Project Management Foundations: Small Projects
with Bonnie Biafore
Office Relocation Project
Optimistic Most Likely Pessimistic Labor Equipment and Other Non-Time-
Materials Total Cost Avg. Labor Rate
Hours Hours Hours Cost Facilities Based Cost
$100
Find new office space 30 40 60 $4,000 $4,000
Define office requirements 8 12 16 $1,200 $1,200
Design office layout 8 12 20 $0 $0
Negotiate and sign lease 6 8 16 $800 $800
Obtain construction Construction
40 80 120 $0 $4,000 $4,000
permit permit
Build out space 40 60 80 $0 $0
Walk through office space 2 4 6 $400 $400
Correct build-out issues 8 16 24 $0 $0
Approve build-out 2 2 2 $200 $200
Identify network
4 8 12 $800 $800
requirements
Design network 8 16 24 $1,600 $1,600
Review network design 2 4 8 $400 $400
Project Management Foundations: Small Projects with Bonnie Biafore
1 of 3
Install and configure Network
8 16 24 $1,600 $3,000 $4,600
network equipment
Test network 4 6 16 $600 $600
Identify phone system
4 8 12 $800 $800
requirements
Design phone system 8 16 24 $1,600 $1,600
Review phone system
2 4 8 $400 $400
design
Install and configure
8 16 24 $1,600 $5,000 $6,600 Phone system
phone system
Test phone system 4 6 16 $600 $600
Identify software
8 12 16 $1,200 $1,200
requirements
Specify software and
8 16 24 $1,600 $1,600
configuration
Review software plan 2 4 8 $400 $400
Install and configure
16 20 24 $2,000 $5,000 $7,000 Software
software
Test software 8 16 24 $1,600 $400
Project Management Foundations: Small Projects with Bonnie Biafore
2 of 3
Negotiate and sign IT
6 8 16 $800 $800
contract
Identify internet
4 6 8 $600 $600
requirements
Sign up for internet service 2 4 8 $400 $400
Test internet service 8 12 16 $1,200 $1,200
Approve IT systems 2 2 2 $200 $200
260 434 658 $26,600 $13,000 $0 $4,000 $43,600
Project Management Foundations: Small Projects with Bonnie Biafore
3 of 3