, for example, the demand for electricity could be met by supplying more
energy or through using energy more efficiently by managing demand.
5. Scheduling alternatives
These are sometimes known as sequencing or phasing alternatives. In this case an activity may
comprise a number of components, which can be scheduled in a different order or at different
times and as such produce different impacts.
For example, activities that produce noise could be scheduled during the day to minimize
impacts, and activities that may impact on birds could be scheduled to avoid the migratory
season
6. Input alternatives
By their nature, input alternatives are most applicable to industrial applications that may use
different raw materials or energy sources in their processes.
For example, an industry may consider using either high sulphur coal or natural gas as a source
of fuel.
7. Routing alternatives
Consideration of alternative routes generally applies to linear developments such as power lines,
transport and pipeline routes. In route investigations, various corridors are investigated and
compared in terms of their impacts.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 17
8. Site layout alternatives
9. Scale alternatives
In some cases, activities that can be broken down into smaller units can be undertaken on
different scales. For example, in a housing development there could be the option of 100, 150 or
200 housing units. Each of these scale alternatives may have different impacts.
3. Ranking , rating or scaling approach: the qualitative and quantitative information on each
issues are summarized through assigning rank, rating or scale values usually based on
characteristics of impacts
Effects An "effect" is a change or result. "The rain had an effect on the condition of the
grass." An effect can be positive or negative.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 18
Impacts The main difference between impact and effect is that impact is the influence of
an action/phenomenon on something or someone whereas effect is the consequence or
outcome of an action or a phenomenon
Prediction – most likely to occur related to other project action during construction and
operation with ROW of road /canal
There are various methods available for predicting the impacts on variety of resources.
Predictive methods must be explorative i.e. it must use past and present data, trends,
analysis, analogies and intuition to arrive proper conclusion.
Impact prediction methods are broadly classified into following five types:
1. Mathematical Models
They are based on cause and effect relationship expressed in the form of mathematical
function. They include input – output as well as complex dynamic models. They generally
predict partial impacts. They are of two types:
2. Statistical Methods
Statistical tools such as regregassion and component analysis are used to relationship
between data and test hypothesis
Eg prediction of flood
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 19
Satellite images, physical maps and aerial photographs provide required information on
existing resources. GIS allows analysis of effects of projects activities.
A field work is carried out before the implementation in order to provide baseline
information about the resources available. Eg fish resources, survey of river
Laboratory tests also provide some information into the effects of certain development
activities on resources
5. Expert Judgments
Judgments given by the experts based on the events which occur due to the implantation of
certain or specific development activities in particular location helps in prediction of similar
impacts on other location.
acceptable results
Predicting the impact of some development activity gives the clear image of what is going to
happen but there always remains a factor of uncertainty in prediction. These uncertainties are
about:
To resolve the question of uncertainties, the issues of probability of occurrence and confidence
level impact prediction need to be addressed properly. All the predictions should be expressed
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 20
such that each of the predicted outcomes is within a certain range of percentage of confidence
level
Example:
Predicted that industry emits a noise level of 65-70dB at 90% confidence interval that means
only 10 times out of 100 times, it would be likely to exceed noise range ( expect)
Impact ranking is the most commonly used method for choosing alternatives due to its
simplicity. In this method, impacts are predicted in terms of
Magnitude
Extent and
Duration
Each of this prediction is then translated into values. These impact values are then summed up
and then multiplied by probability of occurrence of any particular impacts. The final impact
value thus obtained for all the alternatives is then compared and highest value corresponds to
greatest potential for environmental impact where as lowest impact values are generally
considered and selected
EIA guidelines (1993) award the following numerical values in its impact assessment
framework.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 21
Topic Types of Impacts
Physical impacts refer to impacts on soil and landform such as soil erosion, flooding,
sedimentation.
Chemical impacts relate to project activities that can change the quality of ambient
air, water or soil
b. Biological Impacts
c. Social Impacts
iii. Cultural impacts: traditional pattern, family structures, religion and belief etc
Occupation
d. Health Impact
Traditionally health issues have been given very little attention in EIA study but
following are some reason why health impact must be integrated in EIA process:
Economic Impacts
Various impacts on economy can be seen or likely to arise due to changes in economic variables
caused by:
Size of investment
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 23
Lively demographic changes arising due to project
1. Direct Impact
Eg, construction of irrigation diversion on stream bank may affect the aquatic ecosystem,
stream valley vegetation
2. Indirect Impact
Results when impact on one component of existing environment affects other related
components. Direct impacts can have far reaching effects, producing numerous indirect
impacts depending up on structure and function of system.
