Centrifugal Compressor Maintenance Guide
Centrifugal Compressor Maintenance Guide
1/
GE /
BCL / PCL MAJOR MAINTENACE
2/
GE /
Maintenance
• Front head and rear head flanges connected to casing by stud bolts
• Front head flange connected to casing by shear ring of traditional
design, casing bell type
• Front head flange connected to casing by shear ring of modern
design, casing bell type
• Accident; compressor bundle removing (shear ring disassemble)
• Modern PCL design
• Old PCL design
• Labyrinth Seal Clearance
• Tool for Horizontal Removing/Fitting CO/CE 2BCL 800-1000
• Rotor centering relative to diaphragms
• Rotor Axial float calculation
• Thrust bearing thickness calculation
3/
GE /
MAJOR INSPECTION FOR BARREL COMPRESSOR
Disassembly of parts
Outside the centrifugal compressor
• Removal of coupling cover
• Removal of coupling spacer
• Alignment check
• Removal of coupling hub
Parts to be replaced
• Seals
• Pads
• O-rings
• Labyrinths
5/
GE /
MAJOR INSPECTION FOR BARREL COMPRESSOR
Re-assembly of Parts
On the centrifugal compressor
• Installation of rotor and clearance check
• Bundle closing
• Installation of bundle
• Installation of suction head flange
• Installation of seals
• Installation of thrust collar
• Installation of bearing
• Installation of bearing cover
• Installation of piping
• Installation and connection of instrumentation
6/
GE /
Front head and rear head flanges connected
to casing by stud bolts
7/
GE /
Front head and rear head flanges connected to casing by
stud bolts
Conceptual disassembly
procedure is:
• Disassemble couplings,
bearings, and DGS both
ends
• Disassemble front head
and stud bolts
• Disassemble internal
bundle from casing
8/
GE /
Front head and rear head flanges connected to casing by
stud bolts
Conceptual disassembly
procedure is:
• Disassemble couplings,
bearings, and DGS both
ends
• Disassemble front head
and stud bolts
• Disassemble internal
bundle from casing
9/
GE /
Front head and rear head flanges connected to casing by
stud bolts
Remove the nuts from the reference studs of the casing head, and
screw on them the guide pins, supplied with the standard
assembling tools
10 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Remove all stud bolts nuts. Install jack screw in the casing head and
tighten evenly to force casing head out
11 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Adjust hoisting equipment, draw or put the casing head and lower it
carefully to floor resting it on wooden blocks
12 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Adjust hoisting equipment, draw or put the casing head and lower it
carefully to floor resting it on wooden blocks
13 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Withdraw rotor/diaphragms
bundle assembly as indicated
in the dwg
Diaphragm bundle
disassembly “Assembly/disassembly
rotor/diaphragms bundle”
14 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
15 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Front head
disassembly
Front head
disassembly
Diaphragm bundle
disassembly
18 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Diaphragm bundle
disassembly
19 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Front head
disassembly
Diaphragm bundle
disassembly
20 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Diaphragm bundle
disassembly
21 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Lifting the rotor (typical sketch)
Keep the rotor in good balance, guiding it by hands to avoid damaging on the
impellers or labyrinths at lifting or during lowering. Remember to use a water-level to
lift the rotor in a balanced position.
22 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
23 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Bundle disassembly
24 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
25 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
26 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Bundle open
27 /
GE /
Front head and rear head flanges connected to casing by
stud bolts
Diaphragms
Counter casing
28 /
GE /
Intermediate, Centrifugal Compressor
bell type
(high pressure compressors)
29 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
30 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Conceptual disassembly
procedure is:
1. Disassemble bearings,
couplings and DGS both ends
2. Disassemble end gasket
3. Disengage shear ring
4. Remove front head
5. Disengage internal shear ring
6. Disassemble internal bundle
from casing
31 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
32 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
But this solution has the disavantage of a very heavy head flange with major
difficulties for the ass/diss and the possibility to lock one or more sectors of
the shear rings.
