18FJ0021 - Backup Computation

The document is a backup computation for a road construction project. It outlines the planned, actual, and represented quantities for various project items such as earthworks, subbase and base course construction, surface courses, drainage, and slope protection. The quantities provided indicate no mobilization of structures was needed but embankment, subbase, and concrete road surface were constructed according to plan.

Uploaded by

Dennis Sagao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
741 views5 pages

18FJ0021 - Backup Computation

The document is a backup computation for a road construction project. It outlines the planned, actual, and represented quantities for various project items such as earthworks, subbase and base course construction, surface courses, drainage, and slope protection. The quantities provided indicate no mobilization of structures was needed but embankment, subbase, and concrete road surface were constructed according to plan.

Uploaded by

Dennis Sagao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

18FJ0021

Asset Preservation Program, Preventive Maintenance, Secondary Roads, Buenavista - Kawayan Road, K0056 + 851 - K0057
+ 482, K0057 + 719 - K0058 +400

BACK-UP COMPUTATION

PART A - FACILITIES FOR THE ENGINEERS

ITEM A.1.1(6) Provision of Combined Field Office, Laboratory and Living Quarters Building for the Engineer
Qplanned = 0.00 mo.
Qactual = 0.00 mo.
Qrepresented = 0.00 mo.

PART B - OTHER GENERAL REQUIREMENTS

ITEM B.5 Project billboard/Signboard


Qplanned = 0.00 each
Qactual = 0.00 each
Qrepresented = 0.00 each

ITEM B.7 Occupational Safety and Health Program


Qplanned = 0.00 mo
Qactual = 0.00 mo.
Qrepresented = 0.00 mo.

ITEM B.8 Traffic Management


Qplanned = 0.00 mo.
Qactual = 0.00 mo.
Qrepresented = 0.00 mo.

ITEM B.9 Mobilization/Demobilization


Qplanned = 0.50 l.s
Qactual = 0.50 l.s
Qrepresented = 0.50 l.s

PART C - EARTHWORKS

ITEM 100(3)a3 Removal of Structures and Obstruction


Qplanned = 0.00 sq.m.
Qactual = 0.00 sq.m.
Qrepresented = 0.00 sq.m.

ITEM 102(2) Surplus Common Excavation


Qplanned = 0.00 cu.m.
Qactual = 0.00 cu.m.
Qrepresented = 0.00 cu.m.

ITEM 104(1)a Embankment from Roadway Excavation


Qplanned = 0.00 cu.m.
Qactual = 0.00 cu.m.
Qrepresented = 0.00 cu.m.

ITEM 105(1)a Subgrade Preparation (Common Material)


Qplanned = 0.00 sq.m.
Qactual = 0.00 sq.m.
Qrepresented = 0.00 sq.m.

PART D - SUBBASE AND BASE COURSE

ITEM 200(1) Aggregate Sub Base Course


Qplanned = 0.00 cu.m.

Page 1 of 2
Qactual = 0.00 cu.m.
Qrepresented = 0.00 cu.m.

ITEM 201 Aggregate Base Course


Qplanned = 0.00 sq.m.
Qactual = 0.00 sq.m.
Qrepresented = 0.00 sq.m.

PART E - SURFACE COURSE

ITEM 311(1)e1 PCCP (Unreinforced, 280mm thk., 14 days)


Qplanned = 0.00 sq.m.
Qactual = 0.00 sq.m.
Qrepresented = 0.00 sq.m.

ITEM 301(2)a Bituminous Prime Coat - RC - Cut-back Asphalt Grade 70


Qplanned = 92.05 sq.m.
Qactual = 92.05 sq.m.
Qrepresented = 92.05 sq.m.

ITEM 302(2) Emulsified Asphalt


Qplanned = 616.74 sq.m.
Qactual = 616.74 sq.m.
Qrepresented = 616.74 sq.m.

ITEM 310(1)a3 Bituminous Concrete Wearing Course, Hot Laid


Qplanned = 959.95 sq.m.
Qactual = 959.95 sq.m.
Qrepresented = 959.95 sq.m.

PART H - MISCELLANEOUS STRUCTURE

ITEM 612(1) Reflectorized Thermoplastic Pavement Markings White


Qplanned = 263.90 sq.m.
Qactual = 263.90 sq.m.
Qrepresented = 263.90 sq.m.

ARIEL N. LIM
Contractor

Page 2 of 2
19FJ0033
Local Infrastructure Program, Construction of Concrete Road-Concreting of Dapdap -
Simawa Road, Uson, Masbate
MASBATE CITY

BACK-UP COMPUTATION

PART A - FACILITIES FOR THE ENGINEERS

ITEM A.1.1(6) Provision of Field Office for the Engineers


Qplanned = 1.08 mo.
Qactual = 1.08 mo.
Qrepresented = 1.08 mo.

PART B - OTHER GENERAL REQUIREMENTS

ITEM B.5 Project billboard/Signboard


Qplanned = 0.00 each
Qactual = 0.00 each
Qrepresented = 0.00 each

ITEM B.7(1) Occupational Safety and Health Program


Qplanned = 0.50 mo
Qactual = 0.50 mo
Qrepresented = 0.50 mo

ITEM B.8(1) Traffic Management


Qplanned = 1.08 mo.
Qactual = 1.08 mo.
Qrepresented = 1.08 mo.

ITEM B.9 Mobilization/Demobilization


Qplanned = 0.40 l.s
Qactual = 0.40 l.s
Qrepresented = 0.40 l.s

PART C - EARTHWORKS

ITEM 101(4)a1 Removal of Actual of Structures/ Obstruction (610mm dia. RCPC)


Qplanned = 0.00 l.m
Qactual = 0.00 l.m
Qrepresented = 0.00 l.m

ITEM 102(2) Surplus Common Excavation


Qplanned = 3062.50 cu.m.
Qactual = VOLUME = 3828.13 cu.m.
(14437.78) x (80% Actual)
Qrepresented = 3062.5 cu.m.

ITEM 104(1)a Embankment from roadway excavation (Common Soil)


Qplanned = 741.08 cu.m.
Qactual = VOLUME = 926.35 cu.m.

Page 3 of 2
(14437.78) x (80% Actual)
Qrepresented = 741.08 cu.m.

Page 4 of 2
ITEM 105(1)a Subgrade Preparation (common Soil)
Qplanned = 3663 sq.m.
Qactual = 3663 sq.m.
Qrepresented = 3663 sq.m.

PART D - SUBBASE AND BASE COURSE

ITEM 200(1) Aggregate Sub Base Course


Qplanned = 1346.56 cu.m.
Qactual = 1346.56 cu.m.
Qrepresented = 1346.56 cu.m.

PART E - SURFACE COURSES

ITEM 311(1)b PCCP (Unreinforced, 200mm, 14 days)


Qplanned = 2553.3 sq.m
Qactual = 2553.3 sq.m
Qrepresented = 2553.3 sq.m

PART H - DRAINAGE AND SLOPE PROTECTION

ITEM 506(1) Stone Masonry


Qplanned = 0 cu.m
Qactual = 0 cu.m
Qrepresented = 0 cu.m

ITEM 505(2)a Grouted Riprap (Class A)


Qplanned = 296.31 cu.m
Qactual = 296.31 cu.m
Qrepresented = 296.31 cu.m

ITEM 500(1)a3 Pipe Culverts, 910mm dia.


Qplanned = 22 l.m
Qactual = 22 l.m
Qrepresented = 22 l.m

ARIEL N. LIM