Eg Effects which are caused by the action that are later in time or farther removed in
distance, but are still reasonably foreseeable. Indirect effects may include growth-
inducing effects and other effects related to induced changes in the pattern of land use,
population density or growth rate, and related effects on air and water and other natural
systems, including ecosystems
Cumulative Impacts:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 24
Topic
1. Checklists
i. Simple checklist
Matrix is gridline like table that is used to identify the intection between project activities
which are displayed on the axis and environmental characteristics on the other axis.
Types of matrix:
i. Simple matrix
3. Overlay mapping
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 25
Series of transparencies are used to identify, predict and design relative significance
and communicate impacts in geographical reference. It can accommodate both
qualitative and quantitative data.
4. Networks
Networks are attractive for focusing on indirect effects/impacts. This does not include
quantitative measure of impact magnitude.
GIS has potential for storing and providing access to very large data sets.
When prediction is involved, computer model design for specific purpose is utilized
in EIA analysis. Such models often incorporate mathematical representation.
7. Expert systems are also task specific but they may or may not be computer based.
Expert system incorporate the knowledge and experience of expert from relent
disciplines into analytical tools use for decision making.
Mitigation measures are action recommended to reduce, avoid the potential adverse
impacts on environment resulting from proposed development activities.
1. Preventive Measures
Some potential impacts can be reduced or eliminated before they occur. Examples
of preventives measure are
2. Compensatory Measures
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 26
These are actions undertaken to compensate for unavoidable adverse impacts.
possible compensatory measure are
3. Corrective Measures
They are adopted to reduce the adverse impacts to acceptable levels. Some of the
corrective measures are:
There are hundreds of reasons for conflicts in project management. They can be a huge
impediment towards the success of a completed project.
The following are common sources of conflicts, especially in the project environment.
Schedules.
Prior unresolved conflicts.
Project priorities.
Resource competition.
Cultural differences.
Technical issues.
Team or clique.
Personality conflicts.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 27
The participation of local People is very much essential to run the project. But Nepal has
sufficient examples of the lack of people's participation in projects. There is lack of public
participation in projects for most of the projects are run in rural areas and the rural people have
generally negative attitude towards projects.
Project Mediation
It is a structured, interactive process where an impartial third party assists disputing parties in
resolving conflict through the use of specialized communication and negotiation techniques. All
participants in mediation are encouraged to actively participate in the process.
Mediation is a "party-centered" process in that it is focused primarily upon the needs, rights, and
interests of the parties. The mediator uses a wide variety of techniques to guide the process in a
constructive direction and to help the parties find their optimal solution.
A mediator is facilitative in that she/he manages the interaction between parties and facilitates
open communication. Mediation is also evaluative in that the mediator analyzes issues and
relevant norms ("reality-testing"), while refraining from providing prescriptive advice to the
parties (e.g., "You should do)
In participatory decision- making, there is no single source of ultimate control of authority. The
participating parties must discuss and reach a decision by means of agreed upon process. Some
of many methods which can be utilized to involve stakeholders, especially public in the EIA are:
Public Meeting- opens with no restriction; anybody with interested can attend
Advisory Panels- group of individuals who are chosen to represent stakeholders; they meet
periodically to assess work done and result obtained to advice on future work.
Questionnaires- written, structured series of questions are asked to local people to gather ideas
and matter concerns
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 28
Participatory Appraisal Techniques- systematic approach to appraisal based on group inquiry
and analysis with multiple and varied inputs.
Scoping
Preparation of TOR
Project valuation
The stakeholder groups typically involved in a participatory M&E activity include: the end users
of project goods and services, including both men and women at the community level;
intermediary organizations, including NGOs; private sector businesses involved in the project;
and government staff at all levels.
Principles of Participatory Monitoring & Evaluation
Conventionally, monitoring and evaluation has involved outside experts coming in to measure
performance against pre-set indicators, using standardized procedures and tools.