33 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
34 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
35 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
36 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Device for
fitting/removing
head flange SOS 78600/3
37 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Fitting
38 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Positioning of shear
ring in the casing
Fitting
Items 6, 7, 8 are
fitted on the two
shear ring sectors at
the top
39 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Fitting
Fitting
41 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Fitting
42 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Fitting
43 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Fitting
Remove the screw (15) fit the
rods (D) and nuts (C)
Use the nuts (7) to put the
shroud rings in their working
position
Since is necessary to ensure
that the main flange is home
against the shroud rings and
casing (to avoid kickback
during compressor start-up),
the main flange mast be
moved back. To do this it is
necessary to act on the n° 4
tie rods (C) using the nuts (D)
44 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
45 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Bundle assembly / disassembly in / from casing
46 /
GE /
Front head flange connected to casing by shear ring of
traditional design, casing bell type (high pressure compressors)
Bundle
assembly/disassembly tools
by means of jacks
47 /
GE /
Bundle assembly/disassembly tools
48 /
GE /
Bundle assembly/disassembly tools
49 /
GE /
Bundle assembly/disassembly tools
50 /
GE /
Bundle assembly/disassembly tools
51 /
GE /
Bundle assembly/disassembly tools
52 /
GE /
Intermediate, Centrifugal Compressor
bell type
(high pressure compressors)
53 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
Conceptual disassembly
procedure is:
1. Disassemble bearings,
couplings and DGS both
ends
2. Disassemble head flange
positioning screws
3. Disassemble shear ring-
outer ring
4. Disassemble shear ring-
inner ring
5. Disassemble front head
6. Disassemble internal
bundle from casing
54 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
Conceptual disassembly
procedure is:
1. Disassemble bearings,
couplings and DGS both
ends
2. Disassemble head flange
positioning screws
3. Disassemble shear ring-
outer ring
4. Disassemble shear ring-
inner ring
5. Disassemble front head
6. Disassemble internal
bundle from casing
55 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
Conceptual disassembly
procedure is:
1. Disassemble bearings,
couplings and DGS both
ends
2. Disassemble head flange
positioning screws
3. Disassemble shear ring-
outer ring
4. Disassemble shear ring-
inner ring
5. Disassemble front head
6. Disassemble internal
bundle from casing
56 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
Conceptual disassembly
procedure is:
1. Disassemble bearings,
couplings and DGS both
ends
2. Disassemble head flange
positioning screws
3. Disassemble shear ring-
outer ring
4. Disassemble shear ring-
inner ring
5. Disassemble front head
6. Disassemble internal
bundle from casing
57 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
Advantages
Forged casing more light
and with a reduced
maximum diameter
Easy to disassemble
assemble the head flange
and the shear rings
Avoid to lock one or more
sectors of shear rings in
their seats during the
movement to fit or
remove them
58 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
To flare
O-rings
“C” seal rings
energized by an
internal spring
Note:
The N2 buffer system is afterwards the flare
Measurement of pressure inside the chamber between the two C – rings
In the old design all the seals were afterwards the shear rings
59 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
61 /
GE /
Front head flange connected to casing by shear ring of
modern design, casing bell type (high pressure compressors)
62 /
GE /
Accident occurred
during compressor bundle removing
(shear ring disassemble)
64 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
Machine : BCL405C
Location : Off Shore Platform
Activity: Compressor bundle removal
Event: Shear ring shoot away during disassemble
Reason (Causes): A chamber inside the machine was still pressurized
Root Causes: 1- Internal O-ring wrongly installed in a past work
2- incorrect procedure followed by manpower
Reference drawing: SOS94060 – SW56444 – SW 57700
65 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
BCL405C
Dwg n° SOS94060
66 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
67 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
68 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
1- Internal O-ring wrongly installed
Between compressor casing and main head
flange are installed n°2 “C” O-Ring at item 35E
external and 34E internal, (see SOS94060).
In a past maintenance work the internal ring 34E
was mounted incorrectly in a reverse way (see
picture below) so that process gas leaked
through it creating a pressurized chamber
between the two o-rings; that area remained
under pressure even once the compressor
casing was completely depressurized.
Due to the chamber geometrical shape the gas
trapped inside applied an axial force towards the
head flange and the shear rings, sticking the two
together and making the last hard to be
removed.
69 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
2- incorrect procedure followed
The personnel involved on the diaphragms
bundle removal didn’t use a correct procedure.
Shear rings can be taken out pretty easily once
their lock screws are loose, if the ring seems
stuck or very hard to get out stop any activities
and investigate the reasons. The TA’s on site
didn’t realized that there was still a residual
axial force and decided to remove the rings
using an hydraulic tool.
