HPE UGC Priok Timur - Pelindo 1

This document is a budget plan for the procurement and installation of a 150kV GIS at Priok Barat - Priok for Pelindo. It includes two tables: 1) A bill of quantities (BOQ) table listing the items needed, their quantities, unit prices, transportation costs, installation costs, and total prices. 2) A construction work table listing civil works items like trench excavation and backfilling, concrete channels, cable bridges and ducts, and joint pits along with their quantities, unit prices and total prices. The document provides a detailed cost estimate for all materials, equipment, and civil works needed for the 150kV GIS installation project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views6 pages

HPE UGC Priok Timur - Pelindo 1

This document is a budget plan for the procurement and installation of a 150kV GIS at Priok Barat - Priok for Pelindo. It includes two tables: 1) A bill of quantities (BOQ) table listing the items needed, their quantities, unit prices, transportation costs, installation costs, and total prices. 2) A construction work table listing civil works items like trench excavation and backfilling, concrete channels, cable bridges and ducts, and joint pits along with their quantities, unit prices and total prices. The document provides a detailed cost estimate for all materials, equipment, and civil works needed for the 150kV GIS installation project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

RENCANA ANGGARAN BIAYA

Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)

No DESCRIPTIONS TOTAL PRICES

1 150 KV UNDERGROUND CABLE FOR SUPPLY -

2 150 KV UNDERGROUND CABLE FOR ERECTION -

TOTAL -

PPN 10% -

TOTAL EQUIVALENT RUPIAH -

GRAND TOTAL EQUIVALENT RUPIAH DIBULATKAN -


Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)
### DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
Pengadaan Material Termasuk Transportasi, Pemasangan, Comissioning dan Asuransi (Electrical, Civil Works and Miscellaneous)

Quantity PROCUREMENT INLAND TRANSPORT ERECTION TOTAL PRICE

No ITEM Unit
UNIT PRICE PRICE UNIT PRICE PRICE UNIT PRICE PRICE PRICE
(Rp) (Rp) (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3=1x2 4 5=1 x 4 6 7= 1 x 6 8=3+5+7

1 150 KV UNDERGROUND CABLE AND ACCESSORIES


1 set 3 phasa
1.1 Single core XLPE cable 150 kV 1200 sqmm copper conductor (2 circuit, 3 x m 28,200 N/A N/A
1 single core cable)
1.2 Single core straight joints with integrated screen for cross joint unit 48 N/A N/A
1.3 Link box with SVL for Cross Bonding (3 in 1) complete with all acessories set 12

1.4 Link box SVL for earthing (3 in 1) complete with all acessories set 8
1.5 Indoor SF6 Gas Sealing End complete with acessories (GIS Periok) unit 6
1.6 Outdoor SF6 Gas Sealing End complete with all acessories and supporting unit 6
structure (GIS Priok Barat)
1.7 Clamp and connector for six connection between outdoor sealing end and bays 2
switchgear bushing.
1.8 Lightning Arrester 10 kA with counter (SCADA Compatible) complete with unit 6
supporting structure
1.9 Acessories lain (Cable N2XCY 1x300 sqmm 3 kV for cross bonding) meter 540
1.10 Acessories lain (Cable N2XY 1x300 sqmm 3 kV for earthing) meter 360

1.11 Web-based electronic meter for 2 bays 150kV UGC feeder class 0,2 intalled unit 2
on panel
1.12 Interface and adaptation with existing busbar protection, substation lot 1
authomation (SAS ABB) etc. (if any)
1.13 LV power and control cable, power cable and necessary equipment to bays 2
complete the specified scope of work

2 PROTECTION AND COMMUNICATION


2.1 Fiber Optic (FO) cable direct burried type with accessories, 24 core m 4700 N/A N/A
2.2 Optical Gantry Box (OGB) for 24 core FO with accessories set 0
2.3 Optical Terminal Box (OTB) for 24 core FO with accessories include optical set 2
connection to relay (see tech. spec 13A).
2.4 Diffrential relay protection support dirrect optic feature for 2 Cct unit 4

2 of 6
Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)
### DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
Pengadaan Material Termasuk Transportasi, Pemasangan, Comissioning dan Asuransi (Electrical, Civil Works and Miscellaneous)

Quantity PROCUREMENT INLAND TRANSPORT ERECTION TOTAL PRICE

No ITEM Unit
UNIT PRICE PRICE UNIT PRICE PRICE UNIT PRICE PRICE PRICE
(Rp) (Rp) (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3=1x2 4 5=1 x 4 6 7= 1 x 6 8=3+5+7