PM&E differs from more conventional approaches in that it seeks to engage key project
stakeholders more actively in reflecting and assessing the progress of their project and in
particular the achievement of results :
Core principles of PM&E are:
Local people are active participants — not just sources of information.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 29
Topic Environmental Management Plan (EMP)
The EMP should be necessarily based on consideration of resource and pollution control.
Holgate, 1979 makes a distinction among monitoring, surveillance and survey. He considered
that monitoring is an action orientated activity designed to determine the extent to which
environmental regulation is working
Principle of Monitoring
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 30
Types of Monitoring
1. Baseline Monitoring:
A survey of baseline environmental parameters in the proposed project area and its
surrounding should be conducted before the construction phase. This is known as base
line monitoring or pre- audit study.
2. Impact Monitoring:
The biophysical and socioeconomic parameters within the project area must be measured
during the project construction and operational phases in order to detect any
environmental changes occurring due to project implementation.
3. Compliance Monitoring:
Impact monitoring is an important component of EIA. It must be given proper emphasis within
project cycle. It is not possible to monitor all aspects coverd by the impacts identification
process, a selection of the most important and critical parameters that could influence the project
and its surrounding environment must be made. Depending on the project, the selected
parameters may vary. The intensity or criteria of the monitoring ids determined on the basis of
the identified different parameters and potential severity of the environmental impact being
monitored.
Monitoring Indicators
For each of the impacts and corresponding measures, indicators to be measured during projects
construction should be developed. The indicators should be selected such that up on their
measurement, they reflect the condition of that particular component.
Monitoring Plan:
The term audit is usually associated with finance and accounting, but actually refers broadly to
the examination and assessment of certain type of performance. In the case of an EIA, an audit
assesses the actual environmental impact, the accuracy of prediction, the effectiveness of
environmental impact mitigation and enhancement measures and the function of the monitoring
mechanism. An audit should be performed after a project has been in operation for some time
and is usually performed once or twice in the entire project cycle.
Types of Audit
It is recommended that following types of audit are implemented in different phases of EIA
process
The audit should be carried out by agency which approves the project, with assistance from
relevant organizations if required. It should be scheduled immediately after project construction
is completed or at another point in project cycle at which it seems essential. In Nepal, MOFE is
responsible for auditing, which conducts it with concerned agencies and the project proponent.
The audit gives clear idea of ways to reduce or present unwanted consequences that may be seen
during implementation.
Information collected while monitoring outputs should be utilized for carrying out and
environmental audit.
Topic EIA Study and Report Approval Process (Administrative Procedure in Nepal)
• Proponent
• Field study
Scoping Phase:
ToR phase:
1. Methodology
2. Prioritized issues
3. EIA format
EIA phase:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 33
4. Public hearing
Desk Study/Field study, preparation of draft EIA report based on the approved ToR
Send a letter to the proponent for revision of EIA as per suggestions of RSC and EIA
section of Ministry,
Table of Contents
List of Tables
List of Figures
List of Annexes
Executive Summary
sfo{sf/L ;f/f+z
Acronyms
CHAPTER ONE: INTRODUCTION
1.1 Background
1.2 Project Proponent
1.3 The Consultant
1.4 Objectives of EIA Study
1.5 Rational of the Study
1.6 Limitation of the Study
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 34
CHAPTER FOUR: EXISTING ENVIRONMENTAL CONDITION
References
The benefits of EIA are now widely accepted and there is a growing belief that the EA of
policies, plans, and program may also be necessary to ensure that alternatives and impacts which
cannot be fully considered at project level are adequately evaluated.
This is a consequence of the growing belief that project EIA may occur too late in the planning
process to ensure that all the relevant alternatives and impacts are adequately considered.
Such an assessment of policies, plans, and program is termed strategic environmental assessment
(SEA). It can also be applied to enable cumulative impacts between projects, policies, and
program to be taken into consideration.
Partly because the advantages of project EIA are so widely recognized, the desirability of taking
the environment into account earlier in the planning process has gained acceptance worldwide.
Steps of SEA
The tasks involved in SEA are similar to those in EIA and many EIA methods can be adapted to
SEA methods.