70 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
3- Consequences
On Personnel : Nobody was injured but
witnesses suffered severe shock
On Material : Minimal damages, screws and
thrusting screw twisted, shear ring dented
Potential : Extreme potential danger to
personnel safety
71 /
GE /
Accident occurred during compressor
bundle removing (shear ring disassemble)
4- Suggestion and corrective action
A. Pay attention during bundle assembling in
order to install correctly all compressor
components
B. During dismantling , ensure that there aren’t
any pressurized gas pocket once the
compressor is depressurized
b. to verify that ,open all casing drain
72 /
GE /
Front head flange connected to casing by shear ring of
modern design, front head, diaphragms bundle and
rear head connected together in a single piece
73 /
GE /
PCL modern design
Casing head
Shear rings
74 /
GE /
PCL modern design
75 /
GE /
PCL modern design
76 /
GE /
PCL modern design
Shear ring and cartridge disassembly
77 /
GE /
PCL modern design
Cartridge disassembly
Note: the bearings and the seals haven’t to be disassembly from the bundle
78 /
GE /
PCL modern design
79 /
GE /
Front head flange bolted to casing in old design
PCL type
80 /
GE /
PCL old design
85 /
GE /
BCL head flange removal
86 /
GE /
BCL head flange removal
87 /
GE /
BCL bundle removal
88 /
GE /
BCL bundle removal
89 /
GE /
BCL bundle removal
90 /
GE /
BCL bundle removal
91 /
GE /
BCL bundle removal
92 /
GE /
BCL bundle removal
93 /
GE /
BCL bundle removal
94 /
GE /
BCL bundle and Rotor on load bay
95 /
GE /
Diaphragm bundle disassembly for barrel compressors
96 /
GE /
Diaphragm bundle assembly
97 /
GE /
Diaphragm bundle assembly for barrel compressors
note:
It is made performing the operations of disassembly but in the opposite order
In particular take the following measures:
98 /
GE /
Diaphragm bundle assembly for barrel compressors
THE CASING HEAD FLANGE LOCKING BOLTS SHOULD BE TIGHTENED TO A TORQUE VALUE
SHOWN IN TABLE ON “PROCEDURE FOR TIGHTENING CASINGS”
99 /
GE /
Diaphragm bundle assembly for barrel compressors
100 /
GE /
Labyrinth
SealClearance
101 /
GE /
Labyrinth Seal Clearance
• Lateral clearances
• Vertical clearances
102 /
GE /
Labyrinth Seal Clearance
false labyrinth
103 /
GE /
Labyrinth Seal Clearance
104 /
GE /
Labyrinth Seal Clearance
The nr.4...
105 /
GE /
Labyrinth Seal Clearance
Side clearances
a) Gauge, by means of feeler
gauges, the labyrinth seal
side clearances
b) Two values (one for each
side) are taken for each
labyrinth and added to each
other
106 /
GE /
Labyrinth Seal Clearance
Labyrinth Seals
Lateral
Clearance
Check
Filler gauge
107 /
GE /
Labyrinth Seal Clearance
Vertical clearances
109 /
GE /
Labyrinth Seal Clearance
d) Place, on the rotor top, in the zones of the labyrinth seals of the upper half-
assembly, some pieces of lead wires as indicated at point b)
e) Install upper half diaphragm assembly on lower half. Install split-line cap
screws and tighten
f) Then remove the split-line cap-screws and lift the upper half assembly
g) Remove the rotor
h) Remove the lead wires that now are shaped as the free space between the
labyrinth seal and the relevant rotor part
i) Measure by a micrometer screw gauge the flattening made by the labyrinth
seals on the lead wires
j) Now add the values of upper and lower clearances of the same labyrinth
and compare the result with the value indicated in the “Diametral
Clearances table” for each labyrinth seal ring. The seals, whose clearances
complies with the established value but have the blades slightly rounded or
dented, can be restored by a tool of the same type as those used for the
lathe having the profile like that included between two seal blades.
111 /
GE /
Replacement of
labyrinth seals
112 /
GE /
Replacement of labyrinth seals
Replacement of labyrinth seals
Usually the labyrinth seal rings are supplied in two halves (in four sections these of
bigger compressor) and with the clearances already established, therefore no
adjustment is required.
However it is advisable to always check the clearance again.
