Energy Monitoring System Overview

The document proposes an energy monitoring system with the following key elements: 1. The system architecture includes transmitters that send data via Ethernet to receivers connected to a controller unit and operator desktop. 2. A concept design and preliminary engineering schedule are presented, outlining activities from data collection to design completion over 60 days. 3. A list of 8 preliminary deliverables is provided, including system architecture, cost estimation, and bill of materials.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
170 views11 pages

Energy Monitoring System Overview

The document proposes an energy monitoring system with the following key elements: 1. The system architecture includes transmitters that send data via Ethernet to receivers connected to a controller unit and operator desktop. 2. A concept design and preliminary engineering schedule are presented, outlining activities from data collection to design completion over 60 days. 3. A list of 8 preliminary deliverables is provided, including system architecture, cost estimation, and bill of materials.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ENERGY

MONITORING
Energy Monitoring System
Concept Design

Device (Electrical & Instrument)

System Architecture

Schedule
Concept Design Time Synchronization Device

Operator Desktop
Transmitter

Ethernet Ethernet

Ethernet
Receiver

Controller
Unit
Concept
Design
3

4 5
1 2

Yard

One cycle load movement are times that need for moving bucket crane to loading material from ship and unloading
to yard
Load Movement VS Energy (kWh)
Date 07/07/2020 Time 11:30 AM
Load Ampere Power Energy
Wait for Boom Auto Command 100 LT 38 A 100 kW 1000 kWh
System Architecture
Preliminary Engineering Schedule

WO Release
Preparation Collecting Data
Site Survey
30 days Developing Engineering Design
Engineering 15 days BOM & Cost Estimation

Completion of Design
Review 10 days Owner Review
& Recovery Final Document
Completion of Work

Crisis communication

Day 1 5 10 20 30 40 50 60 2020

Start
Completion of
Activity
Activity
Preliminary Deliverable List

01. Deliverable Document. 02. Modification Concept

03. System Architecture 04. Communication Diagram

Datasheet Equipment &


05. Device 06. Bill Of Material

Reference Product
07. Cost Estimation 08. Catalog
Thanks!
Any questions?