There exists a tiered forward-planning process which starts with the formulation of a policy at
the upper level, is followed by a plan at the second stage, and by a programme at the end.
The tiered EA process can permit relevant alternative approaches and cumulative, synergistic,
global, and non-project impacts to be assessed. The tiered process can be applied at the national
as well as local levels. It can apply to sectoral actions and physical planning actions.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 35
Encourages the consideration of environmental objectives during policy, plan and program
making activities within non-environmental organizations
• Facilitates consultations between authorities on, and enhances public involvement in evaluation
of environmental aspects of policy, plan and program formulation.
• May render some project EIAs redundant if impacts have been assessed adequately.
• Can help determine appropriate sites for projects subsequently subject to EIA.
• Allow more effective analysis of cumulative effects of both large and small projects.
• Allows analysis of the impacts of policies which may not be implemented through projects.
There are several reasons for the perceived need for SEA. Alternative approaches, cumulative
impacts, and synergistic impacts (which may be cross-sectoral in nature), ancillary impacts,
regional or global impacts, and non-project impacts (for e.g., impacts resulting from management
practices) may all be better assessed initially at policy, plan, or program level rather than at the
project level.
The main elements of the EIA process and its most tangible output (the EIA report) are in
principle applicable to all levels of decision-making including policies, plans, and program.
However, in practice, it is likely that the scope and purpose of the EA of policies, plans and
program will be different from that of projects in five main ways:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 36
• The lead time is greater;
• The decision-making procedures and the organizations involved may differ, requiring a greater
degree of coordination;
SEA methodologies are not well developed. However, nearly all the tasks involved in SEA are
similar to those in project-level EIA. As with project EIA, the skill of the assessor comes to bear
in selecting an appropriate mixture from different approaches, tools, and techniques available.
The key considerations that assessors should bear in mind in designing their approach to SEA are
listed in Table 9.6.
Effectiveness of SEA
Like EIA, SEA faces a number of important political and institutional barriers, in fact more so
since setting policies is a political issue. Currently, SEA processes vary considerably. They may
be formal or informal, comprehensive or more limited in scope, and closely linked with or
unrelated to either policy or planning instruments.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 37
Topic Life Cycle Assessment:
A broader approach to deal with environmental impacts in manufacturing is called life cycle
analysis. This approach recognizes that environmental concerns enter into every step of the
process with respect to the manufacturing, of the products and thus examines environmental
impacts of the product at all stages of the product life cycle.
This includes the product design, development, manufacturing, packaging, distribution, usage
and disposal. LCA is concerned with reducing environmental impacts at all these stages and
looking at the total picture rather than just one stage of the production process. Through utilizing
this concept, firms minimize the life cycle environmental costs of their total product system.
LCA gives sufficient scope to think about the alternatives which are lower at cost.
From the above discussion, it is clear that EIA shall be integrated at all the levels i.e. strategic,
regional, sectoral and the project level. Whereas, the strategic EIA is a structural change, the
regional EIA refers to substantial information processing and drawing complex inferences.
Introduction
Nepal integrated environment aspects in all its development activities and projects only from
early 1980s.
Environment conservation was included in the policies since the Fifth Plan (1975-1980).
The second milestone was taken during the Sixth Plan. The Sixth Plan under the environment
and land use policy emphasized the integration of environmental aspects into the construction of
large-scale development projects.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 38
Then finally, in the Seventh Plan it was stated that developmental programs would be
implemented only after an approved EIA/IEE report.
The Eighth, Ninth and Tenth Five Year Plans have further emphasized the making of more
effective EIA systems.
The formulation of Sectoral Guidelines, promotion of participatory EIA/IEE system and
inclusion of mitigation cost into the total project cost were some of the activities included in
these three five year plans.
Article 35(5) of the Interim Constitution requires the State to give priority to the protection of the
environment and also the prevention to its further damage due to physical development activities
by increasing the awareness of the general public environment cleanliness.
The state shall also make arrangements for the special protection of the environment and rare
wildlife. Provision shall be made for the protection of the forest, vegetation and biodiversity, its
sustainable use and equitable distribution of the benefit derived from it.