To remove and then replace the labyrinth seal rings act as follows:
1) With a hammer or a brass bar (or another equivalent soft metal) whose section is smaller
than that of the half-ring, beat on one of two sides of such a ring to let it rotate and therefore
come out. First beats shall be light to avoid deforming the half ring
2) In the event, after the first beats, the half ring does not begin to slide, put in its housing some
penetrating oil and let it soak for some hours
114 /
GE /
Replacement of labyrinth seals
3) The half ring removed, clean the housing carefully by thinners and scrapers and blow air in
4) Introduce the new half-ring in the relevant housing. The half-ring is shaped in order that no
positioning mistake is allowed
5) Should the half ring not fit owing to its different bending in respect of its housing, rest it
upside-down on a plane and beat slightly on the top to increase the relevant bending radius
(To reduce the bending radius it will be necessary to beat on one end)
115 /
GE /
Replacement of labyrinth seals
6) The labyrinth seal half ring just replaced shall be marked with the same numbers as those
removed and therefore as those of the half-casing (or half diaphragm assembly)
117 /
GE /
Replacement of labyrinth seals
118 /
GE /
Tool for Horizontal Removing/Fitting
119 /
GE /
Tool for Horizontal Removing/Fitting CO/CE 2BCL 800-1000
120 /
GE /
Thrust bearing side
A - Remove the cover (1M) on the thrust
bearing side, by loosening screws
B – Remove the oil splash rings positioned
between the cover and the joint
C – Disassemble the joint according the
apposite spec (before removing the joint on
the collar side, fit the cap to the shaft)
D – remove cover (12M) on the instrument box by unscrewing the screws and remove the gasket
(13M)
121 /
GE /
Thrust bearing side
122 /
GE /
Thrust bearing side – Flange removal
G – Use two pullers (4G) to detach flange, then pull it out by making
it slide along columns. Do this by keeping the flange lifted.
123 /
GE /
Thrust bearing side – Thrust collar removal
A - Straighten the safety plate (9Y) by using
the special tool according to spec. SOS86540
124 /
GE /
Thrust bearing removal
A – Disconnect thrust bearing
internal thermoelements connections
from terminal board and remove
them from the instrument box.
125 /
GE /
Thrust bearing side
126 /
GE /
Thrust bearing side – Journal bearing removal
A – Disconnect the journal bearing thermoelement
connections from terminal box; do the same with
vibration probe connection
B – Loosen screws (2E) and their relative washers
(15E)
A – pull out the Journal bearing by making it slide along columns, by means of two pullers
128 /
GE /
Thrust bearing side A – pull out the stop ring by using the handling tool
B – Disassemble locking ring in four parts by means
of puller, which is fit into the suitable hole.
Do this by pulling out one sector at a time, removing
the two lateral sectors first.
129 /
GE /
Thrust bearing side
A – Pull out the separation ring by making the cage slide along the columns until it
comes out the head flange.
130 /
GE /
Thrust bearing side
131 /
GE /
Thrust bearing side
132 /
GE /
Thrust bearing side – oil seals removal
133 /
GE /
Thrust bearing side – oil seals removal
A – Pull out the oil seals by making the cage slide along the columns until they come out the
head flange.
134 /
GE /
Thrust bearing side – end seal removal
special nuts
clamping screws
A – fit the special nut (52G 51G) onto the tie rods (after
having disassemble the locking nuts 20E). These nuts
permit to push the head flange so as to remove the
clamping screws (6A) and as a consequence to
disassemble the ring in four part.
B – disassemble the blocks (4A) and their relative
screws.
136 /
GE /
Thrust bearing side – sector ring removal
137 /
GE /
Thrust bearing side – sector ring removal
138 /
GE /
Thrust bearing side – Flange removal
A – Fix the lifting bracket (7G) on the head flange (1E); tighten screws (27G) 135Nm; assemble tie rods (19E),
nuts (52G), shims (62G 63G) and reassemble block (4A)
B – Assemble special equipment (3G) onto lifting bracket [spec SSO0667261]
C – Lift the head flange up to the indication marked on the equipment plate
C – Now act on nuts (52G) to pull out the head flange
139 /
GE /
Thrust bearing side – Bundle removal
140 /
GE /
Thrust bearing side – Bundle removal
141 /
GE /
Thrust bearing side – Bundle removal
142 /
GE /
Thrust bearing side – Bundle removal
144 /
GE /
Thrust bearing side – Bundle removal
stop blocks
145 /
GE /
Thrust bearing side – Bundle removal
D – Go on with the extraction
of the diaphragm bundle, until
it reaches stop block on the
brackets. Do this by
displacing the hydraulic
cylinder supports when the
latter stop running.