TOTAL PRICE

3 of 6
Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
Pengadaan Material Termasuk Transportasi, Pemasangan, Comissioning dan Asuransi (Electrical, Civil Works and Miscellaneous)

Erection
HARGA TOTAL
Quantity UNIT PRICE PRICE
No PARTICULARS Unit
(Rp) (Rp) (Rp)
1 2 3=1x2 4=3

3 CONSTRUCTION
3.1. Lay cable direct in the ground including excavation, supply and laying of m 3600
protective covers etc. Including backfiling above over covers concrete and
reistatement for 2x3x150 kV XLPE cable and Fiber Optic in 5.0 meters deep
trench ( type 1 )

3.2. Lay cable direct in the ground including excavation, supply and laying of m 421
protective covers etc. Including backfiling above over covers concrete and
reistatement for 2x3x150 kV XLPE cable and Fiber Optic in 5.0 meters deep
trench ( type 2 )

3.3 Lay cable direct in the ground including excavation supply and laying of m 0
protective covers etc. Including backfiling above over covers concrete and
reistatement for 2x3x150 kV XLPE cable and Fiber Optic in 5.0 meters deep
trench ( type 3 )

3.4 Lay cable direct in the ground including excavation supply and laying of m 0
protective covers etc. Including backfiling above over covers concrete and
reistatement for 2x3x150 kV XLPE cable and Fiber Optic in 5.0 meters deep
trench ( type 4 )

3.5 Supply and placing of concrete cable channel (boring) including excavation m 400
including backfiling up to 500 mm only over covers concrete and including
Cable's hanger for 2x3x150 kV XLPE single core power cable and Fiber Optic
in 5.00 meters deep trench. (type 5)

3.6 Supply and placing of concrete cable channel (boring) including excavation m 279
including backfiling up to 500 mm only over covers concrete and including
Cable's hanger for 2x3x150 kV XLPE single core power cable and Fiber Optic
in 5.00 meters deep trench. (type 6)

3.7 Supply and placing of cable bridge including cable's hanger for 2x3x150 kV set 2
single core power cable and FO ( type 7 ) Cable bridge up to 5 m in length.

3.8 Supply and placing of cable duct including cable's hanger for 2x3x150 kV m 85
single core power cable and FO (type 8 )

3.9 Supply and placing of concrete for joint pit and cross bonding cable channel set 8
including excavation including backfiling up to 500 mm only over covers
concrete for 2x3x150 kV XLPE single core power cable and Fiber Optic in
4.00 meters deep trench. (type 9)
Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
Pengadaan Material Termasuk Transportasi, Pemasangan, Comissioning dan Asuransi (Electrical, Civil Works and Miscellaneous)

Erection
HARGA TOTAL
Quantity UNIT PRICE PRICE
No PARTICULARS Unit
(Rp) (Rp) (Rp)
1 2 3=1x2 4=3
3.10 Supply & install cable rack for 2x3 XLPE 1200 mm2 cable and for Control m 80
cable in the GIS Building (Including Accessories to complete the works)

3.11 Erection of 150 kv straight jointing. unit 48

3.12 CABLE BRIDGES

3.12.1 Up to 5 m in length. unit

3.12.1 5 m to 8 m in length. unit

3.12.1 8 m to 12 m in length. unit

3.12.1 12 m to 15 m in length. unit

3.12.1 15 m to 20 m in length. unit

3.12.1 20 m to 25 m in length. unit

3.12.1 25 m to 30 m in length. unit

3.12.1 30 m to 35 m in length. unit

3.12.1 35 m to 40 m in length. unit

3.12.1 40 m to 45 m in length. unit 1

3.12.1 55 m to 60 m in length. unit 1

3.13 Detail Survey and Georadar along cable route for interfacing common meter 4700
utilities

3.14 Land Clearing from surplus soil lot 1


Pengadaan dan Pemasangan SKTT 150 kV GIS Priok Barat - Priok (Pelindo)
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
Pengadaan Material Termasuk Transportasi, Pemasangan, Comissioning dan Asuransi (Electrical, Civil Works and Miscellaneous)

Erection
HARGA TOTAL
Quantity UNIT PRICE PRICE
No PARTICULARS Unit
(Rp) (Rp) (Rp)
1 2 3=1x2 4=3

4 COMISSIONING
4.1 Commissioning for completion to scope of work lot 1

TOTAL PRICE