Nepal Environmental Policy and Action Plan, 2050 (1993) and 2055 (1998)
Nepal Environmental Policy and Action Plan (NEPAP) were endorsed to further institutionalize
environmental protection in the development processes. The NEPAP recognize that a growing
number of people are exposed to pollute from industrial enterprises.
The NEPAP identifies the following factors as contributing to this process: Industrial plan
inappropriately cited close to population centers insufficient emphasis on fuel efficiency little, if
any pollution abatement equipment used for reducing emission, and a total lack of industry
pollution standards.
Hence, the NEPAP emphasizes the need for mitigating adverse environmental impacts to address
urban and industrial development, air and water pollution and infrastructures development.
The Forest Sector Policy of Nepal such as the National Forestry Plan, 1976, Master Plan for the
ForestrySector, 1988, Periodic Five Year Plan and Forestry Sector Policy, 2000 has emphasized
people’s participation in the forestry management.
Nepal’s main forest management is based on people’s participation and various management
models are underway.
Similarly, Forestry Sector Policy, 2000 stresses on conservation of biodiversity, ecosystem and
protection of land degradation by soil erosion, landslide, floods desertification and other
ecological disturbances.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 39
The Public participation in forest management is sought through community forestry,
collaborative forest management, leasehold forestry etc.
The mitigation measures such as plantation, NTFP program and other social and community
support program proposed by the project will be implemented by mobilizing the local people
which is in line with the Forest Sector Policy.
The procedural guidelines for the use of forest land for other purpose stated that feasibility study
will be carried out with no use of forest land to the extent possible. If it is not possible, the
alternate will be considered with minimum use of forest land.
This guideline also stated that the project proponent will be responsible for the plantation of two
tree species for the loss of one tree and their management for 5 years and handing over to the
concerned forest office of the district.
The Hydropower Development Policy was promulgated in 2001. The main objectives of the
policy include producing clean energy through the development of hydroelectric projects and to
help conserve the environment.
It is stipulated that one of the policies is to extend the use of electricity for achieving a reduction
in the utilization of fuel wood and to render necessary assistance in the conservation of forest and
environment.
Acts
This Act provided legislative protection of the habitats of aquatic species. Under this Act, it is
offence to introduce poisonous, noxious or explosive material in to a water source or destroy any
dam, bridge, fish ladder or water system the intent of catching or killing aquatic life. The Act
was amended in 1988 to prohibit the use of unsafe pesticides.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 40
Water Resources Act, 2049 (1992)
The objectives of the Water Resources Act, 2049 is to make legal arrangements for determining
beneficial uses of water resources, preventing environmental and other hazardous effects thereof
and also for keeping water resources free from pollution.
The Act strives to minimize environmental damage to water bodies, especially lakes and rivers
through environmental impact assessment studies and the proponents who wish rosewater
resources for various purposes should prepare IEE report before a license can be granted.
The Act stipulates that soil erosion, flooding, landslides or any significant impact on the
environment should be avoided in all uses of a water resource. The provisions made in Water
Resources Act, 2049 (1992) is mandatory in case of the implementation of the proposed project.
As per the provision, the environmental impact mitigation and enhancement measures have been
proposed in view of environment conservation.
The Electricity Act, 2049 also contain provisions to minimize soil erosion, flood, air pollution
and damage on environment while producing electricity and transmission of the power
(Article24).
Forest Act, 2049 (1993)
The Forest Act, 2049 (Amendment 2055) recognizes the importance of forests in maintaining a
healthy environment.
One of the major objectives of the enhancement and enforcement of the Forest Act is the
promotion of a healthy environment.
The Act requires decision-makers to take account of all forest values, including environmental
services and bio-diversity.
It emphasizes the development and implementation of an approved work plan for different
categories of forest, i.e. Community Forests, Leasehold Forests, Private Forests and religious
forests.
This Act is relegating case of the proposed project as the project will acquire an area equivalent
to 23.1046 ha forest land belonging to community, and national. It is mandatory to follow the
Forest Act, 2049 (1992) while proposing the mitigation measures and also in implementation
phase.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 41
Labour Act, 2049 (1993)
This act is enforced by GoN in 2049/2/2. This Act classified below 15 years as child and
‘anabolic’ for the age group of above 14 years and below 18 years. The Act has also made
provision of labour court and department of labour. The Act clearly mentions that the
appointment letter should be issued for all the employees which include their working hours,
working time, wages and other benefits.