146 /
GE /
Thrust bearing side – Bundle removal
147 /
GE /
Thrust bearing side – Bundle removal
Lifting stake
148 /
GE /
Rotor removal
WARNING
During handling rest the rotor in the
journal bearing or sleeve collet zone
149 /
GE /
Rotor removal and check clearances
A – Assemble half rings to check the clearance
between the rotor and the seals.
B – Insert the rotor in the diaphragm bundle by
means of the balance
C – After having checked the clearances, remove the
two half rings and reassemble the labyrinth seals.
D – Reassemble the new rotor and the bundle in the
compressor by following the steps of the previous
procedure in the reverse way and by means of the
Half rings same special tools.
150 /
GE /
Rotor removal and gasket assembly
151 /
GE /
152 /
GE /
153 /
GE /
154 /
GE /
155 /
GE /
156 /
GE /
Rotor centering
relative to diaphragms
157 /
GE /
Rotor centering relative to diaphragms
158 /
GE /
Rotor centering relative to diaphragms
1) Check that the lower diaphragm bundle half is completely assembled and
horizontal.
2) Carefully lower the rotor, guiding it by hand, into lower diaphragm bundle half
and set it on labyrinth halves. The rotor should be axially positioned to obtain
optimum impeller - diffuser passage alignment.
Clearances
Clearances
159 /
see Clearance table GE /
Rotor centering relative to diaphragms
1) Check that the lower diaphragm bundle half is completely assembled and
horizontal.
2) Carefully lower the rotor, guiding it by hand, into lower diaphragm bundle half
and set it on labyrinth halves. The rotor should be axially positioned to obtain
optimum impeller - diffuser passage alignment.
Diffusers width
160 /
GE /
Rotor centering relative to diaphragms
3) Measure distance between shaft end and No-Drive face of bundle. Take two
values, +/- 0.05 mm, 180° apart and record the average value.
4) Assemble the diaphragm rotor bundle and fitting it into the casing.
5) Set rotor to center position using dimension established in step 3 above. Measure
+/-0.05 mm distance from shaft end to face of casing on Drive End and record the
value.
161 /
GE /
Rotor centering relative to diaphragms
6) Install the head flange. Using value taken in step 5 above, set rotor to center
position. Measure +/- 0.05 mm, the distance from the shaft end to the face of the
head flange and record the value.
7) Install oil seals or dry mechanical seals, install journal bearings and thrust
bearing using existing thickness rings.
162 /
GE /
Rotor centering relative to diaphragms
8) Force rotor against outboard thrust assembly. Measure the distance, +/- 0.05 mm,
between shaft end and the head flange outer face.
9) Compare this value with that taken in step 6 above. When rotor is against
outboard thrust assembly, it should be in the center position, +/-0.1 mm. If it is
not, the outboard thickness ring must be adjusted. This will alter thrust bearing
clearance, therefore adjustment of the inboard thickness ring may required.
163 /
GE /
Rotor Axial float calculation - BCL
type A – labyrinth end seal fitted on the flange (old type)
1) With the bundle open in two half (outside the casing) align diaphragm with
impeller (as previously explained in the procedure) in order to establish the
zero position of the rotor
2) Measure the total float. Suppose that you find NDE 4mm and DE 4,5mm
3) According the specification value in the ass. dwg: NDE 2mm and DE 2.5mm
are the min axial float required
164 /
GE /
Rotor Axial float calculation - BCL
type A – labyrinth end seal fitted on the flange (old type)
4) Assembly the internal bundle in the casing, assembly the head flange and
interpose between the casing and the flange 5mm thickness
5) Move the rotor completely towards NDE, set the zero on the dial indicator
6) Move the rotor (4mm) versus DE, (working position)
7) Now reset the dial indicator and move versus DE, store the new value
(3.8mm)(due to the contact with the rear flange labyrinth)
8) DON’T touch the dial indicator, remove the thickness from the front head
flange and tighten the stud bolts until final torque value
9) At this point move again the rotor versus NDE store the new value (3.5mm)
166 /
GE /
Exercise
167 /
GE /
Exercise
168 /
GE /
Old type shaft end labyrinth
It is avisable to compare
the thickness between the
old and the new
labyrinth
Rotor
@zero
position
gap
171 /
GE /
New type shaft end labyrinth external fitting
Head Head
Flange Flange
Rotor Rotor
@zero @zero
position position
gap
B Gap= A-B
172 /
GE /
Rotor Axial float calculation - BCL
type B – labyrinth end seal external fitting
1) Start with the rotor centering position in the diaphragm bundle
2) Introduce the bundle in the external casing, assembly the front head flange (also with the shear
rings) without any thickness interposition on the flange
3) Move the rotor completely vs NDE set zero the dial indicator. Move the rotor vs DE in order to have
the previous value of the zero position (vs NDE of 4mm)
4) At this point set zero on the dial indicator and move the rotor vs DE, a lower value vs DE will be find
that’s due to the fact that the rotor will touch the statoric part of the end seal on the balancing
drum
5) The new value for example will be (instead of 4,5mm DE) 3mm DE and 4 mm NDE
6) Move again the rotor in the zero position
173 /
GE /
Rotor Axial float calculation - BCL
type B – labyrinth end seal external fitting
Note: if the gap between the rotor and the flange is 20 mm the end laby has a
thickness of 17,5 mm, on the DE i will find a value of 2,5mm of total float.