The Act allows for the time bond contract for the manpower required for development work. The
Act specifies that working hours for the Anabolic and women must be within 6 AM to 6 PM
which clearly restrict to deploy women in night works. The Act also state that equal opportunity
shall be given to women as men.
Similarly working period for the other employees must not exceed 8 hours a day and 48hours in
a week. If some people work beyond that period, over-time allowances must be paid which is
150% of the normal per hour wages and such over-time must not exceed 4 hours in a day.
According to this act the wage rate of the employees shall not be less than the rate fixed by the
concerned offices of GoN.
Environment Protection Act, 2053 (1997)
Nepal has enacted a comprehensive and umbrella type Act, the Environment Protection Act,
1997 (EPA, 97) which is now enforced through appropriate regulatory measures. The EPA
provides a legal basis for the concerned authorities for regulation an initial Environmental
Examination (IEE) or Environmental Impact Assessment (EIA).
Section 3 of the Act requires the proponent to conduct an IEE or EIA in relation to the prescribed
proposals. The Act uses the word proposal instead of Projects which makes the scope of the Act
much broader in relation to environmental studies.
According to the provision in Section 6 (1) of the Act, the relevant agency is empowered to grant
approval for the IEE and EIA report, only if it finds that no significant adverse effects will be
caused to the environment by the implementation of the proposal.
Implementation of any proposal without the approval of the relevant agency is prohibited by the
Act. As per EPA, 1997, the proposed project has obligation to carry out IEE study prior to the
implementation of the proposed project.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 42
Section 96 stipulates that it is the duty of the municipality to protect the environment through
the control of air, water and sound pollution. It also obligates the Municipality to maintain
environmental cleanliness through the implementation of solid waste management, flood and
landslide control programs.
This Act is relevant as the proposed project will utilize natural resources and carry out
development activities in the project affected VDCs. Hence, it is mandatory to the project for
proposing mitigation measures.
Child Labor (Prohibition and Regulation) Act, 2056 (2000)
The Child Labor (Prohibition and Regulation) Act, 2056 is enacted and enforced adopting ILO
Convention concerning Elimination of Worst Forms of Child Labor and Minimum Age
Convention. This Act has defined the ‘Child’ as a person who has not achieved the age of16year.
Article 3 bans the employing a child below the age of 14 to work as a laborer and engaging a
child in the hazardous and risky works listed in the Schedule of the Act.
The proponent is mandatory to follow the Child Labour (Prohibition and Regulation) Act,
2056(2000) during the project implementation phase.
The project requires 255 manpower including skilled, semi-skilled and unskilled for the
construction activities. Priority will be given for local employment. The contractor may use child
labour during construction period. Hence, the contractor will be instructed to follow the Child
Labor (Prohibition and Regulation) Act, 2056 (2000).
The Electricity Rules, 2050 emphasize environmental analysis, which should include
environmental mitigation measures to minimize adverse impacts likely to occur while
developing hydro-electricity (Rule 12 and 13).Rule 12 (f) and Rule (g) are related to the EIA/
IEE process which emphasize that the IEE report should include measures to be taken to
minimize the adverse effects of the project on social, biological and physical environments and
should also elaborate utilization of local labour, source of materials, benefits to the local people
after the completion of the project, training to local people in relation to construction,
maintenance and operation, facilities required for construction site and safety arrangements.
Water Resources Rules, 2050 (1993)
It is mandatory under Rule 17(e) of the regulation that any person or corporate body, who desires
to obtain a license for utilization of water resources must state in his application that appropriate
measures will be taken to lessen the adverse effects due to the project on the overall
environment.
Rule 19 stipulates that the water resources committee shall publish a notice giving detail
information about the project to the people.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 43
Environment Protection Rules, 2054 (1997)
The Environment Protection Rules (EPR) was endorsed in June 1997 and was made under the
provisions of the Environment Protection Act.
The EPR has been amended several times and the recent was done in 2010/01/27. The recent
amendment states that transmission line projects up to 400 kV voltage level requires only IEE
unless it traverses through protected area, buffer zone or national parks.
The EPR adopts the environmental assessment criteria mentioned in the EIA guidelines.
However, the EPR establishes the administrative framework for assessing, exhibition and
determination of the EIA/IEE, in terms of issues needing to be addressed and the format/layout
of the EIA/IEE document.
Under section (18) of EPA, any person who contravenes any of the provisions of the Act, or the
Regulations or the guidelines issued under the Act, shall be punishable with a fine up to Rs
50,000.
If a proposal is implemented without the approval of the Ministry of Environment (in case of
IEE, Ministry of Energy) or relevant government agency, or the person implementing the
proposal is not complying with the conditions of the approval or license, the authorized official is
empowered to close down that activity and may impose fine of up to Rs. 100,000 on such person
or organization.
This Act is relevant to the proposed project. Under this Rules, the IEE study of the proposed
project has to be carried out by the proponent and get approval from the Ministry of Energy prior
to the project implementation.
Article -7 (69) empowers the VDCs for monitoring and supervision of development work
implemented in the VDC. The Article - 4 of DDC has provision of 3 members (Agriculture,
Forest and Environment) committee to look after the concerned issues. Article-6 (206) specifies
that the need of social, economic, environmental and public facilities should be considered while
planning the project.
Article-7 (210) focuses on environmental studies and stresses due consideration while
implementing the project like sand quarry, stone quarry, coal mines and others.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 44
the aspects of the project which is likely to have significant adverse effects on biological
diversity at genetic, species and ecosystem level, and
the steps to be taken to avoid or minimize significant adverse effects to ensure that the proposed
project comply with existing environmental legislation.
the GoN has included 17 species of plants and 39 species of wild animals in the protection list.
If the project area is in the core habitat of these species and project activity will likely to affect
them, mitigation measures shall be proposed and be implemented to avoid and/ or mitigate the
adverse impacts. Nepal is a party to the convention of Biological diversity and in accordance to
the article 14, adequate attention should be given to minimize and or avoid the impacts.
The guideline was part of a comprehensive program to develop the national and sectoral
guidelines for establishing a national system for Environmental Impact Assessment which was
part of GoN's National Conservation Strategy. The EIA Guideline was endorsed by GoN on 27
September 1992 and gazette on 19 July 1993.
The Guideline aim to facilitate the sustainable use of forest resources for socio-economic
development and meeting basic need to the community regarding the forest products, to make
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 45
proposals socio culturally acceptable, economically feasible, and environmental friendly to
conserve genetic resources and biodiversity and minimize environmental damage in forest areas
and facilitate in identification of positive and negative impacts of programs to be implemented
by other agencies in forest areas.
The guideline emphasized the need of carrying out an EIA/IEE study of development projects
and programs proposed for implementation in forest areas.
The project requires to fell down an estimated of 5875 trees (size having DBH greater that 10
cm) from national and community forests and some 1760 privately owned trees. Hence, it is
obligation to the project for getting approval in view of vegetation clearance and evaluation of
wood volume from district forest office prior to the construction phase.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 46
As Nepal is party to the convention related to species conservation, attention should be given to
evaluate the impacts of the project activities on meeting their obligation. It is relevant to IEE
study that species protection list could also be used to evaluate the significant of the identified
and predicted impacts. Plant and wild animal species under legal protection provides a basis to
purpose EMPs for their conservation and for least damaging them during project
implementation.
Nepal is signatory to this agreement, which classified species according to criteria where access
or control is important (eg. I-species threatened with extinction; II-species which could become
endangered; III-species that are protected).
The declaration reaffirms the importance of the principle and approaches provided for under
Convention No.169 and its adoption therefore provide a fresh impetus for promoting the
ratification and implementation of 169. ILO Convention No. 169 highlights the need to
recognize indigenous and tribal people’s specific knowledge, skills and technologies as the basis
for their traditional economies and self determined development process.
The responsibility owned institutions in the environmental impact assessment process are:
The Cabinet,
Department of Environment
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 47
Local Governments, donor agencies and NGOs/private sector,
Even though EIA has become mandatory under the EPA, many private sector and governmental
developers still escape their responsibility, in that many projects which were supposed to
undergo EIA have not undertaken the process.