On the NDE for example if i find a gap between the rotor and the flange of 21mm
and the thickness of the end laby is 17,5 mm the float vs NDE will be of 3,5mm.
174 /
GE /
BCL compressor – thrust bearing thickness
determination
For the alignment, the rotor was Faces to be aligned. For the offset
seating on dummy Discharge tolerance refere to the dwg.
Diaphragm
labyrinths placed on bottom half Where not specified has to be considered
diaphragms bundle 3-5% of the diaphragm gap
Rotor locking
device
Thrust bearing
clearence
collar
DE SHAFT NDE
Dial
Gauge
Reference
Measure
175 /
GE /
Exercise 1 (example) – thrust bearing
thickness calculation
Actual Thrust
bearing
clearance=0,45mm
Old shims:
Non active Active side
3,82 mm active side
side 6,18 mm non active side
DE collar NDE
-0,34 NDE
+0,34 DE
@ zero rotor position
dial gauge setting 5,00
Min clearance according the specification
0,30 mm
5,34 In the non active side i have to consider
0,45-0,30=0,15 mm to add
New shims:
(3,82-0,34)mm = 3,48 mm active side
(6,18+0,34+0,15)mm = 6,67 mm non active side
176 /
GE /
Exercise 2 – thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,40mm
Old shims:
Non active Active side
3,82 mm active side
side 6,18 mm non active side
DE collar NDE
5,15
177 /
GE /
Exercise 2 sol. – thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,40mm
Old shims:
Non active Active side
3,82 mm active side
side 6,18 mm non active side
DE collar NDE
New shims:
(3,82-0,15)mm = 3,67mm active side
(6,18+0,15+0,10)mm = 6,43mm non active side
178 /
GE /
Exercise 3– thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,18mm
Old shims:
Non active Active side
6,45 mm active side
side 4,20 mm non active side
DE collar NDE
Min clearance according the specification
0,30 mm
@ zero rotor position
dial gauge setting 5,00
New shims:
4,61
179 /
GE /
Exercise 3 sol. – thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,18mm
Old shims:
Non active Active side
6,45 mm active side
side 4,20 mm non active side
DE collar NDE
+0,39 NDE
- 0,39 DE
@ zero rotor position
dial gauge setting 5,00
Min clearance according the specification
0,30 mm
4,61 In the non active side i have to consider
0,30-0,18=0,12 mm to remove
New shims:
(6,45+0,39)mm = 6,84 mm active side
(4,20-0,39-0,12)mm = 3,69 mm non active side
180 /
GE /
Exercise 4– thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,20mm
Old shims:
Non active Active side
4,10 mm active side
side 6,72 mm non active side
DE collar NDE
New shims:
4,15
181 /
GE /
Exercise 4 sol. – thrust bearing thickness
calculation
Actual Thrust
bearing
clearance=0,20mm
Old shims:
Non active Active side
4,10 mm active side
side 6,72 mm non active side
DE collar NDE
+0,85 NDE
- 0,85 DE
@ zero rotor position
dial gauge setting 5,00
Min clearance according the specification
0,35 mm
4,15 In the non active side i have to consider
0,35-0,20=0,15 mm to remove
New shims:
(4,10+0,85)mm = 4,95 mm active side
(6,72-0,85-0,15)mm = 5,72 mm non active side
182 /
GE /