National EIA requirements are only structurally complied in those cases where projects are to
undergo EIA as per donor agency’s requirement. In most cases, the National EIA Guidelines
1993 are followed while conducting EIA, except for those matters which are covered by the EPR
.
In Nepal’s EIA system, National EIA Guidelines 1993 and Environmental Protection Act 1996
and its regulation 1997 are being used as policy level documents.
ANNEX 1:
ANNEX 2:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 48
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 49
Network
Simple checklist
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 50
Questionnaire checklist:
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 51
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 52
Environment Management Plan
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 53
Some Model Questions
1. What is EA? What are the objectives and importance of EA in environmental conservation?
2. What is project screening? What information is required for screening? What is it important?
3. What does scoping mean in EA study? Describe its objectives and methods.
5. What is SEA? How it differs from project level EA? Give to two examples of SEA
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 54
7. What are the major provisions of Environment Protection Act ,2053 and Environment
Protection Rule , 2054
1. How impact differs from effect? Write with examples. What are methods of impacts identification?
2. What is alternative analysis? What are types of alternatives in EIA process? Describe with examples?
3. What are environment management plan and mitigation measures? Describe types of mitigation
measures and monitoring with examples?
4. What is baseline information EIA study? Describe components of existing environment condition with
examples.
Madan Thapa , Purbanchal University College of Environment and Forestry( PUCEF) Page 55
The performance of mitigation measures over a project's lifecycle can be ensured through compliance monitoring, impact monitoring, and environmental auditing. Compliance monitoring involves periodic sampling or continuous recording to verify adherence to environmental standards. Impact monitoring measures socio-economic and biophysical parameters during project phases to detect changes. Environmental audits assess the effectiveness of mitigation measures and the responses from project management agencies .
The Forest Act, 2049 (1993) is relevant as it ensures all values of forest land, including environmental services and biodiversity, are considered in project development. The Act mandates approved work plans for forest types and requires proposals acquiring forest land to adhere to environmental standards and mitigation measures aligned with forest conservation .
Implementing Environmental Assessments such as IEE and EIA is essential due to several reasons: they foster global commitment, are mandatory for all donors, and help in reducing environmental damage. Additionally, they lower project costs in the long term by ensuring development aligns with national quality standards, government policies, and international obligations .
Baseline monitoring establishes the pre-project environmental conditions, impact monitoring tracks environmental changes during project phases, and compliance monitoring ensures adherence to environmental standards. Together, these monitoring types ensure projects are implemented responsibly, with minimal negative environmental impacts and adherence to legal obligations .
Scoping is crucial in the EIA process as it identifies all potentially significant impacts and serves as the foundation for creating the Terms of Reference (ToR). The scoping phase ensures that all pertinent issues are prioritized and lays down the methodology and format for the EIA study, making it a vital step in addressing environmental concerns comprehensively .
In the project screening phase of an EIA, the process involves determining whether a project requires a full EIA. This involves assessing the project's potential environmental impacts, consulting legal frameworks and guidelines, and evaluating project nature and location. Criteria include the project's scale, potential for significant environmental impact, and alignment with environmental policies .
The Water Resources Act, 2049 (1992) integrates environmental concerns by mandating IEE reports before granting licenses for water resource use, aiming to prevent soil erosion, flooding, and landslides. Proponents must demonstrate minimal environmental impact and implement both impact mitigation and enhancement measures to comply with environmental conservation requirements .
Non-compliance with the Environment Protection Act, 2053 (1997) could lead to halted project approvals, legal challenges, and penalties. The Act requires IEE or EIA approvals before implementation, and failures in these requirements can cause significant project delays and potential environmental harm if unexamined impacts occur .
The Local Self-Governance Act, 2055 (1998) empowers local communities by assigning responsibilities to the Village and District Development Committees for formulating and implementing environmental protection programs. These local bodies work on pollution control, biodiversity conservation, and sustainable resource use, directly involving local communities in environmental governance .
The administrative procedure for IEE in Nepal ensures public participation and accountability by mandating a 15-day public notice in national newspapers and posting notices in local offices, including DDC, VDC/Municipality, health posts, schools, and other organizations. This procedure allows the inclusion of public suggestions in the Final Report, which must be submitted to the concerned ministry with proof of public notice and a deed of recognizance .